Home / Youi / Determination 869062

Determination 869062

Storm damage claim declined due to incomplete underpinning works

FirmYoui
Decided2022-12-07
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainant's home suffered collapse after storm water entered incomplete underpinning works during a COVID-19 construction shutdown, and the insurer declined the claim. AFCA found the storm was an insured concurrent proximate cause, the exclusions did not apply, and the insurer must cash settle reasonable repair costs with statutory interest.

Storm was an insured event and concurrent with the uninsured open underpinning; the insured event prevails, and the 'in the course of construction', opening, and in-ground structure exclusions were not established.

Issues

Subjects and remedies

home or building damagenatural disasterpay compensationpay interestreassess claim

Related

All Youi determinations · Find similar determinations

Text of the determination

Determination Case number 869062 Financial firm Youi Pty Ltd Determination | Case number: 869062 Page 1 of 9 Case number: 869062 28 November 2022 1 Determination overview 1.1 Complaint The complainant holds a home insurance policy with the financial firm (insurer). He lodged a claim for damage following a storm and an earthquake. The complainant had begun underpinning works at the insured property when a COVID-19 restriction on construction work began on 20 September 2020, meaning some of the footings were left unsupported. There was an earthquake event two days later, and also a storm at around that time, following which a section of the property collapsed. The insurer assessed the damage and declined the claim, saying the cause of the damage was the underpinning works being left open, which is not covered under the policy. It also relies on exclusions for damage to a building under construction, and for rain entering the building through an opening made for renovations or repairs. The complainant does not accept that decision. He believes the claim should be paid. 1.2 Issues and key findings Is the insurer liable for the claim? Yes. The insurer is liable to the full extent of the claim. The available evidence shows, on balance, the concurrent proximate causes of the damage were the storm (an insured event) and the state of the incomplete underpinning works at the time (which is not an insured event). That means the insured event prevails. The building was not ‘ in the course of construction’; nor was the underpinning void /opening part of the ‘building s ’ . None of the exclusions relied on by the insurer applies, nor has the insurer shown any other entitlement to decline the claim. Why is the outcome fair? The complainant has established a valid claim for damage from a storm. The insurer has not established exclusions apply, or that it has any other basis for denying the claim. It would not be fair for the insurer to decline the claim in the particular circumstances. 1.3 Determination This determination is in favour of the complainant. The insurer is required to cover the claim- related damage in accordance with the policy terms and conditions. If the complainant has already conducted the repairs, then the insurer must cash settle as set out in section 2.1 below. Determination | Case number: 869062 Page 2 of 9 2 Reasons for determination 2.1 Is the insurer liable for the claim? Onus is on the complainant to establish a valid claim The complainant is required to show, on the balance of probabilities, he has suffered a loss caused by a risk insured against under the policy. This is known as a ‘valid’ or prima facie claim. The policy provides cover for ‘Insured Events’ to the property that occur during the Period of Insurance. The listed Insured Events include ‘Storm’ and ‘Earthquake’ as follows:  cover applies for loss or damage caused to the insured property ‘ as a direct result of …[earthquake]…occurring for up to 72 hours after the occurrence…’…  cover applies for loss or damage to the insured proper ty by ‘ storm, lightning, wind, hail, snow and storm water overflow from roof gutters and their downpipes or from the area immediately around the premises ’ . So, to establish a valid claim, the complainant must show, on balance, the damage being claimed occurred during the period of insurance and was caused by an insured event. However, that cover is subject to terms, conditions and exclusions. Once the complainant establishes a valid claim, the insurer is liable for the loss unless it shows an exclusion applies or it is otherwise entitled to deny the claim. The insurer has the onus of proof in establishing this. The policy specifically excludes cover for loss or damage caused by: rain, wind, hail or snow entering the buildings through open windows, doors or openings made for alterations, renovations or repairs;… Cover for ‘buildings’ under the policy excludes ‘buildings in the course of construction’. Experts broadly agree about contributory causes of the damage The complainant says he was conducting underpinning works to his home when Covid-19 restrictions relating to the construction industry were imposed and work onsite had to stop. Some underpinning work had been completed to other sections of the home, but one corner of the house had been excavated with no supports put in place when the lockdown began on 20 September 2021. The site remained closed until 18 October 2021, when the tradespeople notified the complainant that a wall of the home had collapsed. The insurer organised an engineer (HE) to attend and determine the cause of the damage. HE determined that the excavation of the footings and the delay in pouring the foundation concrete was the cause of the collapse. He did not comment on any other contributing factors in his report. The complainant organised an engineer (NK) to inspect the damage. NK concluded that water runoff from storm conditions had saturated the soils supporting the footings and caused Determination | Case number: 869062 Page 3 of 9 the subsequent collapse. He also observed the earthquake could have contributed to the loss of stability, but this comment is not conclusive and does not analyse the earthquake ’ s possible impact on the home. HE reviewed NK’s report and agreed that stormwater would have contributed to the loss of bearing capacity of the soil supporting the footings. He maintained that the excavation of the footings allowed this to occur, since if the footing works had been completed or relevant temporary support been put in place, the damage likely would not have happened. HE explained that underpinning excavations are generally filled within 24 hours to reduce the chance of any damage occurring to the home due to movement. HE said the longer excavations are left open, the more likely damage will happen. This could be due to concentrated loadings or due to stormwater entering the void. The complainant provided weather data showing the rainfall in the period between the lockdown commencing and the collapse being discovered. HE and NK both reference storm water saturating the soils and NK specifically notes 85mm of rainfall. Although the exact date of the collapse is not clear since no-one was at the site, information supplied by the insurer from a mapping service shows no evidence of collapse on 26 September 2021, and the complainant says his builder notified him of the collapse on 18 October 2021. The earthquake is reported to have happened on 22 September 2021. Given the evidence that the likely timing of the actual collapse was 4 days later (and the absence of other supporting information), the panel is not satisfied the complainant has established, on balance, a valid claim for damage caused by the earthquake. However, the panel is satisfied the complainant has shown, on balance, he has a valid claim for damage caused by storm. The question is then the extent to which the incomplete state of the underpinning work also contributed to the damage, whether that is covered under the policy or whether exclusions apply. Concurrent proximate causes were storm and incomplete underpinning Determining the proximate cause of a loss is a question of fact, depending on the circumstances in each case. It is well established law that a proximate cause is not necessarily the first, the last or the sole cause of the loss. It is the effective, dominant or operative cause of the loss. There may be circumstances where it is reasonable to conclude that there were two causes, operating contemporaneously, which were equal or concurrent in their efficiency in bringing about the damage. Concurrent causes can occur where there are two or more events or situations, each of which is independently capable of causing the loss, or where there are two events each of which, without the other, could not have caused the loss. If one of those causes was an insured event, and the other an excluded event, then the excluded event would prevail. However, the courts have held that if one of the causes was an insured event and the other was not excluded, then the insured event prevails and the claim should be accepted. Based on the available evidence, the panel is satisfied, on balance, the incomplete underpinning work and the storm (during which rainwater entered the underpinning void and surrounding soils) were interdependent concurrent proximate causes of the damage. Determination | Case number: 869062 Page 4 of 9 Building was not ‘ in the course of construction’ The insurer submits the incomplete underpinning works and delays are not covered under the policy, and says exclusions also apply. The insurer points out that cover for storm damage to ‘buildings’ excludes ‘buildings in the course of construction’. The complainant argues he was completing required maintenance work, not constructing the home, and so that exclusion should not apply. The Macquarie Dictionary defines ‘construction’ as ‘ the act or art of constructing’. It defines ‘construct’ as ‘to form by putting together parts; build; frame; devise’. The policy does not define ‘construction’ . However within the product disclosure statement (PDS), as well as references to ‘construction’, there are references to ‘major repairs’, ‘repairs’, ‘earthworks’, ‘alterations’, ‘maintenance’ and ‘renovation’. That indicates the policy distinguishes between those types of building work. The panel is satisfied that, in that context and consistent with the dictionary definition, ‘construction’ is intended to apply to initial or original building works, rather than repair/maintenance work being conducted in relation to existing structures. Having regard to those distinctions in the policy wording, the circumstances giving rise to the claim, and the evidence overall, the panel does not consider the nature of the work being conducted at the insured property represents ‘construction’. Instead, it is reasonable to regard it as repair and maintenance. That means the insurer may not rely on the exclusion for damage to ‘buildings in the course of construction’ to decline the claim. Stormwater did not enter the ‘buildings’ The insurer also says the policy does not cover ‘water entering the buildings through … openings made for alterations, renovations or repairs’. T he policy definition of ‘buildings’ is: the private domestic residence and other structures at the premises, including permanently attached fixtures, fittings and structural improvements, but excluding earthworks. The complainant’s engineer NK stated: The excavation for the underpinning was inundated with water, submerging the soil left between the pins, affecting the stability of the soils underneath the existing footings that were left exposed (Emphasis added). The insurer’s engineer, HE, also referred to the ‘underpinning excavation’. The panel considers the area excavated for the new underpinning might reasonably be regarded as ‘earthworks’ (involving, as it did, the removal of earth to enable the underpinning repairs to be completed), and therefore excluded fro m the policy definition of ‘building s ’ for that reason. Determination | Case number: 869062 Page 5 of 9 In any case, however, the panel does not consider the underpinning void (while an ‘opening’ in the ordinary sense of the word, and made for repair) w as an opening in the ‘building’. Instead, the photographs of the void show it was not inside the house structure, but was an opening in the ground outside and next to the building. The expert evidence shows water entered the underpinning void and the surrounding exposed soil. The panel is satisfied that does not represent water entering the building. That exclusion also does not apply. Water did not leak down the side of ‘in - ground structures’ The insurer also raised the exclusion for ‘ loss or damage to in-ground structures caused by water leaking down the sides, against the sides or getting underneath them. These in-ground structures include but are not limited to items such as underground water tanks, septic tanks, ponds, pools or spas’. The policy does not define ‘in - ground’, however given the nature of the examples given, the panel is not satisfied the exclusion applies to the circumstances of this claim. The ‘ structure ’ in this case is presumably the house itself, which is for practical purposes above ground (even if some elements of it are below ground). As well, this was not a case of water leaking down or against the sides of the house; it was instead simply a case of water directly entering the void while also saturating the exposed surrounding soil. The panel does not accept that exclusion applies. Insurer not entitled to decline claim Having considered all the available evidence, the panel is not satisfied the insurer has established, on balance, the exclusions on which it relies have been shown to apply. It is therefore not entitled to decline the claim on that basis. As noted above, the complainant has established a valid claim for damage from the insured event of ‘storm’. The concurrent proximate cause of the damage was the underpinning void being left open, which is not an exclusion, but is simply an uninsured event. In this case, the complainant is entitled to recover on the basis that the loss was the result of the operation of an insured event. That means the insurer is liable for the claim. Insurer must reimburse reasonable cost of claim-related repairs The panel understands the complainant has now completed repairs to the property. The insurer had not initially been able to obtain a comprehensive quote for all the claim- related work, given safety concerns at the time of the initial assessment; and at this stage, the complainant has also not provided quotes/invoices for the work he has since undertaken. However, the insurer did provide a quote for $45,682.91 from builder JL, dated 14 December 2021. The complainant’s response to the JL quote is that it omits the following: gas and electricity repairs necessitated when pipes were damaged by falling bricks; internal damage to the house (plaster walls, cornices, flooring, skirting boards); veranda, gutter and stormwater pipes; roof and eaves. The complainant points out he had been told by the insurer not to recommence the underpinning work pending the claim decision being made. He says that in that two month period, the integrity of the house was further compromised and more damage occurred. Determination | Case number: 869062 Page 6 of 9 The insurer is liable for the claim. That includes liability for additional damage which occurred as a consequence of any delay in attending to the necessary work. Given the repairs have now been completed, it is fair and appropriate that the claim be cash settled. The complainant is required to provide the insurer with evidence of the scope of work undertaken and costs he incurred in repairing the property (such as paid invoices). To be clear, that information will need to clearly distinguish between claim-related work and any other additional work the complainant may have undertaken at the time. The insurer is entitled to assess the reasonableness of those costs. It is required to settle the claim (subject to applicable policy limits) by paying the complainant the reasonable costs he incurred for the claim-related damage, and otherwise in accordance with the policy terms and conditions. Statutory interest (under section 57 of the Insurance Contracts Act 1984 ) is to be added to any cash settlement, calculated from the date the respective costs were incurred by the complainant up to the date of settlement. 2.2 Why is the outcome fair? The complainant has established a valid claim under the policy for damage caused by a storm event. The insurer has not established exclusions apply, nor any other basis on which it is entitled to decline the claim. It would not be fair for the insurer to deny liability in the circumstances. Determination | Case number: 869062 Page 7 of 9 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. A panel determined this matter Due to the nature of this complaint, we referred it to a panel for determination. The panel includes:  an ombudsman  a member with significant experience in consumer and small business advocacy  a member with extensive experience in the insurance industry. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. Determination | Case number: 869062 Page 8 of 9 3.2 Expert reports Record Key points Financial firm’s e ngineer ( HE) Report 1 December 2021 HE f urther email comments 14 February 2022 HE f urther email comments 27 June 2022  Underpinning excavation had been open for approximately 3 weeks before the collapse and is deemed to be the cause of the collapse damage  Footing system slumping into the void of the underpin  Loss of bearing and collapse of footing to the North - Eastern corner has caused significant damage to external and internal skins of brickwork  The amount of water within the underpin voids at the time of inspection indicates the vo ids were open for some period of time and the surrounding soils softened  Agrees with the conclusion that the cause of collapse is bearing failure due to water ingress and possible heavy rainfall to soils around the support footings  Earthquake possib ly con tributed to instabilities  It is common practice to fill the excavation void within 24 hours to mitigate as best as possible any bearing issues due to concentrated loadings, weat her affects or anything else that could cause damage  The longer an excavation i s open, the greater the risk of collapse over time Complainant’s engineer ( NK ) Report 10 June 2022  Excavated soil or the underpinning work was left open with no concrete poured under the exposed footings or any temporary support being installed due to the state - wide lockdown  Common practice for concreting work for thes e excavations to be completed as soon as possible after the excavation is approved by the building surveyor, preferably within 24 hours  Rainwat er runoff was up to 85mm over a short period of time  The excavation for the underpinning was inundated with water, submerging the soil left between the pins, affecting the stability of the soils underneath the existing footings that were left expos ed  Supporting soil between the excavated pins became submerged due to heavy rainfall and weakened, resulting in the loss of soil support of the footings and subsequently causing them to settle. This caused the claimed damages.  Earthquake would have contributed to the loss of integrit y to the footing support system 3.3 Relevant policy extracts How we settle your claim 1. If you are claiming for buildings If we can, we will settle your buildings claim by: Determination | Case number: 869062 Page 9 of 9  repairing the damaged parts of your buildings if it is both possible for the parts to be repaired and economical for us to repair those parts because the cost of repair is less than the cost of rebuilding; or  rebuilding the damaged part of your buildings if it is either not possible for those parts to be repaired or not economical for us to repair those parts because the cost of repair is more than the cost of rebuilding… If we cannot repair or rebuild the damaged part of your buildings, we will pay you an amount equal to the reasonable cost that you would incur to repair or rebuild the buildings up to the limits noted in your policy. We will undertake a search of the market to determine what this cost would be in your area, based on factors including scope of works and comparison quotes from repairers or builders.