Insurer declined cover for part of building damage, attributing it to natural ground movement rather than escape of liquid
Text of the determination
Amended Determination
Case number 859219
Financial firm AAI Limited
Amended Determination | Case number: 859219 Page 1 of 15
Case number: 859219 20 June 2023
1 Determination overview
1.1 Complaint
On or about 23 July 2019 the complainant represented by her daughter lodged a claim with
the financial firm (insurer) for building damage caused by a leaking sewer pipe.
The insurer accepted that some of the damage was caused by an escape of liquid covered by
the policy. It declined cover for the remaining damage on the basis it was caused by natural
ground movement.
The complainant is seeking payment of $64,416 for building damage, temporary
accommodation during repairs estimated at $23,400 , payment of her expert’s and lawyer’s
fees and payment of compensation estimated at $50,000.
1.2 Issues and key findings
Has the complainant established that the proximate cause of damage was from
an escape of liquid?
Yes. The complainant has established that escape of liquid was the proximate cause for
damage to the house.
Is the insurer entitled to rely on the earth movement exclusion?
No. The insurer has not established that earth movement was an independent cause of the
damage that occurred in 2019.
What is the extent of damage caused by the escape of fluid?
The cracking and displacement damage caused by the escape of fluid is to the whole of the
complainant’s house.
Is the complainant entitled to compensation for non-financial loss?
It is fair in circumstances the insurer pays $2,000 non-financial loss compensation.
Why is the outcome fair?
The outcome is fair as there was substantial evidence that the insured event of escape of
water was the proximate cause even though there may have been other contributing factors.
1.3 Determination
This determination is in favour of the complainant.
Within 14 days of this determination being accepted the insurer is to;
cash settle the complainant in the sum of $64,312.60, less the $18,150 previously paid.
pay the complainant $10,000 accommodation allowance, $5,000 in respect of expert fees
and $2,000 in respect of non-financial loss compensation.
Amended Determination | Case number: 859219 Page 2 of 15
2 Reasons for determination
2.1 Has the complainant established that the proximate cause
of damage was from escape of liquid?
Yes, the complainant has established that escape of liquid was the proximate cause for
damage to the house.
The policy covers loss or damage caused by an escape of liquid
The insurance policy covers loss or damage caused by an escape of liquid from any drains,
fixed pipes, rainwater downpipes, drainage and sewerage systems, subject to policy terms
and conditions. No dispute is raised as to the complainant receiving a copy of the relevant
policy wording.
The complainant is required to show on the balance of probabilities (that is, more likely than
not) that the claimed damage was caused by an insured event, namely the escape of liquid. If
this can be established, then the insurer has the same burden of proof, if it wishes to rely on
an exclusion to policy coverage.
In cases such as this where there is evidence of multiple causes in play the accepted
approach is to seek to identify the proximate cause. The proximate (effective) cause of
damage is not necessarily the first, last or sole cause of damage. It is what had the most
significant impact in bringing about the claimed damage.
The expert evidence shows damage was caused or contributed to by escape of
liquid
The complainant’s family had owned and occupied the home since 1983. During 2019 the
complainant experienced cracking damage throughout her house, floor displacement and
jamming doors. The complainant is reported to have said the cracking damage had occurred
over the last 12 months but worsened over the last 6 months.
She engaged a restumper to look at the house foundations. He reported substantial sub floor
moisture below the middle of the house down to the depth of the foundations. The
complainant engaged a plumber who in early June 2019 detected and repaired a leak in the
sewer line along the north side of the property. It is unknown how long the sewer line was
leaking. The plumber had to break up and remove a section of concrete pavement. This left a
missing paver. This area continued to remain moist from surface flow.
The insurer was contacted on 23 July 2019 and a make safe carried out on 12 August 2019.
In particular the front and rear doors of the property were jammed, presenting a safety
hazard. Interim replacement doors were installed. On 21 August 2019 BP did a leak detection
report for the insurer and which found water leaking from a loose stormwater connection.
The insurer arranged a report by engineers HE dated 11 September 2019. HE concluded
there were seasonal changes in moisture content of the foundational material. HE also found
there was poor site surface drainage in breach of the relevant building code and that the
concrete pavement along the east side of the house was allowing surface water to enter
under the house. Soil mapping indicated the soil was highly reactive clay soil and this was
later confirmed by soil testing.
Amended Determination | Case number: 859219 Page 3 of 15
HE concluded that seasonal changes in the moisture content of the foundation material were
accentuated by the sewer leak resulting in the cracking and movement occurring in the north
east and north west bedrooms. Further HE considered that a leaking stormwater pipe
contributed to damage to the kitchen area and south east bedroom.
On the basis of the findings in this report by HE, the insurer accepted there was a valid claim
for damage caused by escape of liquid. However, it disputed the extent of contribution and
extent of the damage. In effect the insurer has accepted that the escape of liquid was a
proximate cause for at least part of the loss.
In the circumstances, I am persuaded the complainant has established a valid claim for
escape of liquid. However, the complainant still needs to prove the extent of damage, whether
it is to part only (as argued by the insurer) or all of the house.
2.2 Is the insurer entitled to rely on the earth movement
exclusion?
No, the insurer has not established that earth movement was an independent cause of the
damage that occurred in 2019.
Insurer relies on exclusion for ground movement
The insurer also relies on an exclusion to the policy coverage: for damage caused by ground
movement (see 3.2 below). Accordingly, the burden of proof shifts to the insurer to establish
the facts that support the exclusion.
Importantly I note it is AFCA’s approach that ground movement caused by an escape of liquid
is covered by the policy.
On 8 October 2019 the insurer’s assessor completed his report. The assessor noted that the
concrete paving around the house needed to be replaced so that it drained away from the
residence, instead of allowing surface runoff to drain under the house. He advised the
complainant that after this work was done a 12 month drying out period was required before
any further remedial work. On 1 December 2019 the complainant advised the insurer that her
plumber had fixed the stormwater connection.
Maintenance work to concrete pavers not attended to, resulting in ongoing
moisture and damage
Unfortunately, the concrete paving around the house was not fixed and this apparently
continued to contribute to the under floor area remaining damp.
There is uncertainty as to whether the complainant was advised in 2019 that it was her
responsibility to rectify the missing concrete paver and remove and replace the pavers which
were found to be contributing to dampness from surface runoff.
In July 2020 HE reported water pooling where there was a concrete paver missing after the
sewer repair. In the Assessor ’ s Report of 1 July 2020 the Assessor notes there is the missing
paver plus 12 square metres plus 3.5M x 1.8M of paving on the left hand side to be rectified.
He says “ this is claims related damages ”. He states there is another 8M x 1.8M on the left
hand side which is from ground movement and is the complainant’s responsibility to fix.
In a 22 July 2020 email from a claims officer to the complainant it is stated that to get the
property dry properly we need to rectify the concrete surrounds and adds “ much of this is
covered under the claim however there is the portion on the left hand side is your
Amended Determination | Case number: 859219 Page 4 of 15
responsibility”. In an email reply of 23 July 2020 the complainant refers to negligence by the
insurer in that the concrete pavement had not been fixed previously making it impossible for
the soil to dry out. The claims officer replied on 24 July 2020, “ I apologise for not clarifying in
my prior em ail that the concrete should have been removed by (the insurer)”.
The file contains a quote by the builder JL dated 10 August 2020 in the sum of $30,634 to
replace 43sqm of paving. There is a separate quote by JL dated 21 August 2020 in the sum
of $23,851 to replace 26sqm of the concrete pavement. This latter was said to be the
complainant’s responsibility. The complainant apparently objected to the amount and lack of
detail of the quote.
JL provided a third quote dated 24 August 2020 in the sum of $18,150 to undertake the post-
drying out repairs, namely preparing a proper water flow plan, replacing concrete pavers and
internal painting and plastering (but only for the two northern bedrooms).
T he 6 April 2021 assessor’s report expresses surprise that the complainant has not done any
of the maintenance work to the paving. However, neither did the insurer undertake the
rectification work which it had accepted as claim related. The result was that the sub floor soil
did not dry out. The assessor in his report of 27 April 2021 accepted that the fact that the
maintenance work was not done had resulted in further seepage and further earth movement.
Expert engineers disagree on cause of movement to house
HE reinspected and provided a report dated 21 August 2020. HE again concluded seasonal
changes in moisture content were the main cause accentuated by the sewer leak but that
damage was confined to the two north bedrooms. HE observed that the ground movement
predated installation of the kitchen because the kitchen kick boards had been cut to the
shape of the uneven floor. The insurer subsequently accepted this latter observation was
incorrect. This undermined confidence in HE.
The complainant retained an engineer J who provided a report of 31 January 2021. J
concluded that the failure to replace the removed concrete paver had caused ongoing pooling
of water which then flowed below the house. J provided a scope of works and estimate of
$48,138 to undertake repairs to the property.
The insurer retained engineer ME who provided a report dated 23 April 2021. ME concluded
that the nature of the break in the sewer pipe meant there would not have been any leaking
and that the break in the stormwater pipe was a hairline fracture from which there would have
been no significant leak. ME concluded the sewer and stormwater drainage system were not
the proximate cause nor exacerbating factors. Further ME identified and photographed:
pre-existing crack repairs in external brickwork.
pre-existing fillings and repairs in corners and wall linings
pre-existing cracking in concrete surfaces. The complainant informed him of cement
patching work some 11 years earlier.
I note also that the BP plumbing report of 21 April 2019 mentions the complainant had
painted over cracks “ last Christmas ” , but the cracks had come back.
The insurer maintained the $18,150 estimate of JL was correct and, as the complainant was
unwilling to rectify the concrete pavers, offered to cash settle this amount. In June 2021 the
complainant told the insurer she had not received the previous reports of required
maintenance work and related reports. These were provided to her. I understand the insurer
then paid the cash settlement amount of $18,150 into the complainant’s bank account. The
complainant was unaware of this payment at the time and it is not taken to have been an
Amended Determination | Case number: 859219 Page 5 of 15
agreed final settlement. The insurer I understand has separately paid an amount in respect of
the original plumber’s invoice that represe nts investigation costs.
ME and J provided further expert and generally conflicting commentary in August, September
and October 2022. J expressed the view that the problem with the paving was due to
subsidence from the water leaks. This appears to be speculative. However, J did obtain
photographs from the June 2019 sewer repairs which indicate significant escape of liquid.
The fact that the sub floor area remained damp is an indicator that the leaking pipes were not
the only active causes. However, J expressed the view that the unrectified exposed area
where the concrete was removed for the sewer repair was the cause of the ongoing
dampness.
On balance and considering the fact that ME’s observations were 2 years after the event I am
inclined to accept the sewer leak, and possibly to a lesser extent the stormwater leak, were
the proximate causes of the cracking and displacement damage that occurred in 2019. I
accept there was some pre-existing damage and that due to the unrectified surface run off
issues, this was likely ongoing, but insufficient to have caused the more severe earth
movement and damage in 2019. Accordingly I am not persuaded by the insurer on the
balance of probabilities that the earth movement exclusion applies to the damage that
occurred in 2019.
So far as I am aware the paving work has never been undertaken. Due to passage of time J
increased his estimate of loss to $64,416 as at July 2022. The insurer’s Notice of Response
explains that the pavement rectification was not done because the complainant thought the
insurer should be paying for all of it and further it was more economical to fix all the paving at
the same time. In light of the above July 2020 emails, I am not satisfied by this explanation.
2.3 What is the extent of damage caused by the escape of
fluid?
The cracking and displacement damage caused by the escape of fluid is to the whole of the
compla inant’s house.
Complainant has the burden of proving the extent of damage caused
It is the complainant that has the burden of proving the extent of damage caused by the
insured event. I accept there was natural ground movement arising from seasonal changes in
moisture content and that poor surface drainage would have contributed to that ground
movement. However, damage which occurred before 2019 had been repaired by the
complainant.
I accept also that some of the ongoing damage could be attributed to natural ground
movement. Both parties agree that damage continued after 2019 and that this is due to the
failure to attend to rectification and maintenance work on the concrete pavers. In my view this
is a result of the insurer not meeting its policy obligations in a timely manner. In any event I
am satisfied the proximate cause remains the escape of liquid and I do not see a basis for
any reduction or apportionment. The stumping and packing of foundations is required in any
event and cracks require filling even if they have slightly increased since 2019.
I do not accept the comment of HE that the damage can be confined to the two northern
bedrooms. This seems unlikely. HE’s original view was that the damage was more
widespread. The stumper and plumber in 2019 reported the ground under the middle of the
Amended Determination | Case number: 859219 Page 6 of 15
house was drenched. Further, the urgent stay safe repairs involved fixing both the front and
rear doors of the house.
What steps must the insurer take to resolve the complaint?
The insurer is required to replace or repair the displacement and cracking damage caused by
the escape of liquid. The scope of work prepared by JL does not cover the whole property
and is inadequate. The scope of work and cost assessment dated 19 July 2022 prepared by J
appears to provide for the damage caused and includes the concrete pavement work for
which the insurer is responsible, save that there is no evidence before me to justify
rectification of the front paving ($5950) and which item should be excluded. After deducting
this amount, the total costing comes to $ 58,466 . It is an assessment not a quote. It is
appropriate in my view to include a modest uplift of 10% to account for contingencies. The
insurer is to proceed to cash settle the complainant in the sum of $64,312.60.
This outcome is fair because a cash settlement is the only mode of resolution available and
the material shows the amount of the cash settlement is reasonable.
The insurer to pay an amount for temporary accommodation
It is likely in the circumstances that temporary accommodation will be required by the
complainant. The complainant proposed a figure of $20,000. The insurer is to include an
allowance in the cash settlement in the sum of $10,000 for temporary accommodation.
The insurer is to pay an amount for complainant’s costs of dealing with the
complaint
The complainant pai d $7,590 for J’s assistance as an expert.
AFCA may require an insurer to reimburse a complainant for their costs of dealing with the
complaint, including expert fees. We will only do so where such fees are reasonable, and the
expert’s assistance helped re solve the claim. Unless there are exceptional circumstances, we
will not require the insurer to contribute more than $5,000 to these costs.
In my view the insurer should pay the sum of $5,000 in respect of J’s costs. The complainant
also incurred some out of pocket legal fees but the relevance and utility of this legal
assistance is not apparent on the AFCA file. I am not persuaded to require the insurer to
reimburse these costs.
2.4 Is the complainant entitled to compensation for non
financial loss?
It is fair in circumstances the insurer pays $2,000 non-financial loss compensation.
It is fair the insurer pays non-financial loss compensation
Under the AFCA Rules, we can award up to $5,400 compensation for non-financial loss. We
will only award this type of compensation if the complainant suffers an unusual degree of
stress, inconvenience, or delay because the insurer mishandled the claim.
While the complaint involved legitimate and complex issues , I am persuaded the insurer’s
handling was less than ideal, in particular the failure to remedy the gap caused by the
plumber’s removal of concrete pavers.
Amended Determination | Case number: 859219 Page 7 of 15
I am satisfied the complainant who is an older woman suffered an unusual degree of stress
and inconvenience. The complainant had a number of falls which her daughter attributed to
the uneven surfaces. This risk could have been reduced if repairs had been done promptly.
It is fair the insurer pays $2,000 non-financial loss compensation.
2.5 Why is the outcome fair?
The outcome is fair
The outcome is fair as there was substantial evidence that the insured event of escape of
water was the proximate cause even though there may have been other contributing factors.
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
Amended Determination | Case number: 859219 Page 8 of 15
3.2 Policy terms and Evidence
Expert Report Extracts
Report Key P oints
Amended Determination | Case number: 859219 Page 9 of 15
Report Key P oints
HE Report
01 - 08 - 2019
It was reported by the owner that cracking of the internal areas of
the dwelling and jamming of the internal doors was first observed
to be occurring approximately 12 months ago and was observed to
have worsened approximat ely 6 months ago
It was reported by the owner that a leaking sewer drain was found
adjacent to the nor th wall of the dwelling and the rear bedrooms
which was subsequently repaired in June 2019.
An inspection of the stormwater drains in the sub - floor showed
that one of the fittings where the stormwater drain exits under the
house is loose which is allowing water to escape into the sub - floor
area and is causing the ground to be wet and muddy in this area.
It was reported by the plumber that this loose fitting was located
below the east side of the residence, near the ducted heating
motor.
A visual inspection of the sub - floor area showed that the ground
along the bas e brickwork is damp in areas and it is mentioned in
the report that the drainage around the house is poor for surface
water.
In our opinion, in this case the seasonal changes in the moisture
content of the foundation material have been accentuated by the
leaking service pipe in the vicinity of the east side of the residence.
In our opinion, the leaking service pipe has accentuated the
differential settlement of the footings and resultant
cracking/mo vement of the structure above on the east side of the
residence.
In our opinion, the leaking service pipe has contributed to the
cracking/movement occurring in the kitchen area and south - east
bedroom only.
In our opinion, the poor site surface drainage has accentuated the
differential settlement of the footings and resultant movement of
the structure above, on the east side of the dwelling.
In our opinion, the cracking and movement occurring in the north
east and north west bedrooms is a result of different ial settlement
of the footings due to seasonal changes in the moisture content of
the foundation material being accentuated by the recent sewer
leak.
We would recommend that a monit oring period of approximat ely
12 mont hs be carried out
Asse ssor Report
08 - 10 - 2019
H ave spoken to the customer about the engineer’s report and
finding. I would recommend a copy of the SOW and engineers
report be sent to the customer for review.
The customer is also looking at claiming under ex ploratory costs
for the breaking of the concrete to fix the leaking pipe. The policy
limit of 5750 applies –
please have customer supply invoices for re instatement
/exploration prior to paying.
[Complainant] advis ed that since Marc h they had noticed some
Amended Determination | Case number: 859219 Page 10 of 15
Report Key P oints
movement in the house. They had a trade attend to attempt to re
stump the home. When the trade tried to re stump, as he dug
deep, he noticed wat er pooling. The customer has then had a
plumber attend to inspect the found a broken pipe at the back of
the home.
HE Report
19 - 02 - 2020
The site has been classified as a Class P (Problem Site) due to
trees on and near the property, with a soil classification H1 which
is a Highly Reactive Clay Soil.
Moisture content readings at the rear of the residence, near
where the sewer leak occurred, showed the moisture content to
be elevat ed up to 1,100mm deep.
Asse ssor Report
01 - 07 - 2020
Soil under home at rear from the subfloor access was still moist
Missing concrete paving at the rear of approx 2m x 1m where
leaking stormwat er pipe was repaired has not been replaced . This
is allowing rainwat er to pool and seep under house preventing soil
from drying
This area of missing concrete paving and approx a further 12m x
1m plus a section of the LHS appr ox 3.5m x 1.8m needs to be
removed and replaced and graded away from the house before
any further moisture tests are carried out. This is claim related
damages and will be scoped by [J]
The above paving has been identified by the engineer as
damaged by the event
There are further areas of paving that slope towards the house on
the LHS which is due to ground movement over the years that
needs to be redone as part of the customers liability approx 8m x
1.8m
Assessor informed [complainant] that all the claim r elated
damaged concrete needs to be replaced & graded away from the
home before the drying process properly commences.
Asse ssor Report
13 - 08 - 2020
[J] are to submit sow/quote for private works onto the customers to
review. (if private works are not accept ed by the customer the
entire claimable damages as per sow/quote need to be C/S.
The customers were advised on the 1/ 7/20 by the assessor that all
drainage/upgrades & additional concret e work approx. 14.4m2
need to be carried out before any of the claim relat ed damages
can be reinstated. (Customers asked [J] to quote for the private
works)
HE Report
21 - 08 - 2020
In addition to the observations made during our first sit e
inspection, it was noted that the kickboards of the kitchen
cupboards vary in height and have been cut in order to
accommodate the unevenness of the kitchen floor. T
This indicates that movement of the kitchen occurred prior to the
kitchen cupboards bein g installed, (Photos 1 to 4).
Amended Determination | Case number: 859219 Page 11 of 15
Report Key P oints
In our opinion the seasonal changes in the moisture content have
also been accentuated by the previously leaking sewer pipe
adjacent to the north wall of the residence. In our opinion the
previously leaking pipe has accentuate d the differential settlement
of the footings and cracking/ movement of the two bedrooms at
the north end of the residence.
In our opinion the previous leaking sewer pipe has not affected the
remainder of the residence, which occurs uphill of the leak
loca tion.
Therefore, in our opinion, the damage that has occurred to the
residence at the above property is a result of differential settlement
of the footings due to the following factors: - Seasonal changes in
the moisture content of the foundation materia l. Poor site surface
drainage. Leaking sewer drain (two north bedrooms only).
We would recommend that the concrete paving to the east side,
north end and rear west side of the residence be upgraded as
detailed on the drawings prepared by our office, inclu ding
temporarily covering the area where the paving adjacent to the
north wall has been removed
Once this has been carried out, we recommend that a drying out
period be allowed to elapse until the end of the following summer,
after whic h further soil testi ng can be carried out.
If the soil testing finds that the moisture level in the foundation
material has reached equilibrium, then a Scope of Works for
repairs to the rear two bedrooms can be formulated.
Asse ssor Report
24 - 08 - 2020
In engineer’s opinion, the seasonal changes in the moisture
content of the foundation material have been accentuated by the
poor site surface drainage on the east side of the residence,
where the paving grades towards the residence. In our opinion the
poor site surface drainage has accentuated the differential
settlement of the footings and resultant cracking/ movement of the
residence above.
The customers n eed to carry out the engineer’s recommendations
regarding the plumbing/ drainage upgrades & concrete paving
that’s n ot claim related & a drying out period be allowed to elapse
until the end of the following summer, after which furt her soil
testing can be carried out. If the customers do not wish to carry out
the recommend works, the claim needs to be Cash settled for th e
current sow/quote being $18,150.02 all Incl.
JM Report
31 - 01 - 2021
The Insured advised that on July 1, 2020 [the assessor] visited the
site and confirmed that the conc rete paving marked up on the
Explanatory Diagram attached would be replaced at [the insurer’s]
expense
18 mont hs have passed with the only corrective action taken by
[the insurer] being the replacement of the front and rear main
doors - refer Phot os 2, 3. The Insured advised that this delay has
Amended Determination | Case number: 859219 Page 12 of 15
Report Key P oints
been most stressful, noting the severe cracking througho ut much
of the house and obvious floor level misalignment and the lack of
corrective action by the Insurer.
Apart from the actual leak in the sewer, rainwater runoff has been
accumulating in the section of missing paving generating seepage
and spreading it widely under the house foundations. A
commitment was made by [the insurer] some 7 months ago to
replace it with no follow up action. Careful look at Photo 5
illustrates that this section of missing paving has been subject to
progressively collecting rainw ater since it was removed on June 3,
2019 and this has also contributed to the amount of water affecting
the foundations of the house.
The Explanatory Diagram clearly illustrates how this seepage has
not only affected the stability of the house foundations generally,
but has also caused misalignment of the front concrete path to the
street – refer Photos 11, 12 and 13.
Front Path Paving Also Damaged.
M Report
23 - 04 - 2021
The external ground surface levels graded towards the home and
absence of a surface st ormwater drainage system to collect
surface water run off to flow towards the home has caused surface
stormwat er runoff to flow towards the home and seep int o
underlying soils and subfloor over a long period of time, resulting
in long term building movemen t and subsidenc e.
The purported leaks to the sewer and stormwater drainage system
are not the proximate cause nor ex acerbating factors
Asse ssor Report
27 - 04 - 2021
D ue to pre - existing damages which are non - claim related we will
be arranging a settlement to the policy holder as per Johns Lyngs
quote totalling $18,150.12 in order for the repairs to be completed
on conclusion of the drying out period.
JM Email
06 - 08 - 2022
I refer to my original report on the leak damage assessment
dated January 31, 2021 and Explanatory Diagram dated
January 27, 2021 illustrating how the sewer leak had
caused widespread wetting under the house.
Being highly reactive soil moistur e induces foundation
movement causing considerable int ernal cracks, binding
doors and floor movement. I formed this view regarding the
sewer leak by inspecting the sub - floor via the sub - floor
access door located towards the northern end of the east
wall wh ich revealed the sub - floor area was wet.. Following
AFCA’s request for my furt her involvement for technical
comments on the GIO " Notice of Response", I have now
become aware of an additional leak source - stormwater
drain fairly close to the leaking sewer d rain.
In retrospect, leaks from both the sewer and stormwater
drains have therefore combined to cause widespread
wetting of the sub - floor ground.
Accordingly, please find a revised Explanatory Diagram
dated illustrating how the combined affect of both le ak
sources have, in my opinion, affected the hous e foundation
Amended Determination | Case number: 859219 Page 13 of 15
Report Key P oints
stability. Both the sewer leak and stormwater drain leaks
would have readily fed along the sub - floor via their
respective trenc hes extending under the sub - floor with a
general ground fall toward s the front of the house. There is
no way of determining the length of time that both leaks had
persis ted before they were identified.
M Report
15 - 09 - 2022
This report is to undertake a review of the supplied
documentation and provide reply to the queries raised wit hin
the instruction.
M Report on 91151 (23 - 04 - 2021) remains current and valid.
M Report 91151 Item 7. 19.3 outlines hairline cracking to a
junction and would not allow any significant volume to
escape from the pipework to cause the claimed global
movement and building damage
M Report 91151 reiterates the Bourke Plumbing Services
work order report that outlines that the pipes were likely
damaged due to ground movement indicating pre - existing
movement
M Report 91151 Item 9. 3.8 outlines that the purp orted slight
dislodgement to the stormwater drainage system would not
readily allow any signific ant volume of water to leak.
Comment in relation to the response of building party for the
replacement of the concrete pavement cannot be provided
by M.
The com ments acknowledge that the perimet er pavements
fall towards the home, acknowledging that the pavement
falls do not meet the minimum requirements of Part 3.1.3.3
of the BCA and allows a surface stormwater run - off to flow
towards the building perimeter durin g periods of rainfall,
however this prominent source of moisture has been
completely excluded as a proximate cause of the source of
the
moisture and/or building movement
The inappropriat ely graded pavements have been allowing
surface stormwater run - off to flow into the subfloor and
subsoils since the home’s construction in
1983, for an approximate 39 year period.
A pool of wat er below the pipe does not indicate a leak. The
pooling of water may be due to rain, surfac e stormwater run -
off, water seepage, etc. The muddy conditions have been
caused by the long - t erm surfac e stormwater runoff allowing
water to flow toward s and drain into the underlying soil and
the subfloor since the construction of the home in 1983, for
an approximate 39 year period.
Amended Determination | Case number: 859219 Page 14 of 15
Report Key P oints
JM Report
26 - 09 - 2022
[M] opinion that the leaking stormwater drain appears to be
contradicted by [FF] plumber and [HE]. [BP] who found the
leaking stormwat er drain (Aug 21, 2019) reported the
ground was wet at the time. Further, [HE] Geotech
Investigat or in report Feb 4, 2020 also confirmed that the
ground was wet. Significantly, Photo 6 shows that bot h the
stormwat er and s ewer drains are locat ed close to one
another.
Photos 6, 8, 10 are various views of the concrete paving
which I believe would have been level when originally laid
and has subsided because of long term ground saturation of
the soil supporting it due to leaks . This paving has still
provided a sealed surface around the house preventing
rainwater from being absorbed into the ground. There has
been no long term hous e instability since the house was
built in 1983 contrary to [M] opinion. The internal binding
doors , floor movement Wall and ceiling cracks only
developed several months before the sewer leak was
discovered in June 2019. This confirms that stable support
for the house had been provided for approximately 36 years.
There has been no downpipe discharge as the downpipes
are connected to underground drains at the rear of the
house where the seepage under the house has been
sourced. Photo 6 clearly shows that the downpipe is
connected to a stormwater drain laid under the floor of the
house
M Report
18 - 10 - 2022
The purported damaged sewer pipe is external to the
perimeter of the home, is not beneath the footing system
and not within the subfloor, is not severely damaged and
has not been substantially feeding moisture directly into the
subfloor.
The oc currence of moisture ingress seeping through to the
underlying soils is a long term issue, developing over a
period of several years/dec ades and not related to a short
term event
The downpipes to the rear patio discharges directly onto the
concrete pavemen t and is not connected to the stormwat er
drainage system
MCS Report 91151 Image 10 demonstrates the concrete
pavement is graded towards the subfloor hatch and allows
surface stormwater run - off to drain into the subfloor during
periods of rain.
Amended Determination | Case number: 859219 Page 15 of 15
Report Key P oints
JM Final R esponse
22 - 10 - 2022
I have now illustrated on Photo 6 that marks on the
brickwork clearly confirm that the leaking sewer has caused
the paving to settle.
A secondary associated issue is the timing of the house
instability. [M] incorrectly alleges the hous e instability has
been long term from the time the house was first
constructed. However, the house was built in 1983 and
internal cracks/binding doors and floor movement did not
occur until 2018 and this prompted the sewer leak
investigations.
Photo 50 clear ly confirms that the leaking sewer was deep
and beneath the rear footing. The weather was dry at the
time of the sewer repair was dry yet there was a pool of
effluent when ex posed. With the site falling directly from rear
to front, this seepage would have fanned out under the floor
of the house as illustrated on the attached Explanatory
Diagram. The subfloor ground dampness was confirmed by
the underpinner in May 2019 who advised that the
excessively damp stump foundations could not be worked
on as there wa s a suspected leak. This led to the sewer leak
being discovered.
Photo 9 illustrates the sub - floor dampness under the floor of
the house. Any loose fitting has a fundamental propensity to
leakage. Under heavy rain conditions with the pipe flowing
full lea kage must be expected
Photo 6 clearly illustrates that the paving had settled due to
the sewer leak softening the ground support for the paving.
Paving subsided bec ause of the sewer leak. It was not laid
with a fall towards the house contrary to what [M] i s alleging.
Refer Photo 6.