Cash settlement amount for fire-damaged home and non-financial loss for claim handling delays
Text of the determination
Determination
Case number 842774
Financial firm Allianz Australia Insurance Limited
Determination | Case number: 842774 Page 1 of 6
Case number: 842774 6 June 2022
1 Determination overview
1.1 Complaint
The complainants hold a home and contents insurance policy with the financial firm (insurer)
and on 16 January 2021, lodged a claim after their home was damaged in a fire following a
gas bottle explosion.
The insurer accepted the claim and has paid the complainants $459,064.87 plus $2,500 non-
financial loss to cash settle the claim. The complainants disagree with the cash settlement
and seek a settlement of $540,000 being the sum insured plus $5,000 for non-financial loss.
1.2 Issues and key findings
Is the insurer’s offer the settle the claim reasonable?
No. The insurer should increase the settlement to $535,000 to take into account the items
missing from the scope of works (SOW), contingencies and likely professional costs.
Is the complainant entitled to non-financial loss compensation?
Yes. The panel accepts the level of service provided to the complaint under the claim was not
at the level expected from a professional organisation. The panel is s atisfied the insurer’s
apology and a payment of $2,500 in non-financial loss compensation is fair in all the
circumstances.
Why is the outcome fair?
The insurer’s proposed settlement does not adequately account for the SOW or the
contingencies including the rapidly increasing costs of repairs or likely professional costs
including architect and engineering costs.
It is also fair and reasonable that the insurer also pays the complainants $2,500 for non-
financial loss compensation for delays in handling the claim.
1.3 Determination
This determination is significantly in favour the complainant.
The insurer is to increase its cash settlement of the claim to $535,000. As the insurer has
already paid $459,064.87, then within 14 days of the complainant’s acceptance of this
determination, the insurer must pay the complainants the balance of $75,935.13.
Interest is payable pursuant to section 57 of the Insurance Contacts Act 1984 (Cth) on the
$75,935.13 from 2 February 2022 until date of payment of the determination.
As the insurer has paid the complainants $2,500 it has met its liability to pay compensation
for non-financial loss.
Determination | Case number: 842774 Page 2 of 6
2 Reasons for determination
2.1 Is the insurer’s offer the settle the claim reasonable ?
No. The insurer should increase the settlement offer to $535,000 to take into account the
items missing from the scope of works (SOW), contingencies and likely professional costs .
Policy provides an insurer with a discretion whether to cash settle a claim.
The complainants policy is a home and contents policy covering the home for a sum insured
of $535,000 and contents for $105,000. The policy includes additional benefits for temporary
accommodation, removal of debris and rebuilding and professional fees.
There is no dispute the complainants have a valid claim for damage sustained to the home
and contents following a fire on 16 January 2021. The insurer has already paid the
complainant the sum insured for the contents of $105,000 and the maximum allowance for
temporary accommodation being 10% of the sum insured.
The product disclosure statement (PDS) states the insurer can, at its discretion, choose to
repair the building or pay the reasonable cost to repair the property. The insurer had offered
to repair the property or pay a cash settlement to repair the property. The complainants
expressed a preference to be cash settled.
The insurer has now paid of $461,564.87 in settlement of the claim based on a quote from ABS of
$399,186.84 with a 15% uplift to $459,064.87 plus $2,500 in recognition of any stress this
matter has caused.
Although the complainants rejected the offer the insurer paid the settlement of $461,564.87 to
the complainants on 1 February 2022. The complainants initially sought $558,400 to settle the
claim. They have since indicated they would accept the sum insured of $535,00 plus $5,000
for the inconvenience to finalise the claim.
Dispute as to scope of works
The panel acknowledges the insures initial offer to complete the repairs. We note that offer
was made when the insurer considered only the façade of the house was heritage listed.
The insurer obtained a scope of works (SOW) from an engineer SWP dated 11 February
2021. The complainants raised concern with the insurers loss adjuster CC that the SOW did
not include various items. It is unclear which of those items the insurer now agrees should be
included in the SOW.
The insurer obtained quotes from ABS and SGB. According to CC these quotes were based
on the SOW from SWP additional items raised by the complainants. It is unclear just what
additional items were included in the quotes.
The quote from ABS simply states it is based on the SOW. It is not itemised but notably
excludes any allowance for replacing the dining room ceiling, restoration works, testing for
environmental hazards or any unforeseen damage. It also fails to account for the professional
costs of $15,000 as contained in SWP’s scope of works.
The insurer provided a separate quote from SGB for $410,018.40. This quote is said to be
based on the SOW plus review of the additional items claimed by the complainants. Again,
this quote is not itemised, but it does acknowledge possible variations.
Determination | Case number: 842774 Page 3 of 6
Dispute as to items included in quotes
The insurers claim notes suggest that the insurer and CC first became aware the entire home
was heritage listed on 23 July 2021. This is after the quotes obtained from ABS and SGB.
Development authority had to be obtained from the local council covering internal and
external repairs. This not only resulted in delays in commencing the repairs, but no doubt
caused frustration to both the insurer and complainants. It was following these additional
delays that the complainants sought to cash settle the claim.
The complainants say the following items have not been included in the quote from ABS:
replacing the dining room ceiling plasterboard;
reproduction and replacement of existing decorative ceiling and cornice to match existing
in living room and hallway (SOW contains a specific statement around the difficulty of
restoring these);
rendering/skim coating the hallway, which will be required if cornice is removed;
ceiling joist rectifications to dining room, living room and hallway (required if removing
ceiling);
new floorboards, given age of current floorboards (discussed at length in paragraph 1.8.5)
sanding and polishing floorboards in Bedroom 2 to match the remaining floors;
new skirting to Bedroom 1 and hallway (due to new flooring);
kitchen roof framework (the Architectural Drawings “Reinstatement of Fire Damaged
Dwelling” reference upgrading to Australian Standards. This will be a requirement
considering the high probability that the joists have been affected by the fire);
reframing kitchen, laundry and WC walls – there is no reference to this in the documents,
but given that the state of these walls cannot be properly assessed due to lining
covering, it is highly likely they will be damaged and warped from fire and water damage
and need to be reframed and sarked before re-lining;
new insulation to the external perimeter of the kitchen, laundry and WC (required in
accordance with the National Construction Code (NCC);
replacement of picture rails (required if removing render and replastering)
new electrical wiring throughout, which is highly likely in the case of a fire and
strip screed from kitchen, laundry and WC and supply new (kitchen screed is missing
from the SOW and ABS Quotation but is obviously required).
The complainants provided an itemised quote from TSG for $534,845.85 dated 26 August
2021. The quote includes an allowance for replacing/repairing damaged turf in the backyard
of the property. The complainant says this was included for two reasons:
new footings are required to be excavated; and
the property has rear-lane access. As most of the damage is to the rear of the property,
the backyard will be the main thoroughfare for any builders/workers/deliveries.
The quote also includes a $10,000 allowance for supply of kitchen appliances. The panel
accepts these items are considered contents and should not be included in the quote. The
panel also notes that as part of the building cost validation report provided by CC it
acknowledges TSG was not given the opportunity to correct the scope of works.
Cash settlement to be sufficient to place complainants in pre-loss position
The panel accepts that where a claim is to be cash settled the settlement must be fair,
reasonable and sufficient to place the complainants in the position that existed prior to the
loss.
The insurer in offering to cash settle the claim based on ABS quote says that ABS have
confirmed to CC they can complete the repairs for the quoted amount. The panel notes the
Determination | Case number: 842774 Page 4 of 6
building validation report from CC for cash settlement purposes suggests that most of the
additional items identified by the complainants can be included in the scope provided by ABS
with a variation of $5,000 -$10,000.
Although ABS might say it would honour the quote, the panel does not consider the quote
sufficient to allow the complainant to complete the necessary repairs. As indicated earlier the
quote from ABS was obtained in March 2021. Since then there has been a well documented
significant increase in building costs associated with supply of building materials and labour
issues due to various factors including Covid -19.
A cash settlement requires the complainants to engage their own contractors/
architects/engineers to complete repairs. They lose the lifetime guarantee on the repairs. A
cash settlement should also consider contingencies such as unforeseen damage not included
in the ABS quote and price rises as referred to above.
In the panels view a fair cash settlement is reached by starting with the ABS quote of
$399,186.84, allowing $15,000 for permits, levies and professional services (as per SOW)
and $20,000 for the additional SOW items identified by the complainants ($434,186.44). It is
fair to the allow 25% for contingencies given the impact on building supplies and labour due
to covid, the heritage DA requirements and transfer of risk. This brings you to a settlement
figure of $542,000.
Insurer to cash settle for sum insured.
The sum insured for the home is $535,000. Given the above, the panel is satisfied it is fair
that the insurer cash settle the claim for the sum insured.
The insurer has already paid the complainants $459,064.87 plus $2,500 for non-financial
loss. This was paid by the insurer on 2 February 2022.
It is fair in the circumstances that the insurer pays the complainants the balance of
$75,935.13 plus interest pursuant to section 57 of the Act on the balance of the cash
settlement from 2 February 2022 to date of payment of the claim.
2.2 Is the insurer required to pay non-financial compensation?
AFCA can award compensation for non-financial loss.
AFCA can award up to $5,400 for non-financial loss compensation, if the insurer caused the
complainant to suffer an unusual degree or extent of inconvenience, delay or interference.
AFCA takes a conservative approach when considering any award of compensation.
The complainants have expressed dissatisfaction for the way the insurer has handled the
claims. The complainant says:
the insurer has not adequately addressed the issues raised and has been dismissive in its
responses; and
the insurer has unreasonably delayed the claim.
Insurer’s offer of non -financial loss compensation is reasonable
The insurer accepts that the service was below standard. The insurer offered to pay the
complainants $2,500 in non-financial loss compensation given the level of service provided
and associated delays experienced.
Determination | Case number: 842774 Page 5 of 6
The panel acknowledges that the complainant’s concerns and dissatisfaction with the fact
they had to chase up and dispute several decisions made by the insurer since the claim was
lodged in January 2021. The insurer does not dispute this.
The panel accepts t he insurer’s poor management of the claim would have caused the
complainants an unusual degree of inconvenience, stress, anxiety and interference with their
expectation of enjoyment or peace of mind. While many of the issues have been out of the
insurers control, the poor claims handling has led to finalisation of the claim being
unreasonably delayed. The panel consider the insurer’s offer of $ 2,500 is fair and reasonable
in the circumstances.
As this has been paid to the complainants the insurer has no further liability.
2.3 Why is the outcome fair?
This outcome is fair because both parties have had the opportunity to provide information to
support their position. Accordingly, all the available material has been considered and the
outcome is in line with AFCA’s approach to these types of matters and what is fair under the
circumstances to both parties.
Based on the available information, it is fair the claim be settled for the sum insured plus the
allowance for non-financial loss compensation for delays in handling the claim.
Determination | Case number: 842774 Page 6 of 6
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel
includes an ombudsman, a member with significant experience in consumer and small
business advocacy and a member with extensive experience in general insurance
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.