Text of the determination
Determination
Case number 839541
Financial firm Insurance Manufacturers of Australia Pty Ltd
Determination | Case number: 839541 Page 2 of 10
Case number: 839541 27 September 2022
1 Determination overview
1.1 Complaint
The complainant holds a home and contents insurance policy with the financial firm (insurer).
On 30 December 2021, a claim was lodged after a storm flooded the basement. The insurer
accepted the claim; however, a dispute has arisen over the true extent of insured repairs and
what constitutes a fair and reasonable settlement.
The complainant seeks cover for the cost of replacing the basement wall waterproofing and
says it failed because of the insured event. The insurer disagrees, saying either waterproofing
did not exists and/or it was inadequate. The complainant says the insurer’s cash settlement
offer is insufficient and it should base the settlement on his preferred builder’s quotes.
1.2 Issues and key findings
Can the insurer deny cover for the waterproofing costs?
No. The complainant has shown the basement walls were waterproofed and were damaged
by the claim event.
Is the insurer’s settlement offer for the damage not in dispute reasonable?
No. The insurer’s offer to cash settle the complainant in the amount of $27,469.23 plus uplift,
is not fair in the circumstances. The damage accepted under the claim is to be based on a
fresh actionable quote from a suitably qualified consultant, in line with section 2.2 of this
determination. The insurer is to cover the additional damage caused by the insurer’s
consultants and reasonable contents storage costs for the period of repairs.
The insurer is to also pay a further 15% on top of the settlement amount to account for
contingencies and the loss of warranty.
Is the complainant entitled to non-financial loss compensation?
Yes. Given the concerns with the insurer’s overall management of the claim, it is to increase
its offer of compensation from $2,000 to $3,000.
Why is the outcome fair?
The complainant has established a valid claim for the disputed damage as well as it would not
be fair to base settlement for the remaining insured repairs on the insurer’s consultant ‘ U ’ s ’
quote.
The insurer has offered $2,000 in compensation on an ex-gratia basis. I am satisfied it is fair
in all the circumstances to award an additional $1,000 compensation.
1.3 Determination
The determination is substantially in favour of the complainant.
Determination | Case number: 839541 Page 3 of 10
Within 14 days of the complainant’s acceptance of this determination, the insurer is;
to pay the complainant $49,566.00 plus an additional 15% uplift ($7,434) for the works
relating to the repairs to the basement walls waterproofing
to settle the complainant for the cost to replace the damaged carpet
to continue to cover the complainant’s storage costs up to a period of eight weeks from the
date of final settlement being paid to the complainant
pay the complainant $3,000 in non-financial loss compensation.
Within 21 days of the complainant accepting this determination, the insurer is to:
obtain a new actionable quote for repairs from a suitably qualified consultant in line with
section 2.2 of this determination plus a 15% uplift for contingencies and loss of warranty.
Determination | Case number: 839541 Page 4 of 10
2 Reasons for determination
2.1 Can the insurer deny cover for the waterproofing repairs?
No. The insurer has not established an entitlement to decline cover for the damaged
waterproofing and is to cover the cost to repair this damage.
The insurer must cover the cost of restoring the failed waterproofing
Based upon the report (dated 10 February 2022) from engineer (H), the insurer has sought to
decline cover for any costs relating to waterproofing the basement walls. H’s opinion is that
the waterproofing either did not exist and/or was inadequate and failed before the claim event
occurred.
The complainant has provided a report from waterproofing consultants ‘MB’ dated 26 May
2021. MB attributes the waterproofing failure to the claim event, saying it was unable to cope
with the excess water/hydrostatic pressure.
In February 2022, the insurer engaged ano ther expert ‘E’ to review MB’s report. ‘E’ says:
there was a negative waterproofing system in place
it agrees with MB that the waterproofing failed because it was unable to cope with the
excess water/hydrostatic pressure
the replacement of the failed waterproofing should be included in the rectification works
as recommended by the ins urer’s other expert H , it does not recommend a negative
waterproofing system, and says a different type of waterproofing system should be
installed.
Having considered the various consultants ’ reports and photographs, I find the information
from MB and E more compelling. I am satisfied the complainant has established:
waterproofing to the basement walls did exist; and
this waterproofing was damaged because of the claim event.
Accordingly, there exists a valid claim for this damage under the policy. The onus rests with
the insurer to show, on balance, it is entitled to decline cover for this damage.
The insurer has not provided any persuasive or supported explanation to justify its decision to
decline cover for the damage.
The complainant has provided a quote for repairs relating to the damaged waterproofing from
consultants ‘SL’ in the amount of $49,566.00 (Quote 1). The insurer has not provided a quote
of its own or any information to show this quote from SL is excessive or inadequate in the
circumstances.
Accordingly, I determine the insurer, in addition to the damage already accepted under the
claim, is to cash settle the complainant for the damage to the waterproofing based on SL’s
quote. The insurer is to pay a 15% uplift on this settlement for the waterproofing to account
for contingencies and loss of warranty.
2.2 Is the insurer’s claim settlement offer fair ?
The insurer has offered to cash settle the complainant for repairs it has accepted under the
claim. This offer is based on a scope of works and quote provided by U, which the insurer
Determination | Case number: 839541 Page 5 of 10
says is in the amount of $27,469.23. The insurer has offered to increase this amount by a
further 20%.
The complainant remains dissatisfied with the insurer’s offer and U’ s scope of works. The
complainant wants the insurer to settle the claim based on the scope of works and a quote
provided by SL, in the amount of $52,184.00 (Quote 2).
Where the insurer cash settles a claim, the policy terms require the cash settlement to be
based on the reasonable cost to repair or rebuild the damage. I am not satisfied U ’s scope of
works/costings fairly reflect the reasonable cost of insured repairs.
I nsurer’s assessment of U’s scope of works and quote is incorrect
I am not satisfied the insurer has properly assessed the claim or the documentation provided
by U. On my review, I not U’s quote for the cost of repairs sits at $20,784.71 and not
$27,469.23 as claimed by the insurer. The $27,469.23 in U’s documents relates to a negative
variation (Variation 5) applied to the original quote and subsequent four variations.
It would seem the insurer’s internal dispute resolution and claims area have missed this , as
did the assessor. This suggests the quote has not been adequately reviewed by the insurer
and its representatives. This is further supported by the fact, the insurer has missed or
ignored the findings and opinion of its appointed consultant E regarding the basement wall
waterproofing.
The complainant also raised the following concerns with U ’s scope of works:
U has not quoted to replace the direct stick flooring under the stairs. The complainant
estimates this to cost at least $1,785, which the insurer has not disputed
U has not quoted to remove the existing (damaged) floor waterproofing, which must be
removed to install the replacement floor waterproofing.
Without compelling information to the contrary, I accept it is fair that the insurer be required to
include the cost of these repairs in its final claim settlement. These being $1,785.00 as noted
above and $4,150.00 for the removal of the damaged floor waterproofing in line with the
complainant’s original quote .
In view of the above, and given I am neither satisfied with the accuracy of U ’s scope of works
or the insurer’s assessment of this quote, I do not consider it would be fair in the
circumstances to allow the insurer to settle the claim based on U’s scope of works and quote.
Complainant’s quote from SL is, on balance, excessive
The insurer provided an extract of its assessor’s advice that the complainant’s quote is
excessive when compared to U ’s quote. While this does not provide specifics, it states a
proper cost comparison between the two quotes is not possible without a detailed breakdown
like that provided by U.
I have reviewed the scope of works and quote for repairs accepted under the claim put
forward by SL. I note the scope of works, for the most part, are similar to that put forward by
U. However, SL’s quote is significantly higher ($52,184.00) than U’s and the insurer has
raised the concern that it seems excessive.
Having reviewed the quote, I am persuaded by the insurer’s assessment that SL’s quote
(Quote 2) is likely to be excessive. I am not satisfied it would be fair to require the insurer to
settle the claim on the basis of this quote in the circumstances.
Determination | Case number: 839541 Page 6 of 10
In line with the policy, and accepted industry practices, it is reasonable to permit the insurer to
settle the claim based on what it would cost the insurer to complete the repairs. In saying that,
the settlement must be based on a reasonable and actionable quote from a suitably qualified
consultant.
I determine, within 21 days of the complainant accepting this determination, the insurer is to
arrange for a fresh actionable quote for the repairs in line with this determination. This is to be
based on the scope of works provided by SL in Quote 2 and will form the basis for the
insurer’s cash settlement . The insurer is to also pay a 15% uplift on the new actionable quote
to allow for contingencies and loss of warranty.
I acknowledge the complainant’s view that the uplift should be 25%, however, I am not of the
same opinion and do not agree this would be fair in all the circumstances.
The insurer is to include cover for the carpet and additional damage
The insurer has not disputed the claimed damage to the carpet and the evidence shows it
was likely damaged by the claim event. Accordingly, the insurer must cover the reasonable
cost of restoring this damage, determined on a current quote at market rates.
The complainant has raised concerns regarding further damage caused to the insured
property by the insurer’s appointed consultants. The insurer says the consultants had not
caused any additional damage. I note the additional damage referred to by the complainant
includes damage in the areas of:
front porch tiles
basement entrance/passageway timber flooring.
Having considered the available information, I am satisfied it is more likely than not that this
damage was caused by the insurer’s appointed consultants. For the most part, this will have
occurred during the transport of heavy equipment used in the restoration works and removal
of items from the basement.
I note these items seem to be included in the scope of works and quotes from SL. Therefore,
in line with the above findings, the cost of repairs will form part of the settlement to be made
by the insurer in line with this determination.
Storage costs are covered over reasonable period of repairs
The insurer agreed to cover the cost of storing the complainant’s contents until 1 March 2022.
Given the above findings and considering there is no evidence of fault/delay caused by the
complainant. I t is fair the insurer covers the complainant’s storage costs for a reasonable
period equal to what it will take to complete the repairs accepted under the claim.
In the absence of an estimated time period form the relevant consultants, I determine the
insurer to include within its final cash settlement cover for a further eight weeks (from the date
of settlement) of storage of the contents.
2.3 Is the complainant entitled to compensation?
Under the AFCA rules, we can award up to $5,400 compensation for non-financial loss. We
only award this type of compensation if a complainant suffers an unusual degree of stress,
inconvenience or delay because the insurer made an error/mishandled the claim.
Determination | Case number: 839541 Page 7 of 10
The insurer has offered $2,000 to the complainant to compensate him for his negative claims
experience, on an ex-gratia basis (without admitting liability). The complainant is seeking
$5,000.
I am satisfied the insurer and its agents have mishandled aspects of the claim. For example,
while the complainant submitted his waterproofing expert MB ’s report in around mid-2021, it
appears this was only reviewed/considered by the insurer in February 2022.
The complainant has been inconvenienced over an extended period which includes having to
provide detailed submissions to identify the deficiencies in the insurer’s position. I am
satisfied he has suffered an unusual degree of stress and inconvenience because of the
insurer’s handling of the claim.
In view of the above, I consider the complainant is entitled to an additional $1,000 above the
$2,000 already offered by the insurer as non-financial loss compensation under the claim.
2.4 Why is the outcome fair?
The outcome is fair because the complainant has established a valid claim for the disputed
damage, and the insurer has not otherwise shown why it is entitled to deny cover on the
balance of probabilities.
Given the insurer is required to cover the reasonable cost of insured repairs, it is fair for it to
settle the complainant based on a competitive quote at market rates, inclusive of a 15% uplift.
It is also fair for the insurer to cover the cost of storing the insured’s basement content s until
insured repairs are complete , and to settle the complainant’s cost to replace the water -
damaged carpet.
Determination | Case number: 839541 Page 8 of 10
3 Supporting information
3.1 The AFCA Process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
3.2 Relevant Report Extracts
Report Extract
MB Ba sement Inspection
Report
26 May 2021
The basement construction consists of a slab on ground
with masonry walls. I believe the walls have received
some form of tanking as the area is generally dry with
the exception of areas at the base of the masonry walls.
No water ingress was observed during my site
inspection and the owner has noted t here have been no
previous issues of water ingress prior t o construction on
the adjac ent property.
A sump pump is installed within the masonry pit. The
sump pump was co nfirmed as functioning. Note that it
Determination | Case number: 839541 Page 9 of 10
appears that because of the stormwater damage at the
rear, that during the event, the water level in this pit
appears to have been at capacity which is generally not
to be expected were the pump able to discharge
accord ingly.
Based upon my site inspection and moisture testing I
believe that the water ingress was as the result of an
event, in this case I believe a storm where a failure the
existing stormwater system has resulted in all key
elements prot ecting the basement from wat er ingress
not being able to function as intended, irres pective of
their working state.
My inspection indicated that the stormwater system
located at the rear of the property has been
compromised during construction and earthworks ….
The basement tanking and drainage system has then
simply been unable to function with the excessive
volume of water which is normally removed through the
pump located within the sump at the front corner of the
property and discharged into the buildings main
stormwat er system.
Simply put the buildings stormwater has been fully
charged and unable to discharge into the main
stormwat er system, as such the added water from the
basement drainage has not been able to be releas ed
causing considerable hy drostatic pressure to occ ur.
This hydrostatic pressure has forced water to migrate
through sections of the floor to wall detail which being
compromised this detail allowing water t o enter at low
level into the bas ement.
It is my opinion that the caus e of the large amount of
water ingress is not due to a negligence of maint enance
to the building but rather as the result of the building
being exposed to an abnormal amount of wat er due to
its stormwat er not being able to discharge into the
council’s main stormwater drainage system lo cated at
the rear of the property.
E Specialist Re sponse
10 February 2022
Our office has reviewed the report by MB
Photos are provided in the report showing a
waterproofing membrane being installed over the
concrete floor and the base brickwork on some walls
and the retaining section of the brickwork on the side
wall, during previous works to the residence. Therefore,
we can now confirm that there was a negative
waterproof system to the basement area prior to the
water ingress occurring and this waterpro ofing system
has failed.
In this instance however, the negative waterproofing
system would be more prone to failure occurring under
the additional stresses from significant hydrostatic
pressure that would have occurred during times of
heavy rain, with the previous stormwater issues.
Therefore, the replacement of the failed negative
Determination | Case number: 839541 Page 10 of 10
waterproofing system can be deemed to be part of the
rectification works and we would allow to replace the
waterproofing as existing only and not a ny additional
upgrading works.