Determination 847474

Storm damage to driveway; dispute over whether entire driveway must be replaced and settlement amount

FirmAllianz Australia
Decided2022-08-18
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$5,767
Non-financial loss—
Amount claimed$18,900
SourceAFCA PDF

Summary

The complainant claimed a storm-damaged driveway should be fully replaced at $18,900, while the insurer offered $3,645.84 to repair the damaged section. AFCA found the policy only requires repair of the damaged part and ordered the insurer to pay $5,767.47, including a 10% transfer of risk allowance.

Under the policy's obligation to repair the damaged part to the same condition as when new, replacing the entire driveway would be an upgrade beyond its prior condition, so the builder's repair quote plus a cash settlement risk allowance applies.

Issues

Subjects and remedies

home or building damagenatural disasterpay claim

Related

All Allianz Australia determinations · Find similar determinations

Text of the determination

Determination Case number 847474 Financial firm Allianz Australia Insurance Limited Determination | Case number: 847474 Page 1 of 5 Case number: 847474 16 August 2022 1 Determination overview 1.1 Complaint The complainant holds a home insurance policy with the financial firm (the insurer). He lodged a claim after the end of his driveway was damaged by a storm. Only a small section of the driveway was damaged. However, the insurer’s builder said: ‘ To repair the driveway to a warrantable standard, the entire drive way would need to be replaced. ’ The insurer has offered to settle the claim by paying $3,645.84 for the cost of repairing the damaged part of the driveway. The complainant is not satisfied with this because it will not repair the driveway to a warrantable standard. The complainant says the insurer should pay $18,900 for the cost of replacing the entire driveway. 1.2 Issues and key findings Is the insurer required to replace the entire driveway? No. The policy only requires the insurer to pay the cost of repairing the damaged part of the driveway. If the insurer was required to replace the entire driveway, this would upgrade the driveway to a better condition than it was in before the storm. It would also upgrade the driveway to a better condition than it was in when it was new. The policy does not require this. It would not be fair to require the insurer to pay for this. How should the complaint be settled? The insurer should settle the claim by paying $5,767.47, being the cost of repairs quoted by its builder ($5,243.15), plus a 10% contingency ($524.32) for the transfer of risk that comes with a cash settlement. 1.3 Determination This determination is mostly in favour of the insurer. The insurer must settle the claim by paying $5,767.47, less any applicable excess, less any amounts it has already paid. Determination | Case number: 847474 Page 2 of 5 2 Reasons for determination 2.1 Is the insurer required to replace the entire driveway? Policy covers storm damage to driveways The terms of the policy are set out in the policy schedule and the product disclosure statement. Relevant policy terms are quoted in section 3.2 of this determination The policy covers damage caused by a storm, rainwater, or run- off. The complainant’s policy also includes optional additional cover for ‘accidental damage’. The policy covers buildings and contents. The policy’s definition of ‘buildings’ includes ‘p aved paths and driveways ’. End of driveway eroded by storm On or about 23 October 2021, the complainant said his driveway was damaged by a storm. On 27 October 2021, he lodged a claim with the insurer. The insurer appointed a builder (AB), who inspected the driveway on 9 November 2021. AB said the driveway showed ‘signs of cracking and deterioration’, and had no spoon drains or culverts to prevent water from washing it away. However, AB said the driveway was ‘in average condition’, and ‘still serving its purpose’. AB said most of the driveway was ‘re - sealed’ or ‘over laid’. However, a small section at the end of the driveway connected to the road was not overlaid, ‘ leaving it more susceptible to wash out and breaking down ’. This end of the driveway was eroded by the storm. The insurer accepted that the eroded end of the driveway had been damaged by a storm, and this damage was covered under the policy. Insurer did not agree to replace entire driveway AB provided a quote to repair the damaged part of the driveway (31m 2 ) for $5,243.15. However, AB said: ‘ To repair the driveway to a warrantable standard, the entire drive way would need to be replaced. ’ The complainant obtained a quote dated 21 November 2021 from a builder (BTC) to replace the entire driveway (220m 2 ) for $16,500. The complainant obtained a quote dated 28 February 2022 from a different builder (HHB) to replace the entire driveway for $18,900. The insurer says the policy covers storm damage to the driveway. However, it says the policy only covers the repair of the damaged section of the driveway, not the replacement of the entire driveway. Replacing entire driveway would constitute upgrade The policy says t he insurer will pay: ‘ the reasonable cost of repairing or rebuilding the damaged part of your buildings to the same condition as when it was new ’. The complainant says repairing the driveway to the same condition as when it was new means repairing it to a warrantable standard. However, I am not satisfied the driveway was built to a warrantable standard. Determination | Case number: 847474 Page 3 of 5 The driveway was built with overlay over most of its length, but with overlay missing from the end. This left the end susceptible to washing out as it did during the storm. Building a driveway to a warrantable standard would mean building a driveway that is stable along its entire length, and does not have any sections that are prone to washing out during storms. This would mean building the driveway to a better condition than it was in when it was new. In these circumstances, it would not be fair or consistent with the policy terms to require the insurer to pay the cost of replacing the entire driveway. The insurer should settle the claim by paying the cost of repairing or rebuilding the damaged part of the driveway. 2.2 How should the complaint be settled? Best estimate of cost of repairs is $5,243.15 AB provided a quote to repair the damaged part of the driveway for $5,243.15. The insurer obtained a quote from a different builder (RC) to repair the damaged part of the driveway for $3,645.84. However, RC did not inspect the driveway, so their estimate is not as reliable as AB’s. AB’s quote is the best available estimate of the cost of repairing the damaged part of the driveway. Insurer must pay allowance for transfer of risk When an insurer settles a claim by repairing damage, it guarantees the quality of the repairs. If the repairs are unsuccessful, or cause additional damage, the insurer is responsible for the cost of rectification. When the insurer settles a claim by paying the cost of repairs, it transfers this risk to the customer. Furthermore, the customer may find it more difficult and expensive to arrange repairs, because they do not have the insurer’s indus try knowledge and bargaining power. AFCA considers that if an insurer cash settles a claim, it should consider paying an allowance for the transfer of risk. Generally, AFCA considers that a reasonable allowance is likely to be between 5% and 25% of the quoted cost of repairs. The work required to repair the damaged part of the driveway is relatively simple, and unlikely to lead to further damage or other complications. In this case, I consider a reasonable allowance for the transfer of risk to be 10% of the quoted cost of repairs. The insurer must settle the claim by paying the cost of repairs quoted by AB ($5,243.15), plus 10% ($524.32) for the transfer of risk. These amounts total $5,767.47. Determination | Case number: 847474 Page 4 of 5 3 Supporting information 3.1 The AFCA process AFCA’s approach is base d on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. I have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, I have restricted this determination to the issues that are relevant to the outcome. AFCA interprets words in accordance with their ordinary meaning If the meaning of a specific word or phrase is disputed, AFCA will interpret it in accordance with its plain and ordinary meaning. In doing so, AFCA will consider:  how the term is defined in the policy (if the policy provides a definition)  how the term is defined in a dictionary (if the policy does not provide a definition)  how a reasonable person would interpret the term  the context of the term (including the sentence, paragraph, and section of the document it appears in)  the purpose of the policy  whether a proposed interpretation would likely lead to fair and reasonable outcomes. 3.2 Relevant policy terms Product Disclosure Statement Claims (pages 58 – 67) How we settle your claims Buildings claims If we agree to cover your claim for loss of or damage to your buildings, we will pay the reasonable cost of repairing or rebuilding the damaged part of your buildings to the same condition as when it was new. At our discretion (acting reasonably ), we may:  enter int o a contract with a builder to repair or rebuild your home, or  pay you the reasonable cost of repairing or rebuilding your home in cash or cash equivalent. When it is not possible to use original mat erials during the repair or rebuilding process, we will make best efforts to use the nearest available equivalent to the original mat erials. Determination | Case number: 847474 Page 5 of 5 Special items These items have additional settlement conditions:  Dividing fences, gates and free - standing walls: the most we’ll pay is half the cost of repairing or rebuilding, aft er taking into account depreciation, based on its age and condition.  Fixed wall, floor and ceiling coverings: repair or replacement is limited to the room, hall or passage in which the loss or damage actually occurred. When repairing or replacing the fixed wall, floor or ceiling coverings, we will make best efforts to use the nearest available equivalent to the original mat erials or items.  Roof mat erials: repair or replac ement is limited to the physical area where the loss or damage occurred. When repairing or replacing r oof materials, we will make best efforts to use the nearest available equivalent to the original materials.