Home / HSBC / Determination 849563

Determination 849563

Progress payments released on valuations that allegedly did not support milestones reached

FirmHSBC
Decided2022-08-26
ProductCredit · Home loan
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$145,000
SourceAFCA PDF

Summary

The complainant, a borrower under a construction loan, complained that the bank wrongly released two progress payments totalling $145,000 based on valuations that did not show milestones were reached. AFCA decided the bank was entitled to release the payments under the loan terms and made no award.

The relationship is contractual; the bank met the progress payment conditions in the home loan terms, acted reasonably in accepting independent valuations, and was not bound by the Standing Instruction or owed a duty to supervise construction.

Issues

Subjects and remedies

no remedy

Related

All HSBC determinations · Find similar determinations

Text of the determination

Determination Case number 849563 Financial firm HSBC Bank Australia Limited Determination | Case number: 849563 Page 1 of 8 Case number: 849563 26 August 2022 1 Determination overview 1.1 Complaint In December 2020, the complainant obtained a $950,000 construction loan from the bank to build a home on the MW property (loan). The bank made three progress payments – $80,000, $75,000 and $70,000 respectively – to the builder. The complainant says:  The bank made an error in releasing progress payments two and three as: > progress milestones two and three (progress milestones) were not reached and the bank ought to have known this from the valuations conducted > the bank should not have accepted the valuations as they did not comply with the Australian Banking and Finance Industry Residential Valuation Standing Instruction 2020 ( Standing Instruction ) > contrary to appendix 1, clause 7(c) (clause 7(c)) of the home loan terms, the total amount the bank has released exceeded the value of the actual works completed > he did not sign a final authority for the bank to release either of the progress payments.  It is not reasonable to expect borrowers to carry out their own valuations to ensure the works the builder claims at the end of each milestone are, in fact, complete. The complainant is seeking $145,000, being the three progress payments, released. 1.2 Issues and key findings Was the bank entitled to release the progress payments? Yes, I am satisfied the bank was entitled to release the progress payments in accordance with the home loan terms. Has the bank complied with clause 7(c) of the home loan terms? Yes. The bank and complied with clause 7(c) of the home loan terms. The bank released the amounts specified in the construction schedule for each milestone after it was asked to by the complainant. Was the bank entitled to charge the complainant for the valuations? Yes, although t he valuations were for the bank’s benefit only and the complainant could not rely on them, the bank was entitled to charge the complainant for them. Why is the outcome fair? The outcome is fair as while the circumstances the complainant has described are unfortunate, the bank is not responsible for the delay or loss suffered by the complainant. The bank acted in line with its agreement with the complainant. Accordingly, it would be unfair to require the bank to pay the complainant any compensation. Determination | Case number: 849563 Page 2 of 8 1.3 Determination This determination is in favour of the bank. The bank should not compensate the complainant. Determination | Case number: 849563 Page 3 of 8 2 Reasons for determination 2.1 Was the bank entitled to release the progress payments? Yes, I am satisfied the bank was entitled to release the progress payments in accordance with the home loan terms. The relationship between the complainant and the bank is contractual The relationship between the complainant and the bank is based on contract. The bank offered to provide the loan to the complainant on the terms set out in:  the letter the bank sent to the complainant on 17 March 2021 (offer letter)  the home loan terms  the personal banking booklet. As set out in the offer letter, the terms in each of the above documents comprised the bank’s offer and were to be read together. The complainant and the bank entered into an agreement on those terms when the complainant accepted the bank’s offer on 18 March 2021. The relationship did not extend to the bank overseeing the construction. The only service under the contract was the provision of the loan. The bank released the progress payments in line with the home loan terms I am satisfied the bank was entitled to release the progress payments as each of the conditions for the release of a progress payment, as contained in the home loan terms, were met. The offer letter and personal banking booklet do not deal with the release of progress payments. The home loan terms provide that the bank was not entitled to make a progress payment until:  it received a signed progress payment request form from the customer  the customer had met all the conditions set out in the letter of offer  the customer had sent the builder’s invoice to the bank  a valuer had confirmed that the building work for the relevant milestone had been done. Therefore, for the bank to have been entitled to release the progress payments, the above steps needed to have been satisfied. The available information shows:  the complainant provided the bank with a ‘Progress Payment Authorit y to Debit’ form (progress payment authority form), signed on 18 March 2021, which requested and authorised the bank to make the progress payments  the complainant sent the bank the builder’s invoices for prog ress milestones two and three on 30 March 2021 and 16 July 2021 respectively, and requested the bank to make the progress payments  the bank engaged a valuer, who confirmed on 31 March 2021 and 19 July 2021 respectively that the progress milestones two and three had been reached. It is not disputed that the complainant met all the conditions set out in the letter of offer. In line with the conditions set out in the home loan terms, I am satisfied the bank was entitled to release the progress payments for milestones two and three. Determination | Case number: 849563 Page 4 of 8 The bank acted reasonably when it accepted the valuations The complainant says the bank should not have released the progress payments because:  the photographs contained in the valuations provided to the bank show the progress milestones were not reached and indicate the valuation was incomplete  the valuations do not comply with clauses 10.4(a) and (b), and 13.1(a), (b) and (c) of the Standing Instruction . Considering these issues, he says there ‘was enough of a flag for a banker, working in construction lending to push for further review’. I am satisfied the bank acted reasonably in accepting the valuations as:  The bank is not expected to be an expert itself in reviewing valuations provided to it.  T he bank acted reasonably in accepting the valuations as they did not raise any ‘red flags’ – the valuations were independently prepared, and they state that progress milestones two and three had been achieved and gave photos in support. These photographs do not show anything that would have, or ought to have, put a reasonable banker in the circumstances on notice that works the valuer said had been completed were, in fact, not completed (if that was the case).  The Standing Instruction is directed at the services given by valuers, not banks. The Standing Instruction does not form part of the agreement between the complainant and the bank. There is also no requirement under the general law or good industry practice for the bank to ensure the valuations it receives accord with the Standing Instruction . The bank was therefore not required to ensure the valuations conformed to the standards set out in that document.  Under the agreement, the law and good industry practice, the bank – as distinct from the builder – did not owe the complainant a duty of care to ensure the work required for each milestone had been satisfactorily completed or that the quality of work completed would be of a particular standard. The complainant authorised the bank to make the progress payments Under the home loan terms, the bank was only entitled to release a progress payment when, amongst other conditions, it received a signed progress payment authority form from the borrower. The complainant signed this form on 18 March 2021 and then provided it to the bank. The form requests and authorises the bank to make the progress payments set out in the loan schedule. This includes progress payments two and three. Therefore, provided the other conditions were met (which, as discussed above, they were), the bank was entitled to release the progress payments. The available information does not show the complainant and the bank agreed, in addition to the process set out in the home loan terms, that the bank would not release a progress payment until after another, separate payment authority was obtained for each progress payment. As there is also no requirement to do so under law or good industry practice, I am satisfied the bank released the funds in line with the agreement reached with the complainant and in compliance with the complainant’s instructions . 2.2 Did the bank comply with clause 7(c) of the home loan terms? Yes. The bank and complied with clause 7(c) of the home loan terms. The bank released the amounts specified in the construction schedule for each milestone after it was asked to by the complainant. Determination | Case number: 849563 Page 5 of 8 The bank correctly interpreted clause 7(c) of the home loan terms The complainant says that due to the defects in construction, the cost to complete the outstanding works exceeds the remaining portion of the loan. On this basis, he submits the bank has not complied with clause 7(c) of the home loan terms in releasing the progress payments. Clause 7(c) provides that: At no time should the cost to complete the works ever exceed the unused portion of the overall loan balance. The complainant says the wording ‘… cost to complete the works’ refers to the cost required to build the unfinished portion of the house, not the remaining amount set out in the construction schedule in the building contract and the progress payment authority form. The bank disagrees, and says the clause is to be interpreted as:  the cost to complete the works per the construction schedule in the building contract  the amount of the unused portion of the overall loan balance. I am satisfied that the bank has correctly interpreted clause 7(c) of the home loan terms. I do not agree with the complainant’s interpretation. The heading under clause 7, which clause 7(c) falls under, reads: ‘Progress Payments … Your progress payment schedule is set out in your building contract’. I consider this shows that the phrase ‘… cost to complete the works’ is to be assessed against the payment schedule in the building contract. Such an interpretation is also a fair and reasonable one having regard to the nature of the contractual relationship. On 18 March 2021, the complainant signed the progress payment authority form, which contained this schedule. I consider the wording of the clause plain and clear. The complainant says the home loan t erms ‘… are worded so that the bank can be lax in its process, allow errors to happen and take no responsibility’ . If the complainant was unhappy with the wording of the home loan terms, he was free to enquire with the bank further, go to another funder or seek legal advice before accepting them. The bank complied with clause 7(c) of the home loan terms Immediately after the bank released progress payments two and three:  the costs to complete the remaining building works was $665,755.93  the amount of the unused portion of the loan balance was $665,755.93. Based on the available information, I am satisfied the cost to complete the works did not exceed the unused portion of the loan balance and that the bank has acted in accordance with clause 7(c). 2.3 Was the bank entitled to charge the complainant for the valuations? Yes, a lthough the valuations were for the bank’s benefit only and the complainant could not rely on them, the bank was entitled to charge the complainant for them. Determination | Case number: 849563 Page 6 of 8 The valuations were solely for the bank’s benefit The complainant says the valuations the bank accepted were not for his benefit and did not protect his interest. He says it is not reasonable to expect borrowers to carry out their own valuations to ensure the works the builder claims at the end of each milestone was, in fact, completed. He says he should be able to rely on the bank’s valuations. The bank was entitled to require valuations before releasing the progress payments. Clause 25 of the home loan terms:  expressly state that the valuations the bank obtains on the property under the loan or the security property, or which the bank requires the customer to obtain, will be for the bank’s benefit and that the customer cannot rely on them  recommend that the customer should carry out their own enquiries, such as valuations and searches. I am satisfied the valuations were for the benefit of the bank, not the complainant. The complainant was not entitled to rely on the valuations as a safeguard against the progress milestones not being achieved The home loan terms disclose the complainant would pay for the valuations The complainant says it is not fair for the bank to have required him to pay for a valuation before each progress payment was released but to then claim the valuations were not for his benefit. I am satisfied that the bank was entitled to require the complainant to pay for each of the valuation before it released each progress payment. I have reached this finding after considering the available information, which shows:  the complainant and the bank agreed the complainant would pay $95 for each valuation, which would be undertaken before each progress payment was made, and  under clause 25 of the home loan terms, the bank was entitled to require valuations before releasing the progress payments and to require the complainant to pay for the costs. The relevant clauses of the home loan terms referred to above are set out in section 3 of this determination. 2.4 Why is the outcome fair? The outcome is fair in all the circumstances as the bank was entitled to release the progress payments and acted in accordance with the agreement reached with the complainant and in compliance with the complainant’s instructions. As the bank has not made an error or breached any obligation it owed to the complainant, it would be unfair to require it provide the complainant with compensation. Determination | Case number: 849563 Page 7 of 8 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. 3.2 Relevant extracts from the Home Loan Terms Appendix 1, 7(a). Progress Payments Your progress payment schedule is set out in your building contract. We won’t make a progress payment until we receive a signed progress payment request from you and you have met all the conditions set out in your letter of offer. You’ll need to send us the builder’s invoice so we can pay the builder, and complete the authorisation form instructing us to make the payment. Our valuer will also need to confirm to us that the building work has been done. … 7(c). At no time should the cost to complete the works ever exceed the unused portion of the overall loan balance. 25. We may obtain or require you to obtain a valuation or a report of the security property at any time we reasonably consider necessary. This will be for our benefit, and we can charge the cost of the valuation or report to your loan account or any accounts you hold with us. Other important information Determination | Case number: 849563 Page 8 of 8 When we assess credit applications or during the course of lending, we may carry out searches, inspections, valuations and other enquiries. These are for our own purposes, and you cannot rely on them. We recommend that you: • carry out your own enquiries such as valuations and searches; • seek your own independent professional, financial and legal advice; • take time to careful ly read and understand all documents in connection with your credit and with your purchase.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.