Claim settlement for water damage from burst pipe; cash settlement adequacy, contents, temporary accommodation
Text of the determination
Determination
Case number 858217
Financial firm Allianz Australia General Insurance Limited
Determination | Case number: 858217 Page 1 of 11
Case number: 858217 16 December 2022
1 Determination overview
1.1 Complaint
The complainants hold a home and contents insurance policy with the financial firm (insurer).
On 25 February 2021, they lodged a claim for water damage to their property from a burst
pipe. The insurer assessed and accepted the claim and authorised its preferred builder to
conduct the repairs, including mould remediation.
The repairer completed some work, and for the remaining repairs the insurer offered and paid
a cash settlement ($80,919.90) based on its builder’s scope of work and cost estimates. The
insurer says its builder cannot undertake further repairs due to changes made by the
complainants, including in the internal layout.
The complainants say the cash settlement is insufficient to reinstate the property, and does
not cover other costs including temporary accommodation and damaged contents. They also
say the insurer mismanaged the claim and caused significant stress, delays and
inconvenience, as well as additional damage to the property.
1.2 Issues and key findings
Is the insurer’s settlement of the claim fair an d reasonable?
No. The insurer is required to increase its settlement for claim-related repairs by paying a
further $70,773.14, which is the outstanding balance of $151,693.04 (being the quoted
amount of $137,903.04 plus 10% contingency of $13,790), less the $80,919.90 already paid.
The insurer is also liable for electricity costs it agreed to cover; and for damaged contents,
based on the list and values provided and claimed by the complainants. That includes the
queen bed and mould-affected blinds, subject to the complainants’ provision of reasonable
like-for-like costings for those particular items.
As well, the insurer is required to pay a further $61,600 for temporary accommodation
(calculated at $440 per night for the likely 16 week repair period plus an allowance of a further
4 weeks for potential delays).
The complainant has not established the insurer/its trades should be held responsible for any
extra damage (tiles or driveway), apart from additional reported mould which has occurred
since th e insurer’s initial repairs and which, on balance, is reasonably attributable to the claim
and delays in finalising the necessary repairs. The insurer is required to cover the cost of a
further mould assessment and any necessary remediation identified.
Are the complainants entitled to other compensation?
Yes. The insurer should pay $5,400 in non-financial loss compensation for the unusual
degree of stress and inconvenience suffered by the complainants because of the claims
handling. The insurer should also pay $2,190 towards the complainants’ builders’ quote/ report
costs ($990 and $1,200 respectively) plus statutory interest on those amounts.
Determination | Case number: 858217 Page 2 of 11
Why is the outcome fair?
This outcome is fair because the insurer’s cash settlement, on balance, is insufficient to
complete the outstanding claim-related work , and does not take account of the complainants’
damaged contents, or their entitlement to further temporary accommodation and other costs.
Th e insurer’s handling of the claim also caused significant unnecessary delays, stress and
inconvenience to the complainants in circumstances which were already unsettling and
difficult for them.
1.3 Determination
This determination is substantially in favour of the complainants. The insurer is required to
promptly settle the claim as set out in detail in section 2.1 below.
Determination | Case number: 858217 Page 3 of 11
2 Reasons for determination
2.1 Is insurer ’s settlement of the claim fair and reasonable?
Parties disagree on scope of work and suitability of insurer’s settlement
There is no dispute there was damage to the complainant’s home because of an insured
event.
Repairs were initially authorised based on the scope of works (SOW) provided by the
insurer’s builder, P. This has been subject to several variations during the repair process.
Then repair work by P stopped, on the insurer’s request. The parties disagree on the scope of
claim-related repair work still to be undertaken, and the standard of repairs already
completed.
Having authorised P to commence repairs, the insurer said:
> it is unable to undertake the remaining repairs because the complainants have
completed additional works using private contractors which no longer agree with the
original scope of works
> its cash settlement of $80,919.90 is based on the estimate provided by its preferred
builder (P) for the remaining claim-related work
> that amount has been paid to the complainants, along with any remaining amount for
which they are eligible under the policy for emergency accommodation
> the insurer has met its obligations under the policy terms and conditions.
The complainants submit:
> the insurer’s builder failed to complete the works as per the signed scope of works
> the insurer’s final scope of works is missing items required to reinstate the property to
its pre-loss condition
> the insurer should cash settle fairly using market rates as its builder failed to complete
the repairs
> the insurer’s cash settlement offer is insufficient based on comparison quotes obtained
from two local builders
> the insurer’s service provider caused additional damage to the property and the insurer
must take responsibility for the rectification works
> the insurer has not covered additional costs including for temporary accommodation,
contents, expert reports, agistment costs for horses
> they are entitled to compensation for stress and inconvenience.
Insurer’s scope of work and quote for internal damage is not fair or reasonable
Where an insurer decides to cash settle a claim, the settlement amount should be based on a
fair assessment of the cost to repair or rebuild the property. The amount offered should be
sufficient to ensure the complainants are able to engage their own contractors to complete
the necessary claim-related work.
O verall, the panel is not satisfied P’s quote encompasses the full scope of the claim -related
damage, nor that it reflects a quote which would be actionable by the complainants as retail
customers. In other words, the insurer’s proposed settlement for claim -related repairs does
not, on balance, represent the likely reasonable costs to the complainants of completing the
work for which the insurer is liable. By way of example:
Determination | Case number: 858217 Page 4 of 11
Walk-in robe
P allowed $896 to repair the walk- in robe. The complainants say P’s q uote does not include
labour and costs for replacing the architraves and reconnecting the light switch. To this, P
says the skirting boards have been supplied and the quote only reflects labour costs. P
estimates $18 for skirting board installation which, in the panel’s opinion , does not appear to
be a reasonable allowance. Additionally, P acknowledges 5LM of architraves is missing from
scope.
Bedroom 1
Complainants say P’s quote does not include all the skirting boards damaged by the event.
While P say their quote only made allowance for event-related damage, it acknowledges
10LM of architraves has not been included.
Kitchen
P’s estimate confirms the complainants had a Tasmanian Oak kitchen , but P says the
complainants have changed the lay-out and their quote is no longer tenable. However, the
SOWs provided by both builders sourced by the complainants (S and L) do not differ from
that of P’s with regard to the kitchen and the panel is not satisfied the complainants have
included upgrades in their quotes.
Ensuite
The c omplainants say P’s estimate does not account for several items , including:
> plumbing allowance to reconnect shower and bath
> install existing mirror
> install existing light hood
> supply and install architraves to entry doors.
While P says those costs have been included, that is not apparent in the estimate nor does
the plumbing allowance of $280 appear sufficient to complete all the plumbing works. There is
also no allowance for entry door architraves.
Toilet
The complainants say P’s quote does not include:
> costs to supply, install and paint window architraves (which were removed by P when
walls were removed)
> prepare and paint cornice
> reconnect all electrical as required (these items were disconnected by P and need to be
re-connected).
P has not provided any evidence to refute the complainants ’ comments.
The insurer is required to increase its cash settlement amount for repairs
Having considered all the available information, the panel does not consider the insurer’s
settlement for building repairs (which is based on P’s scope and quote) is fair or reasonable in
the circumstances. This is because P’s SOW is missing certain items and the quote is not
clearly actionable by the complainants as retail customers; nor does it allow for
contingencies/variations in labour or material costs, or the transfer of risk to the complainants.
Determination | Case number: 858217 Page 5 of 11
The panel considers it fair the claim- related building repairs be cash settled based on S’s
quote plus an additional 10% to allow for contingencies and the time which has passed since
the quote was issued (on 29 April 2022). That amounts to $151,693.04 (being the quoted
amount of $137,903.04 plus 10% contingency of $13,790).
The insurer has already paid the complainants an amount of $80,919.90 toward repairs. That
means the insurer is required to pay the outstanding balance, being $70,773.14.
Complainants have not shown additional damage caused by insurer’s trades
The complainants also say there is damage to the driveway because large skip bins were
placed there during repair works. As well, they say about 5 floor tiles are damaged because
of the claimed water leak event and/or due to trades placing heavy items on the floor. The
insurer, in response, says the damage was not caused by the claimed event or by its trades.
So, it denies liability for those matters.
The panel notes:
neither builder S (quote $137,903.04 dated 29 April 2022) nor L (quote $139,762.30 dated
13 June 2022) has provided sufficient information to demonstrate the proximate cause of
those additional losses
while the parties do not dispute skip bin(s) were placed on the driveway, a driveway is
normally designed to carry heavy weights, such as vehicles. While there appear to be
some scrape marks on the driveway (possibly from the skip bin), the cracks do not appear
to be recent
in terms of the floor tiles, the parties accept about 5 tiles were drummy. The complainants
presented quotes for replacing all the floor tiles for matching purposes
considering the entire floor was flooded, and given the time since the event (over a year), it
is reasonable to expect that if the claimed event was responsible, there would be more
damage than just to a small number of tiles
in addressing the tile issue, P noted the one cracked tile was unlikely to have been
damaged by the restoration work or their trades given its location; and they acknowledged
merely that it was ‘possible’ the claimed event could have contributed to the drum my tiles,
but recommended re-glue to address that.
Based on the information available, the panel is not satisfied the complainants have met their
onus to establish, on balance, the damaged driveway or tiles were the result of either the
insured event or the action s of the insurer’s trades. The insurer is not liable for that damage.
Additional temporary accommodation payable in the circumstances
The complainants are seeking further cover for temporary accommodation, given the delays
they say were caused by the insurer and P. However, the insurer says the complainants
delayed the claim-related repairs by carrying-out their own private works. The complainants
point out that any private works completed only took a few weeks, and P was aware of this
before they started repairs. It also appears that was in a different part of the property form
where P was working and so should not reasonably have caused any interference. Indeed,
the evidence indicates the complainants only engaged another builder on P‘s advice. It also
indicates P was already well behind schedule before any additional work was undertaken by
the complainants.
The information available shows P ceased work around the end of November 2021. The
insurer acknowledges it is normal to expect delays over the Christmas/New Year period,
however the panel is not satisfied that is sufficient to explain or justify the way the cessation
of repairs played out. In particular, it does not account for the serious communication failings
Determination | Case number: 858217 Page 6 of 11
with regard to keeping the complainants advised of the decision to stop repair work and to
cash settle for the remainder, and why or when that would happen.
The panel notes the complainants themselves initially took time to review the scope of works
and respond. In the circumstances, however, that is not unreasonable as they needed to
satisfy themselves the scope accurately reflected the work needed to bring their property
back to pre-loss condition.
The panel also notes that P provided several variation requests to the insurer during the claim
process, and these were approved by the insurer. That indicates the repairs were evolving
and required the complainants ’ further attention and input.
The panel considers the breakdown in communication between parties delayed the claim
process. That was largely the responsibility of the insurer, which effectively transferred
responsibility for managing and progressing the claim to the builder, and was neither
proactive nor reliably resp onsive to the complainants’ queries or concerns .
The policy covers the cost of emergency accommodation for up to 12 months or up to 10% of
the building sum insured, whichever is less. It applies if the insured home is unliveable, in
which case the insurer will cover the cost of ‘similar alternative accommodation’.
The complainants have already received accommodation payments equalling 10% of the
building sum insured. In the circumstances, however, the panel considers it fair and
appropriate that the insurer contributes further to temporary accommodation for the
complainant and his family to allow for the fact that repairs have still not been finalised and
the house is still not in a liveable condition.
It is not clear, on the evidence, exactly how long the outstanding repairs might take. Based on
the information available, the panel considers a repair timeframe of 16 weeks to be
reasonable. It is fair that the insurer covers emergency accommodation for a further 16 weeks
(in addition to what has already been paid), plus another 4 weeks to allow for potential delays,
either by arranging suitable temporary accommodation for that period or cash settling the
complainants based on a nightly rate of $440 for 20 weeks, bringing the total to $61,600.
In reaching that figure, the panel appreciates the difficult living arrangements the
complainants and their family have already experienced for a protracted period, while also
acknowledging the choice they have made to stay on their property to be close to their
animals.
Further emergency accommodation for pets (horses) not payable
As outlined in section 3.2, the policy provides limited cover up to $5,000 towards emergency
accommodation for pets under certain circumstances. The complainants say the insurer
caused unnecessary delays and so it should cover this benefit beyond the policy limit.
In response the insurer says the complainants’ horses are not pets and are considered
livestock and any liability is therefore constrained by the policy limit. There is no dispute the
complainants received the full policy benefit and the insurer says it is not required to make
further payments.
The policy is primarily for the building and contents. Emergency accommodation for pets is an
additional benefit with limited cover. The panel is satisfied that regardless of whether the
insurer’s or complainants’ builder completed the repair works, the complainants would have
needed to make necessary arrangements for their horses in any case, given the nature of
Determination | Case number: 858217 Page 7 of 11
their insurance policy and the extent of cover. Despite any delays in repairs or otherwise, the
panel does not consider the insurer should be liable for this benefit beyond the policy limit.
The panel notes, however, that the insurer’s builder initially gave the complainants incorrect
information about their entitlement under the policy for emergency pet accommodation. That
influenced their decision to stay on their property and live in very poor conditions (in their hay
shed) for a considerable period so that they could continue to care for their animals on site.
The award of compensation for non-financial loss (considered below) takes that into account.
The insurer is liable for electricity costs and some other claimed contents
The complainants say a number of contents items were damaged by the escape of water,
from consequential mould and works done by the insurer’s restorers. The complainants ’
submissions, exchanged with the insurer, include photographic evidence.
As well, the complainants seek cover for additional electricity costs incurred for restoration
works.
Electricity costs
In its correspondence dated 20 September 2021, the insurer agreed to cover the
complainants’ additional electricity costs incurred because of restoration works. The
complainants are required to provide evidence of the increased electricity costs incurred
during the relevant period, and the insurer is required to cover those costs, as it offered to do.
Statutory interest is to be added to the amount, calculated from the date the complainants
incurred the costs to the date of settlement.
Dining table, chairs and television unit
The complainants say the dining table/chairs and television cabinet were damaged by the
restorers during their mould remediation works, but the evidence does not substantiate that
claim. The insurer engaged RC to inspect these items and their report findings indicate, on
balance, the damage was pre-existing. The panel is not satisfied, on the available evidence,
that the complainants’ have established the insurer is responsible for the condition of those
contents items. The insurer is not liable for those items.
Blinds and other content items
The complainants say the blinds and other items were damaged by mould following the
event. The other items being claimed are listed (most with costings) in the complainants’ letter
to the insurer of January 2022, and include a range of bedding items (including queen bed),
hair dryer and straightener, and lounge suite.
While the insurer has said the contents have been addressed, the contemporaneous notes
and submissions indicate the contents loss has not been settled or fully considered. Indeed,
in September 2021, the insurer acknowledged the contents component of the claim had not
been dealt with. It said P had been instructed to complete a contents assessment, but that did
not happen.
Both parties accept there was mould growth in the property following the event and that
required mould remediation work. RC inspected the property on 18 March 2021 and says the
mould on many of the claimed items (including the blinds) was from ‘environmental conditions
and being stored during [the] claim’.
In the circumstances, the panel is satisfied it is more likely than not the event caused the
mould and resultant damage to the contents (which was then exacerbated by the delay in
Determination | Case number: 858217 Page 8 of 11
finalising repairs). The complainants have established a valid claim for contents damage and
the insurer is required to cover these items in accordance with the policy terms and
conditions.
To be clear, the policy does not cover repair or replacement of undamaged contents so as to
match any that have been repaired/restored or replaced.
The insurer liable for further mould assessment and required remediation
The complainants have also provided photographic evidence of other areas of mould in the
property, which they say has arisen since the insurer’s repairs were carried out.
The panel considers it is reasonable to also attribute that to the claim event and the
subsequent delays in finalising repair of the property. It is fair and appropriate in the
circumstances that the insurer be responsible for a further mould assessment of the property,
and for any necessary remediation identified.
An assessment by an appropriately qualified expert is to be arranged as soon as possible, at
the insurer’s expense, following which the insurer is also required to cover the cost of any
further mould remediation. The assessment and remediation may be conducted, at the
complainants’ option, by an expert of their choosing . It should be conducted as a priority, so
as to minimise any further delay in repairs.
2.2 Are the complainants entitled to other compensation?
Under the AFCA Rules, we may award compensation (capped at $5,400) for non-financial
loss where a complainant has suffered an unusual degree or extent of physical
inconvenience, time taken to resolve the situation or interference with their expectation of
enjoyment or peace of mind.
We take a conservative approach to compensation for non-financial loss. It is not awarded
when a person simply suffers the normal degree of inconvenience to be expected when a
problem occurs.
Evidence shows breakdown in communication between parties
The contemporaneous notes show a significant breakdown in communication between the
parties. While builder P says they were asked to cease works by the insurer, the
contemporaneous notes indicate inconsistent messaging to the complainants about what was
happening. On 25 November 2021, P contacted the insurer regarding the potential cash
settlement, given the private works conducted by the complainants. However P later says the
insurer’s works would be completed by end of January 2022. So although work ceased, the
complainants were not clearly informed of this until they followed up the insurer for updates.
The panel is not satisfied the complainant was fully aware of the next steps leading up to and
following the insurer’s decision to stop repair work. T he complainants were effectively led to
believe P was still going to complete the work but were later asked to source builders.
It is also clear that throughout the life of the claim, the complainants had been encouraged to
deal with P rather than the insurer directly. There were many unanswered emails and phone
calls from the complainants to both P and the insurer. The evidence indicates that P failed to
attend certain onsite meetings and missed their own scheduled deadlines. P also incorrectly
interpreted the policy provision regarding pet accommodation.
Determination | Case number: 858217 Page 9 of 11
All of this – coupled with unexplained and unjustified delays – has caused the complainants a
significant degree of upset and inconvenience (particularly given their unsatisfactory living
arrangements in the meantime).
In the circumstances, the panel considers it fair the insurer pays the complainants $5,400 as
non-financial loss compensation.
Report/quote costs should be reimbursed
Under Rule D.5, AFCA may decide a financial firm should contribute to the professional costs
incurred by a complainant in the course of a complaint. These costs can be awarded if the
complainant needed an expert to understand or establish their claim, and are normally
capped at $5,000 unless exceptional circumstances apply.
In the circumstances, the panel considers it fair the insurer reimburses the complainants
$2,190 for the costs incurred to obtain comparison building repair quotes which assisted in
establishing a fair settlement of the claim. Statutory interest should be added to the amounts,
calculated from the date the complainants incurred the respective costs to the date of
settlement.
2.3 Why is the outcome fair?
Where an insurer decides to cash settle a claim, the settlement amount should be based on a
fair assessment of the cost to the complainant to repair or rebuild the property. The amount
offered should be sufficient to ensure the complainant is able to engage their own contractors
to complete the necessary work.
The insurer’s offer is insufficient to complete the repairs and does not discharge its liability
under the policy and conditions. Therefore, the insured is required to contribute further to
satisfactorily complete the repairs, replace other damaged contents and cover other costs to
which the complainant is entitled under the policy or because of the insurer’s handling of the
claim.
Determination | Case number: 858217 Page 10 of 11
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel
includes:
an ombudsman
a member with significant experience in consumer and small business advocacy
a member with extensive experience in the insurance industry.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
Determination | Case number: 858217 Page 11 of 11
3.2 Relevant Policy wording
Page 28 - Building additional benefits.
If we agree to pay a claim for loss or damage to your building, we will also pay for the
additional benefits listed below that are directly related to that loss or damage.
Page 34 - Contents additional benefits.
If we agree to pay a claim for loss or damage to your contents, we will also pay for the
additional benefits listed below that are directly related to that loss or damage.