Home / Suncorp Group / Determination 858062

Determination 858062

Earthquake damage claim cash settlement dispute

FirmSuncorp Group
Decided2022-10-20
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$500
Amount claimed$62,761
SourceAFCA PDF

Summary

The complainant claimed earthquake damage to his home after the insurer cash settled the chimney and disputed other damage as pre-existing or excluded. AFCA found the earthquake was the proximate cause of the remaining covered damage, required further assessment and settlement, and ordered $500 for delay-related non-financial loss.

Once a prima facie earthquake claim is shown, the insurer bears the onus to prove an exclusion applies, and it failed to establish wear and tear or defects as the proximate cause.

Issues

Subjects and remedies

health or medicalhome or building damagenatural disasterpay claimpay compensationpay non financial lossreassess claim

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 858062 Financial firm AAI Limited Determination | Case number: 858062 Page 1 of 9 Case number: 858062 21 September 2022 1 Determination overview 1.1 Complaint The complainant holds a home and contents insurance policy with the financial firm (insurer). On 28 September 2021, he lodged a claim for damage to his property caused by an earthquake. The insurer accepted the damage to the chimney and agreed to cash settle the complainant for his quote of $62,760.65. However, the parties dispute the extent of the damage to the property caused by the earthquake. The complainant also raises concerns with the insurer no longer providing temporary accommodation and the insurer’s overall handling of the claim. The complainant is represented. Reference to ‘the complainant’ in this determination includes reference to his representative. 1.2 Issues and key findings Is the insurer’s offer of settlement fair ? No. The complainant has shown he has a valid claim for earthquake damage. The insurer has not shown it was entitled to rely on the exclusions it did to decline the claimed damage. It is fair in the circumstances for the insurer to settle the remainder of the claim in line with the policy terms and conditions. Was the chimney make-safe adequate? Yes. The insurer carried out additional make-safe works which its builder confirmed were adequate. Is the complainant entitled to further compensation? No. I consider the insurer’s offer of compensation of $500 is fair in the circumstances. 1.3 Determination This determination is substantially in favour of the complainant. On acceptance of this determination:  the parties must work together to scope the cost to repair the remaining accepted damage as per section 2.1 of this determination;  the insurer must settle the remainder of the claim, including any further temporary accommodation reasonably required, in line with the policy terms and conditions;  the insurer must pay the complainant the $500 compensation it offered him for non- financial loss caused by delays. Determination | Case number: 858062 Page 2 of 9 2 Reasons for determination 2.1 Is the insurer’s offer of settlement fair ? No. The complainant has shown he has a valid claim for earthquake damage. The insurer has not shown it was entitled to rely on the exclusions it did to decline the claimed damage. It is fair in the circumstances for the insurer to settle the remainder of the claim in line with the policy terms and conditions. Policy covers earthquake damage that is not otherwise excluded The initial onus is with the complainant to establish the loss is covered by the policy. This is known as a valid (or prima facie ) claim. Once the complainant has established a valid claim, the onus shifts to the insurer to establish, on balance, the application of a policy exclusion or that it is otherwise entitled to decline the claim under the policy. The policy is an ‘insured events’ policy. This means not all loss and damage is automatically covered. Rather, only loss or damage caused by one or more of the insured events and not subject to exclusions, is covered. The insured events are set out in the product disclosure statement (PDS) and include earthquake. The insurer limited its liability to the chimney damage The insurer accepted the damage to the chimney and agreed to cash settle the complainant for his quote of $62,760.65. It says it is cash settling the claim due to pre-existing damage present to the property. The insurer disputes the earthquake caused the remainder of the damage. It says the plasterboard and timber cracking were caused by poor construction methods, long-term decay, and wear and tear. These causes are excluded from cover under the policy. The insurer says it covered all temporary accommodation costs until its claims decision was made. Complainant says an earthquake caused damage to his property The complainant says:  he was forced to leave the home after the earthquake because the large stone chimney was split down the side and dangerous  he wants the insurer to repair the damage to his home and to be compensated for the stress and disruption to his life. The complainant says the earthquake damaged his home in the following areas:  cracking to the fireplace;  cracking to the plasterboard walls throughout the dwelling;  loose timber decking;  leaking and staining to the upstairs ceiling. Determination | Case number: 858062 Page 3 of 9 Roof/ceiling damage to be considered separately The complainant says since the earthquake the ceiling upstairs is leaking, and the ceiling stained. He says he has not obtained a quote and the insurer has ignored this damage. The insurer appointed a roofer (NL) to attend the property to assess this damage on 27 July 2022. The complainant has also indicated his desire to obtain a report on this cause of damage. The ceiling staining was first raised as an issue in dispute some months after the complaint was first lodged with AFCA. The insurer must be given the opportunity to resolve the new issue before AFCA is involved. Therefore, this determination will not consider the roof/ceiling damage further. If the complainant and the insurer cannot resolve the issue, he can lodge a new complaint with AFCA. Parties provided information commenting on the cause of damage The insurer’s builder (JL) attended the complainant’s property . JL’s report dated 18 October 2021 stated it found there was earthquake damage to the chimney. The insurer engaged an engineer (CR) to further inspect the property on 9 November 2021. In its report dated 20 January 2022, CR found:  the earthquake epicentre was approximately 23 km from the complainant’s property  cracks ranging from hairline to 2mm in width to the walls throughout the dwelling due to poor general finish of the plasterboard  many rooms incomplete and lacking cornices, with exposed plasterboard ends susceptible to normal differential footings movement and seismic events  fresh cracking to the internal brickwork of the chimney from the earthquake, with no soot or fire marking within the cracks, indicating the cracks are fresh and have occurred since the last fire was lit  the external chimney flue and walls in good condition  subfloor framing and stumps in good condition  loose timber decking of poor construction with long term dilapidation of the nail fixings and corrosion, and decay and swelling/expansion of the timber  GA isoseismal mapping indicated the equivalent MMI around the property was between the MMI 5.0 to MMI 5.5, therefore, structural damage was unlikely and was not observed  it did not test the soil, however a visual inspection showed it had a percentage of clay, and clay founding soils are moderately to highly reactive  reactive clays tend to experience differential movement. CR stated the damage to the plasterboard walls and ceilings have been caused by long-term dilapidation and poor construction and more recent damage has worsened by the earthquake. It stated the damage to the fireplace and surrounds is long-term dilapidation and poor construction, and the recent cracking is due to the earthquake. CR also provided photographs. This included descriptions of the damage, including:  recent cracking to stone work of fireplace  fresh cracking within the brickwork of the chimney  recent cracking to plasterboard wall at the location of timber framing  evidence of recently detached plasterboard and paint  poor installation of plasterboard and timber framing connection leading to crushing of plasterboard Determination | Case number: 858062 Page 4 of 9  corrosion and timber decay to decking boards.  base of fireplace and chimney in a fair condition. CR referred to the Modified Mercalli Intensity (MMI) scale (a seismic intensity scale used for measuring the intensity of shaking produced by an earthquake). The MMI scale indicates for a rating less than MMI 6, loose fittings and furnishings move, cosmetic damage can be expected, but structural damage is unlikely. I note the scale states for MMI 6, many objects fall from shelves and a few instances of fallen plaster, broken windows, damaged chimneys can occur. The complainant criticised CR’s report, saying its claim the house has long-term dilapidation and poor construction are untrue and unreasonable because the house was only constructed 12 years ago and built with all necessary and required permits. Further, he says, the timber used to build the deck was Silvertop Ash, the appearance of which becomes aged very quickly and which was the look he sought. The complainant also says CR’s report contains contradictions and disregards the complainant’s choice of construction. In support, the complainant provided:  a copy of the certificate of occupancy dated 17 May 2011  numerous photographs taken before the earthquake  sworn statements from friends and relatives stating the above damage was absent from the house before the earthquake. Evidence shows the earthquake was the proximate cause of the damage When deciding whether the policy responds, I need to be satisfied the proximate cause of the damage is earthquake. Proximate cause is a question of fact depending on the circumstances. The proximate cause is not necessarily the first or last or the sole cause of the loss. It is the effective, dominant or operative cause of the loss. I am not persuaded by CR’s report for the following reasons. CR did not explain how the cracks to the walls throughout the dwelling occurred, other than to generally refer to ‘ poor general finish of the plasterboard ’ . It did not explain why the finish was poor or how this caused the damage. CR did not provide the results of any soil testing, geological reports, or floor level surveys to support its assertion the dwelling was subject to differential ground movement. While CR refers to the MMI scale, I do not consider it gave adequate consideration to the location of the complainant’s property and close proximity to the epicentre of th e earthquake. CR’s report includes a report stating severe damage around the epicentre of an earthquake is within 20 to 50km. The complainant’s property was only approximately 23km from the epicentre. CR stated exposed plasterboard ends are susceptible to differential footing movement and seismic events. It did not state which was the more likely cause of damage. Given the absence of floor level surveys, CR has not shown differential footing movement was the more likely cause of the cracking damage. Therefore, I accept it was the seismic event. This is more likely the cause of damage given there is no dispute the earthquake caused damage to the property. I am satisfied it also caused damage to the plasterboard, given CR also confirms there is recent cracking. It is not enough to state the plasterboard was poorly installed. It must show this was the cause of the damage. I do not consider the information provided shows this. Determination | Case number: 858062 Page 5 of 9 The insurer has not comment ed on the complainant’s assertion the weathered appearance of the timber is attributable to type of wood. The photographs show the nails in the timber decking have popped and some weathering and moss or algae growth on the decking. The nails do not appear dilapidated nor does the wood appear decayed. I am not satisfied the insurer has shown poor construction methods, long-term decay, and wear and tear caused the nails to pop or the timber to loosen. Finally, I am not persuaded by CR’s reliance on the MMI scale in this case. I accept the MMI scale is a useful starting point when ascertaining the likelihood of damage at a location. However, while the MMI scale states ‘ structural damage is unlikely ’ for a rating less than MMI 6 (as was the case here) it does not say it is impossible. Further, structural damage did occur to the internal chimney and objects did fall (in line with expected observations at MMI 6). The property appears to have been subject to damage in line with a rating of MMI 6. Considered as a whole I am persuaded the evidence shows, on balance, the earthquake was the more likely cause of the claimed damage. Fair for the insurer to accept the claimed damage The insurer’s policy consists of the policy schedule and PDS. It is not in dispute the insurer provided the policy documents to the complainant. The insurer is therefore entitled to rely on those terms when assessing any claim made against the policy. The policy covers several insured events, including earthquake. The complainant has shown he has a valid claim. The onus therefore shifts to the insurer to show it is entitled to decline the claim. The insurer relied on the following exclusions to decline cover for the additional damage: Loss or damage to, or caused by, connected with or arising from, or liability caused by, connected with or arising from: … Wear, tear and gradual deterioration any part of the home or contents that has wear, tear, rust, fading, rising damp, corrosion, rot, action of light, atmospheric or climatic conditions or gradual deterioration such as, but not limited to: • tiles and their adhesive or grouting breaking down; • weathering of roof tiles or roof ridge capping; • gradual weathering and breakdown of bricks, mortar or concrete; • wear and tear of carpets, furniture and furnishings; • fading of curtains and drapes; • gradual weathering of pot plants. … We do not cover … Defects, faults, workmanship • loss or damage caused by, connected with or arising from, or liability caused by, connected with or arising from inherent defects, faulty design, structural defects, structural fault or faulty/poor workmanship (e.g. structural posts, beams or load bearing walls have been removed without taking into account structural Determination | Case number: 858062 Page 6 of 9 engineering requirements), if you knew or should have reasonably known about it (e.g. because the defect or fault was able to be observed by you or because it was identified in a pre-purchase building inspection report); • any loss or damage to the part of the home or contents with an inherent defect, faulty design, structural defect or faulty/poor workmanship, whether or not you knew or should reasonably have known about it. To show the damage is due to wear and tear, the insurer must show this was the proximate cause of the damage. I do not consider it has done so. Given the age of the house, and based on the photos provided, I do not consider the insurer has established the damage to the property is from wear and tear over time. I also do not consider the insurer has established the exclusion for defects applies. It has not explained what defect caused the loss and whether the property did not comply with any building codes at the time it wa s constructed. While CR refers to poor installation, CR’s report is brief on this point and does not include the basis for this conclusion. There is insufficient information to show any defect or faulty workmanship was the proximate cause of any damage at the property. The insurer is to accept cover for the chimney, cracking damage to the plaster walls, and decking boards. It is to arrange a further assessment of this damage and either repair the damage or cash settle the complainant for these costs, in line with the policy terms and conditions. Temporary accommodation costs payable for fair period of repairs The PDS outlines the insurer will pay the following costs for temporary accommodation: When we cover loss or damage to the home and the insured incident damages the home to the extent that it cannot be lived in by you, we will pay for your reasonable and necessary temporary accommodation costs for the time it will take to repair or rebuild the home so that it can be lived in again. We will also pay for temporary accommodation for your domestic pets in a commercial boarding establishment for the same period that we pay for your temporary accommodation. The most we will pay is the reasonable and necessary costs for: • short term accommodation agreed to by u s (e.g. standard rates for a hotel, motel or serviced apartment) (up to 4 weeks only); • residential accommodation of a similar standard to the home (e.g. if the insured home is a 3 bedroom home we will aim to put you in a 3 bedroom home). The PDS defines ‘cannot be lived in’ as: means destroyed or made completely or partially unfit to live in. This might include if the utilities are not available or it is not safe to live in Whilst the insurer says the property is currently safe to live in, I accept the property will not be able to be lived in whilst repairs are undertaken, given the extent of repairs required. The Determination | Case number: 858062 Page 7 of 9 insurer is therefore liable to pay for the complainant’s temporary accommodation costs for the time it will take to repair the damage covered under this claim. If the insurer conducts repairs, it is to pay the complainant his temporary accommodation costs for the duration of repairs. If the insurer cash settles the claim, it is to obtain a fair estimate for the duration of repairs required and settle the complainant the temporary accommodation costs for this time. 2.2 Was the chimney make-safe adequate? Yes. The insurer carried out additional make-safe works which its builder confirmed were adequate. Parties dispute the adequacy of the make-safe The insurer’s builder (JL) attended the complainant’s property on 11 October 2021 and completed a make-safe to the chimney. After the complainant raised concerns over the adequacy of the make-safe, JL reattended the property on 10 January 2022 and completed further works to prevent any potential collapse of the chimney. The complainant raised concerns JL’s additional make -safe was inadequate and the property remains unsafe for him to live him. He believed the chimney was in danger of collapsing. He says the insurer’s continued provision of his temporary accommodation supports this. The insurer disputes this. It says JL is a licensed and experienced professional and completed the make-safe in line with an engineer’s recommendation . It says its provision of temporary accommodation is in line with the policy terms and conditions. Insufficient evidence the make-safe was inadequate In its response to the complaint, the insurer says CR initially attended the property on 10 November 2021 and advised further props would be required to the chimney. It says it arranged JL to reattend to install the additional make-safe. It also provided an email confirmation from JL stating the property is liveable. Given the size of the chimney and extent of damage, I appreciate the complainant’s concerns with safety at the property. However, there is insufficient information to show there are issues with the most recent make-safe. The complainant has not submitted any evidence to support his assertion the additional make-safe was inadequate or how a more adequate make-safe could be carried out. The insurer cash settled the chimney damage based on the complainan t’s quote to repair the damage of $62,760.65. It fulfilled its liability for the chimney under the policy and I do not require it to do anything further for this aspect of his complaint. 2.3 Is the complainant entitled to further compensation? No. I consider the insurer’s offer of compensation of $500 is fair in the circumstances . Complainant says insurer caused him immense stress Under our Rules, AFCA can consider making an award of up to $5,400 compensation for non-financial loss. However, we will only award this type of compensation if a complainant suffers an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the complainant’s enjoyment o r peace of mind. Determination | Case number: 858062 Page 8 of 9 AFCA takes a conservative approach to compensation and expects a complainant to bear a normal degree of inconvenience during a claim. The complainant says the insurer should pay him $10,000 compensation for non-financial loss because his life has been totally disrupted and this has caused him immense stress. The complainant provided correspondence to the insurer, including a letter dated 15 January 2022. The letter states he lodged the claim on 28 September 2021 and the insurer was still waiting for an engineering report, with the delays causing him severe stress and hardship. The complainant also states he is concerned the chimney has not been made safe and this denies him the use of his home. The insurer acknowledged there were delays in obtaining a report from CR. However, it submits the was outside its control and the overall claim was managed adequately and in a timely manner. Nevertheless, it offered the complainant $500 in recognition of the delays in obtaining CR’s report. Complainant not entitled to further non-financial loss compensation I accept the insurer incorrectly declining the claim would have caused the complainant inconvenience and stress. I also accept there were delays on the claim. Some delays were to be expected due to the nature of the event and the large volume of claims it generated. I accept the appointment of an engineer and time taken to obtain the report was outside the insur er’s control and it should not be held liable for this time. The complainant has not asserted the property is uninhabitable for any reason other than his concerns over the adequacy of the chimney make-safe. I acknowledge the complainant firmly believes the make-safe is inadequate. However, there is no evidence this is the case. The insurer acknowledged the complainant’s concerns over the adequacy of the make -safe when he raised it and acted to rectify the issue by promptly arranging further works. Further, it continues to pay his temporary accommodation. It is understandable, if the first make-safe was inadequate, the complainant would have concerns over the adequacy of the second make-safe. However, in the absence of any evidence the further works failed to secure the chimney, I cannot fairly say the complainant has shown his property continues to be uninhabitable. I accept the insurer could have processed the claim in a timelier manner overall. However, it responded to the complainant’s concerns to make -safe the chimney and made an offer of compensation for delays. I am satisfied this was a satisfactory response to the problem. Given AFCA’s conservative approach to compensation, I consider the insurer’s off er of $500 in fair in the circumstances. If it has not already done so, the insurer must pay the complainant the $500 compensation it offered him for non-financial loss caused by delays. Determination | Case number: 858062 Page 9 of 9 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA determined this complaint based on what is fair in all the circumstances, regarding:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties completed a full exchange of the relevant information and each party had the opportunity to address any issues raised. We reviewed and considered all the information the parties provided. While the parties raised several issues in their submissions, we restricted this determination to the issues that are relevant to the outcome.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.