Determination 847790
Business interruption / loss of rent claim under consequential loss section and related leasing fees
Summary
A business insured under an ISR policy claimed loss of rent and leasing costs after tenant damage to its premises and delays in claim settlement. AFCA found the insurer liable for fourteen weeks of business interruption loss of rent but rejected the agent and re-marketing fees and compensation for delay.
Section 2 consequential loss cover applies where accepted material damage interrupts the insured business, but the policy does not extend to vacancy-related costs or compensation for delays attributable to both parties.
Issues
- Claim denial primary · upheld
“The panel is satisfied the complainant has a valid claim under section 2 of the policy for fourteen weeks business interruption/loss of rent costs.”
- Claim amount dispute secondary · not upheld
“The panel is not satisfied the complainant established the agent fees and re-marketing fee are a claimable loss.”
- Delay secondary · not upheld
“While there were delays in the assessment these can be attributed to both parties and it would not be fair to require the insurer to compensate the complainant for these delays.”
Subjects and remedies
business interruptionsmall businesspay claim
Text of the determination
Determination
Case number 847790
Financial firm Chubb Insurance Australia Limited
Determination | Case number: 847790 Page 1 of 5
Case number: 847790 17 August 2022
1 Determination overview
1.1 Complaint
The complainant, a business, holds an industrial special risk policy (ISR) with the financial
firm (the insurer). A claim was lodged on 3 November 2020 for material damage and
consequential loss after its tenants modified the premises and then abandoned the property.
After investigation of the claim the insurer the insurer paid $92,712.00 for material damage. It
denied liability for consequential loss and says the loss of rent claimed did not arise from the
material damage but from the tenants breaking the rental agreement and failure to pay rent.
The complainant is claiming a further $268,537.50 for loss of rent and associated leasing and
marketing costs. The complainant says the loss of rent and associated costs are a
consequence of the material damage and delays in settling the claim.
The insurer says the complainant has not submitted any evidence of the nexus between the
material damage and the alleged consequential loss of rent claimed under Section 2. The
insurer says Section 2 of the ISR Policy does not cover loss of rent allegedly arising from
delays in the assessment process or from delays in repairing the material damage.
1.2 Issues and key findings
Is the complainant entitled to loss of rent under Section 2 of the policy?
Yes. The panel is satisfied the complainant has a valid claim under section 2 of the policy for
fourteen weeks business interruption/loss of rent costs as set out in section 2.1 of this
determination.
Is the insurer liable for consequential loss?
No. The panel is not satisfied the complainant established the agent fees and re-marketing
fee are a claimable loss. The insurer is not liable for these fees.
Why is the outcome fair?
The outcome is fair as the panel is satisfied that a reasonable period to assess and then
repair the premises would be fourteen weeks. While there were delays in the assessment
these can be attributed to both parties and it would not be fair to require the insurer to
compensate the complainant for these delays
1.3 Determination
This determination is partially in favour of the complainant.
The insurer is liable to meet the complainants claim under section 2 of the policy. Within
twenty-one days of the complainant’s acceptance of this determination, the insurer is to pay
the complainant compensation for fourteen weeks business interruption/loss of rent.
Determination | Case number: 847790 Page 2 of 5
2 Reasons for determination
2.1 Is the insurer liable for business interruption?
Yes. The panel is satisfied the complainant has a valid claim under section 2 of the policy for
business interruption/loss of rent costs for the fourteen-week repair period.
Policy covers consequential loss if material damage accepted
The complainant holds an industrial special risks policy. Section 1 of the policy covers
Material Loss or Damage to the insured premises, subject to policy terms, conditions and
exclusions.
If the insurer accepts liability for material damage to the insured property under section 1,
section 2 of the policy may be triggered. Section 2 of the policy covers Consequential Loss:
In the event of any building or any other property or any part thereof used by the
Insured at the Premises for the purpose of the Business being physically lost,
destroyed or damaged during the period of insurance by any cause or event not
hereinafter excluded (loss, destruction or damage so caused being hereinafter
termed “Damage”) and the Business carried on by the Insured being in
consequence thereof interrupted or interfered with, the Insurer(s) will, subject to
the provisions of this Policy including the limitation on the Insurer(s) liability, pay
to the Insured the amount of loss resulting from such interruption or interference
in accordance with the applicable Basis of Settlement.
This means for Section 2 to apply the complainant must show:
The insurer accepted liability for physical loss or damage to the insured premises under
Section 1.
The business carried on by the insured at the premises was interrupted or interfered with
because of the damage accepted under Section 1.
Delays in assessment of material damage claim under Section 1 of policy
The exchanged information shows:
The complainant entered into a lease agreement with PL on 1 April 2020
An application for an internal fit out was approved on 18 May 2020
A notice of breach was sent to PL on 13 July 2020
A final demand for rent was sent 17 August 2020 and the complainant took possession of
premises on 26 August 2020.
Notice of default sent to PL with notice to make good repairs sent 24 September 2020.
Termination notice sent 30 October 2020
The complainant lodged the claim on 3 November 2020.
The insurer commenced its investigations on 16 November 2020.
There were delays in providing the agreed scope of works (SOW) for the approved fit out.
The broker notified the insurer on 18 January that there was no agreed SOW
29 April 2020 insurer accepts material damage claim and pays the first instalment of repair
costs of $69,905.44 on 15 June 2021.
Complainant notifies insurer of business interruption claim under Section 2 of policy
The complainant commenced repairs on 16 June 2021.
A second cash payment was issued on 30 August 2021
Determination | Case number: 847790 Page 3 of 5
Third and final cash settlement issued 7 September 2021
Construction works took 12 weeks to finalise.
Tenants could not view level 12, take possession and guarantee the property was
compliant with the relevant codes until repairs were completed.
The panel notes from emails between parties that information was requested by the insurer
but provided in a piecemeal manner. The panel is surprised that information such as an
approved scope of works or invoices for the make safe work were not readily available to the
complainant’s broker. At the same time, the panel is surprised at the insurers continued delay
in accepting liability after inspection of the property in February 2020, receipt of the CDC and
relevant invoices.
Complainant has established claim under section 2 of policy
The panel accepts there is valid claim under section 1 of the policy. To establish a claim
under section 2 of the policy the complainant must still prove that the business interruption
was caused by the material damage.
The insurer says it should not be liable for business interruption because the complainant
failed to mitigate its loss. It says the complainant could have placed interested tenants in
another available floor. It says that because the complainant has not shown there were any
interested parties in the floor or any other floor, the claimed loss was the result of market
downturn and lack of interest from tenants.
The panel accepts the insurer is not liable for business interruption resulting from the vacancy
of the building. The panel does not agree that the complainant was required to place
interested parties in a different location to reduce the claim. The damage would have made it
difficult to lease the premises. It is reasonable to accept the floor could not be fully tenanted
until the repairs were completed.
The panel accepts the insurer is liable for business interruption / loss of rent under section 2.
The panel is satisfied that the building was damaged within the period of insurance and
because of the damage the complainant’s business was interrupted or interfered with as the
premises could not be tenanted.
Insurer entitled to limit claim for loss of rent.
The complainant seeks compensation for business interruption for a period of nine and a half
months being six and a half months for the delay in assessment of the material damage claim
and three months for the repairs.
While the panel acknowledges the delays, as indicated earlier in this determination, those
delays were contributed to by the complainant’s difficulty in providing the relevant information.
The available information confirms the complainant had organised for new tenants to take up
a portion of the floor on 1 June 2021 and another tenant on 12 July 2021. The complaint
notice lodged with AFCA indicates the floor was fully tenanted by 27 August 2021 despite the
repairs still being completed.
The evidence shows the repair period was approximately twelve weeks. Although a bit
subjective, the panel considers this a fair starting point to assess the quantum of the claim.
The panel accepts a reasonable assessment period after obtaining the relevant information
would be approximately two weeks. This would bring the total loss of rent payable to
approximately fourteen weeks.
Determination | Case number: 847790 Page 4 of 5
This would allow for the assessment period to have commenced mid to late February 2020
(after the insurer had the relevant damage reports) and for the repairs to be completed prior
new tenants entering the premises in June 2021.
The panel considers it fair in the circumstances the insurer pays compensation for loss of rent
under section 2 of the policy for a period of fourteen weeks.
2.2 Is the complainant entitled to consequential loss?
Insurer not liable for real estate and marketing fees
The complainant seeks for the insurer to reimburse it for agent fees for introducing three new
tenants to the premises and re-marketing fee of $3,397.90 for listing and advertising the
premises for lease.
The insurer declined liability for these costs because it says they were not incurred because
of the accepted damage, rather consequence of the complainant seeking to find new tenants.
The panel agrees with the insurer’s submission that the these are costs the complainant
would have incurred regardless of any damage to the propert y and relate solely to property’s
vacancy, not the damage.
The panel is not satisfied the complainant established these costs fall under section 2 and the
insurer is entitled to deny the claim.
2.3 Why is the outcome fair?
Outcome is fair
The complainant is required it suffered a claimable loss. If the complainant can show the
policy respond, the insurer is required to settle the claim within the policy terms and
conditions.
The outcome is fair as the panel is satisfied that a reasonable period to assess and then
repair the premises would be fourteen weeks. There were delays in the assessment of
damage, but these can be attributed to both parties and it would not be fair to require the
insurer to compensate the complainant for these delays.
Determination | Case number: 847790 Page 5 of 5
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel
includes an ombudsman, a member with significant experience in consumer and small
business advocacy and a member with extensive industry experience.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.