Determination 860899

Temporary accommodation, painting and shutter costs following building works

FirmQBE
Decided2022-10-10
ProductGeneral Insurance · Strata
OutcomeFor the complainant
Amount awarded$11,162
Non-financial loss$3,000
Amount claimed$15,332
SourceAFCA PDF

Summary

The complainant, a strata unit owner, sought temporary accommodation, painting, cleaning and shutter costs after building works required relocation. AFCA found the unit was not fit for reoccupation by 10 December 2021 and ordered the insurer to pay the accommodation, painting, shutter and cleaning costs, plus non-financial loss compensation and interest.

Under the policy's temporary accommodation benefit, cover continues until the unit is reoccupiable after completed repairs, and the insurer's insistence on carpet installation before repairs were finished was unreasonable.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay compensationpay interestpay non financial loss

Related

All QBE determinations · Find similar determinations

Text of the determination

Determination Case number 860899 Financial firm QBE Insurance (Australia) Limited Determination | Case number: 860899 Page 1 of 6 Case number: 860899 6 October 2022 1 Determination overview 1.1 Complaint The complainant is a beneficiary under a residential strata insurance policy held with the financial firm (insurer). The complainant’s unit is part of a complex that was undergoing significant building works. This required vacant possession of the building and the complainant was required to be in temporary accommodation during the repairs. The complainant raised concerns regarding building works being completed at the insured property. The complainant is seeking additional temporary accommodation, painting costs, cleaning costs, and says the insurer has not settled the full costs for shutters at the property. The insurer completed repairs to the unit and says it is not required to pay the complainant any further amount. However, it agreed to cover the comp lainant’s cleaning costs of $530. 1.2 Issues and key findings Is the complainant entitled to any further compensation? Yes. The complainant has established an entitlement to further costs. Why is the outcome fair? The information provided shows the property was not made fit to be occupied for its intended purpose by 10 December 2021. It was not fair for the insurer to require the complainant to reoccupy the property by that date. The information also shows the complainant incurred additional costs that were reasonable in the circumstances. It is fair for the insurer to reimburse these costs. 1.3 Determination This determination is in favour of the complainant. If the complainant accepts this determination, the insurer is to pay him:  $530 for the cleaning costs the insurer has already accepted under the claim  temporary accommodation from 10 December 2021 to 25 March 2022  $7,722 for the painting costs, with interest payable on the amount paid from the date of the invoice until the date of payment in accordance with section 57 of the Insurance Contracts Act 1984 (the Act)  $2,910 for the shutters in the bedroom, with interest payable on the amount paid from the date of the invoice until the date of payment in accordance with section 57 of the Act  $3,000 in non-financial loss compensation. Determination | Case number: 860899 Page 2 of 6 2 Reasons for determination 2.1 Is the complainant entitled to any further compensation? Yes. The complainant has established an entitlement to further costs. Claim relates to ongoing building works at insured property There is no dispute the complainant has a valid claim under the policy for costs incurred due to the ongoing building works at the insured property. The insurer has already settled the complainant for costs associated with the claim, including temporary accommodation and other expenses incurred. However, there is a dispute regarding the extent of the insurer’s liability. The claim relates to iron oxide rust damage to the building from construction works at a neighbouring property. The insurer appointed a loss adjuster (ML) to manage the claim, which included repairs to the insured building totalling over $3million and the relocation of all residents, including the complainant. The policy covers accidental physical loss of, or destruction of property from any sudden and accidental cause not otherwise excluded. It also includes several benefits, including temporary accommodation. The product disclosure statement (PDS) states temporary accommodation will be paid as follows: When You occupy Your Lot/Unit We will pay the reasonable cost of Temporary Accommodation You necessarily incur if Your Lot/Unit is made unfit to be occupied for its intended purpose due to: i. Damage to Your Insured Property that is admitted as a claim under Policy 1 – Insured Property; or ii. reasonable access to or occupancy of Your Lot/Unit being prevented by Damage from an Event claimable under Policy 1 – Insured Property happening to other property in the immediate vicinity. We will pay: • under Clause a.i. from the time of the Event until the time You reoccupy Your Lot/Unit following completion of rebuilding, repairs or replacement; and • under Clause a.ii. from the time of the Event until the time when access to Your Lot/Unit is re-established. The complainant raises concerns with the insurer’s and ML’s handling of the claim and outstanding payments for temporary accommodation, painting and shutters. Fair for the insurer to cover additional temporary accommodation The insurer says its builder completed works to the complainant’s property and while there w ere some defects, the unit was ready to hand over to the complainant’s contractor for replacement of the carpet and installation of window shutters in December 2021. The insurer says the complainant’s delay in allowing the installation of the carpet was no t reasonable and contravened provisions of the policy. ML stated in its report dated 13 December 2021 that the complainant had refused to accept that defect rectification work could be completed following installation of the carpet. It stated the unit was available for the flooring supplier for installation on 7 December 2021, however Determination | Case number: 860899 Page 3 of 6 the complainant cancelled the installation. ML stated the rectification work required included cleaning up marks and scratches on windows, doors and balconies. ML also stated the shutter design had been accepted, however they were not available until January 2022. ML stated a reasonable solution to enable the complainant to re-occupy the unit was to install temporary privacy curtains at no cost to the complainant, however the complainant declined this offer. The insurer says by 10 December 2021 the complainant could have comfortably reoccupied the unit and it is not responsible for any additional temporary accommodation costs incurred after this date. The complainant provided emails throughout the claim and detailed his concerns with the carpet being installed in December 2021. He says there were many issues with the property, including marks and damage from the window replacement and building dust throughout. The complainant says he did not want trades working on a new carpet. He says he only delayed the carpet installation because the insurer’s builder failed to have the unit ready/complete and in a condition for the new carpet to be installed. The complainant says th e insurer’s builder ignored his concerns about the quality of repairs and only focussed on the lots who engaged them to undertake private renovation of their units. He says door locks were missing and emergency fire equipment access was not in place, meaning it was not safe to occupy the property in December 2021. The complainant says his actions were purely to have his property returned in complete condition without any further destruction of the property or disruption of his peace and quiet enjoyment of the property as it was handed over in June 2021. The complainant is seeking additional temporary accommodation from 10 December 2021 to 25 March 2022 (15 weeks at $780 per week) for $11,700. He says the shutter installation was finalised at the end of March 2022. I have reviewed the information provided. The insurer accepts there were rectification repairs required but says these could have been completed after the carpet was installed. However, the complainant provided detailed submissions addressing the issues with the unit, including building dust and painting issues. I appreciate the complainant’s concerns regarding installing new carpet under these circumstances. I consider it was unreasonable for the insurer to require the complainant to accept a new carpet when still undergoing necessary rectification repairs. I do not consider the insurer provided sufficient flexibility to the complainant in these circumstances. Given the additional rectification work required, including the requirement for carpet, I do not consider the property was made fit to be occupied for its intended purpose by 10 December 2021. The policy states payment will be made until the complainant reoccupies the property following completion of repairs. Given the repairs were not adequately completed until 25 March 2022, it is fair for the insurer to reimburse the complainant for these temporary accommodation costs. Fair for the insurer to reimburse painting costs The complainant says his property was presented so badly he engaged professional painters to repair the mess left by the insurance works. He says he had no choice but to engage quality tradespeople to remedy the issue. He provided an invoice for $7,722. Determination | Case number: 860899 Page 4 of 6 The complainant says he had lost all faith in the insurer’s builder by the tim e he appointed a new painter to remedy the issues. He says the builder had painted some walls in one room and not others, leading to different colours in the one room. He also says the tradesmen damaged walls, and these were not painted. The insurer says the painting was limited to areas damaged, and the policy excludes undamaged property. It says if the complainant wants undamaged areas painted, this will be at the complainant’s own cost. ML stated in its report dated 13 December 2021 that all damage had been repaired at the complainant’s unit and the unpainted areas were not damaged. The insurer also says its builder accepted the list of defects to rectify but were not afforded the opportunity to rectify them. It appears there were also delays for this due to the Christmas break and the builder taking leave over this time. Information provided shows the builders returned from leave on or about 17 January 2022. However, the insurer says by this time the defects had been covered by the co mplainant’s painters. I do not accept the insurer’s position on the painting. While it says it is not required to paint undamaged areas, I do not accept this extends to leaving entire rooms mismatched. If only some walls are painted, leaving unpainted walls a different colour to the others, I do not consider this is adequately repairing the property to an acceptance level. The complainant’s property is unlikely to have had mismatched rooms prior to the claimed repairs commencing so it would be unfair to leave the complainant with mismatched rooms following this. The information also shows there were issues with the painting following the repairs. It appears there was a relationship breakdown between the complainant and the builder due to issues with the repairs. It also appears there were delays in the builder being able to complete these rectification repairs. Given the number of concerns the complainant raised with the building works and delays in the builder responding to these concerns, it was not unreasonable for the complainant to appoint his own builder to complete the painting works. I consider it fair for the insurer to cover the complainant’s painting costs. Interest is payable on the amount paid from the date of the invoice until the date of payment in accordance with section 57 of the Act. Fair for the insurer to cover the shutter costs The complainant says the insurer originally approved his quote for shutter replacement. However, it later deducted the price for shutters in one bedroom. He says the cost outstanding is $2,910. The complainant provided an email he says shows the insurer accepted the quote prior to them putting in the order for the shutters. He says the insurer removed the curtains and were responsible for replacing window coverings. He says there was no price difference between curtains and shutters so he chose shutters. He says the shutters were already being manufactured when the insurer deducted this amount from the settlement. The insurer says it deducted the cost of shutters for a bedroom because they did not require replacement. It says the room had curtains and the complainant chose to replace them with shutters. Having reviewed the information provided, I consider the insurer indicated to the complainant it would cover the cost of all shutters. The information shows the complainant then ordered the shutters based on this acceptance. I do not consider it would be fair to deduct this cost Determination | Case number: 860899 Page 5 of 6 from the settlement after the complainant, on balance, proceeded to order all shutters based on this acceptance. It is fair for the insurer to cover $2,910 for the shutters in the bedroom. Interest is payable on this amount from the date of the invoice until the date of payment in accordance with section 57 of the Act. Compensation may be awarded in certain circumstances The complainant also seeks non-financial loss for the significant physical and mental impact on him and his wife. The complainant provided detailed submissions on the insurer’s and the ML’s handling of the claim and the amount of time spent following up payments. Under our Rules, AFCA may award compensation for non-financial loss where there has been an unusual amount of:  physical inconvenience  time taken to resolve the situation  interference with a complainant’s expectation of enjoyment or peace of mind. AFCA takes a conservative approach to compensation and expects a complainant to bear a normal degree of inconvenience during a claim. Compensation warranted in the circumstances I have reviewed the information provided and do not consider the insurer has adequately considered the complainant’s concerns regarding ML’s actions and delays on the claim. The complainant provided detailed submissions regarding these delays and lack of communication. This has led to a breakdown in relationship between the parties. I accept the ongoing delays and communication issues has caused an undue amount of stress, inconvenience, and interference with the complainant’s expectation of enjoyment or peace of mind. Having regard to all the circumstances of the complaint, I consider it fair for the insurer to pay the complainant $3,000 in non-financial loss compensation. Determination | Case number: 860899 Page 6 of 6 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.