Home / QBE / Determination 837031

Determination 837031

delay in completing repairs under business insurance claim

FirmQBE
Decided2022-07-15
ProductGeneral Insurance · Business / commercial
OutcomeFor the complainant
Amount awarded$5,000
Non-financial loss$2,000
Amount claimed$105,000
SourceAFCA PDF

Summary

A business's excavator damaged in a river incident was repaired over about 10 months after the insurer's repair process. AFCA found the insurer unreasonably delayed repairs and ordered $5,000 damages for delay plus $2,000 non-financial loss.

Where the insurer elected to repair under the policy, it must complete repairs within a reasonable timeframe, and the policy's consequential loss exclusion did not limit damages for the insurer's breach.

Issues

Subjects and remedies

business interruptionmotor vehicle collisionpay compensationpay non financial loss

Related

All QBE determinations · Find similar determinations

Text of the determination

Determination Case number 837031 Financial firm QBE Insurance (Australia) Limited Determination | Case number: 837031 Page 1 of 5 Case number: 837031 27 June 2022 1 Determination overview 1.1 Complaint On 19 May 2021 the complainant company ’s excavator fell into a river and the complainant’s broker lodged a claim for damage under its business insurance cover with the financial firm (insurer). The insurer authorised and completed repairs, but the process occupied about 10 months. The complainant is seeking compensation for delay. The insurer offered compensation for non-financial loss in the amount of $2,000, which the complainant refused. 1.2 Issues and key findings Is the insurer responsible for delay in completing repairs? Yes. The insurer is liable for damages of $5,000 for unreasonable delay Does the policy exclude compensation for delay? No. The policy does not limit damages suffered as a result of breach of the policy by the insurer. Is the insurer required to provide compensation for non-financial loss. Yes. The insurer is to pay $2,000 as non-financial loss for the stress caused. Why is the outcome fair? On the facts of this case, 10 months was an unreasonable period of delay to achieve repairs of the complainant’s excavator which was plainly required for use in the complainant’s business. As a result, it is fair that the insurer pay compensation for the unreasonable delay. 1.3 Determination This determination is in favour of the complainant. Upon acceptance of this determination by the complainant, the insurer is to pay the complainant: (a) $5,000 damages for the delays caused. (b) $2,000 by way of non-financial loss. Determination | Case number: 837031 Page 2 of 5 2 Reasons for determination 2.1 Is the insurer responsible for delay in completing repairs? Yes. The insurer is liable for damages of $5,000 for unreasonable delay. Chronology The complainant says that on or about 19 May 2021 while under operation the excavator fell into a river. Liability was accepted under the terms of the policy and repairs completed. The relevant timeline appears to be as follows: 19.05.21: Incident reported 20.05.21: Excavator collected by insurer’s repairer 01.07.21: Repairer advises complainant it is waiting for insurer authorisation to repair 19.07.21: Assessor authorises repairs 23.07.21: Complainant buys new excavator 03.08.21: Repairer advises parts from Japan could take 4 to 6 weeks 19.08.21: Insurer denies any business loss claim (policy does not cover business interruption) 06.09.21: Excavator returned but complainant says not repaired 20.09.21: Insurer final IDR decision finds no delay by its claims team and assessor 12.10.21: Claim lodged with AFCA 13.10.21: Excavator returned to repairer 08.12.21: Insurer authorises further partial repairs 17.12.21: Insurer agrees to cover hydraulic boom 14.03.22: Repairs complete, excavator to be delivered to complainant Complainant alleges delays caused loss The complainant has stated on its referral to AFCA ” we have had to continue to cover our loan repayments, insurance repayments, the excess for repairs and also had to finance a new machine to continue work and are out of pocket over $105,000.00 in lost work ” . Unfortunately, AFCA has not been provided with any reasoned calculation of the alleged loss of work. The complainant acquired a new excavator in July 2021, but it is not known to what extent this was a planned acquisition in any event. The insurance schedule indicates the complainant owned and insured two other excavators at that time. The schedule indicates the damaged excavator was on finance. It had a sum insured of $70,000. The policy contained reference to optional “downtime cover” but this was not taken out by the complainant. Mechanical breakdowns are a common event. Invariably there will be delays in repairs of larger machines and vehicles. It appears the complainant did not have applicable insurance for this type of loss. Determination | Case number: 837031 Page 3 of 5 Delay from multiple factors When the excavator was first returned to the complainant in September 2021 the complainant advised that pipes had not been replaced and were leaking, painting was incomplete, bridge timber was embedded and there was a fuel leak. The complainant fixed the fuel leak at its own cost. The insurer initially declined to repair some components which showed evidence of prior inadequate repairs. Ultimately the insurer agreed to do the further work required although it did so without admission. The fact that a component has previously been damaged does not mean it is not indemnified, if a new event causes it to fail. The insurer submitted it has complied with the timeframes in the General Insurance Code of Conduct. It has also pointed to the repairer for sending inconsistent messages. It also appears that some of the insurer’s communications to the broker may not have been passed onto the complainant. The insurer has referred to the delays which were caused by the covid epidemic. There are also the inevitable delays when parts are needed from overseas. The complainant has stated on its referral to AFCA ” we have had to continue to cover our loan repayments, insurance repayments, the excess for repairs and also had to finance a new machine to continue work and are out of pocket over $105,000.00 in lost work ” . I am satisfied there has been a lack of proper oversight in the repair process which resulted in particular in the excavator being returned in the absence of proper checking. It is possible that distance may have been a factor in this regard. Delay due to insurer The insurer exercised its option under the policy to repair the excavator. Having so elected the repairs were required to be carried out within a reasonable timeframe. The insurer breached this obligation as a result of which the complainant suffered damage. In my estimate there is a period of about 5 months which should not have occurred if the repairs had been more closely overseen and there had been better communication with the complainant. In the absence of a detailed proof of loss it is impossible to make an accurate assessment. In the circumstances and considering the insured value of the damaged excavator and moderate interest rates I consider an amount of $1,000 a month totalling $5,000 fair and reasonable. 2.2 Does the policy exclude damages for delay? No. The policy does not limit damages suffered as a result of breach of the policy by the insurer. Delays caused by claims handling The insurer submits the policy excludes cover for consequential loss, including loss of use, and loss resulting from delay. Para 5 on page 13 excludes liability for “ any additional costs such as but not limited to car hire costs ”. Determination | Case number: 837031 Page 4 of 5 This exclusion relates to additional costs caused by the insured event, namely the excavator falling into the river. It does not limit any damages suffered by breach of the policy by the insurer. 2.3 Is the insurer required to provide compensation for non- financial loss? Yes. The insurer is to pay $2,000 as non-financial loss for the stress caused. AFCA can award compensation for non-financial loss The insurer has acknowledged that the services it has provided under the claim have not met the complainant’s expectations . As stated above I consider the complainant suffered damages as a result of the extended delay. The complainant appears to be a small company. The main person chasing the insurer was one of the directors. The AFCA complaint refers to the added stress due to the lack of communication. The complainant had to argue with the insurer on more than one occasion to have the excavator repaired. The insurer offered $2,000 in non-financial compensation. Having reviewed all the available information, I consider this amount to be fair in the circumstances. 2.4 Is the outcome fair ? On the facts of this case 10 months was an unreasonable period of delay to achieve repairs of the complainant’s excavator which was plainly required for use in the complainant’s business. As a result it is fair that the insurer pay compensation as set out. Determination | Case number: 837031 Page 5 of 5 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.