Progress payments released on valuations that allegedly did not support milestones reached
Text of the determination
Determination
Case number 849563
Financial firm HSBC Bank Australia Limited
Determination | Case number: 849563 Page 1 of 8
Case number: 849563 26 August 2022
1 Determination overview
1.1 Complaint
In December 2020, the complainant obtained a $950,000 construction loan from the bank to
build a home on the MW property (loan). The bank made three progress payments – $80,000,
$75,000 and $70,000 respectively – to the builder. The complainant says:
The bank made an error in releasing progress payments two and three as:
> progress milestones two and three (progress milestones) were not reached and the
bank ought to have known this from the valuations conducted
> the bank should not have accepted the valuations as they did not comply with the
Australian Banking and Finance Industry Residential Valuation Standing Instruction
2020 ( Standing Instruction )
> contrary to appendix 1, clause 7(c) (clause 7(c)) of the home loan terms, the total
amount the bank has released exceeded the value of the actual works completed
> he did not sign a final authority for the bank to release either of the progress payments.
It is not reasonable to expect borrowers to carry out their own valuations to ensure the
works the builder claims at the end of each milestone are, in fact, complete.
The complainant is seeking $145,000, being the three progress payments, released.
1.2 Issues and key findings
Was the bank entitled to release the progress payments?
Yes, I am satisfied the bank was entitled to release the progress payments in accordance
with the home loan terms.
Has the bank complied with clause 7(c) of the home loan terms?
Yes. The bank and complied with clause 7(c) of the home loan terms. The bank released the
amounts specified in the construction schedule for each milestone after it was asked to by the
complainant.
Was the bank entitled to charge the complainant for the valuations?
Yes, although t he valuations were for the bank’s benefit only and the complainant could not
rely on them, the bank was entitled to charge the complainant for them.
Why is the outcome fair?
The outcome is fair as while the circumstances the complainant has described are
unfortunate, the bank is not responsible for the delay or loss suffered by the complainant. The
bank acted in line with its agreement with the complainant. Accordingly, it would be unfair to
require the bank to pay the complainant any compensation.
Determination | Case number: 849563 Page 2 of 8
1.3 Determination
This determination is in favour of the bank. The bank should not compensate the
complainant.
Determination | Case number: 849563 Page 3 of 8
2 Reasons for determination
2.1 Was the bank entitled to release the progress payments?
Yes, I am satisfied the bank was entitled to release the progress payments in accordance
with the home loan terms.
The relationship between the complainant and the bank is contractual
The relationship between the complainant and the bank is based on contract. The bank
offered to provide the loan to the complainant on the terms set out in:
the letter the bank sent to the complainant on 17 March 2021 (offer letter)
the home loan terms
the personal banking booklet.
As set out in the offer letter, the terms in each of the above documents comprised the bank’s
offer and were to be read together. The complainant and the bank entered into an agreement
on those terms when the complainant accepted the bank’s offer on 18 March 2021. The
relationship did not extend to the bank overseeing the construction. The only service under
the contract was the provision of the loan.
The bank released the progress payments in line with the home loan terms
I am satisfied the bank was entitled to release the progress payments as each of the
conditions for the release of a progress payment, as contained in the home loan terms, were
met. The offer letter and personal banking booklet do not deal with the release of progress
payments.
The home loan terms provide that the bank was not entitled to make a progress payment
until:
it received a signed progress payment request form from the customer
the customer had met all the conditions set out in the letter of offer
the customer had sent the builder’s invoice to the bank
a valuer had confirmed that the building work for the relevant milestone had been done.
Therefore, for the bank to have been entitled to release the progress payments, the above
steps needed to have been satisfied.
The available information shows:
the complainant provided the bank with a ‘Progress Payment Authorit y to Debit’ form
(progress payment authority form), signed on 18 March 2021, which requested and
authorised the bank to make the progress payments
the complainant sent the bank the builder’s invoices for prog ress milestones two and three
on 30 March 2021 and 16 July 2021 respectively, and requested the bank to make the
progress payments
the bank engaged a valuer, who confirmed on 31 March 2021 and 19 July 2021
respectively that the progress milestones two and three had been reached.
It is not disputed that the complainant met all the conditions set out in the letter of offer. In line
with the conditions set out in the home loan terms, I am satisfied the bank was entitled to
release the progress payments for milestones two and three.
Determination | Case number: 849563 Page 4 of 8
The bank acted reasonably when it accepted the valuations
The complainant says the bank should not have released the progress payments because:
the photographs contained in the valuations provided to the bank show the progress
milestones were not reached and indicate the valuation was incomplete
the valuations do not comply with clauses 10.4(a) and (b), and 13.1(a), (b) and (c) of the
Standing Instruction .
Considering these issues, he says there ‘was enough of a flag for a banker, working in
construction lending to push for further review’.
I am satisfied the bank acted reasonably in accepting the valuations as:
The bank is not expected to be an expert itself in reviewing valuations provided to it.
T he bank acted reasonably in accepting the valuations as they did not raise any ‘red flags’
– the valuations were independently prepared, and they state that progress milestones two
and three had been achieved and gave photos in support. These photographs do not show
anything that would have, or ought to have, put a reasonable banker in the circumstances
on notice that works the valuer said had been completed were, in fact, not completed (if
that was the case).
The Standing Instruction is directed at the services given by valuers, not banks. The
Standing Instruction does not form part of the agreement between the complainant and the
bank. There is also no requirement under the general law or good industry practice for the
bank to ensure the valuations it receives accord with the Standing Instruction . The bank
was therefore not required to ensure the valuations conformed to the standards set out in
that document.
Under the agreement, the law and good industry practice, the bank – as distinct from the
builder – did not owe the complainant a duty of care to ensure the work required for each
milestone had been satisfactorily completed or that the quality of work completed would be
of a particular standard.
The complainant authorised the bank to make the progress payments
Under the home loan terms, the bank was only entitled to release a progress payment when,
amongst other conditions, it received a signed progress payment authority form from the
borrower. The complainant signed this form on 18 March 2021 and then provided it to the
bank. The form requests and authorises the bank to make the progress payments set out in
the loan schedule. This includes progress payments two and three. Therefore, provided the
other conditions were met (which, as discussed above, they were), the bank was entitled to
release the progress payments.
The available information does not show the complainant and the bank agreed, in addition to
the process set out in the home loan terms, that the bank would not release a progress
payment until after another, separate payment authority was obtained for each progress
payment. As there is also no requirement to do so under law or good industry practice, I am
satisfied the bank released the funds in line with the agreement reached with the complainant
and in compliance with the complainant’s instructions .
2.2 Did the bank comply with clause 7(c) of the home loan
terms?
Yes. The bank and complied with clause 7(c) of the home loan terms. The bank released the
amounts specified in the construction schedule for each milestone after it was asked to by the
complainant.
Determination | Case number: 849563 Page 5 of 8
The bank correctly interpreted clause 7(c) of the home loan terms
The complainant says that due to the defects in construction, the cost to complete the
outstanding works exceeds the remaining portion of the loan. On this basis, he submits the
bank has not complied with clause 7(c) of the home loan terms in releasing the progress
payments. Clause 7(c) provides that:
At no time should the cost to complete the works ever exceed the unused portion of
the overall loan balance.
The complainant says the wording ‘… cost to complete the works’ refers to the cost required
to build the unfinished portion of the house, not the remaining amount set out in the
construction schedule in the building contract and the progress payment authority form.
The bank disagrees, and says the clause is to be interpreted as:
the cost to complete the works per the construction schedule in the building contract
the amount of the unused portion of the overall loan balance.
I am satisfied that the bank has correctly interpreted clause 7(c) of the home loan terms. I do
not agree with the complainant’s interpretation. The heading under clause 7, which clause
7(c) falls under, reads:
‘Progress Payments … Your progress payment schedule is set out in your
building contract’.
I consider this shows that the phrase ‘… cost to complete the works’ is to be assessed
against the payment schedule in the building contract. Such an interpretation is also a fair and
reasonable one having regard to the nature of the contractual relationship.
On 18 March 2021, the complainant signed the progress payment authority form, which
contained this schedule. I consider the wording of the clause plain and clear. The complainant
says the home loan t erms ‘… are worded so that the bank can be lax in its process, allow
errors to happen and take no responsibility’ . If the complainant was unhappy with the wording
of the home loan terms, he was free to enquire with the bank further, go to another funder or
seek legal advice before accepting them.
The bank complied with clause 7(c) of the home loan terms
Immediately after the bank released progress payments two and three:
the costs to complete the remaining building works was $665,755.93
the amount of the unused portion of the loan balance was $665,755.93.
Based on the available information, I am satisfied the cost to complete the works did not
exceed the unused portion of the loan balance and that the bank has acted in accordance
with clause 7(c).
2.3 Was the bank entitled to charge the complainant for the
valuations?
Yes, a lthough the valuations were for the bank’s benefit only and the complainant could not
rely on them, the bank was entitled to charge the complainant for them.
Determination | Case number: 849563 Page 6 of 8
The valuations were solely for the bank’s benefit
The complainant says the valuations the bank accepted were not for his benefit and did not
protect his interest. He says it is not reasonable to expect borrowers to carry out their own
valuations to ensure the works the builder claims at the end of each milestone was, in fact,
completed. He says he should be able to rely on the bank’s valuations.
The bank was entitled to require valuations before releasing the progress payments. Clause
25 of the home loan terms:
expressly state that the valuations the bank obtains on the property under the loan or the
security property, or which the bank requires the customer to obtain, will be for the bank’s
benefit and that the customer cannot rely on them
recommend that the customer should carry out their own enquiries, such as valuations and
searches.
I am satisfied the valuations were for the benefit of the bank, not the complainant. The
complainant was not entitled to rely on the valuations as a safeguard against the progress
milestones not being achieved
The home loan terms disclose the complainant would pay for the valuations
The complainant says it is not fair for the bank to have required him to pay for a valuation
before each progress payment was released but to then claim the valuations were not for his
benefit.
I am satisfied that the bank was entitled to require the complainant to pay for each of the
valuation before it released each progress payment. I have reached this finding after
considering the available information, which shows:
the complainant and the bank agreed the complainant would pay $95 for each valuation,
which would be undertaken before each progress payment was made, and
under clause 25 of the home loan terms, the bank was entitled to require valuations before
releasing the progress payments and to require the complainant to pay for the costs.
The relevant clauses of the home loan terms referred to above are set out in section 3 of this
determination.
2.4 Why is the outcome fair?
The outcome is fair in all the circumstances as the bank was entitled to release the progress
payments and acted in accordance with the agreement reached with the complainant and in
compliance with the complainant’s instructions.
As the bank has not made an error or breached any obligation it owed to the complainant, it
would be unfair to require it provide the complainant with compensation.
Determination | Case number: 849563 Page 7 of 8
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
3.2 Relevant extracts from the Home Loan Terms
Appendix 1, 7(a).
Progress Payments
Your progress payment schedule is set out in your building contract. We won’t
make a progress payment until we receive a signed progress payment request
from you and you have met all the conditions set out in your letter of offer. You’ll
need to send us the builder’s invoice so we can pay the builder, and complete the
authorisation form instructing us to make the payment. Our valuer will also need
to confirm to us that the building work has been done.
…
7(c).
At no time should the cost to complete the works ever exceed the unused portion
of the overall loan balance.
25.
We may obtain or require you to obtain a valuation or a report of the security
property at any time we reasonably consider necessary. This will be for our
benefit, and we can charge the cost of the valuation or report to your loan account
or any accounts you hold with us.
Other important information
Determination | Case number: 849563 Page 8 of 8
When we assess credit applications or during the course of lending, we may carry
out searches, inspections, valuations and other enquiries. These are for our own
purposes, and you cannot rely on them. We recommend that you:
• carry out your own enquiries such as valuations and searches;
• seek your own independent professional, financial and legal advice;
• take time to careful ly read and understand all documents in connection with your
credit and with your purchase.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.