Home / Suncorp Group / Determination 860178

Determination 860178

Storm damage claim handling, repairs scope and delays

FirmSuncorp Group
Decided2023-02-23
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$145,271
Non-financial loss$1,000
Amount claimed—
SourceAFCA PDF

Summary

The complainant claimed storm damage to her home and contents and disputed the insurer's repair methodology, veranda cash settlement and claim delays. AFCA found the insurer's scopes reasonable, ordered the claim cash settled, ordered further temporary accommodation payments and $1,000 non-financial loss compensation.

Storm damage claim should be cash settled as the relationship deteriorated and ongoing delay caused further damage, with contingency uplifts applied to actionable quotes and TA payable under the policy's automatic benefit.

Issues

Subjects and remedies

elderly or capacityhealth or medicalhome or building damagemental healthnatural disasterpay claimpay compensationpay non financial lossreassess claim

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 860178 Financial firm AAI Limited Determination | Case number: 860178 Page 1 of 8 Case number: 860178 23 January 2023 1 Determination overview 1.1 Complaint The complainant holds home and contents insurance with the financial firm (the insurer). On 10 June 2021, she lodged a claim for storm damage to the insured property and contents. The insurer accepted the claim. It proposed to repair the property’s roof then attend to internal repairs and assessment of the contents claim. The insurer also offered to cash settle the cost to repair the veranda, given that some of the damage to it was unrelated to the storm. The complainant disagrees with the insurer’s proposed order and methods of repair and with the decision to cash settle the veranda repairs. She also says the insurer’s poor claim handling and delays have caused additional damage, stress and inconvenience. 1.2 Issues and key findings Is the insurer’s claim settlement approach reasonable? For the most part, yes. The panel is satisfied that the insurer’s scopes of works for roof and veranda repairs are reasonable. However, though mostly not due to delay by the insurer, it has taken too long to progress the claim. This has led to additional damage. It is therefore reasonable for the entire claim to be cash settled as soon as possible. Is the complainant entitled to further temporary accommodation (TA) costs? Yes. The panel is satisfied the insurer’s proposal to pay out the remaining 33 weeks of the TA benefit is reasonable, taking into account the extent of repairs required but given that it did not significantly contribute to the delays experienced. The rate is to be increased for inflation. Is non-financial loss compensation payable? Yes. There were some deficienc ies in the insurer’s claim handling. These issues contributed to the complainant’s stress and inconvenience. The insurer is to pay her $1,000 in non- financial loss compensation. Why is the outcome fair? The insurer’s appr oach to the claim has overall been reasonable. However, the delays experienced and resulting additional damage mean it is fair that steps be taken to cash settle the entire claim as soon as possible. While the insurer did not significantly contribute to the delays, there were some claim handling issues. It is fair that it pays $1,000 in compensation. 1.3 Determination This determination is partially in favour of the complainant. If the complainant accepts this determination, the insurer is required to:  settle the claim in the manner set out in section 2.1 of this determination  within 14 days, pay the complainant $15,675 in TA costs ($475/week for 33 weeks)  within 14 days, pay the complainant $1,000 in non-financial loss compensation. Determination | Case number: 860178 Page 2 of 8 2 Reasons for determination Amongst other things, the complainant says there is water leaking from the shower. The insurer says this is unrelated to the storm event and asked the complainant to lodge a separate claim. No evidence has been provided that suggests the shower leak is related to the storm. Therefore, AFCA accepts the insurer’s position this falls outside the scopes of the subject claim and the complaint. This determination does not deal with the shower leak. If the complainant lodges a separate claim for the shower leak, the insurer must assess the claim in accordance with the policy. 2.1 Is the insurer’s claim settlement approach reasonable? For the most part, yes. The panel is satisfied that the insurer’s scopes of works for roof and veranda repairs are reasonable. However, though mostly not due to delay by the insurer, it has taken too long to progress the claim. This has led to additional damage. It is therefore reasonable for the entire claim to be cash settled as soon as possible. Parties disagree on the approach to building repairs There is no dispute that the insured property’s roof was significantly damaged by a storm event on 10 June 2021, with numerous roofing sheets ripped off. The insurer arranged for ‘tarping’ of the roof as a temporary mak e safe repair. The insurer engaged RM, engineers. In its report dated 1 July 2021, RM said:  internally, the storm had caused water damage to plasterboard ceilings and plaster wall linings, detachment of a small section of ceiling trim in the kitchen and some staining of exposed timber roof beams  water ingress through the temporary roof covers had contributed to the plasterboard ceiling damage and had caused moisture damage to the music room’s floor  externally, the storm had detached roof sheeting from the house and the veranda as well as damaging guttering, a satellite dish, the chimney flue and the veranda structure  the veranda was poorly constructed, with structurally inadequate rafter fixings, undersized and inadequate footings, severe corrosion of veranda post stirrups and brickwork cracking where the hip rafters entered the home  the veranda did not comply with current building regulations and standards  there were pre-existing gaps between window framing and corner brick piers  it appeared that the storm had damaged the roof framing, but further investigation was necessary to determine the extent of this. A number of attempts were made over time to ensure the tarping provided a waterproof seal but have been unsuccessful. The insurer says this is due to wind exposure from the property’s elevated position. Delays were experienced due to COVID- 19 concerns, the complainant’s concerns about the competence of RX (the restorers the insurer engaged to pack and store contents) and issues related to obtaining building permits from the local council. It also appears the relationship between the complainant and the insurer as well as the insurer’s builder, JL, became frayed. In late November/early December 2021, JL confirmed from original plans and permits that the veranda was non-compliant when it was built in 1985. On 29 November 2021, JL provided a scope of works (SOW) and quote for covered veranda repairs totalling $32,406.61. Determination | Case number: 860178 Page 3 of 8 The insurer says that as the veranda has pre-existing issues and damage unrelated to the storm and is and has always been non-compliant, JL cannot warrant repairs. Accordingly, it has offered to pay the complainant JL’s quoted amount as a cash settlement. The complainant says the local council signed off on compliance at the time of construction. She says the insurer should repair the veranda or, at least, obtain a second quote for comparison purposes. Following an emergency works order being issued by the local council to the complainant’s mother, JL provided the complainant with a contract and SOW for roofing repairs on 21 January 2022. The complainant responded, saying that repairs to the ceilings and veranda would need to be completed before the roofing repairs could proceed. She was also concerned about additional damage due to the unsuccessful make safe repairs. On 31 January 2022, following discussions with JL, the insurer advised the complainant:  it was not necessary for the veranda or the ceilings to be repaired before the roofing repairs could be undertaken  the make safe related damage would be included in the SOW for internal damage repairs, which could not be prepared until after the re-roofing was completed  she could either sign the contract/SOW to enable JL to commence the roof repairs or appoint a builder to provide a ‘like for like’ quote for the insurer’s consideration . On 30 April 2022, the complainant provided an undated letter from AP, builder. AP said:  it had inspected the insured property  the make safe was inadequate and was allowing water ingress  the roof battens were installed above pine lining boards which were installed above the rafters  the pine lining boards were extensively water damaged  the remaining roofing and the roof battens would need to be removed before the pine lining boards could be removed and replaced. On 5 May 2022, the complainant provided a single page quote from JB, builder. JB said that due to ongoing water ingress, widespread replacement work would need to be undertaken. JB quoted the work at $495,000. The quote covered internal and external work. No itemised costing was provided. On 2 June 2022, the insurer provided a second additional notice of response to AFCA in which it said: The insurer’s paramount concern throughout the entirety of the claim has been to have a permanent repair of the roof undertaken to prevent further damage occurring. If the insurer is not able to undertake these repairs in the near future, the insurer will consider a cash settlement payment to finalise its involvement in the claim and allow the customer to undertake repairs herself. It also submitted JL’s quote dated 27 August 2021 for the roof repairs, totalling $75,590.04. Unfortunately, the roof remains unrepaired, with water ingress continuing to occur. Contents have been damaged It is not in dispute that the storm event caused damage to contents. On 10 June 2021, the insurer arranged an emergency payment of $2,000 out of the contents sum insured. It has also replaced an oven and re-gassed the air conditioning unit. Determination | Case number: 860178 Page 4 of 8 The insurer says it is necessary to pack and store contents before commencing building work. In July 2021, the insurer engaged RX to attend to contents pack-out and to inventory damaged contents items. It says significant delays were experienced due to the complainant cancelling scheduled appointments for RX to attend the property. Further, RX informed the insurer on 10 March 2022, that the complainant told RX not to attend the property until her AFCA complaint was finalised. The complainant denies this, saying the insurer or JL terminated RX’s retainer. The insurer has provided RX’s inventory of contents damaged by the storm. All items are noted as non-salvageable except for three items designated restorable, which the complainant wanted restored. Those items are a timber antique dresser, a piano and a timber glass display cabinet. Claim is to be cash settled The policy provides that when settling a covered claim, the insurer may choose between attending to repairs/replacement or paying the complainant the amount it would reasonably cost the insurer to do so (cash settling). Generally, a ‘new for old’ approach is to be adopted. The insurer has an overarching obligation to act reasonably in exercising its policy rights. The panel is satisfied that the all aspects of the claim should be cash settled because:  the relationship between the parties has significantly deteriorated  there is persuasive evidence of covered and uncovered damage, meaning the insurer and its trades will not be able to warrant all repairs  the ongoing delay in resolution is resulting in further damage being sustained. A cash settlement must be based on a quote that would be actionable and must allow an uplift for contingencies and for the loss of warranty applying to insurer authorised repairs. The insurer was prepared to attend to the roof repairs as 21 January 2022. On the available information, the panel is on balance satisfied that the complainant is responsible for the delay in having the roof repaired since then and the associated further water damage. The panel considers that as at late January 2022, JL’s roof repair SOW/quote was actionable. Further, the panel is satisfied that its proposed repair methodology (repair the roof then attend to internal repairs) was reasonable. The panel notes that JL repeatedly confirmed it would be able to attend to the ceiling repairs after the roof was fixed. Further, if the internal repairs were attended to first, there would be a risk of additional water ingress and damage pending completion of the roof repair. In the circumstances, the panel does not find persuasive the brief letter from AP indicating the internal repairs should be done first. JB’s quote was prepared three months after the insurer indicated it was able to attend to the roof repairs. It is reasonable to assume that additional water ingress (for which the insurer was not responsible) occurred over those three months. Accordingly, the panel does not consider JB’s quote dated 5 May 2022 to be a reasonable reflection of the extent of the insurer’s liability for the roof d amage. The panel also notes that JB’s quote lacks detail when compared to the JL SOW/quote. Further, the quotes are not like for like as the JB quote includes internal damage items. The only available quote in relation to the veranda damage is that provided by JL. As at January 2022, the insurer was prepared to cash settle the veranda claim for the amount JL Determination | Case number: 860178 Page 5 of 8 had quoted. To the extent the veranda has deteriorated since then, the panel considers the complainant is responsible for that deterioration. There is no objective evidence to suggest that JL’s quote is insuffic ient to account for the veranda damage which is to be covered under the policy. Accordingly, the panel is not satisfied that the insurer has any obligation to obtain a second quote for the veranda damage. The panel is satisfied that a reasonable contingencies uplift to apply to JL’s quotes for the roof and veranda repairs is 20%. T he panel considers the insurer’s inventory to be a reasonable basis on which the content s claim may be settled. Almost all of the listed items were unsalvageable. In terms of the three items the complainant wanted restored, it is unclear whether that remains possible. The panel also notes the policy limits the amount payable for unspecified antiques to $1,000 per item. Accordingly, the panel considers it fair and reasonable for the insurer to settle the contents claim by paying for all of the items on the inventory list on a ‘new for old’ replacement basis. The $1,000 limit is to apply to the timber antique dresser. The same limit will apply to any other antiques, and the total amount payable for all antiques under the policy is $5,000. To the extent additional contents damage has been sustained due to water ingress since January 2022, the insurer is not responsible for that damage. No uplift is payable as the insurer will be paying the contents claim based on current pricing. The panel acknowledges that the insurer is yet to formally assess the internal damage to the property. However, for the reasons previously outlined, it considers that aspect of the claim should also be cash settled promptly. The insurer and JL would have sufficient information on file from attending trades and the complainant to enable preparation by JL of a desktop SOW/quote on the internal damage as at the end of January 2022. Consistent with the insurer’s commitment on 31 January 2022 , the SOW/quote is to include all damage related to the make safe issues up to that point of time. The panel is satisfied that the insurer is not responsible for any additional internal damage post January 2022. Recognising that the internal damage claim is to be paid without completion of a formal on- site assessment of the storm related damage alone as at the end of January 2022 (which, due to the passage of time and continuing water ingress damage, is likely to be difficult), the panel considers an appropriate uplift to be 30%. Accordingly, if the complainant provides written notice that she accepts this determination, the insurer is to:  within 14 days of rec eiving the notice, pay her $90,708.05 for the roof damage (JL’s roof quote plus 20%)  within 14 days of receiving the notice, pay her $38,887.93 for the veranda damage (JL’s veranda quote plus 20%)  within 21 days of receiving the notice, complete a ‘new for old’ valuation of the contents claim using RX’s inventory list. All items are to be treated as non -salvageable. Policy limits and sub limits are to apply  within 14 days of completing the contents claim valuation, provide the complainant with a copy of the valuation and pay her the valuation amount  within 7 days of receiving the notice, request JL to complete a desktop SOW/quote for the internal damage as at 31 January 2022, including any additional damage caused to that point by the make safe issues Determination | Case number: 860178 Page 6 of 8  within 14 days of receiving JL’s SOW/quote, provide a copy of it to the complainant and pay her the quoted amount plus 30%. To the extent any applicable excesses that apply have not been paid, the insurer is entitled to deduct those excesses from the settlement amounts. 2.2 Is the complainant entitled to further TA costs? Yes. The panel is satisfied the insurer’s proposal to pay out the remaining 33 weeks of the TA benefit is reasonable, taking into account the extent of repairs required but given that it did not significantly contribute to the delays experienced. The rate is to be increased for inflation. Policy provides TA costs cover The policy includes as an automatic additional benefit cover for TA costs, as follows: When an insured event damages the building to the extent you cannot live there, and we agree, we will pay for your reasonable temporary accommodation costs for the time it will take to repair or rebuild the building to a liveable condition. As the complainant holds ‘complete replacement’ building cov er, there is no monetary limit applicable. However, the maximum indemnity period is 52 weeks. Insurer has paid for TA The complainant says that no ‘concrete offer of emergency housing was made’ . However, the insurer’s claim notes confirm that the insurer offered TA 11 times between 14 June 2021 and 24 September 2021. Further, the insurer has paid for 19 weeks of emergency accommodation. Insurer has offered to pay further TA costs In its second additional notice of response dated 2 June 2022, the insurer said: The insurer is prepared to pay out the remaining 33 weeks of temporary accommodation that is provided for under the customer’s policy (52 weeks, of which 19 have been used) at a rate of $454 per week. To avoid all doubt, in addition to what has already been paid the insurer is able to provide a payment of $14,932. The $454/week rate was calculated by averaging the rental rates for three properties in the complainant’s area. Insurer offer is reasonable subject to a rate increase The panel is satisfied that the insurer is not responsible for delays experienced since January 2022. Accordingly, the insurer’s obligation to pay for TA is limited to that set out in the policy. The insurer’s offer to pay out the remaining 33 weeks of the maximum indemnity per iod specified in the policy is reasonable. Determination | Case number: 860178 Page 7 of 8 However, it is reasonable to increase the applicable rate to allow for the likelihood rental rates have increased in the six months since 2 June 2022. The panel regards $475/week as fair. Accordingly, the insurer is to pay the complainant $15,675 for additional TA costs. 2.3 Is non-financial loss compensation payable? Yes . There were some deficiencies in the insurer’s claim handling. These issues contributed to the complainant’s stress and inconvenience. The insurer i s to pay her $1,000 in non- financial loss compensation. AFCA can award compensation for poor claim handling Under paragraph D.3 of the AFCA Rules, we may award compensation for non-financial loss (capped at $5,400) where the insurer’s actions have caused an unusual amount of:  physical inconvenience  time taken to resolve the situation  interference with the complainant’s expectation of enjoyment or peace of mind. Insurer’s claim handling contributed to the complainant’s stress The complainant says the claim process and failed make-safe repairs have caused her unnecessary stress and inconvenience. She has provided a letter dated 2 May 2022 from her GP that states: [the complainant] has been struggling with physical and mental health (adjustment disorder with anxious and depressed mood) after her house was damaged by a severe storm in June 2021. The panel notes that the insurer has offered counselling services to the complainant on a number of occasions, including on 24 June 2021. It is also satisfied that the insurer is not responsible for delays experienced after January 2022. There were issues with progression of the claim between June 2021 and January 2022. Some delays were for reasons out of the insurer’s control, such as the impact of COVID -19 and the complainant’s cancellation of pre -arranged appointments. However, having considered all of the available information, the panel is satisfied that during the first seven months of the claim, the insurer did to a degree contribute to the delays experienced. Further, there were occasions when its communications caused the complainant confusion and concern. The panel accepts that these issues contributed to the stress and inconvenience the complainant experienced. While th e insurer’s contribution was not signi ficant overall, it is fair that it pays the complainant some non-financial loss compensation. The insurer is to pay her $1,000. 2.4 Why is the outcome fair? The insurer’s approach to the claim has overall been reasonable. However, the delays experienced and resulting additional damage mean it is fair that steps be taken to cash settle the entire claim as soon as possible. While the insurer did not significantly contribute to the delays, there were some claim handling issues. It is fair that it pays $1,000 in compensation. Determination | Case number: 860178 Page 8 of 8 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. A panel determined this matter Due to the nature of this complaint, we referred it to a panel for determination. The panel includes:  an ombudsman  a member with significant experience in consumer and small business advocacy  a member with extensive experience in the insurance industry. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.