Determination 854058

Storm/rainwater run-off damage claim settlement amount

FirmIAG
Decided2022-12-06
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed$283,910
SourceAFCA PDF

Summary

The complainant claimed storm and rainwater run-off damage to her home and the insurer offered 50% of repair costs. AFCA found the insurer liable for the full storm-related damage, settled on the insurer's builder's amended quote with a 20% cash-settlement allowance, and rejected several disputed repair items.

Damage caused by rainwater run-off was covered and the insurer did not establish that faulty design or workmanship of the drainage system caused or contributed to it, so no reduction applied.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay compensation

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination Case number 854058 Financial firm Insurance Australia Limited Determination | Case number: 854058 Page 1 of 16 Case number: 854058 5 December 2022 1 Determination overview 1.1 Complaint The complainant holds a home insurance policy with the financial firm (the insurer). She lodged a claim saying her home was damaged by a storm. The insurer says the damage was caused partly by the storm and partly by the pre-existing condition of the property’s drainage system. The insurer has offered to pay 50% of the cost of repairs. The complainant says the insurer should pay the full cost of repairs. The parties disagree on the cost of repairs. The insurer’s builder has quoted $150,278.17. The complainant’s builder has quoted $283,910. 1.2 Issues and key findings Is the insurer required to pay the full cost of repairs? The policy excludes cover for damage caused by faulty design or workmanship. The insurer has not established that the drainage system was faulty. Therefore, the insurer must pay the full cost of repairing the damage caused by the storm. What repairs does the insurer need to pay for? In addition to the repairs it has offered to pay for, the insurer must pay for:  replacement of the garage slab  removal and reinstatement of the deck on the corner of the swimming pool. The complainant’s builder’s quote includes other work the insurer has not agreed to pay for. However, the available information does not show this work is necessary to repair storm- related damage. How should the claim be settled? The claim should be settled as stated below (section 1.3). 1.3 Determination This determination is partly in favour of the complainant. The claim settlement should be based on the insurer’s builder’s quote. However, the quote should be amended to include:  replacement of the garage slab  removal and reinstatement of the deck on the corner of the swimming pool  building costs at the time of settlement. The insurer must pay an additional 20% of the quoted cost of repairs to compensate for the transfer of risk due to cash settlement. If the complainant needs to move out of her home so it can be repaired, the insurer must assess her entitlement to accommodation and storage costs. Determination | Case number: 854058 Page 2 of 16 2 Reasons for determination 2.1 Is the insurer required to pay the full cost of repairs? Policy covers damage caused by rainwater run-off The cover provided by the policy is set out in the product disclosure statement. Relevant policy terms are quoted in section 3.2 of this determination. The policy is an ‘insured events’ pol icy, meaning it only covers damage caused by specific events. The insured events include storm, flood, and rainwater run-off. The insurer offers optional additional cover for ‘accidental damage’. However, the complainant’s policy does not include this cove r. The policy excludes cover for damage caused by certain factors, including:  wear and tear or gradual deterioration  atmospheric conditions  faulty design or workmanship  earth movement (other than landslide or subsidence that happens immediately as a direct result of an insured event). The policy covers damage caused by storm, flood, or rainwater run-off, but excludes cover for damage caused by wear and tear, gradual deterioration, or atmospheric conditions. Wear and tear is the deterioration of an object caused by its ordinary use, and the ordinary effects of natural forces such as weather. Therefore, the policy covers damage caused by a single storm or flood, but does not cover damage that occurs gradually every time it rains, or damage caused by ordinary environmental moisture. Property damaged by rainwater run-off On 27 July 2020, the complainant’s home experienced heavy rain. Rainwater run-off flowed from the street and inundated the property. On 25 January 2021, the complainant lodged a claim with the insurer. According to the insurer’s notes, she said: ‘The floor and concrete were damaged due to storm and also there is a mould on the ceiling.’ The notes say she did not lodge the claim earlier because she had only just noticed the damage. The parties appointed numerous experts to inspect the property. Relevant statements from their reports are quoted in section 3.3 of this determination. One of the experts who inspected the home was the insurer’s engineer (F), who inspected the home on 23 April 2021. F said the inundation of the property had caused the following damage, and recommended the following repairs:  cracking and movement of concrete: > surrounding the swimming pool (remove and replace) > below the clothes line on the south eastern corner (remove and replace) > on the western side of the garage on the north western corner (patch repair; remove and replace where patch repair not suitable)  separation between the rendered brick wall and eaves lining on the eastern side (strip back and repaint)  subsidence of the floor frame on the western side (remove subsided brick pier(s) and replace with new concrete foundations and new steel piers or brick piers). Determination | Case number: 854058 Page 3 of 16 Insurer offered to pay half repair cost F said the inundation occurred partly because of heavy rain and partly because of the property’s drainage system. F said the drainage system was ‘ not functioning adequately to efficiently direct stormwater away from the dwelling ’. The complainant appointed an engineer (ND), who inspected the property on 21 October 2021. ND said the inundation was caused by the rainfall on 27 July 2020. ND said: ‘ Based on evidence provided by the client, the stormwater drainage system was functioning ’. F reviewed ND ’s report . F agreed with ND’s finding that the inundation was caused by the rainfall on 27 July 2020. However, F maintained that the property’s drainage system ‘ substantially contributed to the severity of the flooding ’. The insurer says the damage was caused partly by rainwater run-off (which the policy provides cover for) and partly by the drainage system (which the policy excludes cover for). It says it cannot determine how much each factor contributed to the damage, so the fair outcome is for it to pay for 50% of the damage. Insurer liable for full repair cost The policy excludes cover for damage arising from ‘ faulty design or workmanship ’. If a property is inundated by run-off, this does not prove its drainage system exhibited faulty design or workmanship. If it did, it would mean any damage caused by run-off was caused by faulty design or workmanship. This would mean the insurer could deny any claim for damage caused by run-off. The complainant’s property was inundated by run-off on 27 July 2020. However, ND’s report said the rainfall recorded on 27 July 2020 at the closest gauge was the highest since records began in 1993. The insurer has not provided any information to refute this. The available information does not show the drainage system is overwhelmed by ordinary rainfall. The insurer has not provided any information regarding what regulations were in force at the time of the property’s construction, whether the drainage system complied with those regulations, or whether a regulation-compliant drainage system could have handled the volume of water that entered the property on 27 July 2020. F recommended upgrading the drainage system. However, F did not specify what upgrades were required, or what damage (if any) would have been prevented if the upgrades had been in place on 27 July 2020. The policy excludes cover for wear and tear, failure to maintain the property in good repair and condition, and failure to take reasonable care to prevent damage. The insurer has not provided information showing the drainage system failed because of wear and tear, lack of maintenance, or failure to take reasonable care. Having considered the information provided by both parties, the panel is satisfied that the damage identified in F’s report was caused by the rainwater run -off inundating the property on 27 July 2020. The panel is not satisfied that faulty design or workmanship (or any other factor the policy excludes from cover) caused or contributed to the damage. The insurer is liable for the damage, and is not entitled to reduce its liability. Determination | Case number: 854058 Page 4 of 16 2.2 What repairs does the insurer need to pay for? Parties disagree on cost of repairs The insurer’s builder ( J) provided a scope of works dated 9 July 2021 with an itemised quote totalling $70,538.08. The insurer offered to settle the claim based on this quote. Later, J provided an updated scope of works dated 29 July 2022 with a non-itemised quote totalling $150,278.17. The insurer is now offering to settle the claim based on the updated quote. The complainant’s builder (PB) provided an itemised quote dated 27 April 2022 totalling $283,910. The complainant obtained another itemised quote totalling $530,000, but this quote is not on letterhead and does not identify its author. The panel has disregarded this quote. The main reason PB’s estimate is higher than J’s is that it includes a lot of additional work. The panel has considered whether this additional work is covered under the policy. Damage caused by roof leak not covered PB’s quote allow s $16,500 for the replacement of all internal walls and ceilings, which were damaged by water entering the home through the roof. The insurer says this damage is not covered under the policy. When the complainant lodged the claim on 25 January 2021, she said there was mould on the ceiling. The insurer appointed a builder (T), who inspected the property on 2 February 2021. T confirmed there was mould on the ceiling, and ‘ cracks in the ceiling sheet joins which occurred after the event ’ . T appointed a roof specialist, who obtained aerial photographs of the roof. The roof report said:  there was a roof tile with a broken corner  the broken tile was the most likely cause of water entry through the roof  the roof had no signs of storm damage, so the broken tile may be due to foot traffic or wear and tear. J inspected the property on 25 June 2021 and obtained another roof report. This roof report said:  the roof tiles were porous  the undersides of the tiles had ‘very evident’ water stains , and were soaked with morning dew during the inspection  water entered the home because of a cracked tile, but the porous tiles were contributing heavily to the damage. The complainant says she had her roof restored three months before the storm. However, none of the experts who inspected the home said the roof had been damaged by a storm. The available information does not show the roof was damaged by a storm, or any other insured event. Therefore, the insurer is not required to pay for repairs to the roof, or any damage caused by water entering through the roof. Determination | Case number: 854058 Page 5 of 16 Bathroom renovation not covered PB’s quote allows $25,960 for the renovation of the bathroom. The complainant says the bathroom is over the piers that subsided because of the storm. The insurer says there is a cracked tile in the bathroom, but it is not related to the storm. T, who inspected the property on 2 February 20 21, said the bathroom ‘ has had movement since the event which has allegedly cracked the tile ’. F inspected the property on 23 April 2021, but their report did not mention the bathroom. In a letter dated 17 May 2022, F said there was a cracked tile in the bathroom, but it was not related to the storm. The available information does not show the bathroom has any damage other than the cracked tile. The available information does not show the tile was damaged by a storm, or any other insured event. Therefore, the insurer is not required to pay for the renovation of the bathroom. Insurer must pay for replacement of garage slab PB’s quote allows for the replacement of the entire garage slab. J’s quotes allow for the replacement of part of the garage slab. F said only the concrete on the west side of the garage slab was damaged. However, the complainant provided photographs showing cracks on the other side of the garage slab. In an email on 27 June 2022, the insurer agreed that the entire garage floor needed to be replaced. However, J’s updated scope of works dated 29 July 2022 only allows for the replacement of part of the slab. The insurer must increase its offer to account for the replacement of the entire garage slab. Replacement of carport slab not covered PB’s quote allows for the replacement of the carport slab (including propping up the carport roof and replacing the posts supporting the roof). J’s quotes allow for the replacement of concrete in the garage, under the clothesline, and around the swimming pool. F says the other concrete on the property has no observed damage, and does not need to be replaced. PB’s quote does not say why the carport slab needs to be replaced. None of the experts who inspected the home mentioned any damage to the carport or driveway. The complainant has provided photographs showing minor cracking in the carport/driveway, but it is not clear whether this is storm-related. The available information does not show the carport slab was damaged by an insured event. The insurer is not required to pay for the replacement of the carport slab. Underpinning of garage not covered PB’s quote allows $19,800 for underpinning of the street -facing wall of the garage. It does not say why the underpinning is necessary. F said this wall did not appear to have been damaged by the storm, and it was unclear why PB provided a quote for underpinning it. Determination | Case number: 854058 Page 6 of 16 The complainant says a builder told her the garage should either be taken down or underpinned because there was ‘ no way to tell if there was damage to the foundations ’. The builder’s statement, as reported by the complainant, does not say the garage foundations are damaged, or likely to be damaged. It only says there is no way to tell whether they are damaged. That is not enough to establish a claimable loss under the policy. None of the expert reports said the garage foundations were damaged, or that the garage required underpinning. Therefore, the insurer is not required to pay for underpinning. Insurer must pay for removal of corner deck and roof PB’s quote and J’s quotes allow for the replacement of all concrete surrounding the swimming pool. One corner of the swimming pool perimeter has a covered wooden deck built over it. The complainant says this deck needs to be removed to repair the concrete underneath it. The insurer says: ‘ The concrete can be cut to the edge of the decking and an expansion joint can be laid .’ J’s updated scope of works dated 29 July 2022 includes the following item, which was not included in its original scope of works : ‘Cut section of the path to the edge of the decking and an expansion joint can be laid’. J’s quotes include: ‘Allowance to remove and dispose of all concrete surrounding the swimming pool’. This includes the concrete under the deck. The insurer and its experts have not explained why the concrete around the rest of the pool needs to be replaced, but the concrete under the deck does not. The insurer must increase its offer to account for the removal and reinstatement of the covered wooden deck. PB’s quote allows $ 13,200 for the removal and reinstatement of the deck. However, this does not include the cost of replacing any damaged building materials. The complainant obtained a quote from a different builder (HV) dated 8 April 2022 for $19,297 for the removal and rep lacement of the deck. This quote is more reliable than PB’s estimate. The insurer must increase its offer by $19,297. Insurer’s scope of works sufficient for external walls PB’s quote allows $29,150 for the preparation and painting of all external walls , including cutting control joints into render and brickwork. F, who inspected the property on 23 April 2021, said one wall (on the north side of the house, next to the swimming pool) had lifted and there was peeling paint around the base. F said they did not see any other damage to external walls that could be attributed to the storm. The complainant says the render was cracked after the storm, and the cracking has progressed since she lodged the claim. The insurer said it would pay for repairs to damaged render up to the closest physical joint, but would not pay to have the entire house rendered and painted. The complainant agreed this was fair. J’s updated scope of works dated 29 July 2022 allows for the removal and replacement of damaged render on the north side of the house, and the painting of all external walls. The available information does not show any more work is needed to repair storm-related damage to the external walls. The insurer is not required to pay more for repairs to external walls. Determination | Case number: 854058 Page 7 of 16 Full replacement of flooring not covered PB’s quote allows $35,200 for the replacement of all underlay and flooring in the home. J’s quotes allow for the removal and replacement of some flooring to access the footings and replace a subsided brick pier. The complainant says replacement flooring will not match the rest of her flooring. She wants all of the flooring in her home replaced with new flooring to maintain a uniform appearance. The policy says the insurer will only repair or replace floorboards in the part of the home that is damaged, and will not pay to replace floorboards any adjoining rooms. The insurer is not required pay the cost of replacing all flooring in the home. The insurer is only required to pay the cost of replacing flooring in the rooms where flooring needs to be cut to access the footings. 2.3 How should the claim be settled? Insurer entitled to cash-settle claim The policy says the insurer can settle a claim for building damage by arranging for its builders to repair the damage, or by paying the cost of repairs. The insurer’s builder (J) said it could not warrant repairs to the property because it had a leaky roof and an inadequate drainage system. J recommended the insurer cash-settle the claim rather than arranging repairs. The insurer decided to cash-settle the claim. The complainant has not disputed this decision. The insurer has provided several expert reports showing the property is being damaged by water entering through the roof. This damage is not related to the claim. Therefore, the panel considers it fair for the insurer to cash-settle the claim rather than arranging repairs. Settlement should be based on J’s updated quote The insurer’s engineer (F) identified some damage as being caused by the inundation of the property. The complainant’s engineer (ND) did not identify any storm -related damage that was not identified by F. The complainant has not provided information showing the storm caused damage that was not identified as storm- related in F’s report. J’s updated quote inclu des most of the work needed to repair the storm-related damage. PB’s quote is higher because it includes a lot of additional work. Most of this additional work is not necessary to repair storm- related damage. Therefore, the panel considers J’s updated quot e to be the best available estimate of the cost of repairing claim-related damage. The claim settlement should be based on J’s updated quote. However, the quote should be amended to include:  replacement of the entire garage slab (rather than just part of the slab)  removal and reinstatement of the corner deck and roof (to allow for the replacement of the concrete under the deck)  building costs at the time of settlement (which may have increased since the quote was prepared on 29 July 2022). Determination | Case number: 854058 Page 8 of 16 Insurer must pay allowance for transfer of risk The product disclosure statement says the insurer will provide a lifetime guarantee on the workmanship of repairs it authorises. The General Insurance Code of Practice (to which the insurer subscribes) says that if an insurer ‘selected and directly authorised a repairer’, it must guarantee the quality of the repairs. When an insurer settles a claim by repairing damage, it guarantees the quality of the repairs. If the repairs are unsuccessful, or cause additional damage, the insurer is responsible for the cost of rectification. When the insurer settles a claim by paying the cost of repairs, it transfers this risk to the customer. Furthermore, the customer may find it more difficult and expensive to arrange repairs, because they do not have the insurer’s industry knowledge and bargaining power. AFCA considers that if an insurer cash settles a claim, it should consider paying an allowance for the transfer of risk. Generally, AFCA considers that a reasonable allowance is likely to be between 5% and 25% of the quoted cost of repairs. The insurer has offered to pay ‘a 20% uplift to compensate for the loss of the lifetime guarantee and potential for further/undiscovered damage ’ . The panel is satisfied that this is a reasonable allowance for the transfer of risk. Insurer must assess entitlement to accommodation and storage costs If the complainant needs to move out of her home so it can be repaired, the policy covers the costs of:  temporary accommodation  additional living expenses  removing contents, storing them, and returning them to the home. None of the builders’ quotes say whether the home will be unliveable during repairs, or if so, for how long. If the complainant provides information showing she had to (or will have to) move out of her home for it to be repaired, the insurer must assess her entitlement under this policy benefit. Outcome is fair in the circumstances The policy requires the insurer to pay the cost of repairing damage caused by the storm on 27 July 2020. The best availa ble estimate of this cost is J’s updated quote dated 29 July 2022. The claim settlement should be based on this quote, with the amendments set out in this determination. The panel is satisfied that this determination provides the fairest possible outcome, based on the available information. Determination | Case number: 854058 Page 9 of 16 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. A panel determined this matter Due to the nature of this complaint, we referred it to a panel for determination. The panel includes:  an ombudsman  a member with extensive experience in consumer and small business advocacy  a member with extensive experience in insurance. 3.2 Relevant policy terms Product Disclosure Statement The events we cover (pages 23 – 3 2 ) We cover your home or contents when certain things happen. These are known as 'listed events'. Flood and rainwater run - off If loss or damage is caused by a flood and/or rainwat er run - off. Covered  flood  rainwater run - off, and  landslide or subsidence that happens immediat ely as a direct result of flood or rainwat er run - off. For example, excessive rainfall in your local area causes a build up of wate r in the street gutters and the water enters your home and caus es damage. … Not covered …  loss or damage caus ed by: ‒ erosion, deterioration, collapse, shrinkage or any other earth movement Rainwat er run - off means water that flows over the ground, or backs - up, as a result of a storm, that is not a flood Determination | Case number: 854058 Page 10 of 16 … Storm If loss or damage is caused by a storm. Covered  storm  landslide or subsidence that happens immediat ely as a direct result of a storm. For example, hail damages your roof. Not covered …  loss or damage caus ed by: ‒ erosion, deterioration, collapse, shrinkage or any other earth movement … Storm means:  rain, thunderstorm, hail, snow  violent wind, cyclone, tornado Other benefits (pages 32 – 47 ) We may also provide other benefits that are set out in this section. Temporary accommodation for home owners If a listed event causes loss or damage to your h ome and we agree you can’t live in it and you need to move out so it can be repaired or rebuilt. Covered under Buildings Insurance  costs for temporary accommodation that we agree are reasonable and appropriate for you, your family and your pets that you normally keep at your site  any additional living expens es that we agree are appropriate  costs to remove and store your contents and then ret urn them to y our home. … General exclusions for all covers and benefits (pages 65 – 66 ) The exclusions set out in this section apply t o all covers and benefits under your policy. What we don’t cover Loss, damage, injury or death arising from:  rust, corrosion, gradual deterioration, depreciation, wear or tear  erosion, deterioration, collapse, shrinkage or any other earth movement  landslide or subsidence unless it happens immediately as a direct result of: ‒ flood… ‒ rainwater run - off… ‒ storm … …  atmospheric conditions or extreme temperature … Determination | Case number: 854058 Page 11 of 16 We do not cover: …  the settling, shrinkage or ex pansion in buildings, foundations, walls or pavements … Maintaining and occupying your home We don’t cover loss, damage, injury or death arising from:  faulty design or workmanship  previous damage that has not been repaired …  you not maint aining your home in good repair and condition – this means that your home must be watertight, structurally sound, secure and well maintained  you not maint aining your site in good repair and condition …  you not taking reasonable care to protect your home and contents against loss or damage. Claims and what we pay (pages 69 – 85 ) What we pay for – Buildings Insurance If we agree to cover your claim under Buildings Insurance, then we will:  pay the cost to repair or rebuild the part of your home that was damaged (whichever is lower) … Other benefits We may also pay some costs on top of the Buildings sum insured under ‘ ot her benefits’ for: …  Temporary accommodation for home owners – see page 46 … How we settle your buildings claim We will choose to settle your claim for loss or damage to your home and any ‘other benefits’ in one of the following ways: 1. Arrange for repairers, builders or suppliers to repair or rebuild your home If you agree, we can arrange for our preferred repairers, suppliers or builders to repair or rebuild your home. We may enter into a contract with our selected repairer, builder and/or supplier on your behalf. 2. Pay you the reasonable cost to repair or rebuild your home We can choose to:  pay you  pay your nominated repairer, supplier or builder, or  provide you with store credits from one of our nominat ed suppliers. For example , we may pay you directly when:  you decide not to repair or rebuild your home, or  you don’t start repairing or rebuilding your home within 6 months from when the loss or damage takes place, or within any longer p eriod we agreed to in writing. … Lifetime guarantee We provide a lifetime guarantee on the workmanship of repairs to your home that we authorise. This means we will fix any defect caused by poor workmanship done by our preferred repairers or builders that we authorise. Determination | Case number: 854058 Page 12 of 16 We will decide how to fix an y defect. When you’re not covered by this guarantee This guarant ee does not apply to:  repairs you authorise yourself … How we settle certain things When we pay your claim, we settle certain things in line with the inf ormation shown in this section. Matching materials Under Buildings Insurance  we only repair the damaged part(s) of your home. We don’t pay for materials to match the undamaged parts of your home to create a uniform appearance. Carpet, vinyl, tiles or floorboards Under Buildings Insurance and Contents Insurance  we only repair or replace the carpet, vinyl, tiles or floorboards in the part of your home that was damaged  we don’t pay for any adjoining rooms, or your entire home. 3.3 Relevant expert statements Report Expert statement T (insurer’ s builder) Asse ssment report Date of inspection: 2 February 2021 Date of doc ument: 7 April 2021 CAUSE OF DAMAGE: Our inspection has confirmed that the damages that exist have been caused by Surface run off. … Internally apart from the subfloor subsidence th e Kitchen ceiling requires mould remediation in multiple areas. There are cracks in the ceiling sheet joins which occurred after the event. The Main Bedroom's Ensuite has had movement since the event which has allegedly cracked the tile near the window. … We have marked this claim as 'UNSURE - REQUIRES SPECIALIST" due the possible implications of structural movement. A (T’ s roof specialist) Inspection report Date of inspection: 2 February 2021 Date of doc ument: 2 February 2021 We were advised the water ingress was to the centre of the roof. The roof generally appears in good condition in this area. Ridge and hip cap pointing all good. There is one tile with a broken corner at the end of the ridge in the centre of the roof just above the whirly bird. We b elieve this is the most likely cause of the ingress in this area. There is no signs of any storm damage to the roof so this appears to be a maintenance issue, possible foot traffic or from general wear and tear with ageing. N (T’ s swimming pool specialist ) Inspection report Date of doc ument: 8 March 2021 Filtration system and pipe work appears to be in good condition with no visual signs of cracks or leaks… The pool shell is level with the concrete coping and does not appear to have moved… Determination | Case number: 854058 Page 13 of 16 M (T’ s plumber) Inspection report Date of doc ument: Undated The storm water run off appears to settle under the house at the rear as it is the lowest point in the yard under heavy loads of rain, water would build up under the dwelling and settle and would take a while to either seep into the ground or seep into the agg drainage at the rear. I think a submersible pump and pit may need to be installed to dispense this storm water when these rain water events occur. F (insurer’ s engineer) Structural engineer’s report Date o f inspection: 23 April 2021 Date of doc ument: 14 May 2021 CONCLUSION The damages observed to the dwelling and concrete pavement around the dwelling and fibre glass swimming pool on nort hern side of the dwelling are considered to be attributed to movement of the foundation soils and differential settlement of the building foundation and concrete paving slab associated with abnormal moisture conditions in the foundation soils on the site. The development of abnormal moisture conditions in the foundation soil s on the property is considered to be attributed to the saturation of the foundation material during reported flooding of the property. The flooding is considered to be the result of the current drainage system around the property not functioning adequatel y to efficiently direct stormwater away from the dwelling and off from the property during heavy rainfall events. RECOMMENDATIONS AND SCOPE OF WORKS Following our ins pection the following recommendation(s ) are provided:  Relevant actions should be taken to remove and prevent the occurrence of abnormal moisture conditions…  The subsided brick pier(s) on the western side of dwelling, near the front entry, are to be realigned to pre - settlement levels. To ac hieve this, the affected pier(s) and footing(s) are to b e removed and replaced with new concrete foundations, designed to suit site soil conditions, and new steel piers or brick piers designed to support expected loading.  The concrete paving slab below cloths line at the south eastern corner of the dwelling and cracked conc rete coping surrounding the swimming pool are to be removed and replaced to match existing.  Cracking on the western portion of the concrete garage slab is to be patch repaired to match existing. Where patch repair of the slab is not considered suitable, damaged portion of the garage slab is to be locally remove and replaced to match existing.  The damaged paint work on external rendered brick wall to the south of the swimming is to be stripped back and repainted to match existing. …  The roof gutt er down pipes on the western side of the dwelling are to be plumbed into the drainage system. The stormwater drainage around the property is to be improved… J (insurer’ s builder ) R eport and scope of works Date of inspection: we recommend the roof tiles be assess for possible replacement as tiles may be at the end of their serviceable lifespan .we would also recommend sarking be installed . RECOMMENDATION: Unsure - Unable to warrant Determination | Case number: 854058 Page 14 of 16 25 June 2021 Date of doc ument: 9 July 2021 Roofer has advis ed that tiles ar e porous and are allowing ingress and has stated that water staining is very evident on the underside of the tiles, during my inspection all tiles were soaked with the morning due on the underside until this is rectified we would not be able to warrant int ernal works. we would not be able to warrant external works + footing repairs as The storm water drainage system on the property is not considered to be functioning adequately… We would not be able to warrant repairs unless drainage system has been modifie d to function correctly to better deal with heavy downpours and prevent re occurrence. We would recommend full cash settlement for all works. REPAIR ESTIMATE (inc GST): $70,538. 08 … CONCLUSION: We conclude that damages have occurred due to flood/ storm wat er in combination with an inadequate drainage system and maintenance issues to the roof … J (insurer’ s builder ) Roof report Date of doc ument: 6 July 2021 Is there any maintenance issue s that have either contributed to Ingress or will impact the roof in the future The insured has had the roof restored previously however after gaining access to the roof space it is very obvious the tiles are porus and water staining is very evident on the underside of the tiles, during my inspection all tiles were soaked with the morning due on the underside Ingress cause The primary cause of ingress to the living room ceiling is a cracked tile below the ridge line however the porus tiles are contributing heavily to the damages also ND (complainant’s engineer) Civil repor t Date of inspection: 21 October 2021 Date of doc ument: 10 November 2021 The [ Bureau of Met eorology ] data shows the daily rainfall on the 27/7/20 to be 172.4mm. This is noted to be the highest on record for [the closest rainfall gauge] which contains data back to 1993. … Based on the observations we are of the opinion the most likely cause of the floodin g of the subject site was a res ult of stormwater from the [street name] road frontag e derived off site entering the property via the western boundary. The c onclusion has been reached bas ed on the following:  Record high rainfall was observed on the date the flooding is claimed to have occurred.  Based on evidence provided by the client, the stormwater drainage system was functioning.  Photo and video footage clearly shows significant volume of water flowing in an easterly direction from the road into the subject property;  It is suspected the raised threshold crossing has reduced the flow capacity in the road formation and forced flows over the top of kerb and onto the foot way. Determination | Case number: 854058 Page 15 of 16 ST (complainant’s expert – qualifications unstated) Letter Date of doc ument: 1 December 2021 [Summary of complaint. No additional expert evidenc e.] F (insurer’ s engineer) Email Date of doc ument: 22 December 2021 We agree with drainage report… prepared by [ ND ] on 10 Nov 2021, that stormwater from [street name] has flowed onto the insured property resulting in the reported flooding of the property during the reported heavy rainfall event between 26th and 27th July 2021. However, pre - exist ing issue with the stormwater drainage system on the property are considered to have substantially contributed to the severity of the flooding experienced on the property and remediation measures are required to improve the drainage on the property as o utl ined in our original report. F (insurer’ s engineer) Letter Date of doc ument: 17 May 2022 As requested we have reviewed the builders quotes for repair works as supplied by the insured and provide the following comments: Garage: The cracking observed to the concrete garage slab, that is considered to require repair, was confined to the western portion of the garage… only the damaged portion of the slab requires repair. It is unclear why a quotation for underpinning of the street facing garage wall has been p rovided in [PB’s] quote as there was no apparent damages to this section of wall at the time of our inspection that are considered to be attributed to the claimed event. As such no recommendation has been provided for realignment of this section of wall in our report. Concrete Pavement/Driveway along the southern side of the dwelling & around pool area: The cracking observed to the concrete pavement slab was confined to the area below the clothesline… complete removal of the concrete pavement around the poo l area is not warrant ed and does not form part of the scope of works as part of this claim. External Paintwork to the rendered brick wall s: The paint work to the rendered brick wall to the south of the swimming pool was observed to be damaged at the time of our inspection, however, there was no apparent cracking to the rendered brick work at the time of inspection that is considered to be attribut ed to the claimed the claimed event. Based on this it is our opinion that any works other than repainting of th e wall are not related to this claim. … Floating Floors: It is understood that water did not enter the dwelling during the claimed event and the damages observed to the floating flooring at the time of inspection were confirmed to the area around the locat ion of the subsided brick piers on the western side of the dwelling. As such full removal and replacement of the floating flooring within the dwelling is not considered to be warranted Determination | Case number: 854058 Page 16 of 16 EnSuite Renovation: At the time of inspection cracking was observed to a single tile in the ensuite. The cracking to the tile was not considered to be attribut ed to the claimed storm event in March 2021. It is our opining that renovation of the ensuite is not warranted Internal Wall and Ceiling Lining: Based on the building r eport by [T], the reported water ingress to the centre of the roof is considered to be attributed to a broken tile and is not considered to be attributed to storm damage. Based on this it is our opinion that full removal and replacement of wall and ceiling linings within the dwelling is no warranted as part of this claim. …

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.