The complainant claimed under his home insurance for damage he attributed to the September 2021 Victorian earthquake. The insurer declined, saying the damage was pre-existing or caused by other factors, and AFCA found the earthquake was not shown to be the proximate cause and no non-financial loss was warranted.

The complainant bore the onus of showing an insured event was the proximate cause of the damage, and the expert reports relied on by the insurer were preferred as the complainant provided no contrary expert evidence.

Issues

Subjects and remedies

home or building damagenatural disasterno remedy

Related

All Allianz Australia determinations · Find similar determinations

Text of the determination

Determination Case number 861433 Financial firm Allianz Australia General Insurance Limited Determination | Case number: 861433 Page 1 of 6 Case number: 861433 30 August 2022 1 Determination overview 1.1 Complaint The complainant holds a home and contents insurance policy with the financial firm (insurer). He lodged a claim for damage he says was due to the Victorian earthquake on 22 September 2021. The insurer declined the claim because it says the damage is not consistent with the earthquake. It says the damage is due to a combination of differential footing movement, sagging of the ceiling plaster, and incorrect installation. 1.2 Issues and key findings Is insurer entitled to decline the claim? Yes. The evidence supports the insurer’s decision t o decline the damage. Why is the outcome fair? The initial onus is on the complainant to show an insured event caused the damage. The complainant has not provided persuasive information to show the earthquake was the dominant or effective cause of the damage. Given the damage is not covered under the policy, it would be unfair for the insurer to accept cover for it. 1.3 Determination This determination is in favour of the insurer. The insurer is entitled to decline the claim and is not required to take any further action. Determination | Case number: 861433 Page 2 of 6 2 Reasons for determination 2.1 Is insurer entitled to decline the claim? Yes. The evidence supports the insurer’s decision to decline the damage. Policy covers earthquake damage that is not otherwise excluded The initial onus is with the complainant to establish the loss is covered by the policy. This is known as a valid (or prima facie ) claim. Once the complainant has established a valid claim, the onus shifts to the insurer to establish, on balance, the application of a policy exclusion or that it is otherwise entitled to decline the claim under the policy. The policy is an ‘insured events’ policy. This means not all loss and damage is automatically covered. Rather, only loss or damage caused by one or more of the insured events and not subject to exclusions, is covered. The insured events are set out in the product disclosure statement (PDS) and include earthquake. The insurer says the damage is due to a combination of differential footing movement, sagging of the ceiling plaster, and incorrect installation. It also says the damage predates the earthquake, which is shown in the build-up of debris within the crack. Complainant says an earthquake caused damage to his property The complainant says:  he has been living in the property since March 2015 and began renovating it in 2016, including renovating the bathrooms and painting the house in 2019  the house was built in 2002  the engineer stated the screws were protruding out past the plaster, but the rattling popped the putty out from where the screws were, in three different rooms  the crack between the plaster and cornice is from vibration and he will not accept long term settling as the reason  the stone top has cracks in the corners and is getting darker with every wipe, and there is no other way for the cracks to appear other than vibration  the damage is due to the earthquake  he has 20 years’ experience as a tradesman fitting kitchens and the stone has not cracked due to long term settling as it is still level  he is being dismissed and the insurer is waiting for him to give up. Insurer provided reports stating the damage was not due to the earthquake The insurer appointed a builder (PI) to attend the property on 27 September 2021. PI stated it found the following areas damaged prior to the earthquake:  cracked stone bench top in the kitchen was dark in appearance indicating there is pre- existing build-up of debris inside the cracks  gap between the plaster cornice and the wall due to general house movement  protruding ceiling fixings in the hallway, bathroom and bedroom have signs of corrosion and detaching from the timber ceiling joists Determination | Case number: 861433 Page 3 of 6  cracked Perspex back splash in the laundry is consistent with incorrect adhesion methods and appears to have pre-existing chips around it. PI also considered recent damage included a TV bracket falling off the wall. This was due to being installed incorrectly and not fixed to a solid structure. PI stated the damage has been caused by wear/tear, general building movement related issues and poor workmanship. The insurer appointed an engineer (IL) to attend the property on 18 January 2021. IL stated:  the epicentre of the earthquake was approximately 110km away from the complainant’s property  the damage is not related to the earthquake event in September 2021  referencing the Modified Mercalli Scale, the level of shaking given the proximity to the epicentre of the earthquake would be no more than level V, which is not considered strong enough to have caused any significant structural damage to adequately designed and built structures  lateral forces applied to foundations because of an earthquake would cause the dwelling to move back and forth, with the largest deflections occurring at the uppermost points, such as cornice lines  horizontal cracking along plasterboard joins can also occur because of the back and forth movement during the earthquake event  although some minor separation of the cornice was sighted above the door to the patio, the fact that this nature of distress was not consistent throughout the entire dwelling confirms the damage was not caused by earthquake forces  if the property has been adequately designed to meet the bracing requirements to resist lateral forces from wind actions, the dwelling is not expected to fail under lateral forces from an earthquake  the exposed nail heads to the ceiling plaster fixings is not from lateral forces, but rather vertical forces, where the ceiling has likely sagged, causing the nail to pull through the plaster  the cracking to the stone benchtop has occurred around the sink opening, where there was no discernible rounding that can increase the stress build up and cause cracks to form  it is not an expert on benchtops, however as there was no distress along the junction along the splashback or anywhere else in the kitchen, it concluded this was not due to the earthquake. IL stated the cracking and movement is consistent with damage from differential movement of the structure. It provided several potential causes of damage. The reports the insurer provided state the damage is not due to the earthquake Information does not show damage due to earthquake When deciding whether the policy responds, I need to be satisfied the proximate cause of the damage is earthquake. Proximate cause is a question of fact depending on the circumstances. The proximate cause is not necessarily the first or last or the sole cause of the loss. It is the effective, dominant or operative cause of the loss. The complainant did not provide any report to refute PI’s or IL’s findings. I appreciate the complainant has experience as a tradesman and recently renovated the property. However, he did not provide any independent expert report or other persuasive information to show the earthquake event caused the damage claimed. In the absence of more persuasive information from the complainant, I am persuaded by PI and IL’s reports. I am satisfied the experts are appropriately qualified to comment on the Determination | Case number: 861433 Page 4 of 6 cause of damage. The conclusions are plausible, logical and consistent with the available evidence. The information does not show the earthquake caused the damage and is more consistent with differential movement. For the damage claimed to be covered under the policy, the complainant must show the earthquake was the proximate cause of this damage. I am not satisfied he has done so. Fair for the insurer to decline the claim The insurer’s policy consists of the policy schedule and PDS. It is not in dispute the insurer provided the policy documents to the complainant. The insurer is therefore entitled to rely on those terms when assessing any claim made against the policy. The policy covers several insured events, including earthquake. The insurer also refers to exclusions for: • wear and tear, gradual deterioration, or fading, … • e arth or soil movement including landslide, subsidence, erosion or heave, unless it is a direct result of an insured event, • settling, expansion, shrinkage or vibration, unless it is a direct result of an insured event, The onus is on the complainant to show an insured event covered by the policy caused the damage claimed. I do not consider the complainant has satisfied this onus. I am therefore satisfied it is fair for the insurer to decline cover for the damage. Compensation not warranted in the circumstances The complainant also raises concerns with delays on the claim. Under our Rules, AFCA can consider making an award of up to $5,400 compensation for non-financial loss. However, we will only award this type of compensation if a complainant suffers an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the complainant’s enjoyment o r peace of mind. AFCA takes a conservative approach to compensation and expects a complainant to bear a normal degree of inconvenience during a claim. T he insurer says it initially declined the claim based on its builder’s report. However, as the complainant did not agree with the outcome, it agreed to appoint an engineer. It says there were delays in appointing engineers due to the high demand for their services following the earthquake. It says it notified the complainant of this delay. It also says there were delays due to the impact of the COVID-19 pandemic. It says it also communicated this to the complainant. Having reviewed the correspondence and claim notes, I consider there were some delays on the claim. I consider some delays were to be expected due to the nature of the event and the large volume of claims it generated. I am satisfied most of the delays were outside the insurer’s control. I accept the insurer could have processed the claim in a timelier manner overall. However, given the nature of the claim and number of experts appointed, as well as AFCA’s Determination | Case number: 861433 Page 5 of 6 conservative approach to compensation, I do not consider non-financial loss compensation is warranted in the circumstances. Determination | Case number: 861433 Page 6 of 6 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.