Summary

A business insured under an ISR policy claimed loss of rent and leasing costs after tenant damage to its premises and delays in claim settlement. AFCA found the insurer liable for fourteen weeks of business interruption loss of rent but rejected the agent and re-marketing fees and compensation for delay.

Section 2 consequential loss cover applies where accepted material damage interrupts the insured business, but the policy does not extend to vacancy-related costs or compensation for delays attributable to both parties.

Issues

Subjects and remedies

business interruptionsmall businesspay claim

Related

All Chubb determinations · Find similar determinations

Text of the determination

Determination Case number 847790 Financial firm Chubb Insurance Australia Limited Determination | Case number: 847790 Page 1 of 5 Case number: 847790 17 August 2022 1 Determination overview 1.1 Complaint The complainant, a business, holds an industrial special risk policy (ISR) with the financial firm (the insurer). A claim was lodged on 3 November 2020 for material damage and consequential loss after its tenants modified the premises and then abandoned the property. After investigation of the claim the insurer the insurer paid $92,712.00 for material damage. It denied liability for consequential loss and says the loss of rent claimed did not arise from the material damage but from the tenants breaking the rental agreement and failure to pay rent. The complainant is claiming a further $268,537.50 for loss of rent and associated leasing and marketing costs. The complainant says the loss of rent and associated costs are a consequence of the material damage and delays in settling the claim. The insurer says the complainant has not submitted any evidence of the nexus between the material damage and the alleged consequential loss of rent claimed under Section 2. The insurer says Section 2 of the ISR Policy does not cover loss of rent allegedly arising from delays in the assessment process or from delays in repairing the material damage. 1.2 Issues and key findings Is the complainant entitled to loss of rent under Section 2 of the policy? Yes. The panel is satisfied the complainant has a valid claim under section 2 of the policy for fourteen weeks business interruption/loss of rent costs as set out in section 2.1 of this determination. Is the insurer liable for consequential loss? No. The panel is not satisfied the complainant established the agent fees and re-marketing fee are a claimable loss. The insurer is not liable for these fees. Why is the outcome fair? The outcome is fair as the panel is satisfied that a reasonable period to assess and then repair the premises would be fourteen weeks. While there were delays in the assessment these can be attributed to both parties and it would not be fair to require the insurer to compensate the complainant for these delays 1.3 Determination This determination is partially in favour of the complainant. The insurer is liable to meet the complainants claim under section 2 of the policy. Within twenty-one days of the complainant’s acceptance of this determination, the insurer is to pay the complainant compensation for fourteen weeks business interruption/loss of rent. Determination | Case number: 847790 Page 2 of 5 2 Reasons for determination 2.1 Is the insurer liable for business interruption? Yes. The panel is satisfied the complainant has a valid claim under section 2 of the policy for business interruption/loss of rent costs for the fourteen-week repair period. Policy covers consequential loss if material damage accepted The complainant holds an industrial special risks policy. Section 1 of the policy covers Material Loss or Damage to the insured premises, subject to policy terms, conditions and exclusions. If the insurer accepts liability for material damage to the insured property under section 1, section 2 of the policy may be triggered. Section 2 of the policy covers Consequential Loss: In the event of any building or any other property or any part thereof used by the Insured at the Premises for the purpose of the Business being physically lost, destroyed or damaged during the period of insurance by any cause or event not hereinafter excluded (loss, destruction or damage so caused being hereinafter termed “Damage”) and the Business carried on by the Insured being in consequence thereof interrupted or interfered with, the Insurer(s) will, subject to the provisions of this Policy including the limitation on the Insurer(s) liability, pay to the Insured the amount of loss resulting from such interruption or interference in accordance with the applicable Basis of Settlement. This means for Section 2 to apply the complainant must show:  The insurer accepted liability for physical loss or damage to the insured premises under Section 1.  The business carried on by the insured at the premises was interrupted or interfered with because of the damage accepted under Section 1. Delays in assessment of material damage claim under Section 1 of policy The exchanged information shows:  The complainant entered into a lease agreement with PL on 1 April 2020  An application for an internal fit out was approved on 18 May 2020  A notice of breach was sent to PL on 13 July 2020  A final demand for rent was sent 17 August 2020 and the complainant took possession of premises on 26 August 2020.  Notice of default sent to PL with notice to make good repairs sent 24 September 2020. Termination notice sent 30 October 2020  The complainant lodged the claim on 3 November 2020.  The insurer commenced its investigations on 16 November 2020.  There were delays in providing the agreed scope of works (SOW) for the approved fit out. The broker notified the insurer on 18 January that there was no agreed SOW  29 April 2020 insurer accepts material damage claim and pays the first instalment of repair costs of $69,905.44 on 15 June 2021.  Complainant notifies insurer of business interruption claim under Section 2 of policy  The complainant commenced repairs on 16 June 2021.  A second cash payment was issued on 30 August 2021 Determination | Case number: 847790 Page 3 of 5  Third and final cash settlement issued 7 September 2021  Construction works took 12 weeks to finalise.  Tenants could not view level 12, take possession and guarantee the property was compliant with the relevant codes until repairs were completed. The panel notes from emails between parties that information was requested by the insurer but provided in a piecemeal manner. The panel is surprised that information such as an approved scope of works or invoices for the make safe work were not readily available to the complainant’s broker. At the same time, the panel is surprised at the insurers continued delay in accepting liability after inspection of the property in February 2020, receipt of the CDC and relevant invoices. Complainant has established claim under section 2 of policy The panel accepts there is valid claim under section 1 of the policy. To establish a claim under section 2 of the policy the complainant must still prove that the business interruption was caused by the material damage. The insurer says it should not be liable for business interruption because the complainant failed to mitigate its loss. It says the complainant could have placed interested tenants in another available floor. It says that because the complainant has not shown there were any interested parties in the floor or any other floor, the claimed loss was the result of market downturn and lack of interest from tenants. The panel accepts the insurer is not liable for business interruption resulting from the vacancy of the building. The panel does not agree that the complainant was required to place interested parties in a different location to reduce the claim. The damage would have made it difficult to lease the premises. It is reasonable to accept the floor could not be fully tenanted until the repairs were completed. The panel accepts the insurer is liable for business interruption / loss of rent under section 2. The panel is satisfied that the building was damaged within the period of insurance and because of the damage the complainant’s business was interrupted or interfered with as the premises could not be tenanted. Insurer entitled to limit claim for loss of rent. The complainant seeks compensation for business interruption for a period of nine and a half months being six and a half months for the delay in assessment of the material damage claim and three months for the repairs. While the panel acknowledges the delays, as indicated earlier in this determination, those delays were contributed to by the complainant’s difficulty in providing the relevant information. The available information confirms the complainant had organised for new tenants to take up a portion of the floor on 1 June 2021 and another tenant on 12 July 2021. The complaint notice lodged with AFCA indicates the floor was fully tenanted by 27 August 2021 despite the repairs still being completed. The evidence shows the repair period was approximately twelve weeks. Although a bit subjective, the panel considers this a fair starting point to assess the quantum of the claim. The panel accepts a reasonable assessment period after obtaining the relevant information would be approximately two weeks. This would bring the total loss of rent payable to approximately fourteen weeks. Determination | Case number: 847790 Page 4 of 5 This would allow for the assessment period to have commenced mid to late February 2020 (after the insurer had the relevant damage reports) and for the repairs to be completed prior new tenants entering the premises in June 2021. The panel considers it fair in the circumstances the insurer pays compensation for loss of rent under section 2 of the policy for a period of fourteen weeks. 2.2 Is the complainant entitled to consequential loss? Insurer not liable for real estate and marketing fees The complainant seeks for the insurer to reimburse it for agent fees for introducing three new tenants to the premises and re-marketing fee of $3,397.90 for listing and advertising the premises for lease. The insurer declined liability for these costs because it says they were not incurred because of the accepted damage, rather consequence of the complainant seeking to find new tenants. The panel agrees with the insurer’s submission that the these are costs the complainant would have incurred regardless of any damage to the propert y and relate solely to property’s vacancy, not the damage. The panel is not satisfied the complainant established these costs fall under section 2 and the insurer is entitled to deny the claim. 2.3 Why is the outcome fair? Outcome is fair The complainant is required it suffered a claimable loss. If the complainant can show the policy respond, the insurer is required to settle the claim within the policy terms and conditions. The outcome is fair as the panel is satisfied that a reasonable period to assess and then repair the premises would be fourteen weeks. There were delays in the assessment of damage, but these can be attributed to both parties and it would not be fair to require the insurer to compensate the complainant for these delays. Determination | Case number: 847790 Page 5 of 5 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. A panel determined this matter Due to the nature of this complaint, we referred it to a panel for determination. The panel includes an ombudsman, a member with significant experience in consumer and small business advocacy and a member with extensive industry experience. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.