Escape of liquid claim settlement - insurer's assessment of liability for building damage and footings
Text of the determination
Determination
Case number 866541
Financial firm AAI Limited
Case number: 866541 12 December 2022
1 Determination overview
1.1 Complaint
The complaint holds a home and contents policy with the financial firm (insurer). On 16
December 2020, a claim was lodged for significant damage to the insured building after an
escape of liquid event caused by a burst water pipe.
The insurer has accepted the claim. The insurer is seeking to limit its liability to damage it has
assessed to be consistent with the event. The complainant disagrees with the insurer‟s
assessment and believes the claim should be settled for the sum insured on the basis the
insured building is uneconomical to repair (total loss).
The insurer offered to cash settle its liability for the event related damages for $200,431.30
including allowances and a 20% contingency. Alternatively, the insurer has offered to
complete and warrant event related repairs once the complainant completes the footing
strengthening or underpinning works at the premises.
1.2 Issues and key findings
Is the insurer’s assessment of its liability under the claim fair?
No. The insurer‟s assessment of its liability and final claim settlement offer is not fair in all the
circumstances. The insurer is to increase the level of cover accepted under the claim in line
with section 2.1 of this determination.
Whether the complainant is entitled to compensation?
Based on the available information, the insurer ‟s overall management of this complex claim
has been reasonable in the circumstances. The panel does not believe it would be fair to
require the insurer to pay non-financial loss compensation. However, the insurer is to
reimburse the complainant for expenses incurred in obtaining expert reports up to a maximum
of $5,000 in line with the AFCA Rules.
1.3 Determination
This determination is in favour of the complainant.
The insurer is to authorise and complete the identified damage to the insured building
including the necessary footings strengthening/underpinning works to allow the building
damage repairs to be completed and ensure stabilisation of the site.
Subject to being provided with supporting information, the insurer is to reimburse the
complainant up to $5,000 towards costs incurred in obtaining expert reports.
Determination | Case number: 730453 Page 2 of 10
2 Reasons for determination
2.1 Is the insurer’s assessment of its liability fair?
No. Given the available information and considering what is fair in all the circumstances, the
insurer‟s assessment of its liability and associated claim settlement offer is not fair.
The complainant has established a valid claim
There is no dispute the insured building has suffered significant movement damage because
of the insured escape of liquid event. However, the parties differ in their opinions as to the
appropriate method of repair and costs associated with such repairs.
The policy covers the insured property against loss or damage caused by one or more of the
listed insured events, including „Escape of liquid‟ . Cover under these benefits is subject to the
conditions, limitations and exclusions specified in the product disclosure statement (PDS).
The policy schedule confirms the building sum insured at the time of the loss was $685,600.
The complainant believes the damage is so significant and the repairs required to return the
building to its pre-event condition render it uneconomical to repair. That is the complainant
believes the building needs a complete rebuild. However, the insurer says the insured
building remains repairable and not all the damage claimed is covered under the policy.
Given a valid claim exists, the onus rests with the insurer to show, on balance, an entitlement
to limit is liability under the claim in line with the policy provisions or otherwise.
The insurer is seeking to limit its liability under the claim
The insurer says the policy excludes loss or damage caused by ground movement. This
includes erosion, vibration, subsidence, landslip, landslide, mudslide, collapse, shrinkage or
any other earth movement. The insurer has assessed its liability under the claim to the
amount of $260,976.15. The insurer says this amount includes the following:
J‟s repair q uote $127,413.98
20 % contingency for damage during
drying period
$19,112.10
20% Building contingency $33,405.22
Removal of d rying e quipment $500.00
Mould remediation $5,000.00
Wall r ebuild $10,000.00
Future engineering costs $5,000.00
Temporary a ccommodation $51,149.85
Claims preparation fees $5,000
Supplementary living expenses $1,000
Storage of u ndamaged c ontents
(estimate $300 per month x 6 months)
$1,800.00
Counselling $1,500
Balance of food spoilage $395
Less policy excess $300
Total Settlement $260,976.15
Determination | Case number: 730453 Page 3 of 10
The insurer says the movement and cracking damage caused by the event is limited to the
central area of the home. This includes damage to the kitchen cupboards and joinery, the
skirting boards in the living room and the solid flooring in the kitchen and living room. The
insurer says not all internal walls require to be rebuilt. The insurer has allowed for two walls to
be rebuilt within its cash settlement offer.
The insurer says the damage to the footings are excluded because of breaches of the
building code and that this damage relates to long-term soil movement. It says no damage
has occurred to the footings due to the escape of liquid event with information showing
historic movement issues within the footings. Given this, the insurer places liability for any
footings strengthening or underpinning works with the complainant.
Consultants have provided conflicting opinions
The insurer relies on the investigations and associated reports provided by its appointed
consu ltants „S‟ (loss adjusters), „IE‟ (engineers) and „DK‟ (engineers). The complainant in
maintaining his position relies on his appointed consultants „CC‟ (builder), ST (engineers) and
„LN‟ (geotechnical engineer).
The panel accepts the consultants, for the most part, are in agreeance that:
the insured building presents with significant widespread damage to the internal structure
the escape of liquid event is the dominant cause and/or contributing factor for a majority of
the damage
the insured building has been the subject of some degree of foundational movement in the
past with evidence of previous damage (cracking) having been repaired.
The parties differ in their opinions with respect to the extent of the damage that is to be
associated with the insured event, their preferred method of repair and which party is liable
for recommended works to the building‟s footings.
In its report dated 6 January 2021, IE confirms the foundation soils are moderately to highly
reactive clay soils. It says the soils will expand significantly when the moisture content
increases and shrink significantly when the moisture content reduces. IE says the cracking
damage to the home is consistent with differential footing movement. The insured building‟s
superstructure, specifically around door openings, cornices and wall junctions has
experienced foundation soil heave due to the escape of liquid event.
IE says the increase in moisture to drier underfloor soil will cause the reactive clay soil to
swell and lift the strip footing beams. IE recommends that the existing cracks should not be
repaired until after the foundation soils have fully recovered from the leak and stabilised. In
IE‟s experience, it would take several summers for the foundation soils to return to pre-
leakage condition. Any repairs completed before this cannot be guaranteed because the risk
of ongoing differential footing movement will disrupt repairs, even shortly after they are
completed.
IE notes, based on previous repairs (before the escape of liquid event), in its opinion even
after the influence of the leak on the foundation soils has resolved, the home will continue to
experience foundation related movement and cracking. IE confirms the moisture within the
foundation soils has spread beyond the leak site causing heaving in soil under the footings
further away from the leak and resultant damage to walls.
CC first inspected the insured property on 4 March 2021 and then again on 29 March 2021.
CC noted a strong smell of mould and dampness at both visits and says the home was not in
a liveable state. CC says even if only cosmetic repairs were to be completed to make the
Determination | Case number: 730453 Page 4 of 10
home safe, this would include repairs to many of the internal walls, ceilings, wet areas
(waterproofing compromised) and a new kitchen.
CC formed the opinion the footings had been severely undermined with possible
underpinning required and recommended appointment of an engineer. CC‟s provides an
initial cost of repairs of $280,000.00. However, CC says if the engineer determines the
footings are extensively damaged, then it would not be unfeasible to complete repairs. This is
because re-building from the inside out would be too costly, both financially and time
consuming.
ST was appointed to assess the insured property and provided a report dated 9 April 2021.
ST says the leak event deposited significant amounts of water into the foundation soils. This
resulted in heave causing the footings to deflect (upwards) and rotate causing the internal
cracking damage to the home. ST notes the cracking damage was progressively worsening
and noted some historic cracking to external walls, which is to be expected of a 1930‟s Tudor
with double brick walls.
In ST‟s opinion, the natu ral drying of foundation soils could take between 10 to 15 years as
opposed to just „several summers‟ proposed by IE. ST confirms further damage will continue
to occur even after initial temporary works are completed to make the home habitable leaving
the occupants to live in a partially dilapidated building for years to come.
ST recommends that if repairs are to be completed, these should be expedited in one event
to minimise the risk for future damage, ongoing repairs, costs and disruption. This would
require:
propping of the roof framing
remove existing internal walls and footings
new strip footings designed to current standards installed and integrated within existing
external footings
a stiff footing system will accommodate the effects of expected soil shrinkage as the soils
dry out.
On review of ST‟s report, CC says any attempt at remediation would not be worthwhile.
Rebuilding a structure from the inside out whilst maintaining the external structure is not
feasible. Removal of existing footings to build new footings would require removal of all wet
soils and introduction of new fill to be compacted. The home is beyond repair and best of
course of action is a complete rebuild.
In response to the ST‟s report the insurer sought comment from IE which is provided in a
report dated 6 June 2021. IE acknowledges there exists some cracking to the footings and
which have been exacerbated by the escape of liquid event and its impact on the foundation
soils. However, IE then also says the cracks to the footing are historical in nature and its view
any cracking is unrelated to the insured event. IE reiterates its view that any works to the
footing or underpinning cannot be done until the foundation soils dry out (minimum of a few
years).
Dissatisfied with the comments from IE, the complainant appointed geotechnical engineering
experts LN who completed a site inspection on 22 September 2021. LN says at the very least
the cracking damage to the footings was exacerbated by the leak and the future footing
behaviour will be inferior than that prior to the leak. LN also reviewed the two options for
repair put forward by IE and ST. LN formed the opinion that wall replacement on a new
footing proposed by ST is the appropriate method of repair. The reasons for this were noted
as:
Determination | Case number: 730453 Page 5 of 10
the damage category is up to “severe”, and by AS2870 -2011, the appropriate repair
method is “ Extensive repair work involving breaking out and relacing sections of walls
…….” .
as new walls are to be constructed, the new footings supporting the walls must be
designed by present day methods
due to footing rupture from the plumbing leak, the concrete footings now comprise of
individual concrete sections, rather than a continuous footing without footing ruptures. The
future behaviour of the footings is therefore inferior to that existing prior to the plumbing
leak
In LN‟s experience, even with surface ventilation, soil drying over a depth of at least 3m
can take a significantly long time. Given this, IE ‟s proposed method of repairs was
considered not practical.
In response to the ST and LN reports, IE has provided a further report dated 30 November
2021. In this report IE confirms undamaged strip footings can be structurally damaged due to
soil heave. Further, that in its opinion there were no standards or building codes applicable at
the time of the building‟s construction. From IE‟s observations, the solid masonry walls strip
footing beam depth and grillage arrangement appeared to be consistent with those noted in
many eastern suburbs, on clay soil.
IE says, given the soil testing and bore hole samples, the time required for the soil to dry will
take years. IE disagrees with the reference to decades as required drying time, however,
accepts it will be problematic to determine or comment with conclusive evidence, when the
foundation soils will return to pre-event condition. It will take years but not decades and if
underpinning is to be considered, IE recommends underpinning the entire building.
IE goes on to say it saw no evidence of footing beams documented to be replaced having
been damaged by the mains water supply pipe leak event and as such underpinning is not
required.
The insurer appointed engineering consultants DK to review the issue of whether the footings
were damaged. DK says although cracking is evident to some of the footings, it does not
necessarily mean the reinforcement has been damaged. DK says cracking of reinforced
concrete under induced loads is not uncommon, and cracking of concrete from shrinkage is
common. In DK‟s opinion, the footings are unlikely to have been adversely affected by the
pipe leak event.
DK says demolition of all the internal walls and footings to the original dwelling area is not
considered necessary. DK generally agreed mostly with IE‟s proposed repairs, however, says
in addition to this, localised wall demolition and replacement may be undertaken at the southern
end of the wall (around door area) between the kitchen and dining room.
Unfair to expect the complainant and family to live in damaged home for years
Having consider the available information, the panel accepts the insurer has shown, on
balance, the insured building is likely not a total loss for the purpose of the policy. The panel
accepts there exist options to complete the repairs to the insured building. However, for the
reasons stated above, the panel does not accept it would be fair for the insurer to transfer the
responsibility and risk associated with completing the repairs to the complainant.
The panel accepts it may not be decades before the foundation soils dry. However, even the
insurer‟s consultants have accepted it will be „years‟ before the foundation soils return to their
pre-event condition. The panel notes the insurer‟s experts initial estimate was a few
Determination | Case number: 730453 Page 6 of 10
summers. However, in their later reports they say it is problematic to determine when the
foundation soils will return to pre-event condition, but it will take years.
The panel is not satisfied it would be fair in all the circumstances to expect the complainant
and his young family to have to live in a damaged and dilapidated home for years. Photos
show they were living in a damage free home before the escape of liquid event and are
therefore entitled to be returned to the position they were in before the event within a
reasonable period
The expert information includes reference to solutions to counter the expected continuing
foundation movement and associated damage expected to occur whilst the foundation soils
shrink and return to their pre-event condition. The panel is satisfied, all future damage that is
expected to occur due to the escape of liquid event and its impact on the foundation soils,
does fairly fall within the scope of the claim.
This in th e panel‟s opinion means it would not be fair in all the circumstances for the insurer to
pay a cash settlement based on damage apparent now, only to leave the complainant to bear
the expenses of ongoing and re-occurring damage for years whilst the foundation soils dry.
Rather, it is reasonable to require the insurer to ensure adequate repairs and measures
completed to ensure the stability of the home.
Insurer’s assessment of its liability is not fair in all the circumstances
In addition to concern held b y the panel regarding the insurer‟s proposed settlement of the
claim, the panel believes the following information further supports a view that allowing the
insurer to cash settle the claim would not fair in all the circumstances because:
there is no dispute that any repairs completed to the insured building before the foundation
soils return to their pre-event condition will experience damage on an ongoing basis, even
shortly after completion
despite the difference in opinions from the various consultants regarding the estimated
time for the foundation soils to dry and return to the pre-event condition, it is clear this will
not occur for „years‟
given this, it is fair to say that the insurer‟s assessment of the cost of repairs and
associated cash settlement offer is premature and does not account for the ongoing
damage and associated repairs that will arise over the coming years whilst the foundation
soils dry out and shrink
it is not fair in all the circumstances to place the complainant in a position where the cash
settlement funds are utilised to repair the home to a more liveable state now, but then to
be left to bear the costs to repair the ongoing loss and damage that will continue to occur
for years whilst the foundation soils dry and shrink
the insur er‟s cash settlement offer is based on information that has not yet settled on the
best method to address the damage and quotes for repair which provide no guarantee for
the proposed repairs or reasonably account for future damage
the required methodology and repairs, on balance, will be significantly complex, it would
not be fair to transfer the risk of these works to the complainant.
Insurer to cover the footing strengthening/underpinning works
In addition to the requirement to complete repairs to the insured building in a reasonable
timeframe, the panel is of the opinion it is fair to require the insurer to include works to the
footings.
The panel acknowledges there is some, although limited, information that shows the footings
had been subject to some cracking and rotation over the years due to seasonal foundation
Determination | Case number: 730453 Page 7 of 10
movement. However, in line with the information from the insurer‟s consultants this had not
compromised the function of the footings.
There is no information to show the current footings were defective and/or not built to the
requirements and building practices in place at the time of construction. The information
shows the current footings will not be capable of dealing with the impact of the insured event
on the foundation soils. This means the footings and therefore the insured building is
expected to suffer damage for years because of the event, if not addressed appropriately.
This is supported by the information from the engineers including DK who says there will
occur ongoing damage to the concrete footings during the shrinkage (drying) process of the
foundation soils. The panel is of the view that the insurer ‟s liability under the claim is not
limited to just the damage apparent at present. Rather, it‟s liability extends to all damage that
arises from the insured event and works required to address the expected impact of the event
on the insured building.
Therefore, it is fair that the insurer be required to cover all works necessary to repair the
damaged noted as well as such works necessary to counter the impact of the insured event
and to prevent future damage (expected to arise from the insured event). The panel
acknowledges the extent of damage to the footings from the insured event at present may not
be to the degree claimed by ST and LN.
The panel is satisfied, on balance, that the insured event has damaged and/or exacerbated
damage to the footings. It is likely it will continue to cause further damage to the footings. The
information establishes the insurer will have to rebuild certain internal walls. The panel prefers
LN‟s view that these walls will need to be built on new footings, which the panel accepts will
need to be built to current standards.
The experts do not recommend having different types and/or sections within the footings. This
is because having different footings increases the potential for further foundational movement
damage to a building over time. It would not be reasonable to leave the complainant in a
worse off position that he was before the loss.
Given the reasons discussed above and why works to the footings and/or underpinning of the
of the entire building (as recommended by IE) are necessary the panel does not accept it
would be fair in all the circumstances to place liability for these works with the complainant.
Accordingly, in line with the insurer‟s obligations under the policy and considering what is fair
in all the circumstances, the panel determines that the insurer is to authorise and include the
proposed necessary works to the footings. It is suggested that a stiff footing system will
accommodate the effects of expected soil shrinkage as the soils dry out.
Finally, the panel acknowledges the insurer‟s position that the temporary accommodation
benefit under the policy has been exhausted. However, in line with the above findings and
considering what is fair, the panel determines the insurer is to cover the complainant for
temporary accommodation until such time that the insured building is returned to a habitable
condition.
2.2 Is the insurer required to pay compensation?
Compensation payable in some circumstances
AFCA may award compensation (capped at $5,400) if there has been an unusual degree or
extent of physical inconvenience, time taken to resolve a complaint or interference with the
Determination | Case number: 730453 Page 8 of 10
complainant‟s expectation of enjoyment or peace of mind. AFCA takes a conservative
approach to awarding compensation.
The complainant is not entitled to compensation
Despite some delays, the insurer handled the claim promptly and in line with relevant
standards. This is because:
the insurer was entitled to investigate the claim
regular updates were provided to the complainant during the claims process
the investigation was still completed within times set by the general insurance code of
conduct.
Whilst, the panel acknowledges an unusual degree of physical inconvenience and time taken
to provide a decision, the panel accepts that this was due to the complex nature of the claim.
The panel acknowledges circumstances surrounding this claim, the nature of the damage,
conflicting expert reports and determining what is fair in all the circumstances has not been
an easy process. However, as noted above, the panel is satisfied that the insurer made
reasonable attempts to bring the matter to conclusion and it was responsive to concerns
raised by the complainant.
Accordingly, for these reasons and considering the AFCA Rules, the panel is satisfied an
award of compensation in not warranted in the circumstances.
The insurer is to reimburse costs of appointing consultants
In line with section D.5 of the AFCA Rules, the panel is of the opinion it is reasonable that the
insurer be required to reimburse the complainant for any expenses incurred in obtaining
expert reports in support of his position. Subject to the complainant provided information in
support of such expenses, the insurer is to with 14 days of receiving such information, the
insurer is to reimburse the complainant up to $5,000 towards these costs.
2.3 Why is the outcome fair?
The outcome is fair because it recognises that the available information does not establish
the insured building is a total loss for the purpose of the policy. However, the decision also
acknowledges the complex nature of the repairs to accepted under the claim and places the
res ponsibility to complete these works with the insurer. The insurer‟s overall management of
the claim has been found reasonable and it is fair in all the circumstances that the
complainant be reimbursed up to $5,000 towards expenses incurred in sourcing expert
reports.
Determination | Case number: 730453 Page 9 of 10
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. W e have reviewed and
considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel
includes:
an ombudsman
a member with significant experience in consumer and small business advocacy
a member with extensive experience in general insurance
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
3.2 Policy wording
D.5 Costs of pursuing complaint other than a Superannuation Complaint
D.5.1 An AFCA Decision Maker may decide that the Financial Firm is to
contribute to the legal or other professional costs or travel costs incurred by the
Complainant in the course of the complaint.
Determination | Case number: 730453 Page 10 of 10
D.5.2 Unless special circumstances apply, AFCA will not require the Financial
Firm to contribute more than $5,000 to these costs.
D.5.3 A contribution to the Complainant‟s costs of pursuing a complaint is not
taken into account for the purposes of the maximum value of remedy under D.4.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.