Text of the determination
Determination
Case number 850693
Financial firm Allianz Australia General Insurance Limited
Determination | Case number: 850693 Page 1 of 9
Case number: 850693 11 October 2022
1 Determination overview
1.1 Complaint
The complainant held a home and contents insurance policy with the financial firm (insurer). A
claim was lodged after fire significantly damaged the home on 19 April 2021.
The insurer accepted the claim and commenced repairs. Some months later, the insurer
offered to cash settle the complainant $401,762.40, instead of it finishing the incomplete
repairs. That was because, it said, the cost of completing all the necessary repairs would
have been greater than the building sum insured plus the 20% policy safety net. The insurer
said the cash settlement offer reflected the balance remaining of the sum insured (including
the safety net), after deducting the cost of the work already completed.
The complainant says it will cost him considerably more than that to complete the claim-
related repairs; and as well, there was further damage caused by the insurer’s builder . He is
also unhappy with the insurer’s handling of the claim, including delays in progressing repairs.
1.2 Issues and key findings
Is the insurer’s cash settlement fair and appropriate?
No. The insurer initially elected to undertake the claim-related repairs. Without proper
oversight of the scope or progress of work in the meantime, it then decided to change to a
cash settlement when the expected cost of those repairs looked likely to exceed the sum
insured. That effectively passed back to the complainant the risk of the incomplete repairs
and uncertainty about the cost to finalise the work. In addition, it is not clear that the
calculations on which the in surer’s cash settlement is based are an accurate reflection of the
value or scope of the work already undertaken and that still to be done.
The insurer is liable for the cost of all claim-related repairs carried out to date and for all
further costs required to fully repair the claim-related damage. That includes any such costs
which exceed the policy sum insured plus safety net. A full independent assessment of the
scope and value of claim-related repairs is required to be conducted (as set put in sections
1.3 and 2.1 below).
The insurer is also liable for temporary accommodation costs until the home is repaired to the
point where it is safe and reasonable for the complainant to move back in.
Is the complainant entitled to compensation for non-financial loss?
Yes. The complainant is entitled to $5,400 non-financial loss because of the significant impact
on the complainant and his family of the insurer’s unsatisfactory handling of the claim.
Why is the outcome fair?
It would not be fair for the insurer, having elected to repair the property, to revert to a cash
settlement mid-way through the repair process. That is particularly so, when – through its own
failure to properly oversee and manage the work – the costs to complete the repairs looked
likely to exceed the policy cover; and where there is no independent evidence to support the
Determination | Case number: 850693 Page 2 of 9
calculations on which the cash settlement was based. Deciding, at that late stage and in
those circumstances, to pass the risk back to the complainant represents an abrogation of the
insurer’s duty of utmost good faith.
1.3 Determination
This determination is in favour of the complainant.
The insurer is responsible for the cost and quality of all the claim-related repairs already
conducted and still to be completed. To be clear, that includes any costs that exceed the total
of the sum insured plus safety net.
The insurer is required to engage a suitably qualified external expert to conduct a full
assessment of the scope and value of all the repair work already conducted. The assessment
should also clearly scope and quote for all remaining work which still needs to be done to fully
repair the property.
To the extent the cost of any claim-related repairs incurred by the complainant to date is not
covered by the cash settlement already paid, the insurer is required to reimburse those costs,
together with statutory interest calculated from the date they were paid to the date of
settlement.
To the extent there is claim-related work which still needs to be done, the insurer is liable for
the timely and satisfactory completion and cost of that work.
The insurer is also required to pay the complainant $5,400 compensation for non-financial
loss.
Determination | Case number: 850693 Page 3 of 9
2 Reasons for determination
2.1 Is the insurer’s cash settlement fair and appropriate?
Claim-related repairs subject to variations as additional damage discovered
The complainant lodged the claim for fire damage to his property on 19 April 2021. The
insurer arranged for an assessment, including a forensic investigation, of the circumstances
of loss. The insurer accepted the claim in May 2021. The complainant was moved into
temporary accommodation.
The insurer’s panel builder (AJG) was appointed to deal with the claim-related work. Initially,
AJG installed a tarp over the exposed roofing to minimise water entry pending
commencement of the work. Repairs were due to start in early September 2021 (after
demolition and restoration work was undertaken). AJG estimated repairs would take 6 months
to complete.
Repairs commenced. However, due to the extent and nature of the damage (including the
discovery of mould and asbestos in November 2021), a number of variations to the scope of
work had to be made. The complainant expressed concern in November 2021 about the
progress of the repairs, and sent the insurer a detailed letter of complaint on 10 December
2021.
Insurer changed claim settlement from insurer repairs to part cash settlement
Having originally undertaken to deal with the claim-related repairs, the insurer ceased work
mid-way through the process. That was on the basis AJG had calculated the sum insured
under the policy would be exceeded. After further delays, the insurer proposed cash settling
the claim for the remaining repairs.
The insurer offered a cash settlement payment of $401,762.40 in late December 2021 (after
an initial offer of $377,309.35 was made and rejected by the complainant). That represented
$629,181.60 ($524,318 being the building sum insured, plus the $104,863.60 20% safety net)
less $227,419.20, being AJG’s calculation of the value of the costs already incurred/work
which AJG had already completed.
AJG’s calculation of the costs already incurred included s pecialist report fees of $5,787.95,
make- safe (‘e mergency repairs and protection ’) of $92,376.40, and actual repairs of
$129,254.85.
The complainant initially rejected that $401,762.40 second offer, but then agreed to accept it
on the basis he could continue to dispute the final cash settlement. The $401,762.40 was
paid to the complainant in March 2022.
The insurer says it was only made aware the repair costs would exceed the sum insured and
safety net on 6 December 2021. However, the insurer has reported (in its chronology of
events) that on 19 July 2021 AJG first indicated there could be possible unforeseen costs
greater than the sum insured. This was followed by a similar concern expressed by AJG
about the cost of variations on 11 November 2021.
Insurer’s handling of the claim not fair or consistent with duty of good faith
The insurer, having elected under the policy to be responsible for claim-related repairs (which
includes accepting the risks involved in that work), only changed its position once the scope
Determination | Case number: 850693 Page 4 of 9
of repair work and quantum of the claim escalated. However, by that point (about 7 months
after the claim was accepted), repairs were already significantly progressed and the house
itself could not reasonably or safely have been left in its then current state.
The available evidence shows that, in the meantime, the insurer had effectively played little, if
any, active role in the management of the claim. Instead, it appears to have relied wholly on
its panel builder AJG, until AJG reached the point where they felt it was beyond their
capability to continue to do so (both in terms of how/whether to proceed with the work, and
how to deal with the complainant and his concerns).
The panel considers that reliance amounted to an abrogation of responsibility by the insurer,
and created a potential conflict of interest in that there was no effective or independent
oversight or assessment of the builder’s work (and costs) as repairs progressed. That is
evident in the following concerns raised by the complainant (considered in more detail below):
additional damage he says was caused by the builder in the course of repairs
whether some of the work completed by the builder was necessary at all (removal of
bearers and joists)
the value of work actually completed by the builder (which was to be deducted from
the cash settlement offered)
the fact he felt he had no alternative but to continue to use AJG privately for the
remaining repairs after the insurer declined to proceed, and the cash settlement was
made.
The panel accepts AJG did attempt to help find a resolution of certain concerns with the
complainant, but these were unsuccessful, and the insurer itself failed to engage or
proactively assist. That includes in its communications with the complainant about the works
being undertaken and the reasons for the change to a cash settlement, after AJG had told the
complainant, on 8 December 2021, that he was ‘ underinsured ’ (effectively suggesting the
problem was one of the complainant’s own making) .
It is also not clear on the available evidence that, after the complainant complained to the
insurer about its handling of the claim, the insurer completed an IDR review.
No information to show AJG caused all additional damage to the property
The complainant submits there was additional damage caused by AJG during the repairs. On
3 February 2022, he provided a list of required repairs for that extra damage, which included
replacement of a wall and fence , repair of the rear pergola roof, repair of a side fence and
repairs for the front driveway and skip bin.
The insurer obtained information from AJG regarding this damage. AJG submits the
complainant removed the side fence to facilitate his own works at the rear of the property. As
well, AJG advised the complainant had some of his trades onsite at the same time, and
submits any damage was pre-existing. The panel is not persuaded the available information
shows the damage to the fence was, on balance, caused by AJG.
AJG advised the damage sustained to the rear pergola roof was from extreme weather
conditions which were reported throughout the make-safe and early repair updates. However,
some of damage was caused in part due to scaffolding planks being dislodged and becoming
airborne. The panel understands the insurer did agree to cover that, and it was included in the
cash settlement offered.
Determination | Case number: 850693 Page 5 of 9
Finally, AJG states the complainant never questioned any damage to the driveway during the
process. AJG submits, given the age of the driveway, it is fair to say it has sustained general
wear and tear over the years.
The panel is not satisfied, on balance, the available evidence supports the complainant’s
position that AJG caused that additional damage to the property (apart from the pergola
roofing) for which the insurer should be liable.
The complainant has, however, also more recently said there is water entering the house
because of the incorrect installation of gutters. It is not clear that has been investigated. That
should be included in the assessment required to be conducted (as set out below).
Information does not show the timber bearers and joists needed to be removed
As part of the repair works, AJG removed the timber bearers and joists, which were mould-
affected. The complainant submits the timber bearers and joists did not need to be removed.
He said he was informed the timber bears and joists would be tested, not removed.
The insurer says mould was identified by a hygienist (CES) and seen to be deep-set into the
bearers. It is for that reason (excessive mould) the insurer submits it was necessary to
remove the timber bearers.
However, CES recommended that ‘consideration be given to the removal of the flooring
supplemented by a detailed cleaning of the surfaces below/adjoining’ , due to the significantly
elevated microbial readings. CES states it is generally recommended to remove microbial-
impacted timbers, due to their porous nature. However, CES noted in certain circumstances it
might not be feasible to remove the timbers. CES recommended cleaning and treatment of
the mould.
The panel does not accept the available evidence shows the removal was strictly necessary.
For that reason, it is unfair for the cost of that removal (and the necessary reinstatement) to
be included in the calculation of work already completed by AJG and deducted from the cash
settlement.
That is to be taken account of in the further assessment required (as set out below).
Cash settlement based on AJG’s own calculations
The complainant disputes the extent and value of the work which the insurer says has already
been undertaken in the course of repairs.
The complainant accepted the i nsurer’s cash settlement (pending resolution of his concerns
about the quantum and scope), and agreed to proceed with the outstanding repairs, using
AJG privately. That is understandable, given it would, on balance, have been inefficient and
impracticable for a different repairer to have stepped in at a point. Nor is a new repairer likely
to have been willing to do so in any case, given the risk of dealing with incomplete work
undertaken by another builder.
The insurer obtained an adjusted list of costs from AJG, including works AJG had completed,,
which totalled $227,419.20. The list includes make- safe (‘emergency’ repairs), demolition,
general repairs and expert (structural engineer) fees. However, it is significant that no
independent review of AJG’s wo rk (either as to the scope or value) was undertaken.
The panel notes, for example, the $92,376.40 cost of the make-safe appears
disproportionately very high, being nearly 18% of the base building sum insured.
Determination | Case number: 850693 Page 6 of 9
As well, it appears AJG misinterpreted the policy provisions by including as part of the sum
insured, and deducting from the cash settlement, $22,672.04 that should instead be paid
under the extra policy benefit for ’demolition and removal of debris’ , in addition to the sum
insured. That is to be taken into account in the further assessment required (as set out
below).
In correspondence between the insurer and AJG in December 2021, the insurer estimated
that the cost to complete the remaining work would exceed the sum insured plus safety net by
$39,698.25.
However, the complainant says that as at February 2022, he had already spent $110,000 of
his own/borrowed money to continue the repairs.
Insurer ’s cash settlement not fair or appropriate to resolve the claim
For the reasons given in this dete rmination, the panel is not satisfied the insurer’s cash
settlement amount – or the fact of the cash settlement itself – is fair or sufficient to satisfy its
obligations in respect of this claim.
In the particular circumstances, the insurer should be held responsible for the cost and quality
of all the claim-related repairs conducted (both for that work conducted by AJG while the
insurer was authorising repairs and for that conducted after AJG was engaged directly by the
complainant). To be clear, that includes any costs that exceed the total of the sum insured
plus safety net.
The insurer is required to engage a suitably qualified external expert to conduct a full
assessment of the scope and value of all the repair work conducted by builder AJG (and as
appropriate, by other trades used by the complainant in having any aspect of the claim-
related work completed). The assessment should also clearly scope and quote for all
remaining work which still needs to be done to fully repair the property.
That assessment and report should identify the claim-related work and costs separately from
any additional work/variations undertaken for (or planned by) the complainant to upgrade or
otherwise alter the property. In other words, it must differentiate work not strictly required to
repair the claim-related damage (for which the insurer is not liable).
To the extent the cost of any claim-related repairs incurred by the complainant to date is not
covered by the cash settlement already paid, the insurer is required to reimburse those costs,
together with statutory interest calculated from the date they were paid to the date of
settlement.
To the extent there is claim-related work which still needs to be done, the insurer is liable for
the timely and satisfactory completion and cost of that work.
Temporary accommodation benefit to continue until house repaired/liveable
The complainant also raised a concern regarding temporary accommodation. On 5 May 2022,
he said the temporary accommodation was going to end toward the end of May.
The policy provides cover for temporary accommodation for either 10% of the sum insured or
for up to 12 months, whichever is less. The insurer had been providing temporary
accommodation from the start of the claim in April 2021. It is not clear the amount that has
been paid.
Determination | Case number: 850693 Page 7 of 9
On the evidence, the insurer has met the strict policy obligation for 12 months’ temporary
accommodation. However, delays in finalising the repairs have been, on balance,
exacerbated by the insurer’s mishandling of the claim.
The panel considers it fair, in the particular circumstances, that temporary accommodation
cover should continue until the claim-related repairs have been completed to the point where
the house is liveable and it is reasonable and safe for the complainant to move back in. The
insurer is required to cover those further accommodation costs.
The complainant is required to provide reasonable evidence of accommodation costs he has
already incurred, and not yet paid by the insurer, and the insurer is to reimburse those costs
(plus statutory interest calculated from the date paid by the complainant to the date of
settlement).
2.2 Is complainant entitled to non-financial loss compensation?
AFCA’s approach to non -financial loss
Under the AFCA Rules, we may award compensation (capped at $5,400) for non-financial
loss where a complainant has suffered an unusual degree or extent of physical
inconvenience, time taken to resolve the situation or interference with their expectation of
enjoyment or peace of mind.
Maximum compensation is warranted in the circumstances
The complainant has raised many concerns regarding the handling of the claim. The
complainant was dissatisfied with progress, with some of the repairs, and with the
communication provided by the insurer. His concern and confusion is understandable in the
circumstances, and in December 2021 the insurer had been put on notice by AJG of the
complainan t’s obvious ‘stress’ .
The panel has considered the chronology of events provided by the insurer. It is clear the
extent of the damage to the complainant’s property was severe , and the circumstances of the
damage giving rise to the claim would have caused the complainant an unusual degree of
inconvenience in themselves. The panel also acknowledges the repairs were quite complex,
and became more so as variations needed to be made.
However, the panel considers the complexity and complications arising from repairs and the
claim overall were largely the result of the insurer’s failure to actively and responsibly oversee
and manage the work as it progressed.
The insurer’s decision to c hange its settlement method mid-way through repairs, and the way
that decision was communicated and executed, caused the complainant very significant
upset. Compounding that was the insurer’s failure to properly assess the accuracy of the cash
settlement amount in the first place, which left the complainant financially exposed in
circumstances where:
the complainant had not, up to that point, had any control over what works were being
completed, at what cost or by whom
the insurer had not had any meaningful oversight of what was happening during the
claim process or the complaint process, and had not brought its own, independent
mind to bear when reviewing material submitted by the builder
the insurer had not complied with its complaints handling obligations by completing
the IDR process as required
Determination | Case number: 850693 Page 8 of 9
the insurer allowed the builder to investigate the complaints about itself (contrary to
good industry practice), taking no steps to review the matters independently
the insurer failed to communicate clearly with the complainant during the claim and
repair process about the risks of additional costs and the impact of that on the
available cover (sum insured), even after being put on notice by the builder.
The panel is satisfied an award of $5,400 is warranted in the circumstances.
2.3 Why is the outcome fair?
In the course of a claim, a point is reached where it becomes unfair for the insurer, having
knowledge of/access to the relevant facts (and the capacity and responsibility to manage the
issues), to resile from an election to undertake repairs. That point was passed when the
insurer’s proposed change to a cash settlement was implemented mid-way through significant
repair work, placing the complainant in a position of detriment, uncertainty and increased risk.
The principles of utmost good faith also apply. That requires, amongst other things, that the
insurer act with commercial standards of decency and fairness.
In the particular circumstances of this claim and complaint, it is fair that the insurer remains
responsible for the repair of the complainant’s property , even if the associated costs exceed
the policy sum insured plus safety net.
Determination | Case number: 850693 Page 9 of 9
3 Supporting information
3.1 AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel
includes:
an ombudsman
a member with significant experience in consumer and small business advocacy
a member with extensive experience in the insurance industry.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.