Home / Suncorp Group / Determination 836992

Determination 836992

Water damage claim settlement amount and insurer reassessment

FirmSuncorp Group
Decided2022-03-28
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed$271,046
SourceAFCA PDF

Summary

The complainant, a licensed builder, claimed water storm damage of up to $271,045.50 against an insurer offer of about $22,773.74. AFCA ordered the insurer to appoint a new loss manager for a dual assessment and cash settle on an average of the independent quotes plus 15% contingency, and found no mishandling.

The wide gap between unitemised quotes and the insurer's assessment made further independent assessment fair before settlement, and the insurer's conduct was not shown to be mishandled.

Issues

Subjects and remedies

pay compensationreassess claim

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 836992 Financial firm AAI Limited Determination | Case number: 836992 Page 1 of 7 Case number: 836992 24 March 2022 1 Determination overview 1.1 Complaint The complainant holds a Home and Contents policy with the financial firm (insurer) and lodged a claim on 7 September 2021, for water damage to his property following a storm. Following assessment of the property the insurer although finding no storm damage to the roof, accepted liability for the water related damage. The insurer offered to repair the damage once maintenance issues had been resolved but the complainant, a licensed builder, wanted a cash settlement. The insurer offered to cash settle the claim based on a quote obtained from CRA for $22,773.74. The complainant submitted two quotes (Q1) and (Q2) for $156,865 and $271,045 respectively. Due to the difference in quotes obtained, the insurer offered to appoint a new loss manager to complete a dual assessment with an independent builder and second builder. The insurer says the complainant is prejudicing it by not allowing access to the property. The complainant says he has allowed access to the property. He says the process became frustrating, and he decided to obtain a third-party builder ‟ s quote from Q2. 1.2 Issues and key findings Is the insurer entitled to conduct a further assessment? Yes. The panel is satisfied given the variation in the quotes obtained that t he insurer should be granted access to further asses s the property and determine its liability . T he insurer is to undertake repair of any damage caused by any invasive testing required . Has the insurer mishandled the claim? No. The insurer has responded to the claim in a timely manner. It appointed experts to assess the damage promptly and has been fair and reasonable in its attempts to resolve the dispute. Why is the outcome fair? The outcome is fair as the amount sought by the complainant is substantially higher than the damage as assessed by the insurer. It is fair that the insurer be granted access to further assess the damage and its liability before any further settlement is offered. 1.3 Determination This determination is in favour of the insurer. The panel determines that within 21 days of the complainant‟s acceptance of this determination the insurer is to appoint a new loss manager to complete a dual assessment with an independent building consultant and second builder appointed by the insurer. The insurer must cash settle the claim based on an average of the quotes obtained from the dual assessment plus a 15% contingency to cover the transfer of risk. Determination | Case number: 836992 Page 2 of 7 2 Reasons for determination 2.1 Is the insurer entitled to conduct a further assessment? Yes. The panel is satisfied it is fair for a further independent assessment to be conducted given the discrepancy in the both parties quotes. No dispute property suffered water damage There is no dispute the complainant‟s home suffered water damage following a storm on 3 September 2021. The complainant lodged the claim on 7 September 2021 and the insurer appointed CRA to inspect and provide a report. CRA concluded that the box guttering issue was a design flaw as it was too small and not complainant with AS. CRA further commented that he believed that the complainant would have reasonably been aware of maintenance issues as he is a licensed builder. CRA additionally appointed S Plumbing to provide a further report. This report, dated 14/9/2021, found no evidence of storm damage to the roof and considered the damage were because of the internal gutters above the damaged area being under-designed. The insurer accepted the claim for water damage. As it could not warrant the repairs due to maintenance issues and the complainant wanted a cash settlement it offered to cash settle the claim based on a quote for repairs from CRA of $22,773. Quotes from the parties are vastly different The complainant is a licensed builder. He advised the insurer that he wanted a cash settlement. On 8 September due to the urgency of the works required he provided a quote for $88,000. The insurer rejected the quote as it was not itemised The insurer then obtained the quote from CRA on 16 September 2021. The complainant provided a further quote „ Q1 ” on or about 17 September 2021 for $156,865 which included $33,495 for temporary accommodation. The quote is not itemised in any detail. The insurer says the damage claimed is not consistent with damage from a single storm event. The insurer arranged a further assessment from „ S ‟ on 29 September 2021. S reported that there was no visible mould within the affected areas but noted there had been no drying equipment installed for structural drying. S identified damage to the lounge, study and upstairs bedroom and assessed the repair cost at $14,202.39. The complainant provided a further quote from SF (Q2) on 7 October 2021 for $271,045.50. The complainant says the Q2 quote is higher than Q1 because this quote includes a site management fee, a profit margin and trade costs. He says Q1 does not include any profit margins for the trades in his quote. The complainant says he would be using his own project management and builders licence skills to complete all the works. The complainant says the quote from the insurer is insufficient because his home is worth over five million dollars and the amount being offered from the insurer is nowhere near what it would cost him to repair the damage. He would like the home to be repaired to a high standard. Determination | Case number: 836992 Page 3 of 7 Quotations provided do not allow for accurate assessment of the insured damage The panel has considered the information from the parties and notes the following commentary from the insurer from its assessment report, dated 5 October 2021:  the complainant quoted for structural timbers, which would not be required for a single water event  the home was not considered unliveable as the only affected areas were the lounge room and study  the complainant refused to have a restorer attend to review whether there was mould in the home. In both Q1 and Q2 items were listed with “etc” after some of the materials. Although the complainant does not see this as an issue, it does not clarify exactly what is being replaced or repaired. In other words, the quotes are not itemised, and as such not like for like or comparable. The panel is not persuaded that the various quotes provided accurately assess the extent of damage arising from the insured event. The insurer should be allowed to reassess the property On 27 October 2021 the insurer offered to appoint a new major loss assessor to complete a dual assessment with an independent building consultant QT and second builder to assess the damage. The insurer says the complainant has prejudiced its ability to assess the claim by denying proper access to the property in breach of the obligations under the terms of the policy. The insurer engaged S to attend the home to complete restoration works. An email submitted by the insurer, dated 17 September 2021, supports the position the complainant refused to have S attend his home to complete restoration works because he did not agree with the terms and conditions. The complainant denies refusing access to the property and maintains that the insurer had adequate time and access to the property to assess the damage. The complainant says the insurer is delaying the repair process and has made the situation untenable. He provided a chronology to AFCA, detailing his communications and service experience with the insurer. The complainant says S, who the insurer offered to complete the restoration works, refused to sign an indemnity. The panel considers the complainant ‟ s position with respect to this unreasonable as the insurer is clearly liable for any damage caused by any remediation process it authorises. The complainant has not accepted the insurer ‟ s offer to arrange a dual assessment. In the panels view the insurers offer, given the large discrepancy in the quotes submitted by the parties, is fair and reasonable. The panel acknowledges the complainant says his home is not an average home. However, complainant would, as noted by the insurer, stand to otherwise gain a financial advantage if it was prohibited from re-attending the property based on the quotes submitted. It is unfair for the insurer to settle the complainant with either Q1 or Q2, given they lack detail and are not itemised. Determination | Case number: 836992 Page 4 of 7 Insurer to arrange independent assessment The panel considers the offer made by the insurer on 27 October 2021 to arrange an independent assessment to be fair in the circumstances. Accordingly, the panel determines within 21 days of the complainant‟s acceptance of this determination the insurer is to appoint a new loss manager to complete a dual assessment with an independent building consultant and second builder appointed by the insurer. The insurer may then cash settle the claim based on an average of the quotes obtained from the independent building consultant and the second builder plus a 15% contingency for potential variances in materials and to cover the transfer of risk. Temporary accommodation costs to be considered with further assessment The complainant says he has incurred temporary accommodation costs. He says he chose to move out of the home for the safety of his family. The insurer did not approve these costs. It says the reports did not confirm mould in the home, nor was the home unsafe to live in. The panel is not satisfied the insurer should cover temporary accommodation costs at this time. There is insufficient information to confirm why temporary accommodation is required. The assessment by S did not identify any mould issues. The damage assessed identified damage to 2 rooms only. Based on the email exchanges, the complainant was told when the works commence he would have to re-locate. At this stage, it does not appear any works have commenced. In its response, dated 6 January 2022, the insurer says if any additional damage is identified it would review the temporary accommodation again. It is fair in the circumstances that the need for temporary accommodation be assessed as part of the independent assessment. The insurer must then include in any settlement an allowance for the temporary accommodation based on an average of the temporary accommodation estimates provided in the quotes from the independent building consultant and the second builder. 2.2 Has the insurer mishandled the claim? No. There is insufficient information to show the insurer mishandled the claim. The complainant says the insurer acted inappropriately throughout the claim The complainant says the insurer was consistently difficult to deal with and the representatives acted fraudulently and in breach of the insurance code of conduct. The complainant has not specifically identified how it has acted fraudulently or breached the code. Rather, his experience included the following:  the representatives are telling the complainants “how it is” and “how it was going to be”  the representatives say the complainants did not allow access to the property, despite him chasing, organising and arranging access for the trades  the complainant agreed to a payout, therefore he has not breached the product disclosure statement  the building assessor breached the Code when he advised the complainant he could not quote more than $20,000  after discussing the complaint with insurer, he believes the insurer has “influenced” third - party agents to restrict what they can quote him. Determination | Case number: 836992 Page 5 of 7 The panel acknowledges the complainant‟s concerns and the issues he raised however it does not accept the complainant‟s allegations. Based on the complainant‟s own chronology, the insurer had contacted the complainant to advise him of updates. The claim was lodged online on 7 September 2021 and after discussing the claim at length with the insurer, with quotes being exchanged, an AFCA complaint was lodged on 14 October 2021. On 27 October 2021 it offered to appoint a new major loss assessor to complete a dual assessment with an independent building consultant QT and a second builder. The panel does not consider the time within which the insurer considered the claim to be an unreasonable. The panel does not consider there is any evidence to support suggestions that the insurer had acted fraudulently or had bullied the complainant. The fact that there is now a disagreement as to the quantum of the claim does not mean the insurer has mishandled the claim. 2.3 Why is the outcome fair? The outcome is fair given there is clearly a substantial gap in the quotes provided with the insurer initially quoting a little over $22,000 and the complainant providing quotes for approximately $156,000 and $271,000. The quotes provided by the complainant are not detailed and do not indemnify how the claimed repairs relate to the storm event. It is fair that the insurer has the opportunity to conduct further and more detailed investigations to determine the full extent of the loss and damage claimed. The panel considers it fair that the insurer be given access and the opportunity to further assess the extent of its liability. As the parties agree that a cash settlement is appropriate, and to avoid further delay, it is fair the insurer cash settle the claim based on an average of the quotes provided by the independent building consultant and second builder. A 15 % allowance for contingencies should be added to the settlement amount. Determination | Case number: 836992 Page 6 of 7 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. A panel determined this matter Due to the nature of this complaint, we referred it to a panel for determination. The panel includes:  an ombudsman  a member with significant experience in consumer and small business advocacy  a member with extensive experience in the insurance industry. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. Determination | Case number: 836992 Page 7 of 7 3.2 Relevant policy wording Page 37: HOW WE SETTLE YOUR CLAIM We choose how we settle home claims If we agree to pay a claim for loss, theft or damage to your home, we will decide if we will: • repair damage to your home; • rebuild your home; • pay you what it would cost us to repair or rebuild your home; • pay you the home sum insured shown on your certificate; • give you a voucher, store credit or stored value card for the amount it would cost us to repair or rebuild an item. If we rebuild (or pay you what it would cost us to rebuild), we will rebuild on a „new for old‟ basis. If we repair (or pay you what it would cost us to repair), we will at our option repair on a „new for old‟ basis or repair to a similar conditi on to what your home was in before the loss or damage occurred. If we choose to pay you what it would cost us to rebuild or repair your damaged home, you are not eligible for cover under additional feature „Other repair/rebuilding costs‟, see page 31. Unl ess we tell you otherwise, we will deduct any amounts you owe us from any amount we owe you.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.