Home / Suncorp Group / Determination 871717
Determination 871717
Storm damage claim for internal damage: dispute over scope and settlement method (repair or cash settlement)
Summary
The complainant claimed storm damage to the internal areas of his rental property and disputed the insurer's cash settlement quote. AFCA found there was no adequate scope of works and ordered an independent builder's scope, followed by the insurer deciding to repair or cash settle with a 20% contingency, and payment of the complainant's report costs.
The policy allows the insurer to repair via its builder or cash settle on a reasonable quote, but the existing quote was outdated and the scope of damage was unresolved, so an independent scope of works was needed.
Issues
- Claim amount dispute primary · upheld
“At present, there is no scope of works that adequately identifies the damage that needs to be repaired as a result of the storm event.”
- Inadequate claim investigation secondary · upheld
“I do not accept that the insurer's quote can still be current because it is dated 6 October 2021.”
- Delay secondary · unclear
“Given it has been almost 18 months since the storm event, if the insurer chooses to repair the damage, it needs to do so within the near future.”
Subjects and remedies
home or building damagenatural disasterpay compensationprovide documentsreassess claim
Text of the determination
Determination
Case number 871717
Financial firm AAI Limited
Determination | Case number: 871717 Page 2 of 8
Case number: 871717 30 March 2023
1 Determination overview
1.1 Complaint
The complainant holds a landlord’s insurance policy with the financial firm (insurer).
The complainant lodged a claim for damage to his property following a storm on 1 October
2021. The insurer accepted liability for the internal resultant damage but said that damage to
the roof was caused by maintenance issues. The insurer said it could not repair the internal
damage until the maintenance issues were rectified.
The complainant accepted this and repaired the roof in accordance with the
recommendations in the insurer’s builder’s report. Fol lowing this, water entered the property
again. The insurer sent out its builder who identified further maintenance that needs to be
attended to.
The complainant is critical of the insurer. He says all maintenance issues should have been
identified in the b uilder’s first report.
The insurer has decided to cash settle the complainant for the internal damage. This
complaint is about how the claim for the internal damage should be resolved.
1.2 Issues and key findings
How should the claim be resolved?
At present, there is no scope of works that adequately identifies the damage that needs to be
repaired as a result of the storm event. This needs to be resolved before the insurer decides
to repair the damage or cash settle the complainant in accordance with the terms and
conditions of the policy.
Why is the outcome fair?
The outcome is fair because the insurer should be able to assess its liability in accordance
with the terms and conditions of the policy and be entitled to repair the damage if its builder is
available and prepared to do so. Otherwise, the insurer should be able to cash settle the
complainant on the basis of its builder ’ s quote plus a contingency to reflect the transfer of risk
from the insurer to the complainant.
Given it has been almost 18 months since the storm event, if the insurer chooses to repair the
damage, it needs to do so within the near future so that the complainant can move forward
and relet the property.
Determination | Case number: 871717 Page 3 of 8
1.3 Determination
This determination is in favour of the complainant. Within 14 days of the insurer receiving
notice the complainant accepts this determination:
The parties are to appoint an independent builder to inspect the property and provide a full
scope of works for all of the required repairs. This should include works to require all of the
internal damage to the property arising from the storm event. The expert should be one
agreed between the parties. This can be done by the insurer providing a list of three
builders and the complainant can choose one.
Within 14 days of the agreed scope of works being received, the insurer is to decide
whether its builder will repair the or to cash settle the complainant. If it decides to cash
settle the complainant, it is to pay the quoted amount from its builder plus a 20%
contingency to reflect the transfer of risk to the complainant.
If the insurer’s builder would not be able to complete the works, the complainant’s builder
is to prepare a quote for the cost of repairing the damage that would be actionable by the
complainant. The insurer is then to cash settle the complainant on that basis.
The insurer is to pay the complainant’s professional costs of obtaining the report from F7
upon the provision of an invoice or receipt.
Determination | Case number: 871717 Page 4 of 8
2 Reasons for determination
2.1 Is the insurer liable for the additional damage?
At present, there is no scope of works that adequately identifies the damage that needs to be
repaired as a result of the storm event. This needs to be resolved before the insurer decides
to repair the damage or cash settle the complainant in accordance with the terms and
conditions of the policy.
Complainant has established a valid claim and roof is excluded
It is established insurance law that the complainant carries the initial onus to show that the
terms and conditions of the relevant insurance policy cover the loss.
Once the complainant establishes a valid claim, the onus then shifts to the insurer to
demonstrate the loss is not covered, either by way of one of the policy exclusions or on some
other basis.
The policy covers damage for storm. The complainant says his roof was damaged in a storm
on about 1 October 2021. On that basis, I accept that he has made a valid claim.
The insurer says that the damage to the roof is excluded under the terms and conditions of
the policy because the policy excludes damage caused by a lack of maintenance. It is not in
dispute that the roof has cracked tiles which were not damaged in the storm. The complainant
accepts that the roof required maintenance and has attended to the maintenance identified.
There is internal damage because of the storm which is covered under the terms and
conditions of the policy. This dispute is about how much it will cost to repair that damage.
There is a dispute about the cost to repair the damage
The insurer engaged JWBS to provide a quote to repair the internal damage. The quote dated
6 October 2021 says it will cost $7,421.04 to repair the internal damage.
The complainant obtained his own quote from PBG dated 18 November 2022. This quote
says that it will cost $19,032.53 to repair the damage.
The complainant says the insurer’s quote is out of date, being more than 18 months old.
The insurer disputes that the complainant’s quote is reasonable because:
$157.50 an hour for drying and demolition work is excessive
Line item included for replacement of wall plastering in bathroom – there is no indication
this is required
Line item for replacement of ceiling in the lounge room; there is no indication the entire
33m2 ceiling is required to be replaced; onsite dual assessment may be effective in
determining exact requirements as difficult to see from photos
Assessor notes that JWBS is able to warrant repairs and assessor notes as per the PDS
wording, we will not pay more than the assessed quote to repair or rebuild on a ‘new for
old basis’
the quote is not valid as there is no ABN.
The complainant has provided a further report from F7 which is undated. This was received
by AFCA and sent to the insurer on 28 February 2023. The insurer has not provided a
response to this report. F7 say:
Determination | Case number: 871717 Page 5 of 8
there is internal water damage and the property has some minor structural movement.
Plasterboard ceiling linings and insulation and wall linings were affected as a result of the
storm damage.
12m2 of the living area needs to be replaced and there is water related damage to the
social cove cornice and bulk head in the kitchen
The cost to repair the damage is $12,721, which included a builder’s margin of 19%.
Policy sets out how claims will be settled
The policy sets out how the insurer will settle building claims. See section 3.2 below for the
relevant policy wording.
Essentially, the policy provides the insurer with a choice about whether to repair the damage
(if they have a builder available) or cash settle the complainant the cost of repairing the
damage. If the insurer’s builder is available to repair the damage the n the complainant will be
cash settled on the amount it would cost the insurer using its own builder . If the insurer’s
builder is not available to repair the damage, the complainant will be cash settled on the basis
of a reasonable quote provided by his own builder.
The damage requires further assessment
There have been delays in this matter because the complainant needed to complete repairs
to the roof before the internal damage could be repaired. The repair works to the roof have
been completed.
It has b een over 12 months since the insurer’s builder has inspected the property. On that
basis, I accept there is some uncertainty about the extent of the damage at the property. I do
not accept that the insurer’s quote can still be current because it is dated 6 October 2021.
The insurer has raised some legitimate issues with the complainant’s quote because it
includes items which the insurer disputes are within the scope of repair works required. I
accept this as I note that the complainant’s expert report says that 12m square of the ceiling
lining is damaged. However, the complainant’s builder’s quote says that 33m square needs to
be removed and replaced.
The complainant’s report from F7 differs from the earlier reports provided and there is no
evidence the insurer agrees with the scope of works provided. I also note that the F7 report
does not state that it will complete the works on the costing provided.
From my review of the file, there is no indication that the insurer’s builder is unable to repair
the damage. In the circumstances, it is only fair that the insurer be given the opportunity to
repair the damage or cash settle in accordance with the terms and conditions of the policy
now that the maintenance related issues to the roof have been completed.
Th e insurer has suggested a dual onsite inspection between its builder and the complainant’s
builder may be the most appropriate way to deal with what items need to be repaired
internally. I do not accept this is the most practical way to resolve the dispute between the
parties, and an independent expert would be preferable. The matter should be dealt with as
set out in section 1.3 above.
2.2 Why is the outcome fair?
The outcome is fair because the insurer should be able to assess its liability in accordance
with the terms and conditions of the policy and be entitled to repair the damage if its builder is
available and prepared to do so. Otherwise, the insurer should be able to cash settle the
Determination | Case number: 871717 Page 6 of 8
complainant on the basis of its builder ’ s quote plus a contingency to reflect the transfer of risk
from the insurer to the complainant.
Given it has been almost 18 months since the storm event, if the insurer chooses to repair the
damage, it needs to do so within the near future so that the complainant can move forward
and relet the property.
Determination | Case number: 871717 Page 7 of 8
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
3.2 Relevant provisions of the policy (dated 18 September
2020)
Pages 84 and 85
How we settle building claims
We will aim to use a member of our supplier network to repair or rebuild the
damage to the building. Sometimes, this is not always possible e.g. if there is pre-
existing damage. This will determine how the building claim will be settled.
When a me mber from our supplier network can complete the repair or
rebuild
Determination | Case number: 871717 Page 8 of 8
When your claim for loss or damage to the building is covered, we will engage a
builder from our supplier network to prepare a scope of works and provide a quote
on the cost to repair or rebuild the building on a `new for old’ basis.
Once the scope of works and quote is provided to us, we will arrange for it to be
assessed. This will involve reviewing the quote to make sure that the quote is
appropriate and reasonable for the scope of works. This includes a consideration
of the appropriateness of materials, repair method, labour and material costs and
overall cost effectiveness.
If your policy has a building sum insured
If the amount of the assessed quote to repair or rebuild the building is less than
the building sum insured, we will offer you the choice to have the building repaired
or rebuilt (based on the recommendation of our builder).
If you accept the offer - The builder we engage will complete the repair or rebuild
on a ‘new for old’ basis.
If you choose to not accept the offer - You will be paid the amount of the
assessed quote to repair or rebuild on a ‘new for old’ basis.
Note: this amount to repair or rebuild may be less than what it would cost you to
arrange the repairs or rebuild with your own builder. We are able to secure
supplier discounts from within our supplier network.
When a me mber of our supplier network is unable to complete the repair or
rebuild and you have a building sum insured
When your claim for loss or damage to the building is covered and a member of
our supplier network is unable to complete the repair or rebuild, we will ask you to
engage a builder to provide a scope of works and provide a quote on the cost to
repair or rebuild the building on a `new for old’ basis.
Once the scope of works and quote is provided to us, we will arrange for it to be
assessed. This will involve reviewing the quote to determine it is appropriate and
reasonable for the scope of works. This includes a consideration of the
appropriateness of materials, repair method, labour and material costs and overall
cost effectiveness.
If the quote is appropriate and reasonable for the scope of works, we will then pay
you the assessed amount. If it is not, the quote may be adjusted. This may
include, adjusting the scope of works or the quote. We will then pay you the
adjusted amount of the quote.
If we pay you for the repair or rebuild, the Lifetime guarantee on building repairs
does not apply see page 95.