Home / Allianz Australia / Determination 852343
Determination 852343
Insurer declined landlord insurance claim for earthquake damage, finding damage caused by long-term differential settlement of footings
Summary
The complainant claimed under a landlord policy for earthquake damage to his property after the insurer declined the claim. AFCA decided the insurer was entitled to decline because the damage was predominantly caused by long-term differential settlement of the footings, which is excluded.
The complainant bears the initial onus to show an insured event was the proximate cause of the loss, and on the engineering evidence the earthquake was not the dominant or effective cause.
Issues
- Claim denial primary · not upheld
“The complainant has not established, on balance, the earthquake was the proximate cause of the damage. The information also shows the damage is otherwise excluded.”
- Inadequate claim investigation secondary · not upheld
“I am persuaded by HC's report that the cause of damage is due to long-term factors.”
Subjects and remedies
home or building damagenatural disasterno remedy
Text of the determination
Determination
Case number 852343
Financial firm Allianz Australia General Insurance Limited
Determination | Case number: 852343 Page 1 of 5
Case number: 852343 11 July 2022
1 Determination overview
1.1 Complaint
The complainant holds a landlord insurance policy with the financial firm (insurer). He lodged
a claim for damage he says was due to the Victorian earthquake on 22 September 2021.
The insurer declined the claim because it says the earthquake did not cause the damage. It
says the cracking damage at the property predates the earthquake event and has been
caused by differential movement due to seasonal changes in the soil moisture content. This is
excluded under the policy.
1.2 Issues and key findings
Is the insurer entitled to decline the claim?
Yes. The complainant has not established, on balance, the earthquake was the proximate
cause of the damage. The information also shows the damage is otherwise excluded.
Why is the outcome fair?
The initial onus is on the complainant to show an insured event caused the damage. While
there is no dispute there was an earthquake, he has not provided persuasive information to
show this was the dominant or effective cause of the loss. Given the loss is otherwise
excluded under the policy, it would be unfair to require the insurer to accept the claim.
1.3 Determination
This determination is in favour of the insurer.
The insurer is not required to take any further action in relation to the claim or complaint.
Determination | Case number: 852343 Page 2 of 5
2 Reasons for determination
2.1 Is the insurer entitled to decline the claim?
Yes. The complainant has not established, on balance, the earthquake was the proximate
cause of the damage. The information also shows the damage is otherwise excluded.
Complainant has initial onus to establish a valid claim
The initial onus is with the complainant to establish the loss is covered by the policy. This is
known as a valid (or prima facie ) claim.
Once the complainant has established a valid claim, the onus shifts to the insurer to establish,
on balance, the application of a policy exclusion or that it is otherwise entitled to decline the
claim under the policy.
Policy covers damage from an earthquake
The policy is an ‘insured events’ policy. This means not all loss and damage is automatically
covered. Rather, only loss or damage caused by one or more of the insured events and not
subject to exclusions, is covered.
The insured events are set out in the product disclosure statement (PDS) and includes loss or
damage caused by an earthquake. The PDS also includes specific exclusions under the
earthquake insured event for:
Not covered.
…
• Loss or damage that is predominantly caused by or arises from:
- wear and tear, or gradual deterioration,
…
- earth or soil movement including landslide, subsidence, erosion or heave, unless
it is a direct result of an earthquake during the period of insurance, or
- settling, expansion, shrinkage or vibration, unless it is a direct result of an
earthquake during the period of insurance.
Parties dispute whether earthquake caused the damage
The complainant says:
the damage is from the recent earthquake
the findings in the engineering report are ‘ an absolute fabrication of the facts ’ because
there was no damage prior to this earthquake
the conclusions reached are based on circumstantial evidence and conjecture because if
there was prior damage, he would have contacted the insurer earlier
he did not receive any complaints from the tenants prior to this of any structural damage
the engineering report states the cracks have previously been patched, however this is
also untrue
there has never been any patching on the property aside from in the hallway, which is from
a prior leak in the shower and not part of this claim
there are no photos or evidence in the report to show the damage is due to long-term
differential settlement of the footings
Determination | Case number: 852343 Page 3 of 5
regarding the leak in the roof, the engineer could not conclude whether the damage
caused was due to the earthquake and recommended a plumber attend, but the insurer
did not appoint a plumber
there was no leak prior to the earthquake as we had cleaned, sealed and painted the roof
in December 2020.
The complainant provided an invoice dated 6 December 2020 for repairs to the roof prior to
the earthquake. This included a high pressure clean, changing all broken tiles, re-pointing and
re-painting.
The complainant wants the insurer to accept the claim and repair the damage to the property.
The insurer says the cracking present at the property predates the earthquake event and has
been caused by differential movement due to seasonal changes in the soil moisture content.
It says the reports it provided show previous patch repairs to this cracking.
The insurer also provided information on a previous claim the complainant lodged on 2
January 2017 for escape of liquid. It referred to damage to timber flooring and some repairs
required to plaster walls in the hallway. It says this claim was cash settled and it did not
complete repairs. The insurer says there are patch repairs to other areas of the property, not
just the area subject to the previous claim.
Reports show damage due to long-term differential settlement of the footings
The insurer appointed a builder (PI) to attend the property on 28 September 2021. PI’s report
states it found cracks in the walls and ceiling throughout the property. It recommended an
engineer be appointed.
The insurer appointed an engineer (HC ) to attend the property on 22 October 2021. HC’s
report dated 26 November 2021 states:
the property is located approximately 98km from the earthquake epicentre
the earthquake intensity at the property would only have been significant enough to result
in very minor damage to buildings
the cracking and movement is not due to the earthquake
the cracking and movement is due to long-term differential settlement of the footings, tree
root drying and a previous roof leak
the cracking observed has been previously patched in multiple areas, which shows it is an
ongoing problem that pre-dates the earthquake and is likely due to inadequate footings
dried water staining to the ceiling lining is pre-existing and has affected the integrity of the
bathroom ceiling lining, making it susceptible to cracking
it cannot confirm if there are ongoing roof leak issues without attendance by a roof plumber
even if the recent earthquake resulted in minor accentuation of pre-existing damage to the
property, the earthquake has not substantially increased the extent or severity of the pre-
existing damage.
When deciding whether the policy responds, I need to identify what the proximate cause of
the damage was. This is a question of fact depending on the circumstances. The proximate
cause is not necessarily the first or last or the sole cause of the loss. It is the effective,
dominant or operative cause of the loss.
The complainant did not provide any report to refute HC’s findings. The complainant disputes
many of the contentions raised. He says there was no dried water staining, and this was new
damage caused by the earthquake. Whilst the complainant provided his opinion, he did not
Determination | Case number: 852343 Page 4 of 5
provide any expert report or other persuasive information to show the earthquake event
caused the damage claimed.
I am persuaded by HC’s report that the cause of damage is due to long-term factors. I am
satisfied the damage is more consistent with long-term differential settlement of the footings,
not the earthquake. This is supported by photographs of previously patched cracking damage
in several areas of the property. The complainant’s submissions regarding this damage is not
persuasive in light of HC’s report. I am satisfied HC is appropriately qualified to comment on
the cause of damage. The conclusions are plausible, logical and consistent with the available
evidence.
I accept an earthquake occurred on 22 September 2021 near the insured property. I also
accept it is possible the earthquake caused some damage to the property. However, to be
covered under the policy, the complainant must show the earthquake was the proximate
cause of the damage. I am satisfied the proximate cause of the damage was long-term
differential settlement of the footings. This is because if the property did not have these pre-
existing issues, the earthquake would not have caused any damage.
Fair for the insurer to decline the claim
The insurer’s policy consists of the policy schedule and PDS. It is not in dispute the insurer
provided the policy documents to the complainant. The insurer is therefore entitled to rely on
those terms when assessing any claim made against the policy.
I appreciate the complainant disagrees with HC’s findings. However, the onus is on the
complainant to show an insured event covered by the policy caused the damage claimed. I do
not consider the complainant has satisfied this onus. As the damage is caused by an
excluded event, it is fair for the insurer to decline the claim.
Determination | Case number: 852343 Page 5 of 5
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.