Determination 840998
Hailstorm building damage cash settlement offer
Summary
The complainant's home and contents hailstorm claim was settled by cash offer of $137,549.34, later $144,771.74, which he disputed against a builder's quote of $202,242.15. AFCA found the offer unfair, increased the cash settlement to $252,802.68 and ordered $2,500 for non-financial loss.
The cash settlement must reflect the fair and reasonable cost of repairs, including the builder's project management fee, and the insurer's delays and lack of transparency caused inconvenience.
Issues
- Claim amount dispute primary · upheld“The Panel considers the complainant's quote from CS of $202,242.15 most fairly represents the cost of repairs... increased by 25% to $252,802.68.”
- Delay secondary · upheld“It was not until 30 July 2020 that the insurer offered to cash settle the claim... No explanation has been given for this delay.”
- Poor communication secondary · upheld“The insurer refused to show the complainant the full quote until the AFCA case was raised.”
Subjects and remedies
home or building damagenatural disasterpay compensationpay non financial loss
Related
Text of the determination
Determination
Case number 840998
Financial firm The Hollard Insurance Company Pty Ltd
Determination | Case number: 840998 Page 2 of 6
Case number: 840998 23 May 2022
1 Determination overview
1.1 Complaint
The complainant holds a home and contents policy with the financial firm (insurer) and lodged
a claim on 17 November 2019 for damage following a hailstorm.
The insurer accepted liability for the damage and offered to either repair the damage or cash
settle the claim. When the insurer would not provide the complainant with details of the claim
cost the complainant requested a cash settlement to allow him to complete the repairs
himself.
The insurer offered the complainant $137,549.34 to settle the claim. The complainant says
this was not enough to fix the damages and provided a quote for $202,242.15.
The complainant also seeks non-financial loss compensation for the claims experience.
1.2 Issues and key findings
Is the insurer’s cash settlement offer fair in the circumstances?
No. The Panel considers the complainants quote from CS of $202,242.15 most fairly
represents the cost of repairs. The Panel considers the cash settlement should be increased
by 25% ($50,560.53) to $252,802.68 to allow for the increased cost of building and
contingencies considering the quote is dated April 2020.
Is the complainant entitled to compensation for non-financial loss?
Yes. The insurer did not handle the claim in a prompt and fair manner. While not all delays
are due to the insurers conduct the Panel considers it fair the insurer pay compensation of
$2,500 as compensation for non-financial loss.
Why is the outcome fair?
The complainant elected to cash settle the claim. The insurer should have included the
project management fee in the settlement offer having received a quote in November 2019 for
$175,958.38. It’s fair that the insurer compensates the complainant the likely increased cost
of the repairs given the inflationary pressures on the building industry and contingencies.
1.3 Determination
This determination is in favour of the complainant.
Within 14 days of the complainant’s acceptance of this determination the insurer is to pay the
complainant $252,802.68 plus compensation of $2,500 for non-financial loss in settlement of
the claim.
Determination | Case number: 840998 Page 3 of 6
2 Reasons for determination
2.1 Is the insurer’s cash settlement fair ?
No. The Panel considers the complainants quote from CS of $202,242.15 most fairly
represents the cost of repairs. The Panel considers the cash settlement amount should be
increased by 25% ($50,560.53) to $252,802.68 to allow for the increased cost of building and
contingencies considering the quote is dated April 2020.
No dispute as to scope of works
The complainant lodged the claim for damage following a hailstorm on 17 November 2019
with damage to the roof, shed, items in pool area including furniture, drain pipe is cracked and
broken by hail, smashed window, and shade sail. The complainant noted damages to the air
conditioner and the roof with the gutters dented.
An inspection was undertaken at the insured premises on 22 November 2019 by CC the
insurers assessor. CC confirmed the damage was related to the storm and on or about 6
December 2019 provided a detailed scope of works (SOW) and quote for $175,958.38 for the
claim related damage.
On or about 2 January 2020 the complainant asked the insurer for details of a possible cash
settlement. The insurer advised the complainant if he wished to cash settle to obtain a like for
like quote. The complainant was provided the SOW. There is no dispute over the scope of
works to be completed. The insurer refused to show the complainant the full quote until the
AFCA case was raised.
Contents claim settled
During this complaint, the complainant and his partner separated. On 26 October 2021, the
complainant emailed the insurer a copy of court orders which state that the contents
settlement of the claim in the amount of $10,133.33 is to be provided to his ex-partner, a joint
policy holder at the time of the event.
The insurer has confirmed it paid the content claim as per the court orders on 30 November
2021.
The panel acknowledges the orders further outlined that the complainant would retain sole
ownership of the property which is the subject of this dispute regarding building re lated
damages.
Insurers settlement offer inadequate
The complainant obtained a quote from CS of $202,242.15 on 3 April 2020. He was advised
on 24 April 2020 that the quote was being reviewed. It appears from the insurer ’ s claim notes
that CC reviewed the quote on 27 April 2020 and did not consider it fair and reasonable.
No other explanation has been given for CC’s assessment. It was not until 30 July 2020 that
the insurer offered to cash settle the claim for $137,549.34. No explanation has been given
for this delay or exactly how the insurer calculated its offer given the quote from CC was
$175,958.38.
The panel notes the quote from CC included a 19% management fee. It would appear this
was not included in the offer of $137,549.34 to settle the claim.
Determination | Case number: 840998 Page 4 of 6
On 20 December 2021 the complainant provided a quote of $316,421.13 from T2 based on
the agreed SOW. The insurer had CC review this quote. CC considered the quote not fair
and reasonable although it has not provided a breakdown of the quote. On 26 December the
insurer obtained a ‘cash settlement advice’ from CC that did not include the 19% project
management fee. The total was $143,527.74. This appears to be based on the original
assessment some two years earlier on 20 November 2019. This offer was later increased to
$144,771.74.
The insurer has not explained why it excluded the management fee from the latest cash
settlement offer. As indicated it has also refused to show the complainant the full quote until
the AFCA complaint was raised.
Any cash settlement of a claim must be based on the fair and reasonable cost to a
complainant to place them in the position they were in prior to suffering the loss or damage. In
a claim worth well over $100,000 if is fair to expect a builder’s project management fee to be
included in any such cash settlement.
The panel acknowledges the insurer had offered to complete the repairs but that was in early
2020. It was already aware the complaints preference was a cash settlement. It may have
been able to cash settle at that time, if it had have acted fairly by providing the complainant
with full details of the quote from CC and including the management fee.
The panel also notes that additional works outside the quote may be required as there may
be unforeseen damage. It acknowledges any additional works would be subject to quote
variations. No allowance has been made for this in the insurer ’ s offer.
Insurer must increase cash settlement offer.
The panel considers the initial quote from CC of $175,958.38 is a good starting point for
consideration of a cash settlement but is now 2.5 years old. It was only valid for 30 days. The
assessment from CC in December 2021, nearly two years later comes up with a cash
settlement advice for building damage of $143,527.74. The insurer ups this in the notice of
response to $144,771.74. The panel do not accept this as a fair and reasonable assessment
of the cost of repairs in December 2021. The quote seems to be a tabletop review of the
original quote with the management fee removed. This does not seem consistent with current
repair costs.
In the panels view, the complainant’s quotes when considered with the original quote from CC
are a more persuasive guide as to current costs. The quote from CS in April 2020 for
$202,242.15 is consistent with the earlier CC quote and the initial SOW. It is before the
impact of Covid 19 and the subsequent significant increases in building repair costs.
The quote from T2 ($316,421.13) is also consistent with the SOW. The review by CC only
raised concern with the allowance within the carpentry, painting and rendering allowances for
replacement of the external lounge sheeting. It makes not comment on the rest of the quote.
In the panels view to reach a fair and reasonable cash settlement it is fair to start with the
quote from CS of $202,242.15. This quote is approximately two years old. To account for the
impact on building costs due to various factors including Covid-19 and other contingencies it
is fair to allow a 25% increase ($50,560.53) on the sum quoted making a total cash
settlement of $252,802.68
Determination | Case number: 840998 Page 5 of 6
2.2 Is the complainant entitled to compensation for non-
financial loss?
Yes. The insurer contributed to the issues on the complaint and should pay the complainant
$2,500 non-financial loss.
AFCA can award compensation for non-financial loss
Under AFCA rule D3.3 AFCA can award compensation of up to $5,400 for non-financial loss
where a complainant suffers an unusual degree of physical inconvenience or time taken to
resolve a situation.
AFCA takes a conservative approach to the award of compensation and expects a
complainant to be moderately robust in dealing with the usual inconvenience that arises in
any insurance claim.
The complainant has suffered an unusual degree of inconvenience.
The panel acknowledges the insurer offered to complete the repairs and it was the
complainant who insisted on a cash settlement. This however does not explain why the
insurer did not give the complainant the full details of the quote or why it, once aware the
complainant wanted to cash settled made an offer without allowing for the project
management fee.
The insurer has not explained why it took over three months from receiving CC’s assessment
of the complainant’s quote from CS to make the offer to cash settle. Ag ain, the panel
acknowledges the separation and subsequent court proceedings between the complainant
and his partner complicated the issues. This however does not justify the initial delays or lack
of contact with the complainant for long periods of time.
The panel notes the insurer made an ex gratia payment of $1,265 in October 2020 to cover
pool chlorination and waived the building policy excess of $1,000 in July 2020 due to the
claim handling delays. The panel has taken these into account in reaching its decision.
The panel accepts the insurers claims handling has resulted in significant delays in the
resolution of this claim and has caused the complainant a considerable degree of
inconvenience. The panel considers it fair in the circumstance that considering the payments
already made that the insurer pay the complainant a further $2,500 compensation for non-
financial loss.
2.3 Why is the outcome fair?
The complainant had notified the insurer in January 2020 that he wanted to cash settle the
claim. The insurer should have acknowledged this and been more transparent in its dealings
with the complainant. If it had been transparent and fair in including the management fee in
the initial settlement offer having received a quote in November 2019 for $175,958.38 this
dispute may not have occurred.
It’s fair in these circumstances that the insurer compensates the complainant for the fair and
reasonable costs likely to be incurred in completing the claim related damage and pay
compensation for the inconvenience caused.
Determination | Case number: 840998 Page 6 of 6
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel
includes an ombudsman, a member with significant experience in consumer and small
business advocacy and a member with extensive industry experience.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.