Partial decline of storm/flood damage claim for rear pool area; further assessment ordered and non-financial loss awarded

FirmQBE
Decided2022-10-10
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$2,000
Amount claimed$15,000
SourceAFCA PDF

Summary

The complainant's storm and flood claim for rear pool area damage was partly declined by the insurer based on an engineer's report attributing damage to long-term deterioration. AFCA ordered an independent re-assessment before a final claim decision and increased non-financial loss compensation to $2,000; reimbursement of around $15,000 in expert fees was refused.

Policy covers storm and flood damage but excludes gradual process, deterioration, settling and defects, so the proximate cause and scope of the pool damage must be established by a further independent expert assessment.

Issues

Subjects and remedies

home or building damagenatural disasterpay non financial lossreassess claim

Related

All QBE determinations · Find similar determinations

Text of the determination

Determination Case number 847020 Financial firm QBE Insurance (Australia) Limited Determination | Case number: 847020 Page 1 of 8 Case number: 847020 30 September 2022 1 Determination overview 1.1 Complaint The complainant holds a building and contents insurance policy with the financial firm (insurer). In March 2021, he lodged a claim for damage at the insured property following a major storm and associated flooding event. Based on its engineer ’s report, the insurer partially declined cover (for damage at the rear of the property, including to the retaining wall). The complainant says the insurer’s engineer’s report was incomplete and inaccurate. The complainant has declined the insurer ’s offer to arrange for another assessment of the cause of the damage by an independent engineer. The complainant wants the insurer to pay for the disputed damage (pool area) and cover fees incurred in obtaining expert reports. He is extremely unhappy about the handling of the claim, and alleges multiple breaches of the relevant industry code of practice by the insurer. 1.2 Issues and key findings Is the insurer required to settle the claim for the disputed damage? In the particular circumstances, a further assessment of the property by a suitably qualified expert(s) is reasonable and appropriate to provide more certainty about the cause and extent of the disputed damage. While there was a severe storm/flooding event, and damage was found, neither the insurer ’s nor the complainant’s submissions or expert evidence is compelling as to the proximate cause or scope of all the issues identified. A final decision as to the extent of the claim-related damage should be deferred until that further assessment and necessary scope of work is concluded. The insurer is also required to pay $2,000 as non-financial loss in recognition of its handling of the claim and the impact of that on the complainant. Why is the outcome fair? The insurer ’s offer to arrange an independent reassessment of the damage and the associated scope of work is fair in the circumstances, as it provides the opportunity for a definitive conclusion as to the proximate cause and extent of the disputed damage. 1.3 Determination This determination is substantially in favour of the insurer. As set out in section 2.1 below, the insurer is required to arrange for a re-assessment of the disputed (pool area) damage and a scope of work for any found to be claim-related and not otherwise excluded. The complainant is to allow access to the property for that work. The insurer must then make a decision on cover for the disputed damage, and settle the claim, as appropriate, based on the evidence arising from the re-assessment report. The insurer is also required to pay the sum of $2,000 non-financial loss compensation. Determination | Case number: 847020 Page 2 of 8 2 Reasons for determination Since the complainant first lodged the complaint the subject of this determination, a new claim has been made to deal separately with the damaged retaining wall. The complaint and this determination now only concern the insurer’s decision to decline the remainder of the disputed damage, and its subsequent offer of a re-assessment and scoping of that damage. Any commentary in this determination about the retaining wall and stairs is only for context and reference purposes in relation to the remaining disputed damage. 2.1 Is insurer required to settle the claim for disputed damage? Complainant’s policy covers specified events, subject to conditions/exclusions The complainant holds a home and contents ‘accidental damage’ insurance policy for his property, which backs onto a river. The complainant’s policy covers specified events (including ‘storm, tempest, rainwater, flood, wind…’). However, cover is subject to exclusions, and the policy also states that some loss or damage is only covered under certain conditions. That includes ‘accidental’ loss or damage from ‘erosion, subsidence, landslide or earth movement’, but only if it is directly as a result of one o f the listed specified events (including ‘storm’) and it occurs no more than 72 hours after the insured event. Any other erosion, subsidence, landslide or earth movement is not covered. The policy specifically excludes cover for any loss or damage resulting from or caused by: inherent defects, structural defects, faulty workmanship, faulty design. However, we will pay for resultant loss or damage that is caused directly by an insured event if you did not know about (or could not reasonably have known about) the defect, faulty design or faulty workmanship at the time of the loss. Under no circumstances will we repair the inherent defect, structural defect, faulty workmanship or faulty design that caused the loss, nor any loss that is caused by the inherent defect, structural defect, faulty workmanship or faulty design that is not caused directly by an insured event. The policy also excludes cover for ‘any gradual process’. There is no dispute a major storm event occurred in NSW in March 2021, following which external damage was discovered at the compla inant’s property (to both the front and rear). The insurer has accepted damage at the front of the property due to the storm event. However, the dispute arose from the insurer declining cover for the rear of the property, which included damage to:  retaining wall and stairs  pool paving  pool plumbing  pool fence. The complainant says the retaining wall suffered movement damage during the March 2021 event, however, it completely collapsed in another event in March 2022. As noted above, he Determination | Case number: 847020 Page 3 of 8 is no longer claiming damage to the retaining wall and stairs under the 2021 claim, the subject of this complaint. Engineer reported the damage had been occurring over a period of many years On 7 May 2021, the insurer’s engineer SE attended the property and reported the following:  insured property has moderate to high reactive soil (clay)  minor settlement of rear pool paving  long term rotting/deterioration to the timber sections of the retaining wall  lack of support to the staircase exposed edge  lack of drainage behind the timber retaining wall. SE obtained two aerial images from Google Street View (before and after the event) and reported the retaining wall showed no obvious signs of distortion. SE reported deterioration of the timber retaining wall was due to inadequate timber treatment to the timber sleeper sections and long-term exposure to the environment that has occurred over a period of years. SE reported the settlement of pool pavers and the rear western concrete slab stairway pathway is consistent with consolidation and long-term loss of the fill material from underneath those structures. Although unable to estimate a percentage contribution from each factor, SE attributed the settlement of the fill material to the following:  poor compaction of the fill material  saturation of the fill material over an extended period of time  runoff overflow from the adjoining areas  lack of drainage to divert surface water away from the pool area. SE concluded the settlement of the pool pavers and the concrete slab stairway pathway was not due to the March 2021 storm event, but had instead been occurring over a period of years. On that basis the insurer declined the pool area component of the claim. The insurer refers to the following policy exclusions:  damage due to inherent defects, structural defects, faulty workmanship, faulty design  any gradual process  wear, tear, rust, corrosion, depreciation or gradual deterioration  settling, shrinkage or expansion in buildings, foundations, walls or pavements  erosion, subsidence, landslide or earth movement occurring more than 72 hours after an insured event. After t he complainant disputed the insurer’s decision , and during the course of this complaint, the insurer offered to arrange for an independent engineer to thoroughly re-assess the damage to determine whether it should be covered. The complainant declined that offer. Complainant says insurer’s expert findings are incorrect and incomplete The complainant says S E’s report is inadequate. He says SE did not undertake any soil testing to confirm the property is founded on clay soil, and that SE has made assumptions in its report rather than providing findings based on its own observations. The complainant points out he notified the insurer its report and its decision were incorrect (at the initial stages of the claim), in order to prompt the insurer to undertake a further assessment. He says his requests were ignored. Determination | Case number: 847020 Page 4 of 8 The complainant and his neighbouring lot owners engaged an engineer (TC) to undertake an assessment. TC confirmed the riverbank property has been founded on sand, which is not subject to any movement. The complainant submits that this finding alone proves SE’s report was based on assumptions and is factually incorrect. I note, however, that TC did state more testing would be needed to confirm the presence or otherwise of clay under the stone (pebble) layer. As well, the complainant has acknowledged that consideration of the paved pool area was not within the direct purview of instructions to that engineer, who only had limited relevant information. The complainant also engaged a builder (BB) to report on the cause of damage. BB reported in the following general terms only, with no detailed explanation:  pavers have been washed away consistent with intense rain  it may be long-term but cannot be assessed due to the absence of pre-event photos  paving ‘by observation’ was constructed as per the building code  cracks to the pool plumbing most likely caused by the pressure of heavy rain  flood undermined the foundation resulting in damage to the retaining wall. The complainant’s view is as follows:  in issuing its decision, the insurer knew that SE ’s report was incomplete and its findings were inaccurate  majority of the reasons outlined by SE attributing the damage to settlement are caused by rainwater runoff  the policy covers subsidence due to soil erosion if it occurs during the first 72 hours of the rainwater event  he believes another assessment would not provide any useful information, because of the time which has elapsed since the insured event  policy exclusions of defect and design would not apply because the complainant was unaware of those issues: the policy covers damage if it is due to an insured event and if a reasonable person is unaware of the defect and design issues  at no point has the insurer acknowledged it erred in its assessment or decision  if the exclusion cannot be applied as the report is inconclusive, then the policy should be allowed to respond in full. Section 54 of Insurance Contracts Act 1984 (Cth) (the Act) does not apply/assist The complainant has also raised section 54 of the Act as a relevant consideration in this complaint. He believes that prevents the insurer from declining the claim. The point of section 54 is to strike a fair balance between the interests of the insurer and insured with respect to a contractual term designed to protect the insurer from an increase in the risk during the period of insurance cover. The section provides that an insurer may not refuse to pay a claim because of some act or omission of the insured that occurred after the contract of insurance was entered into – as long as the insured can show that the act or omission could not reasonably be regarded as being capable of causing or contributing to any part of the loss that gave rise to the claim. It is not clear how the complainant believes this section should apply to the facts in this matter. I am not satisfied it is a relevant consideration, nor that it assists the complainant. Determination | Case number: 847020 Page 5 of 8 Insurer to undertake another assessment While there was damage identified to the pool area after the storm/flooding events (plumbing, paving and fence), there are questions about the age/timing and proximate cause of that damage, and the evidence indicates the likelihood that there were other longer-term factors involved (as seen, for example, in cracking of certain tiles). I do not consider the currently available expert evidence or submissions from either party to be sufficiently compelling or conclusive for a final claim decision to be made about cover for the disputed damage at this stage. I note, for example:  BB’s report lacks detail and justification/explanation for its statements  while TC says the property was founded on sandy soils, it has not undertaken any site-specific testing. Rather, its testing was generic, relating to a group of lot owners  TC does not specifically address or provide a conclusion as to the cause of the disputed damage to the complainant’s own property  even if the complainant’s property was founded on sand, there is not sufficient information to confirm the damage around the pool was ‘ accidental ’ and from the specific storm event, rather than being longer-term  at the same time, SE’s findings appear quite broad and generic , and the insurer has acknowledged the complainant’s concerns about the adequacy of its expert reports. In the particular circumstances, it is fair and reasonable that there be a further assessment by an appropriately qualified expert to establish the proximate cause of the disputed damage and provide a scope of work for repairs for any damage found to be claim-related and not otherwise excluded. Within 14 days of the complainant accepting this determination:  the insurer is required to provide the complainant with the details of two appropriately qualified and experienced independent engineers who have not previously been involved in this claim  within a further 14 days, the complainant is to choose one of the engineers to conduct the re-assessment and advise the insurer of his choice  the insurer is required to promptly engage the chosen engineer and arrange for the necessary assessment, report and scope as soon as possible; immediately provide a copy of the report and scope to the complainant; issue a claims decision within 21 days of receiving the report and then promptly settle the claim to the extent damage (if any) is found to be claim-related. I acknowledge there may be issues impacting timing of the assessment and report (for example, with the chosen engineer’s availability), however the parties are to work together co-operatively to facilitate finalisation of this as soon as reasonably practicable. To be clear, however, if the complainant does not accept this determination and a further assessment is not carried out, then the insurer is not liable for the disputed damage. That is because I am not satisfied the currently available evidence is sufficient to establish it all falls within the scope of cover. Complainant not entitled to reimbursement of professional fees The complainant is also claiming for professional costs incurred (around $15,000) for the assessments/reports he is relying on (from BB and TC, which includes advice from geotechnical adviser JK). Determination | Case number: 847020 Page 6 of 8 I do not consider the insurer should be required to pay for these costs, because the latter reports discuss the riverbank and its stabilisation more generally, rather than the complainant’s property and the claimed damage specifically (and, I understand, were not personally commissioned by the complainant for his sole use) ; and BB’s report does not, in any case, include a detailed explanation of the cause of the damage, or address the possible excluded factors. The complainant’s reports have not assisted in establishing his position nor resolving the claim at this stage. Insurer is required to increase compensation for non-financial loss AFCA will only award compensation for non-financial loss where there has been an unusual amount of:  physical inconvenience  time taken to resolve a situation, or  interference with the complainant’s expectations of enjoyment or peace of mind. When assessing whether to award compensation AFCA expects complainants to:  be moderately robust  bear the normal degree of inconvenience to be reasonably expected when a problem occurs, and  taken reasonable steps to minimise the inconvenience suffered. The complainant has raised several issues regarding the insurer’s handling of the claim and what he says were the insurer’s inadequate responses. He says the insurer’s claims management was sub-standard (including breaching the relevant industry code of practice on multiple occasions, and referring to an incorrect PDS in initial investigations) and also that there were extensive delays in it reaching a claims decision. The question is whether the delays were caused by the insurer’s actions , and the extent to which this (and its overall handling of the matter, including the adequacy of its expert reports) caused the complainant an unusual and significant degree of upset and inconvenience. The claim was lodged in April 2021. It was in February 2022 that the insurer offered a re- assessment of the damage and scope of works, after the expert evidence available up to that point, and the parties’ respective responses, had not produced a conclusive outcome. The lengthy overall delays (as well as other issues with response times and communication from the insurer in the meantime) have caused significant upset and inconvenience to the complainant, as well as creating a loss of confidence. The insurer has offered $1,500 as non-financial loss in recognition of any inconvenience caused to the complainant. It has acknowledged and, it says, addressed the complainant’s concerns about breaches of the industry code of practice. In the circumstances, I consider it appropriate that compensation for non-financial loss be increased to $2,000. 2.2 Why is the outcome fair? The insurer’s offer to arrange for an independent re -assessment of the damage by an appropriately qualified expert is fair in the circumstances, as it will allow the opportunity to more accurately identify the cause, and scope of claim-related repairs (if any). Determination | Case number: 847020 Page 7 of 8 I appreciate this will involve further time and effort by the parties, but it should also provide more certainty and a reasonable and fair conclusion of the claim and complaint. Determination | Case number: 847020 Page 8 of 8 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.