Text of the determination
Determination | Case number: 852329 Page 1 of 22
Determination
Case number 852329
Financial firm AIG Australia Limited
Determination | Case number: 852329 Page 2 of 22
Case number: 852329 21 November 2022
1 Determination overview
1.1 Complaint
The complainants held a home and contents policy with the financial firm (insurer). They
lodged a claim for damage on 8 January 2019. The date of loss was recorded as 27
November 2018.
In September 2020, the complainants requested time to obtain their own scope of works and
quotes. They then returned to AFCA with their information to progress the complaint in March
2022.
The insurer says that it has attempted to conduct repairs and mould remediation since
February 2021. However, the complainants have not provided reasonable access to
undertake the repairs and rejected the scope of works (SOW). The insurer says that the
property has sustained extra damage from cross contamination since then. The insurer
further says the complainants have failed to mitigate their loss.
The compl ainants say the insurer‟s SOW and proposed remediation was inadequate based
on the results of their own expert reports. The complainants now seek a cash settlement
based on their quote and SOW from BSS.
The insurer says the complainants‟ inaction has preju diced the claim and it therefore does not
consider it is liable for any extra damage that occurred due to the complainants‟ delays or
inactivity. The insurer‟s offer remains for it to honour the original quote to remediate the
mould, accept the resultant damage, and to pay temporary accommodation for the
reasonable period whist repairs are conducted.
1.2 Issues and key findings
Whether the proposed settlement is reasonable?
The panel does not accept the complainants‟ proposed settlement for the building and oth er
costs are reasonable. Instead, on balance, the panel accepts it is fair the insurer cash settle
the claim based on S‟s SOW for $22,121.68. However, it must include a contingency of 30%
and provide a settlement for the remaining building costs as set out in section 2.1.
The insurer is also required to pay an additional three months of temporary accommodation
and settle other aspects of the claim as set out in section 2.1.
Should the insurer pay the complainant s’ professional costs?
The panel is satisfied the insurer should pay the complainants $3,850 for expert report fees.
Are the complainants entitled to other losses claimed?
There were aspects of the insurer‟s claims handling that were unreasonable. The insurer
should pay $3,000 in non-financial loss for this. The complainants are not entitled to the other
losses claimed.
Determination | Case number: 852329 Page 3 of 22
1.3 Determination
This determination is partially in favour of the complainants. The insurer should settle the
claim in the following way:
cash settle the mould remediation for $22,121.68, plus a 30% contingency ($6,636.50),
for a total of $28,758.18
cash settle the remaining repairs in the manner set out in section 2.1
pay an additional three months of temporary accommodation costs incurred from 10
March until 10 June 2021
settle the additional living expenses claimed in the manner set out in section 2.1
reimburse the complainants $3,850 for expert report fees
pay the complainants $3,000 non-financial loss.
Determination | Case number: 852329 Page 4 of 22
2 Reasons for determination
2.1 Whether the proposed settlement is reasonable?
Circumstances of loss
On 27 November 2018, the complainants discovered there was a leaking pipe in the subfloor
of their property and this was subsequently repaired. A claim was lodged with the insurer by
the co mplainants‟ broker on 8 January 2019.
In January 2020, around the same time the complainants were in discussions for remediation
and repairs for their property relating to the leaking pipe, the insurer failed to notify the
complainants that it would not be renewing the policy from January 2020.
Due to disagreement relating to the mould remediation and repair method, the complainants
said they would seek their own scope of works (SOW) and quotes. Therefore, they placed
their AFCA complaint on hold from October 2020. The complainants returned to AFCA to
progress their complaint in December 2021 and provided further supporting information.
The complainants are seeking the insurer complete the repairs and remediate the property in
line with BSS‟s scope totall ing $281,875.
The insurer says it has been prejudiced by the complainants ‟ failure to allow S to complete
the remediation works in March 2021. This has meant that the mould has grown and caused
cross contamination within the property. The insurer says if it was able to complete the
remediation as per the SOW from S in March 2021, it would have then engaged an engineer
to establish whether the cause of the mould in the ceiling cavity was related to the claim.
However, as it has been prejudiced by the complainants ‟ actions or inaction, the insurer‟s
position is as follows:
pay temporary accommodation to March 2021,
to complete the repairs and remediate as per its quote and SOW from February 2021 for
$22,121.68,
accept the resultant structural damage, and
pay temporary accommodation for the reasonable time during the works.
Complainants are required to establish additional loss claimed is covered
The complainants are disputing the insurer‟s claim settlement. This means they bear the onus
of proving on the balance of probabilities that the settlement payment is insufficient and that
all of the claimed damage falls within the scope of the policy.
If the complainants can establish this, the onus transfers to the insurer to establish a policy
exclusion applies to enable it to deny the claim. The applicable standard is the balance of
probabilities.
Complainants engaged hygienists and a restoration company to scope
The complainants obtained reports from mould remediation company (TMD) dated 20 March
2020, mould inspection, testing and restoration company (A) dated 21 August 2020 and a
hygienist report from (M) dated 20 December 2020. They also obtained a final SOW from
Determination | Case number: 852329 Page 5 of 22
BSS dated 30 March 2022. The BSS SOW recommends the removal of a significant part of
the building due to cross contamination, as outlined in section 3.2 of this determination.
The complainants‟ reports outlined that the removal of flooring, tiles and plaster linings and
insulation from the ceiling cavity would be required before a thorough inspection and scope
could be provided.
The insurer maintains that its offer from March 2021 is adequate. The insurer also confirms
that it would inspect the cause of the mould within the ceiling cavity and agreed to the
subfloor requiring remediation. It further confirmed that should post remediation verification
not be achieved after the initial works, that it will reattend and carry out any additional
cleaning required to achieve Post Remediation Verification (PRV). Once PRV is achieved,
then the repair and reinstatement works could be competed.
TMD ‟s report recommended decontaminated fogging of the internal areas of the property and
the subfloor. A‟s report noted high levels of airborne mould.
Insurer says complainants failed to provide reasonable access
The insurer says restoration company (S) confirmed that the property had been subject to a
leaking pipe from November 2018. This had caused damage and visible mould growth
throughout the hallway, laundry and bathroom subfloor.
In S‟s SOW dated 9 March 2021, it was reported that the tiled flooring in both the bathroom
and the laundry would be removed, as well as the timber flooring in the hallway. The
assessment report indicates that the ceiling cavity is to be remediated. However, the insurer
advised the complainants it would not include the ceiling cavity in the works proposed. This is
because the insurer did not accept the mould in the ceiling cavity was from the insured event
at that time. The insurer said it would investigate the cause of the mould in the ceiling cavity.
The complainants rejected the SOW. They considered it was insufficient and said they would
be obtaining their own SOW along with air quality and mould assessment reports.
Complainants provided quote for remediation of full house
BHS was engaged to do testing and provided a report on 21 August 2020. This shows that
there were high levels of mould contamination and the areas of concern were the subfloor in
the hallway, subfloor in the front of house, the middle of the subfloor under the embankment,
as well as the ceiling cavity. BHS further noted that the mould in the ceiling cavity may have
originated due to cross contamination from the existing mould reservoir from the subfloor.
M‟s report from 20 December 2020 found no signs of surface mould to any surface inside the
house. The moisture readings in the house were dry. Airborne fungal concentrations were
found in the dining room, under floor hatch, ceiling space and heating duct. This report further
states that the moisture readings within the house and, specifically within the walls and ceiling
inside the house, were normal.
Ceiling cavity is contaminated although no causal link to subfloor
The insurer has not accepted the mould contamination in the ceiling cavity is a result of the
leak in the subfloor. As stated above, the insurer advised it would engage an engineer to
further inspect and assess the cause of the mould, at the same time S attended to complete
the remediation works. This did not ultimately happen.
The complainants‟ report from M dated 20 December 2020 noted that:
Determination | Case number: 852329 Page 6 of 22
All moisture reading inside the house were between 8 and 11% WME (dry). The Thermal
infrared (Fluke) camera could not detect any difference in temperature, so no higher-than-
normal levels of moisture are in the walls and ceiling inside the house.
It further noted:
In the underfloor area/storeroom there were signs of water damage to many surfaces. The
underfloor area concrete stumps also showed signs of water damage. The plaster wall to
the entrance of the storeroom has higher than normal levels of moisture up around 30 %
WME (wet).
Given the exchanged information, the panel is satisfied there is mould in the ceiling cavity.
However, the reports outlined above indicates that there were normal levels of moisture in the
walls and the subfloor, while the internal house had higher than normal levels of moisture at
their inspection in December 2020. Furthermore, the testing completed by A in May 2020,
reported that testing of the air conditioning and heating vents were within normal range.
Therefore, the reports have not substantiated a causal link between the subfloor mould and
the ceiling cavity contamination. M provided a hypothesis that the warmer air rose from the
floor, through the walls and cooled in the ceiling, leading to further mould. However, the
objective testing does not substantiate this. For instance, there is no evidence that the wall
cavities have been affected. The testing says otherwise. Neither has any inspection been
conducted of the roof itself to determine if the mould in the ceiling cavities may have
originated from a different source.
The complainants have provided a SOW from BSS dated March 2022. This however does not
provide a causal link to the ceiling contamination to the subfloor.
On this basis, the panel is not satisfied there is sufficient basis to conclude the celling cavity
contamination was caused by the leak in the subfloor.
Having said that, the panel notes the policy provides accidental loss or damage cover. There
is no dispute the ceiling has been affected. Whilst the cause is unclear, it is still accidental.
The insurer has not demonstrated the cause is excluded under the policy. On this basis
alone, it should be included in the settlement.
The claim should be settled this way
Given the above, and after careful consideration of all the available information, the panel
concludes the following.
The panel is not persuaded by the complainants‟ position of the required remediation. In
particular, the panel does not accept all the wall linings need to be removed. This is because
the expert evidence does not show they are contaminated. Neither is the panel persuaded by
M‟s hypothesis that they are likely affected because of subfloor contamination reaching the
ceiling.
The panel ac cepts S‟s SOW, detailed in a report dated 9 March 2021, provides a fairer basis
of the likely remediation works required at that time. Whilst M‟s report dated 27 October 2021
indicated further cross contamination may have occurred since January 2021, the insurer is
not liable for this. This is because the insurer was ready, willing and able to do mould
remediation before then. The insurer was unable to do so due to the complainants disputing
this decision in circumstances when their position has mostly been unsubstantiated.
Determination | Case number: 852329 Page 7 of 22
However, given the history of the claim, and additional damages that may have occurred
since then, it is fair in all the circumstances this claim is cash settled. This is because it will be
too difficult and impractical for the insurer to now attempt to repair the claim related damage
given further damages that may have occurred which it is not liable for.
To calculate a fair cash settlement figure for the building repairs, the panel notes the
following.
The insurer can base its cash settl ement for the remediation works on S‟s SOW. However, a
significant contingency should be allowed. This is due to the following issues with the SOW:
there is no allowance for clearance testing or post remediation verification – these should
have been included
there is a realistic possibility that further works would have been required after the initial
remediation works were done to obtain the relevant clearances
as the claim is being cash settled, the risks of the works are passing to the complainants
there is the loss of any repair guarantee that may be implied under the policy
Given all this, the panel considers the insurer should allow a 30% contingency. This would
increase the mould remediation allowance to $28,758.18.
Interest is not payable on this given the insurer was prepared to do the works back then and
the significant increase in the contingency margin.
In terms of the repair works that are required following the mould remediation, the insurer has
provided no estimate or quote. It is clear this would be extensive. It must, at a minimum,
include replacement of the flooring in the laundry, bathroom and hallway as well as the
insulation of the ceiling. It is possible it would require reinstatement of the bathroom if the
waterproofing membrane is affected.
Therefore, this aspect should be settled in the following way:
the insurer is to obtain an actionable quote for the likely repairs necessary following the
mould remediation based on S‟s SOW
the insurer is to cash settle on this quote with a 30% contingency – the contingency is to
address:
> the likely variances if the mould remediation or the repairs are more extensive than
anticipated in the SOW
> the transfer of the risk
> the loss of the insurer‟s warranty of the repairs
No interest is payable given the sum should be based on current rates.
If there is any dispute about this cost, the complainants can lodge a new complaint at AFCA
for a decision on this point.
Insurer to extend alternative accommodation
The insurer, in an email dated 10 March 2021, confirmed it would cease paying temporary
accommodation from that day. This is because at this point, the insurer proposed the
remediation of the property in line with S‟s SOW and quote.
The complainants are seeking the insurer cover the cost of temporary accommodation from
this point to the date the repairs are actioned.
The policy says:
Determination | Case number: 852329 Page 8 of 22
If you are unable to live in your Buildings after the destruction, loss or damage has
occurred, we will pay for your reasonable alternative accommodation expenses for the
period during which you are unable to live in your Building.
The most we will pay under this additional cover is 20% of your Buildings sum insured, as
listed on your Policy Schedule.
To date the insurer has paid temporary accommodation between 6 June 2020 and 10 March
2021.
The insurer says the remediation and resultant damages would likely be completed and
repaired within eight weeks. However, no information is available, or quote provided, to
determine or support how long the remediation or repairs will take or to confirm that it would
take eight weeks.
In the absence of such information, the panel considers it fair to allow up to three (3) months
for the remediation and reinstatement works to be completed. This is an extra month from the
insurer‟s estimates. This accounts for the likely possibility of further variances being required.
There is nothing to indicate the works will take longer than this.
Therefore , the insurer is only liable to pay for three months‟ accommodation the complainants
incurred since 10 March 2021 in settlement of this issue.
The insurer should also pay interest on these costs pursuant to section 57 of the Insurance
Contracts Act 1984 (the Act). Interest is payable from when these costs were incurred until
payment is made.
Complainants seek reimbursement for additional living expenses costs
The complainants are seeking to be reimbursed for electricity bills $5,785.25, council rates
$2,950.30, gas bills $258.59 and water bills (covering water drainage and sewerage and
service fees) $1,193.37.
The policy states under “Additional things we will pay for when you have insured your
Contents”:
We will pay the reasonable costs of alternative accommodation and additional living
expenses.
We will only pay for these costs for the period for which you are unable to live at your
Situation after the destruction, loss or damage has occurred. We will not pay for these costs if
we pay you for rent following damage to your Buildings under this Policy.
The complainants say their home has a 5kw solar system and that the cost of some of their
electricity is additional living expenses. However, they have not provided any information
comparing their charges at their home to the ones incurred whilst in temporary
accommodation to show they have sustained additional charges.
Insurer should pay additional costs for gas and electricity if substantiated
The panel notes the additional expenses claimed encompass the com plainants‟ full claim for
temporary accommodation. As the panel has only accepted three months of temporary
Determination | Case number: 852329 Page 9 of 22
accommodation is reasonable, then any additional expenses being claimed is capped for this
period.
In terms of the expenses claimed, the panel notes the following:
there is no indication the complainants were required to pay for council rates in their
alternative property – therefore, this cannot be considered an additional living expense
for payment of service, park and sewerage fees in their water bills – the complainants
have not provided evidence to show they are paying for these services at the rental
address as well. Therefore, the panel is not satisfied the complainants have shown these
are additional living expenses
For the gas and electricity, the available information is unclear if the complainants have
incurred additional living expenses in that regard. For instance, no comparison was provided
of their previous usage costs incurred in this regard compared to the costs they incurred
whilst in temporary accommodation.
The panel accepts it is likely an additional cost would have been incurred. The panel is not
persuaded this cost would be significant given it would be limited to a three month timeframe.
In this regard, in the interest of providing finality as much as possible given this longstanding
matter, the panel proposes to allow $750 in this regard.
Complainants are seeking reimbursement for future removal and storage fees
The complainants have not provided a receipt to show the cost of the storage fees for their
contents. They have however provided quotes for future removalist fees for $1,065.35 and
end of lease cleaning costs $570, as well as flea treatment costs $308.
The policy says:
If you are unable to live at your Situation after destruction, loss or damage has occurred,
we will pay the reasonable costs to remove and store your Contents for up to twelve (12)
months from the date of the destruction, loss or damage while your Situation is being
repaired. We will however only pay for the storage of your Contents during the time that
you are unable to live at your Situation.
The insurer is required to include in its cash settlement the cost of the future removalist and
the end of lease cleaning and flea treatment. These should be covered as part of the
reasonable accommodation costs and additional living expenses. The insurer should
reimburse these costs once they have been incurred. No interest is payable given these costs
have not been incurred to date.
S‟s SOW does not show storage of contents is necessary. The complainants‟ spreadsheet
indicates this is dependent on mould testing. However, the contemporaneous information on
5 March 2021, being when the insurer was prepared to begin the mould remediation, does
not indicate contents were affected or required storage away from the premises. The panel is
not persuaded there is sufficient basis to include this cost.
The complainants have referred to gardening fees. If the complainants can show they
incurred costs in gardening the tenanted property up to 10 June 2021, then these should be
included as additional living expenses. No interest is payable given the complainants have yet
to substantiate this claim.
Determination | Case number: 852329 Page 10 of 22
2.2 Should the insurer pay the complainant s’ professional
costs?
AFCA can award limited compensation for professional and expert fees
Under Rule D.5, AFCA may decide a financial firm is to contribute to the professional costs
incurred by a complainant in the course of a complaint. These costs can be awarded if the
complainants needed an expert to understand or establish their claim. These costs are
normally capped at $5,000 unless exceptional circumstances apply.
It is not usually necessary for complainants to be represented. AFCA decides whether the
insurer should contribute to these kinds of claimed costs by considering what is fair in the
circumstances, noting the complexity of the complaint and whether the complainants
genuinely required expert assistance.
The complainants seek the insurer to cover the cost of professional fees and expert reports
they have incurred. In their submission this totalled $32,505. However, this was not the final
amount they were seeking as they continued to utilise their solicitors throughout the course of
their complaint. The table below includes the experts‟ costs claimed.
Report Cost
TMD $709.50
A $2,502.50
BSH $3,300.00
M $9,570.00
BSS $8,250.00
The insurer accepted the fees from M for $3,500 excluding GST. The complainants have
provided a spreadsheet showing the costs of M to be $9,570.00 as well as solicitor fees in
excess of $8,173.
The complainants say the insurer should cover the expert report fees because they had
initially accepted them, and they required this assistance.
Insurer is only liable to pay $3,850 for the professional and expert fees
The panel appreciates this matter became protracted and may have been difficult for the
complainants. The assistance from their solicitors may have given them some comfort. The
panel however is not satisfied the submissions assisted the complaint‟s resolution or
advanced the complainants‟ position.
Given this, the insurer should not be liable f or the representative‟s costs in these
circumstances.
The reports provided from BSH, A, TMD and BSS did not materially assist the complainant‟s
position. This is because they did not establish the mould remediation offered by the insurer
was materially inadequate. The insurer is not liable to meet the costs of the reports from BSH,
A, TMD and BSS.
The panel is satisfied the insurer should pay $3,850 for M‟s expert evidence given it agreed to
do so. Interest pursuant to section 57 of the Act is payable on this amount from when these
costs were incurred until payment is made.
Determination | Case number: 852329 Page 11 of 22
The panel does not accept M‟s fees totalling $9,570 should be payable. This did not
materially assist the complainants and appears excessive.
2.3 Are the complainants entitled to other losses claimed?
Compensation is awarded conservatively
Under the AFCA Rules, we may award compensation (capped at $5,400) for non-financial
loss where a complainant has suffered an unusual degree or extent of physical
inconvenience, time taken to resolve the situation or interference with their expectation of
enjoyment or peace of mind.
We take a conservative approach to compensation for non-financial loss. It is not awarded
when a person suffers the normal degree of inconvenience when a problem occurs.
Insurer did not advise the policy would not be renewed
There is no dispute the insurer failed to provide sufficient notice of its intention not to renew
the policy. This was in breach of its requirements under section 58 of the Insurance Contracts
Act 1984 (Cth).
Given that a policy was arranged and accepted by the complainants, the panel is satisfied
that the complainants have not suffered a financial loss relating to the insurer‟s failure to
notify them of the expiry. However, the panel accepts that this would have caused undue
stress, in what was already a stressful situation for them.
Complainants say insurer mishandled claim
The complainants say that the insurer had failed to:
adequately acknowledge the complexity of the claim
engage the appropriate builder and loss adjuster, resulting in delays and inaction
engage mould inspection and testing until late February 2020, when it was suggested in
mid-2019
acknowledge and resolve any delays
adequately update them when the case manager or loss adjusters were no longer
working on the claim
provide them with the updated SOW or assessments from March 2021.
Further to the above, the complainants say that this matter has:
impacted the family‟s physical and mental health, as well as their wellbeing, due to a loss
of enjoyment
caused financial stress as they cannot afford tutoring or extracurricular activities
having to live in a townhouse with a small courtyard as opposed to their home.
Insurer required to pay $3,000 non-financial loss compensation
The panel accepts there were delays and a failure to respond or undertake mould testing
from when the complainants raised the claim in January 2019. There were also periods
throughout the claim where the loss adjuster and claim manager did not respond in a timely
manner, or failed to notify the complainants the claim manager or loss adjustors/assessors
had moved on from the insurer.
Determination | Case number: 852329 Page 12 of 22
However, the panel does not accept all of the delays were caused by the insurer. It is clear
there were delays in the complainants e ngaging their own experts. Further, the complainants‟
position on the claim was mostly unsubstantiated. The delays experienced in advocating this
dispute cannot be attributed to the insurer.
Therefore, the panel considers it fair in all the circumstances the insurer pay the complainants
a total amount of $3,000 in non-financial loss. This encompasses the initial delays and
service received throughout the claim as outlined above as well as the failure to provide them
with proper notice of its intention not to renew the policy.
Complainants not entitled to other damages
The complainants are seeking $300,000 in health damages. They say the insurer left them in
the property for an extended period, even after it was aware of the mould growth in the
property.
The complainants have provided various medical documents. None of them conclude the
medical issues experienced by the complainants were caused by the mould or the insurer‟s
inappropriate handling of the claim. This claim is therefore unsubstantiated.
The complainants are also seeking $300,000 in compensation for restricting their wealth
building. This is unsubstantiated. The complainants provided no evidence to show they would
have achieved this profit but for the insurer‟s poor claims handling.
The complainants also seek interest of $3,808.47. It is not clear how this is calculated.
Regardless, to the extent any interest is applicable on any payments under this
determination, this has been considered.
Determination | Case number: 852329 Page 13 of 22
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel
includes:
an ombudsman
a member with significant experience in consumer and small business advocacy
a member with extensive experience in general insurance.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
Determination | Case number: 852329 Page 14 of 22
3.2 Relevant reports
Record Key points
Financial firm‟s expert
(S)
Assessment Report
12 February 2021
Recommendations
Builder Assi stance
• [S] will require the assistance of a builder to allow for the isolation and
disconnections of all plumbing fixtures within the laundry and bathroom;
this includes the shower base, batht ub and surrounding, vanity and
associated fixtures, trough and the fixed c abinetry.
• The above is to facilitate the removal of timber flooring.
Structure
• [S] recommend that the home be assessed for any ongoing maintenance
issues that could relate or result in trapped moisture; ventilation within
the subfloor and ceiling cavity s hould be assessed to prevent ongoing
issues.
• Timber is deemed non - restorable and should be replaced with the
equivalent quality in the Hallway
• Tiles is deemed non - restorable and should be replaced with the
equivalent quality in the Laundry and Bathroom
Scope of Works
General
There is visible mould and mould remediation is required.
Supply of all appropriate site specific PPE.
Please note that further damage may become apparent during demolition.
Re inspect timber frames for further damage. Any rotted framework will be
encapsulated and marked for the builders to remove and replace.
Engineering Control s
• Erect critical containment barriers to the hallway to create a n isolated
remediation zone comprising of the 3 affected room (Bat hroom, laundry
and Hallw ay).
• [S] to cover and seal all HVAC registers and vents within the remediation
zone.
• Set up HEPA air filtration devices in all areas of the home, inclusive of
the roof cavity and sub floor to create a negative pressured environment
to control spread of air borne mould spores to prevent cross
contamination. This will also provide the appropriate air changes per
hour required.
Room: Hallway
Total Area(LxWxH):
3.0m x 1.2m x 2.4m
Floor Type:
Timber
Restorable:
No
Non - restorable reason:
Mould
Works to be Completed
Remove, double bag and dispose of affected subfloor
HEPA vacuum, sand/wire brush, HEPA vacuum and wash down and dry
Determination | Case number: 852329 Page 15 of 22
Record Key points
bearers & joists.
HEPA vacuum and was h down remaining ceilings, walls, woodwork,
doors, internal windows andframes.
Disposal of de bris
Following completion of the above, Steamatic will reinspect timbers and
moisture levels of the affected area
Room: Laundry
Total Area(LxWxH):
2.2m x 2.0m x 2.4m
Floor Type:
Tiles
Restorable:
No
Non - restorable reason:
Mould
Works to be Completed
Remove, double bag and dispose of affected tiled floor
Remove, double bag and dispose of affected subfloor
HEPA vacuum, sand/wire brush, HEPA vacuum and wash down and dry
bearers & joists.
HEPA vacuum and was h down remaining ceilings, walls, woodwork,
doors, internal windows and frames.
Disposal of debris
Following completion of the above, [S] will reinspect timbers and
moisture levels of the affected area
Room: Bathroom
Total Area(LxWxH):
2.2m x 2.5m x 2.4m
Floor Type:
Tiles
Restorable:
No
Non - res torable reason:
Mould
Works to be Completed
Remove, double bag and dispose of affected tiled floor
Remove, double bag and dispose of affected subfloor
HEPA vacuum, sand/wire brush, HEPA vacuum and wash down and dry
bearers & joists.
HEPA vacuum and was h d own remaining ceilings, walls, woodwork,
doors, internal windows and frames.
Disposal of debris
Following completion of the above, [S] will reinspect timbers and
moisture levels of the affected area
Sub - Floor Works
Remove, double bag and dispose of affected building debris
Determination | Case number: 852329 Page 16 of 22
Record Key points
HEPA vacuum all timber bearers, joists and columns
HEPA vacuum all internal brickwork linings
Application of anti - microbial to the above surfaces
Install Air Filtration Devices within the sub - floor (1 week allowance)
Ceiling Cavit y Works
Remove, double bag and dispose of affected building debris
Remove, double bag and dispose of insulation
HEPA vacuum all timber bearers, joists and trusses
HEPA vacuum all internal brickwork linings
Application of anti - microbial to the above surface s
Install Air Filtration Devices within the ceiling cavity (1 week allowance)
Remaining Areas of the Home
Installation and hire of HEPA air filt ration device for duration of works
HEPA vacuum and was h down remaining ceilings, walls, woodwork, doors,
internal windows and frames
HEPA vacuum, wash down and dry hard floors
Cost Summary
Labour Cost (ex GST): $8,694.50
Equipment Cost (ex GST): $6,399.75
Material Cost (ex GST): $2,016.36
Ceiling Cavity Extraction – Sub Contractor (PC SUM) (ex GST):
$3,000.00
Sub - Total (ex GST): $20,110.61
GST: $2,011.07
TOTAL = $22,121.68
Complainant’s expert
(TMD)
Mould assessment
report
23 March 2020
(inspection date – 19
March 2020)
Detailed Findings
Testing has been completed.
Owner has reported mould under the containment sheeting at the end of the hall
near the back door.
Defective pipe has been reported by the owner in the subfloor.
Elevated relative humidity levels have been detected and should be reduced and
maintained below 55% to
prevent mould occurring.
Treatment Recommendations
Elevated spore count has been det ected.
Decontamination foggin g of the internal areas of the property and sub floor is
recommended to eliminate
airborne mould spores, contaminants and other bacteria.
Complainant’s expert
(BHS) Mould
asse ssment report
21 August 2020
5.5 Recommendations
• Fail overall for the viable samples (4 OUT OF 6 SAMPLES)
• Professional remediation required
• HEPA air particle extraction required
• Barrier containment required
Determination | Case number: 852329 Page 17 of 22
Record Key points
• Post remediation verification required
• Strip out and partial demolition of affect ed building elements required
• Entry of persons only with use of appropriate PPE
• Hazard signage at entrance should be displayed
• Media blasting with dry ice
• Microfibre and damp wiping and/ or HEPA sandwich method required
• Persons should consider vacating property until clearance achieved
• A „builders clean‟ will be necessary
• Sufficient barrier containment works will need to be applied at this property
while works are underway to minimize cross - contamination
• While any works are occurring sections of the home will need to be zip - locked
with containment barriers to prevent or minimize cross - cont amination.
• Any persons who may be allergenic to mould, spores or mycotoxins should not
reside or ent er this property witho ut full use of PPE and respiratory protection
• The dirty insulation in the roof void should be removed and replaced with new
and the entire roof void HEPA vacuumed. Old insulation should be carefully
handled and not removed through the property
• Strip out works must only occur with complete barrier cont ainment and negative
pressure using HEPA filters properly setup to maintain containment conditions
for strip out.
• Contaminated building materials and mould remediation must follow the IICRC
S500/520 an d R520 and the Australian Mould Guideline any other relevant
Codes of Practice that should be known by skilled trade practitioners working in
the Industry.
• No occupancy should occur until a clearance certificate is provided that maps
testing using bot h viable and non - viable testing and including an assessment of
PM2.5 and PM10 that successfully compares „before‟ and „after‟ conditions as a
condition of re - occupancy.
• Duct cleaning required
• Source removal of mould affected building elements mandatory
• Alert key stakeholders about these results
3.4.2. Key Areas of Concern
The following area has AT MINIMUM FOUR AREAS THAT require remediation:
1. SUBFLOOR – ACCESSED FROM THE CUT OUT IN THE FLLOR IN THE
HALLWAY
2. SUBFLOOR WALL UNDER THE BUILDING
Determination | Case number: 852329 Page 18 of 22
Record Key points
3. RETURN HEATING DUCT INSIDE THE HOME
4. ROOF VOID TRUSS
3.4.3. Solutions to Key Areas of Concern
1. PROFESSIONAL MOULD REMEDIATION – STRIP OUT AND PHYSICAL
SURFACE TREATMENT TO THE SUBFLOOR TIMBERS INCLUDING
BEARERS
2. PROFESSIONAL MOULD REMEDIATION TO THE ROOF VOID TO
INCLUDE STRIP OUT OF ALL EXISTING INSULATION TO BE FOLLOWED BY
MANUAL HEPA VACUUMING OF THE EMPTY ROOF VOID
3. USE OF HEPA AIR SCRUBBERS INSIDE THE HABITABLE ROOMS WHEN
AY WORKS OCCUR TO SUBFLOOR AND ROOF VOID AREAS.
3.5 Conclusions
PROFESSIONAL MOULD REMEDIATION TO SURFACES
Complainant’s expert
(A) Mould asse ssment
report
21 August 2020
5. Conclusion and Recommendations
Continued occupation of the home is not recommended due to the hazardous
level of viable airborne mould.
A minimum recommended level of PPE for routine inspections/sampling includes
a P2 dust mask or half - face respirator with HEPA filters. Where there are strong
odours then an activated carbon filter or organic vapour filter should be used in
addition to HEPA . For work over an extended period of time, this should also
include disposable coveralls, gloves and eye protection.
It is difficult to comment on the conditions at the time of the pipe leak however it
is evident that the subfloor sustained moisture dama ge. The current conditions
have shown a high level of airborne mould with a wood rot fungi identified as the
dominant species. Several areas of the flooring, joists and bearers are damp and
at risk of further mould growth. There is also damp soil and risin g damp in
several areas of the subfloor.
It is recommended that mould cleaning and remediation is conducted in
accordance with best practice guidelines such as IICRC S500 Standard for
Professional Water Damage Restoration & S520 Standard for Professional
M o u ld Remediation
Further testing and inspection will be required to prepare a scope of works for
restoration and mould removal. Further testing should include total and viable
surface samples to det ermine the extent of mould contamination. The scope of
wor ks should be prepared by a restoration professional with cons ultation from a
qualified indoor environmental professional, mycologist and structural engineer.
Additional inspection may also be required during restoration works when areas
are more accessible which may reveal additional hidden areas requiring
Determination | Case number: 852329 Page 19 of 22
Record Key points
treatment.
An independent post remediation verification assessment should be undertaken
following completion of the remediation. This should be done by a qualified
indoor environment al professional/hygien ist and include both total and viable
airborne mould spora testing.
Complainants
hygienist report (M)
December 2020
Comments
Based on the above inspection, test and associated laboratory microbial sample
analysis, the subject dwelling was found to not be in a state of Normal
Environmental Fungal Ecology, at the time of inspection testing and microbial
sampling
Cons equently, rem ediation of the dwelling is recommended, followed by
inspection, test and microbial sampling to demonstrate that a state of Normal
Environmental Fungal Ecology is extant in the subject dwelling.”
The main areas of concern (contaminated) are the roof cavi ty and the
subfloor.
Recommendations
Given the results of inspection, measurement and microbial sample analysis,
remediation is strongly recommended. Suitable PPE should be used when
entering any part of the dwelling.
Its recommended that a detailed a nd comprehensive Scope of Works (SoW) for
remediation be prepared by a suitably qualified/experienc ed/trained party, in
accordance with the recommendations provided below, and consistent with the
specific appointed remediators processes, techniques and mat erials.
It is strongly recommended that remediation be followed by inspection; testing
and microbial sampling to verify the efficacy of remediation works, and
objectively demonstrate a return to Normal Environmental Fungal Ecology.
Testing should only be undertak en by and suitably qualified independent party.
It is recommended that, at a minimum, the following remediation activities be
diligently undertaken with demonstrably efficacious processes and materials.
The recommendations provided below are for remediation of the structure only:
i. Identify suitable anti - microbial agent(s) which have demonstrable, broad -
spectrum multi - log reduction (kill - rate) of both fungi and bacteria. Dependent
upon the specific remediator chosen anti - microbial, it may be n ecessary to apply
more than one form of anti - microbial. All agents selected must be compatible
with materials they are applied to (no damage) and not leave any residual toxic
effects. PPE recommended for any such agent(s) selected must be used.
ii. Ident ify suitable anti - microbial agent (s) for gaseous - phase sanitation. The
selected anti - mic robial agent(s) should have both demonstrable multi - log
reductions in bacteria and fungi, and exhibit oxidative properties. Dependent
upon the specific remediators chos en anti - microbial, it may be necessary to
apply more than one form of anti - microbial. All agents selected must be
compatible with materials they are applied to (no damage) and not leave any
residual toxic effects. PPE recommended for any such agent(s) sele cted must be
used.
iii. Identify suitable Mould Cleaning Solution (MCS) which has a demonstrable,
broad - spectrum multi - log reduction (kill - rate) of fungi. Dependent upon the
specific
remediator chosen MCS it may be necessary to apply more than one form of
Determination | Case number: 852329 Page 20 of 22
Record Key points
MCS. MCS selected must be compatible with materials they are applied to (no
damage) and not leave any residual toxic effects. PPE recommended for any
such MCS selected must be used.
iv. Install suitable air filtration devices as required;
v. Assess the roof cavity and remove any insulation if necessary;
vi. Assess the subfloor area and remove bulk contaminat ed building material;
vii. HEPA vacuum to all surfaces (entire house inc luding roof cavity and
subfloor);
viii. Liberally apply anti - microbial(s) selected in iii above, to the following
interior and exterior surfaces: a. Wooden and other structures in the roof cavity
b. Wooden or concrete flooring and timber structures in t he subfloor area
(storeroom)
c. Including all fixtures,
ix. Remove and replace any timber/ply wood that do not respond to treatment
(verify by IPT);
x. Remediat e all air - conditioners, ceiling fans and the air - path of any other
ventilation/exhaust device;
xi. Application of MCS, MCS wet - wipe, and HEPA vacuum to all surfaces, using
selected MCS(„s ) in v. above;
xii. Gaseous phase sensitization of ent ire property using selected agent in ii.
Above, ensuring that suitable concentration levels are achieved;
xiii. PRV test once all remediation is completed;
xiv. Reintroduce contents (tested);
xv. Clearanc e test (certificate) after reinstatement.
Complainant’s expert
report (M) 27 October
2021
5.6 The property last was measured for mould contaminates in January 2021,
some 9 mont hs ago. It is very likely that environmental conditions have changed
since, and the habitable space of the house is now most likely cross
contaminated wit h mould. The habitable space of the property should be re -
measured before any final SOW is determined. At a minimum the following
should be executed:
5.7 Identify suitable anti - microbial agent(s) which have demonstrable , broad -
spectrum multi - log reduction (kill - rate) of both fungi and bacteria. Dependent
upon the specific remediator chosen anti - microbial, it may be necessary to apply
more than one form of anti - microbial. All agents selected must be compatible
with materi als they are applied to (no damage) and not leave any residual toxic
effects. PPE recommended for any such agent(s) selected must be used.
5.8 Identify suitable anti - microbial agent (s) for gas eous - phase sanitation. The
selected anti - mic robial agent(s) sho uld have both demonstrable multi - log
reductions in bacteria and fungi and ex hibit oxidative properties. Dependent
upon the specific remediators chosen anti - microbial, it may be necessary to
apply more than one form of anti - microbial. All agents selected mu st be
compatible with materials they are applied to (no damage) and not leave any
residual toxic effects. PPE recommended for any such agent(s) selected must be
Determination | Case number: 852329 Page 21 of 22
Record Key points
used.
5.9 Identify suitable Mould Cleaning Solution (MCS) which has a demonstrable,
broad - spec trum multi - log reduction (kill - rate) of fungi. Dependent upon the
specific remediat or chosen MCS it may be necessary to apply more than one
form of MCS. MCS selected must be compatible with materials they are applied
to (no damage) and not leave any residu al toxic effects. PPE recommended for
any such MCS selected must be us ed.
5.10 Install suitable air filtration devices as required.
5.11 Assess the roof cavity and remove any insulation if necessary.
5.12 Assess the subfloor area and remove bulk contami nated building material.
5.13 HEPA vacuum to all surfaces (entire house including roof cavity and
subfloor);
5.14 Liberally apply anti - microbial(s ) selected above, to the following int erior and
exterior surfaces: 5.14.1 Wooden and other structures in the subfloor and roof
cavity
5.14.2 Wooden or concrete flooring and timber structures in the subfloor area
(storeroom)
5.14.3 Including all fixtures,
5.15 Remove and replace any timber/plywood that do not respond to treatment
(verify by IPT).
5.16 Remediate all air - conditioners, ceiling fans and the air - path of any other
ventilation/exhaust device.
5.17 Application of MCS, MCS wet - wipe, and HEPA vacuum to all surfaces,
using selected MCS(„s) above.
5.18 Gas eous phase sensitization of entire p roperty using selected agent above,
ensuring that suitable concentration levels are achieved.
5.19 PRV (Post remediation verification) once all remediation is complet ed.
5.20 Reintroduce contents (tested).
5.21 Clearance test (certificate) after reinsta tement.
Complainant’s Quote
and scope BSS – 30
March 2022
a) The leaking pipe in 2018 is not in my opinion as a building consultant the
cause of the structural movement. The cracking exhibited both externally and
internally is the result of seasonal movement of the underlying foundation clays
over many years. The appearance and condition of the property is consistent
with that of a forty plus year old brick veneer dwelling.
b) Mould infestation of the property, according to reports provided to me, is
present to a majority of the areas of the property. I am of the opinion that to
return the house
to its‟ original condition would require a stripping out of all flooring and
plasterboard linings prior to a full remediation process and a thorough testing
p rogram. Once fully remediated the re - building work could take place.
c) The total cost of the preparation work, remediation and re - instalment of the
property to original condition is estimated by me to be Two hundred and eighty
one thousand eight hundred and seventy five dollars. ($281,875)
Determination | Case number: 852329 Page 22 of 22