Building damage cash settlement based on underestimated floor area; contents and temporary accommodation claims declined; non-financial loss
Text of the determination
Determination
Case number 862607
Financial firm Insurance Australia Limited
Determination | Case number: 862607 Page 1 of 8
Case number: 862607 30 August 2022
1 Determination overview
1.1 Complaint
The complainant holds home and contents insurance with the financial firm (the insurer). On 7
January 2022, the complainant lodged a claim on the policy for damage following water
ingress during a storm. The property’s floorboards were particularly affected.
The insurer accepted the claim. It paid temporary accommodation (TA) costs for the
complainant and his family for a period. After receiving a scope of works (SOW) and quote
from its builder, RZ, the insurer offered the complainant $23,992.33 for building repair costs.
The complainant says RZ underestimated the flooring dimensions, so its quote is inadequate.
He also claims additional amounts for damaged contents and TA costs. Further, the
complainant wants the insurer to pay non-financial loss compensation for the stress it caused.
1.2 Issues and key findings
Is the insurer required to pay more for the building damage?
Yes. RZ significantly underestimated the flooring area. The insurer is to pay what SF, the
complainant’s builder, charged based on a more accurate floor area assessment .
Is the insurer required to pay more for the contents damage?
No. The complainant has not provided adequate proof of loss for the laptop, iPad or the
mobile telephone. The insurer has already agreed to pay for the cooktop and its installation.
Is the insurer required to pay more in TA costs?
No. The complainant has not established an entitlement to TA costs beyond the period the
insurer has covered.
Is the complainant entitled to non-financial loss compensation?
Yes. The insurer caused some delays and did not communicate proactively with the
complainant. It is to pay him $1,500 for the stress and inconvenience it has caused.
Why is the outcome fair?
It is fair that the insurer pays what SF charged for building repairs based on an accurate floor
area calculation. As the complainant has not proven further entitlement for contents or TA
costs, it would not be fair to require the insurer to pay more for them. However, it is fair that
the insurer pays non-financial loss compensation for the stress its claim handling caused.
1.3 Determination
This determination is substantially in favour of the complainant. Within 14 days of being
informed the complainant accepts this determination, the insurer is to pay him:
$37,185.50 (the amount SF charged plus the cooktop amounts less the policy excess)
$1,500.00 in non-financial loss compensation.
Determination | Case number: 862607 Page 2 of 8
2 Reasons for determination
2.1 Is the insurer required to pay more for building damage?
Yes. RZ significantly underestimated the flooring area. The insurer is to pay what SF, the
complainan t’s builder, charged based on a more accurate floor area assessment.
Insurer obtained expert reports
Following notification of the claim, the insurer appointed CR, restoration specialists, to assist
it in its investigations. CR attended the property on 11 January 2022 and reported:
stormwater had leaked through the ceiling and affected the floating floorboards in the six
rooms comprising the house’s lower level (open plan kitchen/living area, laundry,
bathroom/toilet, lounge, study, entry)
the damage was non-restorable
the floor dimensions of each affected room. The measurements provided total 116.8m 2
the complainant did not want any drying equipment installed until he was guaranteed TA
and the claim was accepted.
The insurer appointed RZ to assess the damage. RZ performed a virtual assessment on 13
January 2022. RZ reported that stormwater had damaged the ceiling and floating floorboards
in the rooms CR had identified as being affected. According to RZ, there was no immediate
need for TA and, further, TA would not be required during the repair process.
RZ also provided an SOW and quote for the required repairs. The SOW estimates the
affected floor area to be 80m 2 . The estimated cost of repairs is $25,992.33.
The insurer engaged HP, plumbers, to prepare a roofing report. After inspecting the roof on 1
February 2022, HP said that the water ingress was due to heavy weather conditions
overwhelming the property’s guttering system. HP recommended that the complainant
arrange for extra downpipes to be installed.
On 15 February 2022, the insurer’s make safe contractor, RP, att ended the property. RP
reported that the complainant had already removed the affected floorboards. RP removed
and disposed of the underlay and ‘tile taped anywhere that could be a trip hazard’ .
Based on RZ’s SOW and quote, the insurer has offered the complainant $25,992.33 less the
$2,000 policy excess, to cash settle the building damage claim.
Complainant says RZ underestimated floor area
The complainant says that the insurer’s building damage cash settlement offer is inadequate
because RZ underestimated the floor area damaged by the water.
The complainant relies on an invoice dated 7 April 2022 from SF, for repair work. The invoice
notes the affected floor area to be 110m 2 . The invoice amount is $35,876.50.
In mid May 2022, the insurer asked RZ to reattend the insured property to undertake further
investigations, including reassessment of the affected floor area. RZ emailed the insurer on
27 May 2022, advising that it had been informed by the complainant that SF had already
commenced repair work so it could not reattend.
Insurer is to pay what SF charged
There are three calculations of the dimensions of the affected floor area:
Determination | Case number: 862607 Page 3 of 8
CR says 116.8m 2
RZ says 80m 2
SF says 110m 2 .
SF’s estimate is t he middle estimate between the two estimates the insurer obtained. I am
satisfied that SF’s estimate is likely to be most accurate of the three because SF actually
performed the repair work. I also consider that RZ’s estimate is likely to be the least accurate
given that it was based on a virtual assessment of the property.
SF’s floor area estimate is 37.5% more than RZ’s. If RZ’s quote is increased by 37.5%, the
total becomes $35,739.45. That is very similar to the $35,876.50 SF invoiced.
In the circumstances, I am satisfied that RZ significantly underestimated the flooring area and
that it is reasonable that the insurer pays the complainant the amount SF invoiced to repair
the building damage. The insurer is entitled to deduct the $2,000 excess.
2.2 Is the insurer required to pay for the contents damage?
No. The complainant has not provided adequate proof of loss for the laptop, iPad or the
mobile telephone. The insurer has already agreed to pay for the cooktop and its installation.
Complainant says cooktop, laptop, iPad and mobile phone were water damaged
The complainant says that his cooktop, laptop, iPad and mobile phone were all water
damaged. He says:
he waited a long time for the insurer to inspect the damaged items
the insurer did not do so
he was not told to retain them
he eventually threw them out.
The complainant has provided an invoice dated 2 February 2022 for $1,130 said to be for
purchase of a replacement laptop.
He has also provided an invoice dated 28 February 2022 for $1,769 for the cost of a new
cooktop plus an invoice for $1,540 from MP, plumbers, relating to installation costs. MP note
on its invoice that the existing cooktop needed to be replaced due to water damage from the
roof leak.
Insurer has agreed to pay for cooktop only
The insurer has agreed to pay the complainant the cost of purchasing and installing the
cooktop, given MP’s indication the previous cooktop sustained claim related damage.
However, the insurer is unwilling to pay for the other contents items claimed because:
the invoice for the replacement laptop post dates the claim event
no other proof of ownership or loss has been provided for the items
the items were disposed of by the complainant before they had been assessed.
Insurer is not required to pay for laptop, iPad and mobile phone
The insurer’s claim notes record that the first time the complainant raised a claim for contents
was 11 February 2022. The complainant was told then and on subsequent occasions that the
insurer would need to assess that aspect of the claim.
Determination | Case number: 862607 Page 4 of 8
Page 51 of t he policy’s product disclosure statement (PDS) sets out information on an
insured’s obligations in the event of a claim. Those obligations include:
> We may request that you provide us with quotations for the repair or
replacement of your buildings or contents.
> Allow us or our representatives to inspect your damaged buildings or contents
at a reasonable time and place when necessary to assess your claim.
> Allow us or our representatives to inspect your damaged buildings or contents
when necessary to assess your claim.
> Keep all damaged property so we can inspect it at a reasonable time and place
if required.
> We may request valuations, receipts or other proof of ownership.
The complainant was aware that the insurer was assessing his contents claim. He was not
told it was appropriate to dispose of them. I am not satisfied that was a reasonable conclusion
for him to have reached.
The PDS sets out what the insurer may require from an insured to prove ownership and
damage. The complainant has not met those obligations in regard to the laptop, iPad or
mobile phone.
Accordingly, the insurer is not required to pay for those items.
2.3 Is the insurer required to pay more in TA costs?
No. The complainant has not established an entitlement to TA costs beyond the period the
insurer has covered.
Complainant says home was unliveable for an extended period
On 11 January 2022, the complainant told the insurer he was moving his family into TA as his
home was uninhabitable. At one stage, the complainant submitted to AFCA his entitlement to
TA costs exceeds $65,000. However, by reference to the information provided subsequently,
it appears he is seeking $47,700 (105 days).
The complainant relies on the following in support of his TA claim:
a report from his restorer, RS, who inspected the property on 13 January 2022 and said
TA was required for an estimated period of two weeks to a month
RZ’s unsigned authority to proceed with reinstatement works document, which included a
work period estimate of 84 calendar days (including a 24 day delay allowance)
the insurer did not promptly clear debris from his home, which presented a risk to his
family, particularly his three young children
the make safe was inadequate, as the areas where floorboards were removed were a slip
and trip hazard as evidenced by a fall he had and a letter dated 21 February 2022 from a
builder reporting a ‘near miss’ slip on the tile taping
because the insurer did not install drying equipment, there was a risk of mould
Determination | Case number: 862607 Page 5 of 8
the damaged cooktop was dangerous and the kitchen area could not be safely accessed
due to the floorboard damage
his family moved home on 26 May 2022, when SF had completed most of the work. The
work was completed by the end of June 2022. SF took three months to complete the job.
Insurer says home was only potentially unliveable for a limited period
The insurer has paid the complainant’s TA costs for the period 12 January 2022 to 17
February 2022 (five weeks/36 days), totalling $13,876.
According to the insurer:
the maximum amount of TA payable under the policy is $56,352 (10% of the building sum
insured)
it has paid a week more than RS’s maximum estima te of the TA period required
the make safe appeared to be adequate and the complainant would not let RZ reassess
the property
make safe does not usually extend to complete debris removal
on 11 January 2022, the complainant informed CR he did not want any drying equipment
installed until he was guaranteed TA and the claim was accepted.
Insurer is not required to pay more in TA costs
The TA additional benefit provided by the policy is set out on page 36 of the PDS:
If an insured event causes loss or damage to your home and due to this you are
unable to live in your home.
The insurer has correctly noted that the maximum payable is 10% of the building sum
insured. Accordingly, the complainant’s maximum entitlement is $56,352.
The TA additional benefit is subject to a number of conditions and exclusions. These include
that the insurer will not:
> cover any costs you incur beyond the period it should have reasonably taken to
repair or rebuild your home.
In the circumstances, I am not satisfied that the insurer is required to pay the complainant
more in TA costs. This is because:
RS estimated the repair work would mean TA would be needed for two to four weeks
the insurer has paid TA costs for five weeks
while RZ estimated the repair work may take 84 days, it said TA was not required
SF did not comment on whether the repair work would mean TA would be required and, if
so, for how long
SF took three months (12 weeks) to complete the repairs. However, five weeks of work
was performed after the complainant moved home on 26 May 2022. Further, it is not clear
if the complainant was reasonably unable to move back before then
make safe works are not intended to remove all potential risks
the floorboards the complainant removed appear to have been neatly stacked and the
areas where the floorboards had been removed were clearly visible. I am not satisfied they
presented hazards of such magnitude they should have been addressed in the make safe
it appears the complainant would not allow the insurer to undertake further investigations
there is no evidence that mould developed
Determination | Case number: 862607 Page 6 of 8
even accepting the complainant ’s statement that his religion means food is traditionally
cooked over a fire, I am not satisfied that using a cooktop was the only option available to
the complainant and his family for meal preparation.
Accordingly, the insurer is not required to pay the complainant anything further in TA costs.
2.4 Is complainant entitled to non-financial loss compensation?
Yes. The insurer caused some delays and did not communicate proactively with the
complainant. It is to pay him $1,500 for the stress and inconvenience it has caused.
AFCA can award compensation for poor claim handling
Under paragraph D.3 of the AFCA Rules, we may award compensation for non-financial loss
(capped at $5,400) where the insurer’s actions have caused an unusual amount of:
physical inconvenience
time taken to resolve the situation
interference with the com plainant’s expectation of enjoyment or peace of mind.
Where a complainant has contributed to their loss arising from the insurer’s conduct, their
level of compensation may be reduced accordingly.
Insurer has unreasonably caused stress and inconvenience
The complainant says that the insurer’s delays and poor claim handling have caused
considerable stress and inconvenience. He says he was forced to constantly chase the
insurer for information and that the insurer left his family to live in a dangerous house. The
complainant says that he has experienced high blood pressure and suffered an injury to his
right arm and neck when he tripped on the damaged floor.
The insurer accepts that it should have been more proactive in communicating with the
complainant and that it is responsible for some of the delay experienced. It has offered the
complainant $1,000 in non-financial loss compensation.
Based on the available information, I am satisfied that the insurer has unreasonably caused
stress and inconvenience to the complainant. As the insurer has acknowledged, there have
been some communication issues and the insurer has contributed to the delay experienced.
However, I also consider that the complainant has contributed to some of the delay by not
permitting the insurer to complete its investigations.
I acknowledge the complainant’s submission that he was injured when he tripped on the
damaged floorboards. However, I am unable to find the insurer is responsible for those
injuries because I do not have full details of the fall. Also, the medical documents submitted in
support are MRI requests dated 1 June 2022 referring to a chronic tennis elbow condition and
right sided neck pain radiculopathy to C7. Neither refer to the cause of the problems.
In the circumstances, I am satisfied that it reasonable that the insurer pays the complainant
$1,500 for the stress and inconvenience it has caused.
2.5 Why is the outcome fair?
It is fair that the insurer pays what SF charged for building repairs based on an accurate floor
area calculation. As the complainant has not proven further entitlement for contents or TA
Determination | Case number: 862607 Page 7 of 8
costs, it would not be fair to require the insurer to pay more for them. However, it is fair that
the insurer pays non-financial loss compensation for the stress its claim handling caused.
Determination | Case number: 862607 Page 8 of 8
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. I have reviewed and considered
all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, I have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.