Summary

A strata policy beneficiary claimed for ensuite and ceiling water damage. AFCA found the leak resulted from a missing puddle flange, a defect excluded from cover, so the insurer could decline the bathroom repairs but must fund the accepted ceiling resultant damage.

Cover for defective workmanship and defects is excluded under the PDS, and expert evidence showed the missing puddle flange breached AS 3740 at construction, so the bathroom damage was excluded.

Issues

Subjects and remedies

home or building damagemotor vehicle collisionpay claim

Related

All XL Insurance Company Se determinations · Find similar determinations

Text of the determination

Determination Case number 840614 Financial firm XL Insurance Company Se Determination | Case number: 840614 Page 1 of 8 Case number: 840614 22 February 2022 1 Determination overview 1.1 Complaint The complainant is a beneficiary under a residential strata policy held with the financial firm (insurer). He lodged a claim for damage to his ensuite and downstairs ceiling. He says the waterproofing in the ensuite was compromised, resulting in a leak through the floor and into the ceiling. The insurer says the damage is due to a gradual release of water and liquid over time due to:  faulty workmanship  a construction flaw, and  failure to comply with Australian Building Standards with the installation of a puddle flange. The complainant says the property was built in line with the relevant building codes. He also says the leak was not gradual. He wants the insurer to accept the claim. 1.2 Issues and key findings Is the insurer entitled to decline the claim? The insurer is entitled to decline cover for the damage to the bathroom. However, the insurer has accepted resultant damage to the ceiling in line with its assessor‟s quote. It is fair for the insurer to limit its liability to the resultant damage to the ceiling. Why is the outcome fair? The information provided shows, on balance, the damage is due to a defect and/or defective workmanship. As this cause of damage is excluded, it would not be fair to require the insurer to accept cover for the bathroom. It is fair for the insurer to limit its liability for the resultant damage accepted under the claim. 1.3 Determination This determination is in favour of the insurer. Other than the resultant damage to the ceiling, the insurer is not required to accept the claim. Determination | Case number: 840614 Page 2 of 8 2 Reasons for determination 2.1 Is the insurer entitled to decline the claim? The insurer is entitled to decline cover for the damage to the bathroom. However, the insurer has accepted resultant damage to the ceiling in line with its assessor‟s quote. It is fai r for the insurer to limit its liability to the resultant damage to the ceiling. Policy covers accidental loss or damage, subject to exclusions The initial onus is with the complainant to establish the loss is covered by the policy. This is known as a valid (or prima facie ) claim. Once the complainant has established a valid claim, the onus shifts to the insurer to establish, on balance, the application of a policy exclusion or that it is otherwise entitled to decline the claim under the policy. The policy covers accidental loss or damage to the property. The product disclosure statement (PDS) defines loss or damage as: direct physical loss of, destruction of, or damage to property from any sudden and accidental cause not otherwise excluded by this Policy. Relevant sections of the PDS are included in section 3.2 of this determination. Information shows cause of damage was lack of puddle flange to shower The complainant provided a report from his plumber, B, dated 21 September 2021, which states: I performed a pressure test to the shower and found no leaks. I visually inspected the shower base and found the grout, tiles and silicon to be sound. I removed the shower grate and inspected the waste outlet. I found that there wasn‟t a puddle flange installed to connect the pvc pipe shower waste to the flooring. I ran water down the waste and found it to be leaking immediately. It appears that the 50mm pvc wastepipe is simply penetrating the floor and then waterproofed down into it. The movement in the pipe has caused the waterproofing at this point to crack and come away, allowing water through. I believe a property of this age should have had a puddle flange installed originally to satisfy plumbing and waterproofing codes. The insurer appointed an assessor (CC) t o attend the property. CC‟s report dated 8 October 2021 states: The sighted damage to the ground floor ceiling is a result of a missing puddle flange to the upstairs ensuite shower recess. The plumber has confirmed that a puddle flange should have been installed as per building codes at the time of construction. Determination | Case number: 840614 Page 3 of 8 Owners repairs - To replace the puddle flange to the ensuite area, the ensuite area has to be dismantled to ensure adequate waterproofing as per building codes. CC provided a further email, which states: A puddle flange is used during construction to create a waterproof seal around a pipe which passes through concrete. In this case, a puddle flange was not installed so when general movement has occurred the waterproofing has been disturbed, causing cracks, which is allowing the water to leak at this point. If a puddle flange had been installed, this would encase the pipe, and create an extra barrier around the pipe preventing this leak from occurring. Based on the expert reports provided, I am satisfied the cause of damage was a leak from the shower recess due to the lack of a puddle flange. Complainant wants the insurer to accept the damage to his bathroom The complainant says:  B noted the waterproofing was compromised and said new builds have puddle flanges which would have stopped the leak as a backup  the insurer‟s assessor agreed the waterproofing had been compromised and also agreed a puddle flange would have acted as a backup  neither his plumber nor the assessor suggested it was a slow leak, in fact both suggested it was an immediate compromise of the waterproofing and not gradual  he does not consider a puddle flange was required under the building code when the property was built  either way, he should still be covered under the policy because i t was „an immediate issue and not a gradual leak‟  he also says it would be considered a building defect rather than faulty workmanship, which means it should be covered. The complainant also raised concerns with the insurer‟s reliance on the building codes supplied. He says Australian Standard (AS) 3740 part 5.12.2 does not state all wet areas „must‟ have the drainage flange. He says the bathroom was constructed in accordance with this AS and the puddle flange at the time the property was constructed in 2007 was optional. The insurer says the cause of damage is excluded The insurer provided copies of the relevant building codes. This included Australian Standard (AS) 3740 – Waterproofing of wet areas within residential buildings. This came into effect in 200 4, prior to the construction of the complainant‟s property . The AS states: 5.12 MEMBRANE TO DRAINAGE CONNECTION … 5.12.2 Other floors For membrane drainage connections in other floors, any one of the following shall apply: (a) The drainage riser shall be fixed to the floor substrate and the waterproofing membrane terminated a minimum of 20 mm into the riser. Determination | Case number: 840614 Page 4 of 8 (b) A drainage flange shall be installed with the waterproofing membrane terminated at/in the drainage flange to provide a waterproof connection (see Figure 5.10). NOTE: Drainage flanges may be set into the floor or fixed to the top surface of the floor substrate or tile bed. (c) Where a prefabricated shower tray is used, provision shall be made to drain the tile bed and provide a waterproof connection to the drain. The insurer also provided reports from its building consultant (M). Relevant sections are included in section 3.3 of this determination. The insurer says the reports show why the lack of a puddle flange to the floor waste fixture of the bathroom is a failure to comply with the Building Code of Australia 2004 (BCA) and AS 3740 at the time of construction. The insurer says there is nothing to suggest the drain was fixed to the substrate. It says B‟s report states it appears the waste pipe is simply penetrating the floor and that the movement in the pipe has caused the waterproofing to crack and come away. The insurer says the failure to install a puddle flange at the time of the build is the result of faulty workmanship and/or a construction flaw/defect which is specifically excluded from cover under the policy. It says this failure to install a puddle flange directly caused the loss, as had it been installed it would have prevented leakage. The insurer declined the claim to the bathroom. However, it agreed to accept resultant damage to the ceiling. Based on CC‟s report, it stated once the complainant arranged maintenance works to the bathroom, it would authorise reinstatement works as quoted for $1,659.90. Information shows cause of damage is a defect and/or defective workmanship I have considered the complainant‟s submissions. He says photographs show the pipe is clearly fixed to the floor base. He provided his opinion on why he considers the construction of the bathroom complied with relevant building codes when constructed. However, having reviewed all the available information, I am persuaded by M‟s reports. These reports are logical and supported by the available information. The information indicates the shower was not constructed in accordance with the relevant building codes. M refers to B‟s findings that the pipe had moved, which indicates it was not fixed to the subst rate as required. The complainant has not provided any persuasive evidence to challenge these findings. The photograph the complainant provided is not persuasive. I am satisfied the lack of a puddle flange constitutes a defect and/or defective workmanship under the policy. The policy covers damage from any sudden and accidental cause. However, even if I was satisfied the complainant had established a valid claim for accidental damage, the available cover is subject to any applicable exclusions. I am satisfied the cause of damage is excluded in this instance. This means it is fair for the insurer to decline cover for the repairs to the bathroom. The insurer appears to have accepted the resultant damage to the ceiling in line with CC‟s report. I consider this to be fair in the circumstances. I accept the insurer is not liable to Determination | Case number: 840614 Page 5 of 8 conduct repairs to the ceiling until the complainant has undertaken the maintenance works required. Determination | Case number: 840614 Page 6 of 8 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. 3.2 Relevant sections of the PDS: 1) We will not pay for Loss or Damage: … c) caused by moths, termites or other insects, vermin, mice, rats, rust or oxidisation, mildew mould, contamination or pollution, wet or dry rot, corrosion, gradual corrosion or deterioration, change in colour, dampness of atmosphere or other variations in temperature, evaporation, disease, inherent vice or latent defect, loss of weight, change in texture or finish or pecking, biting, chewing or scratching by birds or animals; d) caused by Wear, Tear, fading, concrete or brick cancer, gradual deterioration or developing flaws; … n) due to normal settling, creeping, heaving, seepage, shrinkage, or expansion in Buildings, foundations / footings, walls, bridges, roadways, kerbing, driveways, paths, garden borders and other structural improvements. … 2) We will not pay for: … b) the cost of rectifying faulty or defective materials or faulty or defective workmanship; c) consequential loss, loss of use or Depreciation other than as specifically provided under Extra Benefits, Special Benefits or Optional Covers. Determination | Case number: 840614 Page 7 of 8 3.3 Expert reports Record Key points Financial firm’s expert (M) Report 16 - 12 - 2021 5.6 Since the insured dwelling was constructed in 2007, its construction would have needed to comply wit h the BCA of 2006 which also calls up AS: 3740 as its referencing standard. AS: 3740, section 5.12.2 other floors, section (b) and figure 5.10, shows th e requirements in plac e at the time of and in fact prior to the insured dwelling being constructed, required a drainage flange/puddle flange to be installed. 5.7 The requirements as set out in AS: 3740 of 1994 remains in force today as a requiremen t as pa rt of AS: 3740 of 2010. 5.8 I can confirm that the requirements for a drainage flange or puddle flange to be installed to the insured property was a requirement dating back to 1996 and is still a requirement today. 5.9 As such the lack of a puddle flange to the floor waste fixture of the insured bathroom is a failure to comply with the BCA and AS: 3740 at the time of constructions and therefore is not only a failure to comply but a building defect. Financial firm’s expert (M) Report 12 - 01 - 2022 5.1 The BCA/ NCC - 2006, Part 3.8.1.21, Membrane to drainage connections Part b (i) states the following: “(i) The drainage riser must be fixed to the floor substrat e and the waterproofing membrane terminat ed not less than 20 m m into the riser.” 5.2 The key words in the above statement are “must be fixed to the floor substrat e”. The plumbing report provided by [B] identifies the following issue: “I ran water down the waste and found it to be leaking immediately. It appears that the 50mm PVC waste pipe is simply penetrating the floor and then waterproofed down into it. The movement in the pipe has caused the waterproofing at this point to crack and come away, allowing water through” 5.3 The fact that the pipe has moved indicates that it wasn‟t fixed to the substrate as required for compliance with BCA/NCC, Part 3.8.1.21 (b) (i) … 5.7 The fact that the wat erproofing membrane has failed as a result of movement having caused the membrane to crack is a failure to use a product that c omplies wit h the requirements of AS:3740, B3 Movement and waterproofing B3.1 General. … 5.9 Had a properly installed “drainage flange” or “puddle flange” been installed to comply wit h AS:3740, Section 5. 12.2, Other floors (b) then the drainage riser woul d not have moved causing the membrane to crack. The purpose of a drainage flange is to prevent leakage. … Determination | Case number: 840614 Page 8 of 8 Record Key points 5.15 The fact that water was able to seep into the floor cavity and cause damage to the plasterboard ceiling below is resultant from movement having cracked the membrane. The cracking of the membrane is a failure to install the drainage rise to comply with the additional requirements as set out above with regards the BCA/NCC and AS:3740.