Cash settlement amount for storm-free water damage claim, plus handling delays and communication
Text of the determination
Determination
Case number 853505
Financial firm Allianz Australia General Insurance Limited
Determination | Case number: 853505 Page 1 of 10
Case number: 853505 13 September 2022
1 Determination overview
1.1 Complaint
The complainant held a home and contents insurance policy with the financial firm (insurer).
She lodged a claim on 4 June 2021 after discovering a burst pipe in the sub-floor under the
laundry/bathroom area, which caused widespread water damage and mould.
The insurer arranged for repairs, however identified certain deficiencies in the building which
it said the complainant was responsible for remediating. The insurer said it could not
undertake repairs until those deficiencies were addressed. On 18 January 2022, it offered to
cash settle the complainant $225,001.28 for the claim-related repairs.
The complainant is unhappy with the settlement offered and with the insurer’s handling of the
claim overall. She says the insurer:
ceased all communication and involvement with the claim after identifying
deficiencies/defects in the property
did not provide reports identifying those deficiencies, preventing her from rectifying them
failed to address the issue of damage to and loss of contents caused by its builders
caused avoidable delays, resulting in the policy limit for alternative accommodation being
reached, and causing consequential financial and non-financial loss.
1.2 Issues and key findings
How should the claim be settled?
Claim-related repairs
The claim for damage caused by the leak should be cash settled, using as a basis the
complainant’s quote which is comprehensive and detailed, includes all scoped works, and is
based on industry pricing guides. The final cash settlement amount should also include an
allowance for contingencies and the transfer of risk to the complainant. It is not required to
cover deficiencies/ defects identified by the complainant’s builder.
Contents
The insurer is required to pay the complainant $4,210.82 for missing/damaged contents items
(except to the extent any or all are located/found to be in storage and are promptly returned
undamaged to the complainant). It is also required to pay $5,825 for the damaged kitchen
benchtop. Statutory interest is to be added to those amounts, calculated from 18 March 2022
to the date of settlement.
Temporary accommodation
The available evidence is not sufficient to show the complainant has incurred additional
accommodation costs. The insurer is not liable for further accommodation costs beyond the
policy limit, which has already been reached.
Determination | Case number: 853505 Page 2 of 10
Compensation for non-financial loss
The insurer has caused avoidable delays, resulting in significant avoidable stress and
disruption for the complainant. $3,000 compensation for non-financial loss is warranted in the
circumstances.
Other costs
The insurer is also liable for reimbursing the complainant’s cost in engaging an expert
building specialist, who assisted in resolution of this complaint.
The dispute is not so complex in itself as to reasonably require legal representation. However,
the complainant’s legal representative did assist in clarifying and outlining the complainant’s
position. It is fair in the circumstances that a contribution of $1,000 be paid towards the
complainant’s legal costs.
Why is the outcome fair?
It is fair that the insurer’s cash settlement for repairs reasonably reflects the cost to the
complainant of having the claim-related work completed, including an allowance for
contingencies and the transfer of risk. The complainant’s quote is a fair and appropriate basis
for that settlement in the circumstances.
To date, the insurer has not specifically addressed the location and status of the contents
being claimed. It is fair that the insurer be held liable for damaged/missing contents, unless it
can show they are safely stored and undamaged, and are promptly returned to the
complainant.
The insurer’s handling of the claim is such that it is fair for compensat ion and certain other
costs incurred in the course of this complaint (contributing to its resolution) to be paid.
1.3 Determination
This determination is substantially in favour of the complainant.
The insurer is required, within 14 business days of the compl ainant’s a cceptance of this
determination, to:
pay the complainant $385,292.85 for the claim-related damage (being $366,945.57, as
claimed, based on QA’s quote, less identified defect costs and the policy excess, then
increased by 5% to allow for contingencies and risk transfer)
pay $4,210.82 for missing/damaged contents, together with statutory interest on that
amount calculated from 18 March 2022 (the date of the complaint’s lawyer’s letter to the
insurer in which they proposed a reasonable settlement) until the date of payment – to be
adjusted, as appropriate, if the insurer locates and returns any/all of the claimed items in
undamaged condition within 14 business days
pay $5,825 for the damaged benchtop, plus statutory interest from 18 March 2022
pay $3,000 compensation for non-financial loss
pay $1,000 towards the complainant’s legal costs
reimburse the complainant’s expert report fee s (up to $5,000) within 14 days of the
complainant supplying the relevant invoice.
Determination | Case number: 853505 Page 3 of 10
2 Reasons for determination
2.1 How should the claim be settled?
Insurer accepted claim but identified deficiencies/defects in construction
The complainant lodged a claim on 4 June 2021 for water and moisture damage. The insurer
identified an ongoing leak which had damaged the subfloor across the entire home. There is
no dispute there was an insured ‘escape of liquid’ event during the period of cover. The
insurer accepted liability for the claim-related damage.
The complainant was also advised to vacate the property because of the health risks
associated with the high moisture and mould readings in the building, and the insurer agreed
to cover temporary accommodation costs (a benefit under the policy).
The insurer engaged engineer AA to provide a scope of work for the damage attributable to
the leak, and to conduct an inspection of the existing sub-floor framing to determine its
suitability to support a new floor. In their report dated 21 October 2021, AA referred to
instances of poor building practices, primarily in relation to the construction of the sub-floor.
AA considered the floor was defective, and reinstatement and repair of the other claim-related
damage should not take place until those deficiencies were rectified.
The deficiencies identified by AA included:
short floor joists which are unlikely to meet load-bearing requirements
deficient wall framing, including breaches in fire rates walls and inadequate support
a large ridge beam supported only by a timber stump which is inadequately connected to a
timber lintel
the subfloor being lower than the surrounding ground and not adequately ventilated
various issues with the subfloor, such as substandard timber packing, rotted packers,
excessive joist spans and untreated pine used as a packer.
It is relevant that AA does not explicitly reference relevant building codes and standards to
support their assessment of the deficiencies, but does describe the subfloor in particular, as
littered with issues. The panel accepts A A’s view that it is unlikely a builder would warrant
repairs which are reliant on this subfloor for support.
The insurer subsequently ceased work, on the basis the complainant would need to rectify
the deficiencies before it could recommence.
In January 2022, the insurer elected to cash settle the complainant (despite the complainant’s
initial preference that the insurer complete the repairs) and on 9 February 2022 it ceased
paying alternative accommodation on the grounds the complainant had not rectified
deficiencies.
Insurer deprived complainant of opportunity to promptly rectify deficiencies
The complainant disputed the insurer’s decision to stop repairs and accommodation
payments. She asked that it provide clear guidance on the obstacles preventing it from
carrying out repairs. She says that despite several requests, she was not provided with a
copy of the AA report which outlined the deficiencies, and so was unable to comply with the
insurer’s request to rectify these.
Determination | Case number: 853505 Page 4 of 10
The AA report was not included in initial submissions to AFCA, nor in response to a request
from AFCA to the insurer on 4 April 2022 for all reports, quotes and scopes. It was first made
available to the complainant and AFCA on 6 May 2022.
While a copy had been sent to the complainant in November 2021, that was sent by post to
the insured property which was, by then, unoccupied in direct response to the insurer’s
recommendation that the complainant should vacate.
By failing to provide a copy of the AA report to the complainant in a timely and appropriate
manner, the insurer deprived the complainant of the opportunity to consider and rectify the
deficiencies, which in turn prevented it from continuing repairs. This meant there were
significant avoidable delays and ongoing upset and inconvenience to the complainant.
Insurer based cash settlement on quote which lacks detail
The insurer’s subsequent cash settlement offer for the cost of claim-related repairs (made
because the complainant had not dealt with the building deficiencies) is based on a quote
from its builder BB, dated 20 December 2021.
BB ’s quote in turn is based on AA’s scope of works dated 22 October 2021. The AA scope is
detailed, with a room by room breakdown of repairs required, room and repair dimensions,
materials required, and so forth.
AA stipulates that any quote should also allow for:
appropriate and adequate supervision, protection, security, and safety measures including
'Worksafe ’ requirements
appropriate contracts, insurances, implied warranties, and realistic timeframe schedules
adequate allowances for specifications, plans, and permits as required
adequate allowances to carry out all required works described in the scope and working
drawings where applicable
appropriate straightening of retained floor, wall, and/or ceiling framing where required.
The BB quote lacks useful detail. It includes 14 items with a total cost for each: carpentry at
$23,099, painting at $11,356, and so forth. It includes no breakdown of these costs to align it
clearly and explicitly with AA’s scope .
BB allows $8,900 for prelims and $5,000 for supervision. It is unclear whether prelims include
relevant insurances, protection, security, safety measures, specifications, plans, permits and
drawings. There appears to be no allowance for straightening of floor, wall and ceiling
framing.
The panel is not satisfied, on the available information, the BB quote adequately addresses
the necessary scope of work and is sufficient to allow for repair of all damage caused by the
leak. In particular, it is not clear that the quote is one which would be actionable by the
complainant as a retail customer. In other words, BB’ s quote of $225,551.28 has not been
shown to be sufficient to allow the complainant herself to finalise all claim-related repairs and
return the property to its pre-loss condition.
Complainant supplied alternative quote for claim-related damage
The complainant supplied a comprehensive report dated 4 February 2022 from builder QA.
QA describes itself as a specialist in litigation claims for building and construction. The panel
is satisfied QA is appropriately qualified and experienced to address the issues. The QA
report includes a scope of works and quote, supported by a room by room examination of the
property with photographs and commentary.
Determination | Case number: 853505 Page 5 of 10
QA says floor joists have been installed short in the lounge, kitchen and dining room area and
may not be sufficiently load-bearing. QA also identified missing insulation in floors and walls,
although is uncertain whether this was omitted by the insurer’s contractors or the original
builders. QA says these issues constitute defects, however identified no other defects across
the property. The other available evidence (including AA’s comments) is not otherwise
conclusive that additional defects/deficiencies apply and should be excluded from cover.
QA considered the quote from BB insufficient based on current rates. QA utilised the
Rawlinson’s Construction Costs Guide 2020 (RCG) and its own experience to arrive at an
estimate of $383,125.99 for all repairs (which did include approximately $14,256 for identified
and accepted defects/deficiencies).
Complainant does not require insurer to rectify defects
The panel notes the insurer provided a letter to AFCA dated 6 February 2022, which said a
cash settlement offer (based on BB’s quote) had been made, and which incorrectly stated
that the complaint had been resolved with the complainant. The complainant promptly
advised that offer had not been accepted.
The complainant’s preference was initially for the insurer to carry out repairs. Following a
relationship breakdown between the parties, the complainant engaged solicitor, WL, to assist
with the claim.
WL wrote to the insurer on 18 March 2022 requesting that it cash settle the claim based by
reference to the cost of the QA quote, and also reimburse the complainant’s other costs.
The available evidence addresses the issue of deficiencies and the complainant is not
disputing her responsibility for those , based on QA’s report .
Cash settlement for building damage should be based on complainant’s quote
As noted, the panel is concerned that the BB quote is not actionable by the complainant. It is
also important to acknowledge that in making a cash settlement, the insurer is transferring the
risk involved in the work to the complainant, including the possibility of related unforeseen
issues and other contingencies.
The report and quote from QA is specific, detailed and persuasive, and was prepared for the
complainant as the customer. The report compellingly addresses the insurer’s expert
evidence, and the quote clearly explains how costings were arrived at, and references RCG,
a cost guide which includes price indices, identifies detailed prices for various trades and
services, and labour costs for major items of work. It also identifies those costings which
apply to defects/deficiencies, for which the insurer is not liable.
Having regard to all the available evidence, the panel considers it is fair and appropriate in
the circumstances that settlement for building damage be based on the scope and quote from
QA. That is because, on balance, it more accurately reflects the likely cost to the complainant
of returning the property to its pre-loss condition; while acknowledging building deficiencies.
The quote from QA already allows 10% for price increases since 2020. Given the quote was
prepared in February 2022, the volatility of the building industry, potential delays which may
result from staffing/material shortages, and so on, the panel is concerned the price may
further increase by the time the complainant is able to arrange for the work to be done.
The panel also notes the complainant does not gain the benefit of a repair guarantee from the
insurer when the claim is cash settled. Given this, the panel considers it fair and appropriate
Determination | Case number: 853505 Page 6 of 10
that the insurer pays $385,292.85 for the claim-related damage (being $366,945.57, as
claimed and based on QA’s quote, less identified defects/deficiencies and the policy excess,
then increased by 5% to allow for contingencies and risk transfer).
The complainant also says the insurer’s contractors failed to clean the prope rty after ceasing
repairs. She wants the insurer to pay $1,060 for the cost of a skip bin. However, the QA
scope and quote already allows $4,158.00 for a commercial clean after repairs are complete.
In the circumstances, the insurer is not liable for the additional $1,060 cost claimed.
Insurer liable for missing/damaged contents
The complainant says that because the insurer’s contractors left the premises unsecured,
certain contents items were stolen. She has provided invoices for the individual costs of the
claimed missing items, totalling $4,210.82.
The insurer says that all items were placed in storage, and no theft has occurred. Despite
having had the opportunity to do so, the insurer has not, however, provided confirmation of
the location of the storage unit, or of exactly what contents are being stored.
In the circumstances, it is fair that the insurer be liable for the claimed cost of $4,210.82,
together with statutory interest on that amount. If, however, the insurer promptly locates and
returns all/any of the claimed items to the complainant in undamaged condition, then that
amount is to be adjusted accordingly.
The complainant also says (and photographs confirm) a concrete kitchen benchtop was left
exposed to the elements on a rear deck area. The complainant says it suffered irreparable
damage. She says a white bathtub was also damaged. Replacement of the benchtop is
included in the AA scope, although with no price. It is not included in the QA quote and scope.
The complainant has supplied quotes for replacement of the benchtop ranging between
$3,950 to $7,700 (depending on the stone used and profile edge). It is unclear which of the
quotes represents a like-for-like replacement for the damaged concrete benchtop. In the
circumstances, it is fair that the insurer pays the complainant $5,825 for the damaged
benchtop (being the mid-point between the lowest and highest quotes submitted), plus
statutory interest.
Complainant says insurer should cover accommodation above policy limit
The policy includes an allowance for emergency accommodation costs (up to a set limit) if the
home is unliveable because of an insured event. However, that expense will only be paid if
the complainant actually incurs costs for emergency accommodation.
There is no dispute the property was unliveable.
The available benefit is the lesser of 10% of the sum insured (equating to $57,500) or 12
months accommodation cost (at $3,911 per month, equating to $46,932). The insurer has
paid this amount in full, plus an additional 72 days.
The complainant says if the insurer had supplied the AA report sooner, she could have
rectified defects and avoided further delay in getting back into the home. She says she has
incurred accommodation costs above the policy limit as a result of the insurer’s error.
Determination | Case number: 853505 Page 7 of 10
No evidence complainant incurred additional accommodation costs
The complainant supplied a copy of a residential rental agreement in support of her claim.
The agreement indicates it was signed and dated on 8 February 2022, and notes a weekly
rental amount of $600.
The document is an electronic PDF file and includes metadata which indicates the file was
created on 7 April 2022. The evidence also shows the complainant has an ownership interest
in the property.
The complainant was asked to provide further proof, including evidence of bank transfers, to
show rent payments were being made. To date, this information has not been supplied.
The submissions made and the evidence provided by the complainant do not establish she
has incurred additional accommodation costs as a result of delays by the insurer, so as to
justify payments over and above the policy limit.
That means the insurer is not liable for further accommodation costs.
Compensation for non-financial loss is warranted
The complainant has provided extensive submissions regarding her concerns with the
insurer’s handling of the claims, including that:
the insurer failed to provide reports relating to the claims, and in doing so the insurer
caused avoidable delays
the insurer’s contractors were disrespectful and caused property damage
the insurer failed to notify the complainant of any objections to completing all repairs
communication was poor.
On 16 November 2021 the insurer instructed the complainant to obtain a quote to repair the
deficiencies identified by AA, but that notification was sent to the address where she was no
longer living. It failed to provide a copy of the AA report, even after a copy was requested by
the c omplainant’s solicitor in December 2021. The report was not supplied until May 2022.
The panel is satisfied, on balance, the complainant would have promptly taken steps to rectify
deficiencies if she had been supplied with the AA report and it had been clear exactly what
they were.
Th e insurer’s errors led to the complainant having to devote considerable additional time and
resources to the complaint. She engaged a solicitor to assist with the matter, and engaged
building specialist QA to provide a scope and quote. Had the matter been resolved earlier,
this would likely have been unnecessary.
Under our Rules, we can award up to $5,400 compensation for non-financial loss. We may
award compensation if a complainant has suffered an unusual degree of physical
inconvenience, time taken to resolve the situation or interference with his or her expectation
of enjoyment or peace of mind due to the insurer’s handling of the claim.
We take a conservative approach to compensation and expect a complainant to bear a
normal degree of inconvenience during a claim.
However, in this case the insurer has caused avoidable delays, resulting in significant stress
and disruption for the complainant. It should pay the complainant $3,000 compensation for
this non-financial loss.
Determination | Case number: 853505 Page 8 of 10
Appropriate that certain professional fees be covered by insurer
Under our Rules, AFCA is also able to consider a claim for indirect financial loss caused by
the insurer’s actions . AFCA will consider whether the costs were reasonable and whether
they helped resolve the complaint. As well, the policy allows a benefit for professional and
legal costs that might be necessary for the repair or replacement of the insured property
following an insured event.
QA’s quote and scope was of direct assistance in resolving the complaint, by clarifying the
likely costs to the complainant of having the claim-related work completed. It was reasonable
(and necessary) in the circumstances that the complainant engaged QA. The cost (claimed
as $3,600) could likely have been avoided if the insurer had ensured the complainant
received the list of deficiencies in November 2021. Given this, on provision of an invoice
confirming the complainant’s payment , the insurer is required to reimburse QA’s fee, up to a
maximum of $5,000.
AFCA tries to make our service accessible and understandable, without any need for legal
representation. If a complainant chooses to be legally represented, they will generally have to
pay for this themselves. However, we may still require the insurer to contribute to legal costs
if the complaint raised complex legal issues. Unless there are exceptional circumstances,
AFCA will not require an insurer to contribute more than $5,000 to these costs.
Having considered the issues in dispute between the parties, the panel does not consider
these were overly complex, or necessarily required legal representation. In this particular
case, however, the lawyer’s correspondence did clearly and reasonably summarise the
complainant’s position and assist in identifying a fair settlement. The panel considers it fair in
the circumstances that the insurer contribute $1,000 towards the complainant’s legal fees in
pursuing the claim and complaint.
The complainant also claims indirect financial loss because the time devoted to the claim
meant she was unable to continue with her regular income-earning activities. The
submissions made do not include any evidence that the complainant’s income was affected ,
or if so, to what extent. It is also unclear how the complainant’s involveme nt would need to be
such that it would prevent her from earning income.
The panel is not satisfied the complainant has established the insurer should be held liable for
lost wages/income.
2.2 Why is the outcome fair?
An insurer is typically entitled, under the terms of a policy, to choose whether to carry out
repairs or to pay the complainant the cost of repairs. AFCA expects that the insurer will
exercise discretion reasonably in making this decision.
In these circumstances, where defects or deficiencies would prevent a builder from
warranting works, the panel accepts it is reasonable for the insurer to refuse to carry out
repairs.
It was fair and reasonable for the insurer to offer to continue with repairs if the complainant
rectified defects. However, in failing to present the complainant with a list of those defects, it
prejudiced her ability to arrange rectification, leading to a dispute over reasonable repair
costs. It would not be fair in these circumstances if the complainant was left out of pocket for
the repairs.
Determination | Case number: 853505 Page 9 of 10
The insurer has based its offer on a very limited quote. It is unclear from this quote whether
the insurer’s offer would enable the complainant to complete all necessary repairs. On the
other hand , the complainant’s quote allows for all wor ks included in the scope of repairs upon
which it is based. The quoted amounts are based on industry costing guides. It is fair, in the
particular circumstances, that settlement is based on this more complete quote provided by
the complainant ’s expert .
Giv en the insurer’s handling of the claim has contributed to delays and caused the
complainant to incur avoidable costs, it is fair and reasonable that the insurer meet these
costs. As the complainant has not established this caused her to incur accommodation costs,
it would not be fair to require the insurer to pay for this.
Determination | Case number: 853505 Page 10 of 10
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel
includes:
an ombudsman
a member with significant experience in consumer and small business advocacy
a member with extensive experience in the insurance industry.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.