Home / IAG / Determination 841028

Determination 841028

Water ingress claim settlement dispute and mould remediation

FirmIAG
Decided2022-12-12
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$1,500
Amount claimed$57,588
SourceAFCA PDF

Summary

The complainant claimed water damage and mould under a home building policy; the insurer initially declined, then accepted the claim and disputed the settlement method and amount. AFCA ordered the insurer to cash settle based on the higher of two quotes plus 15%, reimburse $550 for the scope of works, and pay $1,500 non-financial loss.

The insurer must settle the building damage claim based on the CB scope of works, with the settlement costed through its own actionable quotes, given its poor claim management and the delay caused.

Issues

Subjects and remedies

elderly or capacityhealth or medicalhome or building damagepay claimpay compensationpay non financial lossreassess claim

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination Case number 841028 Financial firm Insurance Manufacturers of Australia Pty Ltd Determination | Case number: 841028 Page 1 of 6 Case number: 841028 9 December 2022 1 Determination overview 1.1 Complaint The complainant holds a home building insurance policy (policy) with the financial firm (insurer). On 2 March 2021, a claim was lodged for water ingress damage to the insured building due to a leak in the hot water system located on the roof. The insurer initially declined the claim. However, after the complaint was brought to AFCA, the insurer reversed its decision and accepted the claim on 4 February 2022. The complainant disputes insurer’s proposed settlement and is seeking a cash settlement for the co st of repairs in line with a quote from consultants ‘CB’ dated 28 November 2022, in the amount $57,587.50. 1.2 Issues and key findings Is the insurer’s required to increase its level of indemnity under the claim? Yes. The insurer is to increase its settlement offer in line with the scope of works (SOW) prepared by CB. However, it is fair that the insurer be allowed to cost these works through an actionable quotes from its preferred consultants, as set out in section 2.1 of this determination. Is the complainant entitled to non-financial loss compensation? Yes. The insurer is to pay the complainant $1,500 in non-financial loss in line with the AFCA Rules, given the complainant’s poor experience over the life of the claim and the stress this caused. Why is the outcome fair? The outcome is fair because the SOW sourced by the complainant best reflects the damage to the insured building. However, it is fair in all the circumstances that the insurer be allowed to assess its liability under the claim based on what it would cost the insurer to complete the repairs. Finally, given the complainant’s poor experience, it is fair that the insurer be required to pay compensation. 1.3 Determination This determination is significantly in favour of the complainant. The insurer is to obtain two actionable quotes for repairs based on the scope of works prepared by CB. The insurer is to cash settle the complainant based on the higher of these two quotes. The settlement is to be increased by a further 15% to allow for contingencies and the transfer of risk to the complainant in having to arrange the repairs. The insurer is to pay the complainant $1,500 in non-financial loss (NFL) compensation in line with the AFCA Rules. The insurer is to also reimburse the complainant $550 towards the cost incurred in sourcing the scope of works and quote from consultants CB. Determination | Case number: 841028 Page 2 of 6 2 Reasons for determination The available information shows that at the time this complaint was brought to AFCA, the insurer was maintaining its decision to decline the complainant’s claim. However, the insurer has since reversed this decision and the claim has been accepted under the policy. The remaining issues in dispute relate to how the claim is to be settled by the insurer and whether it is fair that the insurer pay the complainant non-financial loss compensation. Given the above, consideration under this determination has been limited to the remaining issues in dispute between the parties. 2.1 Is the insurer to increase its indemnity under the claim? Yes. The insurer is to increase its settlement offer in line with the scope of works prepared by CB. The complainant bears the onus to establish a prima facie claim The policy covers the insured property against loss or damage caused by one or more of the listed insured events, including ‘ Water and oil leaks ’. Cover under these benefits is subject to the conditions, limitations and exclusions specified in the product disclosure statement (PDS). It is established law that the complainant has the onus to establish, on the balance of probabilities (that is, more likely than not) that the loss falls within the terms of the policy. Only if a prima facie claim is shown to exist, will the onus shift to the insurer to show, on balance, it is entitled to decline the claim in line with the policy provisions. No dispute the complainant has established a prima facie claim The complainant lodged a claim for water damage to the insured building on 2 March 2021. The insurer arranged for consultants ‘J’ to assess the cause and extent of the damage. J confirmed the presence of water damage and provided a SOW and quote for repairs in the amount of $4,381.22, dated 16 March 2021. The insurer accepted and offered to settle the claim in line with J’s quote. The complainant disputed the scope of J’s assessment and said it did not include all the resultant damage from the event. The insurer subsequently declined the claim saying the damage was not consistent with a single event and referred to a previous claim under the policy, which the complainant did not accept. On 4 February 2022, after the matter had been referred to AFCA, the insurer reversed its decision and accepted a valid claim did exist for water damage. From this point onwards, the parties have been unable to come to an agreement on the method of repairs as well as on a settlement amount for the damage under the claim. Insurer’s management of the claim has complicated the settlement process I have considered all the information from the parties and the history or the claim, I note the following:  After lodgement of the claim on 2 March 2021, the insurer appointed J to assess the cause and extent of the damage claimed  Having received J’s report dated 16 March 2021, the insurer informed the complainant the claim had been accepted and offered a cash settlement in the amount of $3,881.22 (applying the $500 excess) on 22 March 2021 Determination | Case number: 841028 Page 3 of 6  The complainant declined the offer on the basis J ’s SOW did not include all the resultant water damage . The insurer proceeded to appoint consultants ‘R’ to inspect the insured property and provide a quote for mould remediation  R provided its report and quote for mould remediation in the amount of $10,257.32. The complainant requested information from the insurer as to extent of repairs and time it would take to complete the repairs by J and R, which the insurer was unable to confirm  The insurer told the complainant to obtain his own quote, which he arranged through consultants ‘M’, in the amount of $29,818.80 including mould remediation works  On or about 18 August 2021, the insurer sent a decline letter to the complainant advising the damage was not due to a single insured event and because of a failure to complete repairs under a previous claim which was cash settled in 2019  The complainant disputed the insurer’s decision and says it never provided him with an explanation as to why M’s SOW and quote were not acceptable. The complainant registered a complaint with AFCA on 3 November 2021  The insurer has then appointed consultants ‘C’ on or about 23 November 2021 with instructions to assess the damage and provide a SOW and quote, this is despite it maintaining it decision to decline the claim  The complainant refused C access questioning the basis for this given the insurer was maintaining the decision to decline the claim. On 4 February 2022, insurer reversed its decision and confirmed a valid (prima facie) claim under the policy  The complainant agreed to C having access and requested C to attend as soon as possible to provide a quote. However, the insurer refused on the basis that the mould remediation works must first be completed before C could attend  The complainant requested that all the works, mould remediation and building repairs, be completed as one event, given the complainant’s age and impact on his health. The insurer maintained its position and in August 2022 offered to cash settle the complainant for the mould remediation works based on M’s quote  Subsequently, with the assistance of AFCA, the parties agreed for the complainant to obtain a SOW and quote for the works (mould remediation and building repairs) for the insurer’s consideration. The complainant obtained a quote from CB in the amount of $57,587.75 dated 28 November 2022 at a cost of $550.00  The insurer has refused to accept the quote saying it is excessive and reverted to its position that the mould remediation works must be completed first, before it will arrange a builder to attend to determine the repair SOW. Given the information above, I am of the view the insurer’s management of the claim and several instances of shifting positions has significantly contributed to the difficulty in bringing this claim to conclusion. The shi fting in positions relates to the insurer’s acceptance, then decline and subsequent acceptance of the claim. Also, it’s changing position on the method of settlement has confused the process and resulted in a lack of trust between the parties. This is because the insurer first sought to cash settle the claim for an amount that did not include all resultant damage. It then told the complainant to obtain his own quote which was dismissed without reasonable explanation. The insurer then took the position that mould remediation works must first be completed before the building repairs could be assessed. However, the available information shows the insurer had previously appointed C to provide a SOW and quote regardless of mould remediation works having been completed or not. Later, the insurer again said it was prepared to consider a quote from the complainant for the building repairs but then refused to accept the quote and again returned to the position that the building repairs cannot be scoped until mould remediation works are completed. Determination | Case number: 841028 Page 4 of 6 I acknowledge it is not the insurer alone that has contributed to the delays and complexity in bring this claim to conclusion. I accept the complainant has also shown a lack of flexibility and strongly maintained the position that all the works (mould remediation and building repairs) need to be cash settled at the same time. Further, that he did not allow C access to the insured building. However, I also accept the loss in trust in the insurer’s process and the fact C was appointed at a time the claim was declined can reasonably be accepted to be contributing factors for the complainant’s actions. Insurer is to increase the level of indemnity offered under the claim I am satisfied the insured building was water damaged and that this has then led to the noted mould infestation. I am also satisfied it is reasonable to accept the extent of damage and associated cost of repairs will have increased due to the delay in bring the claim to conclusion. I acknowledge the insurer’s position that it would have been better for the mould remediation works to have been completed first, before arranging the SOW for building repairs. However, I am satisfied it was nevertheless possible to arrange a reasonably detailed assessment to determine the extent of damage and associated repairs. I accept the complainant’s position that the insurer was provided with reasonable time and opportunity to complete such assessment. Further, that the insurer, despite being requested for information/clarity, has failed to provide any persuasive information as to why it refused the SOW put forward by M and subsequently CB ’s SOW . The available information shows, given the time lapsed and the insurer’s rigid expectations during the quoting process, M has lost interest in the job, which required the complainant to source a new quote from CB. I note CB’s proposed SOW allows for more works than those put forward by M. However, I am satisfied the extent of damage will have continued to worsen as well as the impact and spreading of mould over the 16 months that past between the dates the two quotes were prepared. I note the insurer also acknowledges that it was possible there could be more damage given M’s SOW was based on a non-invasive assessment. The insurer says that post mould remediation, it was possible that further damage becomes apparent. I accept CB’s quote appear s excessive in terms of the cost of the repairs. I am of the opinion, it is fair that the insurer be allowed to assess its liability under the claim based on what it would cost the insurer to complete the repairs. Therefore, I am satisfied it is fair in all the circumstances (and in the interest of bring the matter to conclusion), that the claim be settled in the manner set out below:  the insurer is to settle the complainant for damage to the insured building based on the SOW identified by CB, this being the latest assessment of the damage and based on an invasive assessment of the areas of damage  the insurer, within 14 days of receiving notice of t he complainant’s acceptance of this determination, is to arrange for two of its preferred consultants to provide actionable quotes based on CB’s SOW . In the interest of clarity, this does not mean two additional assessments of the property, rather, that these two consultants provide their costings based on the SOW presented by CB  within 7 days of receiving these quotes, the insurer is to cash settle the complainant based on the higher of the two quotes. The insurer is entitled to reduce this payment by any amount it may have already paid the complainant towards mould remediation and costs relating to the damaged carpet, as the policy only covers the insured building (not contents) Determination | Case number: 841028 Page 5 of 6  the insurer is to increase the final settlement amount by a further 15% to allow for contingencies and the transfer of risk in arranging the repairs to the complainant  the insurer is entitled to apply the $500 policy excess to the claim. 2.2 Is the complainant entitled to NFL compensation? Insurer is to pay the complainant $1,500 in NFL compensation The AFCA Rules (Rule D 3.3) allow for an award of up to $5,400 for non-financial loss compensation, if the insurer caused the complainant to suffer an unusual degree or extent of inconvenience, delay or interference. AFCA takes a conservative approach when considering any award of compensation. In this instance and considering AFCA’s approach to compensation, I accept the insurer’s overall management of the claim has been poor and significantly contributed to the delay in finalising the claim. I accept this will have caused the complainant to experience an unreasonable level of stress, anxiety and physical inconvenience. In saying that, as discussed above, I also accept it is not the conduct of the insurer alone that has contributed to the delays experienced under the claim. I accept the complainant has also acted with a lack of flexibility towards to possible actions that may have assisted in moving the claim forward at times. I don’t feel these can be completed ignored, however, I accept this relates to and arises from the complainant’s loss of trust in the insurer’s management of and poor experience under the claim. Therefore, the for the reasons previously discussed in this determination and in line with the AFCA Rules, the insurer is to pay the complainant $1,500 in NFL compensation within 14 days of receiving notice of the complainant’s acceptance of this determination. 2.3 Why is the outcome fair? The outcome is fair because the SOW sourced by the complainant best reflects the damage to the insured building. However, it is fair in all the circumstances that the insurer be allowed to assess its liability under the claim based on what it would cost the insurer to complete the repairs. Finally, given the complainant’s poor experience, it is fair that the insurer be required to pay compensation. Determination | Case number: 841028 Page 6 of 6 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 AFCA Rules D.3.3 An AFCA Decision Maker may decide that the Financial Firm is to compensate the Complainant for non-financial loss: a) for a complaint relating to an individual’s privacy rights - injury has occurred to the Complainant’s feelings or humiliation has been suffered by the Complainant; or b) for other complaints – an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the Complainant’s expectation of enjoyment or peace of mind has occurred.