Home / IAG / Determination 861238
Determination 861238
Storm damage claim settlement amount for building and contents
Summary
The complainant sought $450,000 for storm damage to his home and contents, while the insurer offered $45,549.99. AFCA found the insurer's expert evidence more persuasive, increased the building and contents cash settlements, required further assessment of some items, and ordered payment for tarp hire and temporary accommodation.
The insurer's expert evidence was more persuasive than the complainant's engineer on the extent of storm-related damage, so the insurer's scope of works was accepted subject to a 15% contingency allowance.
Issues
- Claim amount dispute primary · not upheld
“The panel accepts the scope of works obtained by the insurer is fair but considers the settlement should be increased to $44,018.07 to provide a 15% allowance for contingencies.”
- Claim denial secondary · not upheld
“The panel is not satisfied the report from JKA can be relied on to establish the extent of the storm related damage.”
- Inadequate claim investigation secondary · not upheld
“The panel is satisfied the explanation and overall conclusions from the insurers engineer EIS, building consultant AA and roofing expert RC are more persuasive.”
Subjects and remedies
home or building damagenatural disasterpay claimpay compensationreassess claim
Text of the determination
Determination
Case number 861238
Financial firm Insurance Australia Limited
Determination | Case number: 861238 Page 2 of 7
Case number: 861238 1 August 2022
1 Determination overview
1.1 Complaint
The complainant held a Home and Contents policy with the financial firm (insurer) and lodged
a claim after the home was damaged in a storm on 10 June 2021.
The insurer accepted the claim, but a dispute exists as to the extent of the loss and damage
sustained. The insurer has offered to settle the building and contents damage for $45,549.99.
The complainant says the storm caused structural damage to the home and significant
contents damage. He is seeking $450,000 to resolve the complaint.
1.2 Issues and key findings
Is the insurers offer the settle the building claim fair in the circumstances?
Yes. The panel accepts the scope of works obtained by the insurer is fair but considers the
settlement should be increased to $44,018.07 to provide a 15% allowance for contingencies
Is the insurers offer to settle the contents claim fair in the circumstances?
No. The insurer is to increase the cash settlement for the contents to $9,457.06 to allow for
contingencies and arrange further items to be assessed as identified in section 2.2 of this
determination.
Is the insurer liable for the tarp costs and temporary accommodation?
Yes, the insurer is to pay the complainant $1,517 for the tarp hire and three weeks temporary
accommodation costs as set out in section 2.3 of this determination.
Why is the outcome fair?
The policy coverage includes damage resulting from the claimed event of storm. The insurer
provided more convincing and thorough expert evidence showing what damage resulted from
the storm. It is fair the insurer should only have to cover damage attributable to the claimed
event.
1.3 Determination
This determination is substantially in favour of the insurer. Within 21 days of the
complainant’s acceptance of this determination the insurer is to pay the complainant:
$44,018.07 for building damage.
$9,457.06 for contents damage.
$1,527 for tarp hire costs.
Reasonable costs for three weeks temporary accommodation
Cash settle the complainant for any additional storm related damage identified following
completion of the further assessments as set out in section 2.2 of this determination.
Determination | Case number: 861238 Page 2 of 7
2 Reasons for determination
2.1 Is the insurers offer to settle the building claim fair in the
circumstances?
Yes. The panel accepts the scope of works obtained by the insurer is fair but considers the
settlement should be increased to $44,018.07 to provide a 15% allowance for contingencies.
No dispute there is a valid claim
The complainants held a Home and Contents policy with the insurer that provides cover for
accidental damage to the building and contents during the period of insurance subject to
several conditions and exclusions.
Accidental damage is not defined but is generally accepted to mean sudden, unexpected and
unforeseen damage.
There is no dispute that the complainants home and contents sustained accidental damage
during a storm on 10 June 2021. The insurers assessor ‘A IS ’ confirmed following an
inspection of the property that rainwater ingress during the storm has caused staining to
ceiling areas in the lounge, kitchen, bedroom and garage. AIS reported that a neighbouring
tree had fallen and also a tree at the insured property but that it did not damage the property.
AIS also identified contents damage to items stored in the garage, a lap top computer and
contents stored outside. The complainant identified as being in the construction industry and
was invited to provide quotes for the repairs.
T he complainant submitted an engineer’s report from JKA together with 3 builders’ quotes.
These quotes were between $480,100 and $548,275. He also claimed contents of
$114,654.74.
Experts disagree as to the storm related damage
The report from the engineer JKA found that house was designed to meet wind speeds of
only 40km/h whereas the event that took place had winds of up to 120km/h with excessive
amount of rain.
JKA found evidence of excessive deflection of the roof structure but did not provide any
photographs in support, nor did he take any measurements. He also found that there is a lack
of anchorage and tie down of all the rafters, ceiling joists, hanging beams and alike. JKA also
advised several tiles had been moved by the storm winds, allowing water entry that had
damaged the home. The report did not directly attribute the deflection of the upper floor and
the claimed event but did indicate strong winds could impact the structure. JKA provided a
detailed explanation of the works required to rectify the damage they observed. No formal
SOW was prepared.
In response, the insurer appointed an engineer, EIS. EIS found that the foundation and
superstructure were not damaged during the storm nor pose a risk to the future use of the
building. EIS found that the building was constructed according to the relevant code at the
time and for winds exceeding the recorded amounts. The building code required buildings to
withstand winds up to 140kmp/h. EIS also advised maximum wind gusts recorded at the
closest weather station, 2.1km from the property was up to 76kmp/h.
Determination | Case number: 861238 Page 3 of 7
EIS found no structural issues and no evidence of deflection. EIS confirmed the roof was in
poor condition due to wear and tear, noting several areas where flashing had deteriorated or
split. EIS also noted moss growth blocking water courses, tiles slipping down out of place and
tile cracks with aged repair attempts. It did also confirm some tiles would have cracked in the
storm.
The insurer also engaged a building consultant and engineer AA who inspected the property
on 21 September 2021. AA appointed a roofing expert RC who identified general
deterioration of the roof due to pre-existing issues. RC identified deteriorated sarking and lead
flashing, poor performing roof lining and numerous roofing and plumbing issues indicating
noncompliance with relevant building standards. While AA found evidence of water ingress
caused by the storm, AA considered the damage was relatively minor.
AA also arranged an inspection of both the evaporative and the split system ACs by AF. They
found that the evaporative cooling had been inoperable for a long time with evidence of mud
at the bottom of the unit. No damage consistent with storm damage.
Insurers reports more persuasive
The panel is satisfied the explanation and overall conclusions from the insurers engineer EIS,
building consultant AA and roofing expert RC are more persuasive.
The panel is not satisfied the report from JKA can be relied on to establish the extent of the
storm related damage. Most of the issues raised by JKA are in the panels view consistent
with pre-existing issues as identified by the insurers experts.
The panel accepts it is fair in the circumstances to rely on the insurers SOW in assessing the
building damage.
The settlement includes all claim related damage
The insurer provided a quote from its builder which came to $33,290.40. The quote from
BRMS includes all water damage to ceilings and fixtures, repairs to fences, pool pump
housing, replacement of broken tiles and other associated works. The insurer has confirmed
the quote would include painting the entire damaged ceilings and not just patch painting.
The insurer also obtained a mould remediation report from FRR. There was a note that there
was some evidence of some pre-existing mould. Some mould was observed in the upstairs
area, however, the downstairs area was shown to have similar counts to the outside area.
FRR quoted $4,986.19 to complete the mould remediation.
The insurer has offer the complainant $38,276,59 to cover the cost of repairing the building
damage including mould restoration. The offer does not account for the possible
contingencies associated with the repair process. The panel considers a 15% contingency fee
($5,741.48) fair.
The insurer is to the increase the settlement of the building and mould damage to $44,018.07
to provide for a 15% allowance for contingencies.
2.2 Is the insurers offer to settle the contents claim fair in the
circumstances?
No. The insurer is to increase the cash settlement for the contents to $9,457.06 to allow for
contingencies and arrange further items to be assessed as identified.
Determination | Case number: 861238 Page 4 of 7
Contents were damaged in the claimed event
The complainant provided a list of damaged contents items he says were in the claimed
event. This included electrical items, items usually stored outdoors and some tools. The
complainant provided photos and estimates or quotes for replacement but no detailed report
on the possibility of salvage. The estimate for the entire list came to $114,645.
The insurer appointed its restoration expert (FRR) who attended the property and provided a
summary of the contents items it says were damaged in the event, along with comments on
the complainants list of contents. The assessed claimable damage was:
External awning blinds $3,000
Four ceramic pots $400
Cantilever umbrella $599
3 outdoor plastic chairs $75
Spit Roaster $119
Sony Speakers $120
Apple Mac laptop $2199
Fisher Paykel fridge $1,499
Test and Tag $213.40
Total $8,224.40
The complainant has not provided any expert evidence to dispute FRR’s assessment of the
damage. Overall the panel agrees with the insurers assessment of the contents and agrees
its settlement offer is fair based on the items assessed. Given the likely variation in pricing of
the items the panel considers it fair the insurer increases the offer to cash settle these items
by 15% ($1,233.66) to $9,457.06.
There are however items that do not appear to have been assessed and in the panel ’ s view
these items should be assessed in order to finalise this aspect of the claim.
Some contents have not been tested or inspected
During its assessment, FRR noted approximately twenty electrical, mechanical or otherwise
specialty items that required further inspection or testing. The testing and tagging relates to
electrical items FRR says had no obvious water damage.
The items include chainsaws, a pool table, and household electrical items. While the insurer
has included in the settlement offer an allowance for the complainant to test and tag the
electrical items, the outcome of this testing is unknown.
FRR also recommended a pool contractor assess the Dolphin pool cleaner (est. $1,000-
$1,500) and a plumber inspect the water tank (est $3,500 - $4,000). FRR report also identifies
minor water damage to a drawing table which it assessed as non-salvageable but provided
no cost estimate.
The panel considers it fair that the complainant allows the insurer access to test and tag the
items identified and for the insurer to have a plumber and pool contractor assess the water
tank and pool cleaner respectively. If any damage is found to be related to the storm event,
then the insurer can cash settle the complainant for the additional damage.
The insurer should also arrange to further assess the drawing table and if found to be
damaged by the event, cash settle the complainant for the cost of the table.
Determination | Case number: 861238 Page 5 of 7
2.3 Is the insurer liable for the tarp hire and temporary
accommodation.?
Yes, the insurer should pay its reasonable cost for tarp hire and temporary accommodation.
Make safe tarping was required and organised by the complainant
The complainant provided an invoice for tarp hire to the insurer for $60 per day from 11 June
2021 to 25 February 2022. This totalled $15,600. The invoice provided was from a company
under the complainant’s name, which the insurer says is the complainants company.
The insurer representative says the tarp was not present during its inspection on 17 June
2021. Further it says it was not advised of the cost of tarp hire until the invoice was provided
by the complainant.
The insurer agrees a tarp was likely required due to the claimed event, as some roof tiles
were broken due to the event. It says its cost for this would not have exceeded $1,527 and
offered this amount to the complainant.
The panel is not satisfied the complainants costs are reasonable or that the insurer was
notified of the cost in a reasonable timeframe. If it hasn’t already done so, the insurer should
pay its cost associated with tarp hire of $1,527.
Temporary accommodation costs are reasonable in the circumstances
The policy provides cover for reasonable alternative accommodation if you are unable to live
tin the damaged premises. The complainant says the extent of repairs would require his
family to move to accommodation while repairs go ahead as large sections of the home would
be under repair.
The insurer says temporary accommodation is not required as repairs are only to ‘patch and
paint’. This seems to be the case for the initial assessment, however, the most recent quote
provided by the insurer includes replacing large sections of ceiling plaster in the kitchen,
lounge room and living room, plus some insulation removal and replacement. There is also
mould remediation required. The complainant also points out the quote the insurer bases its
cash settlement on says it is dependent on ‘free and unrestricted access to work site at all
times’, which he says is not achievable without moving out.
The panel accepts the repairs will require some level of temporary accommodation during the
repair process. Given the nature of the accepted damage and repairs the panel considers a
period of three weeks temporary accommodation would be sufficient.
The panel determines the insurer should obtain a quote for the reasonable cost of short term
accommodation of the complainant and his family for this period. The insurer can cash settle
the complainants for the temporary accommodation.
Why is the outcome fair?
AFCA must weigh expert evidence in its review of complaints and must do what is fair for all
parties. The parties submitted expert reports in support of their differing positions.
The insurers expert report reflected a more holistic approach to the damage claimed by the
complainant and provided more detailed explanations. As the insurers experts were more
persuasive, and the insurers position is aligned to its expert evidence, the panel considered
the outcome fair in the circumstances.
Determination | Case number: 861238 Page 6 of 7
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel
includes:
an ombudsman
a member with significant experience in consumer and small business advocacy
a member with extensive experience in general insurance
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.