Home / IAG / Determination 869463

Determination 869463

Claim settlement amount for impact damage to home building

FirmIAG
Decided2022-12-20
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$69,098
Non-financial loss$1,500
Amount claimed$171,617
SourceAFCA PDF

Summary

A customer's car struck the complainants' farm home and the parties disputed repair costs. AFCA found the insurer should increase its building settlement to $69,097.99, waive the excess, and pay $1,500 for non-financial loss due to delays.

The insurer may rely on the policy terms and the CFT engineering scope of works, but delays and poor communication caused an unusual degree of inconvenience warranting compensation under AFCA Rule D3.3.

Issues

Subjects and remedies

business interruptionhome or building damagemotor vehicle collisionpay claimpay non financial loss

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination Case number 869463 Financial firm Insurance Australia Limited Determination | Case number: 869463 Page 1 of 6 Case number: 869463 16 December 2022 1 Determination overview 1.1 Complaint The complainants held a home building policy with the financial firm (insurer). A claim was lodged for damage sustained after a customer’s car ran into the north -east corner of the home on the 12 February 2022. The insurer accepted liability for impact damage to the home, but a dispute has arisen as to the cost of repairs. The insurer has offered the complainants $66,718.91 based on a quote from its builder MC plus a 15% uplift for contingencies. The complainants rejected the offer and maintain their quotes, obtained from LP of $171,616.50 and from HC of $162,168.60, fairly represent the damage sustained. In addition, the complainants say they have suffered an unusual degree of physical inconvenience because of the insurer’s claim handling and seeks compensat ion for non-financial loss. 1.2 Issues and key findings Is the insurer’s offer of settlement for the damage claimed fair and reasonable? No. While the panel accepts the insurer can rely upon the quotes provided by MC, the panel believes the insurer should increase the offer for the building repairs to $69,097.99 being the quoted repairs by MC of $57,581.66 plus a 20% allowance for contingencies of $11,516.33. Is the complainant entitled to compensation for non-financial loss? Yes. The panel accepts that the complainants suffered an unusual degree of inconvenience because of the insurer’s claims handling. In the circumstances the panel believes compensation for non-financial loss of $1500 is fair. Why is the outcome fair? There is no dispute the complainants had been provided to policy documents. It is fair for the parties to rely on the terms of the policy to settle the claim. 1.3 Determination This determination is substantially in favour of the insurer. Within 14 days of the complainant’s acceptance of this claim the insurer is to pay the complainants:  $69,097.99 in settlement of the building damage claim  $1,500 as compensation for non-financial loss pursuant to AFCA Rules D3.3  Interest is not payable as the assessments are based on current quotes. Determination | Case number: 869463 Page 2 of 6 2 Reasons for determination 2.1 Is the insurer’s offer of settlement for the damage claimed fair and reasonable? No. While the panel accepts the insurer can rely upon the quotes provided by MC, the panel believes the insurer should increase the offer for the building repairs to $69,097.99 being the quoted repairs by MC of $57,581.66 plus a 20% allowance for contingencies of $11,516.33 Complainants have the onus to establish claim falls within the terms of the policy It is established insurance law that an insured person has the initial onus to prove, on the balance of probabilities (that is, more likely than not), that the loss or damage claimed falls within the terms and condition of the policy. This is commonly called a prima facie or valid claim. The complainants policy is a home building policy that provides cover for a series of insured events including impact damage to the home. ‘ Your home ’ is defined under the policy to include:  Domestic residential buildings at your site that can be locked up  Home improvements at your site - for example, garage, carport or inground pool  Fixtures or items permanently attached or fixed to your home - for example, light fixtures, built in wardrobes, kitchen cupboards and floating floorboards. The policy does not insure amongst over things commercial buildings or commercial farm buildings. Carpets are not part of ‘ your home ’ unless you are a landlord. Circumstances leading to claim not in dispute The complainants home is part of a small vegetable farm specialising in growing and selling eggplants. The complainants say that on or around about 12 February 2022 a customer loss control of their car and collided with the front north east corner of the home coming to rest against a greenhouse. There is no dispute that the home was damaged by impact in the incident and that such damage is covered under the terms of the policy. The dispute is to the extent of the claimable damage and the fair and reasonable costs to repair the accepted damage. Significant variations exist as to the quotes provided by each party. Quotes differ as to cost of repairs The insurer initially obtained a quote dated 23 February 2022 from MC, who had initially been appointed to make safe the property. MC quoted $57,601.03 for repairs plus an allowance for painting the bedroom of $8,637.25. In response the complainants provided a quote from a builder ‘ LP ’ dated 6 March 2022 for $163,256.50. The insurer then had its internal assessor PD complete an assessment of the damage. PD completed the report on 10 March 2022 and found:  Minor impact northern corner of dwelling Determination | Case number: 869463 Page 3 of 6  Minor external cladding damage  Minor damages to foundation piers  Impact damage to front bedroom  Minor damage to wall lining  Minor damage to fixed robe unit  Minor damage eastern wall linings  Evidence within bedroom of unrepaired termite damage. Following receipt of the report, the insurer made a cash settlement offer on 29 March 2022 of $48,793.22. It is not clear why the insurer reached this figure or why it was substantially less than the initial quote provided by MC. After the complainants raised issues with the quote provided and rejected the cash settlement offer, the insurer arranged for a builder and engineer CFT to prepare a report and provide a revised scope of works (SOW). Detailed SOW obtained CFT provided a report and detailed (SOW) on 17 May 2022. CFT recommended the following remedial works:  Repair and replacement of wall cladding to northern and eastern elevations of the home.  Repair and replacement of the eave sheeting adjacent to the master bedroom.  Remove and replace the wall sheeting and timber trims of the northern and eastern walls of the master bedroom.  Remove and replace the mirror built-in wardrobe to the northern elevation of the master bedroom.  Prepare and paint the ceiling and wall sheeting to the entire master bedroom. CFT also considered a high probability of asbestos related material being present and any contractor would be required to arrange the demolition and the disposal of the asbestos. Maintenance related issues were identified in the form of termite affected timber in the northern and eastern walls of the master bedroom. No persuasive evidence has been provided by the complainants to dispute the items contained in the SOW. Revised offer of settlement based on SOW The insurer has obtained a subsequent quote from MC for $57,581.66 based on the SOW from CFT. The insurer subsequently offered to settle the claim for $66,718.91 based on the SOW and quote from MC plus a15% uplift of $8,637.25 for contingencies, an ex gratia payment of $500 and waiving $2,000 excess. Complainants dispute offer of settlement and SOW The complainants rejected this offer and submitted further quotes from LP dated 2 June 2022 for $171,616.50 and HQ dated 8 July 2022 for $162,168.60. The complainants dispute the quote from MC and some of the items contained in the SOW and say:  Metal cladding and asbestos works should be completed as per the LP quote as the asbestos is a continuous run. If you clad one side of the building the other side must be done so it is not out of the ordinary. The complainants have not explained why this is necessary or provided any persuasive evidence to justify this claim. Determination | Case number: 869463 Page 4 of 6  the meter should be a new board due to the current meter being damaged and affected. The panel notes that CFT did not observe any damage to the meter box and no obvious damage to the meter box is shown in any of the photographs. The quote from MC includes testing of the meter box.  the roofing tiles should be taken off as the dwelling needs to be realigned before the tiles are replaced. The complainants have not explained why this is necessary. Based on the report from CFT and quote from MC, the roof was not significantly damaged.  the allowance for the bedroom is in adequate and that if you need to replace one wall the other wall would get damaged and will need to be replaced. It is unclear how the complainants have formed this view. It is not supported by the engineering report from CFT.  MC’s allowance of $1,900 for the replacement wardrobe is inadequate. The panel notes LP had quoted $9,000 for a replacement wardrobe which the panel consider it to be excessive. In the panels view, noting the type of wardrobe shown in the photographs the figure of $1,900 to replace the wardrobe is not unreasonable.  the electrical connections need to be replaced. No evidence has been provided to support this. The complainants’ quotes provided from LP and HC are not itemised and do not show the cost of materials and labour allowed. The insurer’s expert considered the quote from LP was extremely excessive in all lined items. There are number of items that appear to be excessive including allowance of $42,000 for the exterior metal cladding, $7,800 to distribute the metal cladding and an allowance of $9,000 for one new wardrobe. The quote from HC simply provides a quote for external dwelling rectification of $72,660 without any serious breakdown of the various items and $61,964 for the internal damage again without providing any breakdown of the items. The panel does not consider either quote from LP or HC to be reliable or consistent with the SOW provided from CFT. The quotes also include costs of replacing the posts and repairs to the exterior lining of the greenhouse. The panel notes that the greenhouse is not a domestic residential building within the terms of the policy but part of the commercial farm buildings on the property. As such the greenhouse is not covered under the terms of the policy. Fair for the insurer to increase offer. In the panels view, in the absence of any persuasive evidence to dispute the SOW provided by CFT, the quote by MC is preferable. The panel accepts it was fair and reasonable for the insurer to base its offer of settlement on the SOW and quote provided by MC of $57,581.66. In the panels view however given the nature of the damage it is fair to allow an uplift of 20% ($11,516.33) to cover contingencies that may arise in any repair process. In the panels view it is fair for the insurer to increase the offer to cash settle the claim for the damage to the building to $69,097.99. The panel also considers, in the circumstances, it is appropriate for the insurer to waive any excess. Determination | Case number: 869463 Page 5 of 6 2.2 Is the complainant entitled to compensation for non- financial loss? AFCA can award compensation for non-financial loss. Under AFCA Rule D3.3 AFCA may award compensation for non-financial loss where a complainant suffers an unusual degree of physical inconvenience or time taken to resolve a situation or interference with a complainant’s expectations of enjoyment or peace of mind. AFCA expects a complainant to be moderately robust and bear the normal degree of inconvenience experienced during a claim process and to take reasonable steps to manage the situation. The complainants have suffered an unusual degree of inconvenience. The complainants note that it took the insurer nearly six weeks to provide the initial builder’s quote and that there were delays in obtaining a response from the insurer with the insurer unable to provide updates. The panel considers the circumstances of the claim were straight forward. The insurer had an assessment and SOW as early as 23 February 2022. Despite this no offer was made until the 29 March 2022 and was then considerably lower than both the assessment provided by MC and the complainant’s quote from LP. The insurer did not arrange for an engineer to assess the building until the 17 May 2022. This more than three months after the incident. It did not put a revised offer to the complainant or provide the various reports until 31 August 2022 when responding to AFCA. The panel accepts there may have been delays with the insurer’s technical assessor reviewing revised quotes due to the Easter holiday period. The insurer has not however provided any explanation as to why it did not notify the complainants on receipt of the SOW and report from the engineer CFT. The report was received on 17 May 2022 but not provided until 31 August 2022, more than three months later. The complaint was already with AFCA. In the panels view the delays have caused the complainants an unusual degree of physical inconvenience and time taken to resolve the situation. While the panel accepts part of the delays have been caused by the complainant’s dispute of the original offers , this matter could have been dealt with much earlier had the insurer exchanged the information with the complainant. In the circumstances, it is fair that the insurer pays the complainant $1,500 compensation for non-financial loss. 2.3 Why is the outcome fair? The outcome is fair as the insurer is entitled to rely upon the terms and conditions of the policy when determining the extent of its liability. The insurer’s liability is limited to damage to the building as defined within the terms of the policy and does not cover damage to carpets and or the greenhouse. The insurer’s offer is based a SOW obtained from an engineer and there is no persuasive evidence that the SOW or the insurer’s builder’s quote is unreasonable. The outcome recognises the inconvenience suffered by the complainant. Determination | Case number: 869463 Page 6 of 6 3 Supporting information 3.1 The AFCA process AFCA’s approach is b ased on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. A panel determined this matter Due to the nature of this complaint, we referred it to a panel for determination. The panel includes:  an ombudsman  a member with significant experience in consumer and small business advocacy  a member with extensive experience in insurance. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.