Home / IAG / Determination 836973
Determination 836973
Claim handling and settlement of storm damage building claim
Summary
The insured farm home was damaged in a storm; the insurer elected to repair, a wall collapsed during works, and the parties disputed the settlement amount. AFCA found the insurer should pay $374,306.44 for building damage plus interest, $10,080 for temporary accommodation plus interest, and $5,000 non-financial loss.
Insurer's decision to repair despite known pre-existing structural issues was likely impractical, so its later reduction of the offer by reference to the sum insured was unfair.
Issues
- Poor claim handling primary · upheld“The panel is not satisfied this is fair. The insurer's decision to attempt to repair the claim related damage was likely impractical given the pre-existing damage and the expert evidence.”
- Claim amount dispute secondary · upheld“The insurer should pay $374,306.44 in full and final settlement of the building damage, plus interest; the later reduced offer was not fair.”
- Claim denial secondary · not upheld“Temporary accommodation costs for improving alternative accommodation were not covered by the policy benefit.”
Subjects and remedies
home or building damagenatural disasterpay claimpay compensationpay interestpay non financial loss
Related
Text of the determination
Determination
Case number 836973
Financial firm Insurance Australia Limited
Case number: 836973 7 June 2022
Determination | Case number: 836973 Page 2 of 12
1 Determination overview
1.1 Complaint
The complainants held a farm insurance policy with the financial firm (insurer) when their
property was damaged during a storm.
The complainants are not satisfied with the insurer’s handling of the claim, or its recent offer
to settle the claim with a cash payment. The complainants say the insurer should replace the
damaged house or repair it, including any additional damage. The complainants also say this
should not be subject to the policy sum insured.
Further, the complainants say the insurer mishandled the claim when it did not provide them
with temporary accommodation during the harvest season. They say the insurer must remedy
this with a cash settlement of $30,000, being the full value payable for temporary
accommodation. The complainants also seek compensation for non-financial loss.
The insurer says its recent offer meets its obligations to the complainants.
1.2 Issues and key findings
What is the insurer’s liability for the building damage ?
The insurer should pay $374,304.44 plus interest in full and final settlement of the building
claim. This is based on the quotes it obtained from its builder and the reasoning set out in
section 2.1.
Is the insurer’s temporary accommodation offer fair?
Yes. The insurer’s offer meets its obligations to the complaina nts and also provides a
contribution to the improvements they made to their alternative accommodation
arrangements. Therefore, the insurer’s position is fair.
Is compensation for non-financial loss payable?
Yes. The insurer’s offer to pay $5,000 in non - financial loss due to the complainants’ claims
experience is fair.
1.3 Determination
This determination is in favour of the insurer.
The insurer must settle the claim in line with section 2 of this determination.
Determination | Case number: 836973 Page 3 of 12
2 Reasons for determination
2.1 What is the insurer’s liability for the building damage ?
Insurer probably should not have attempted repairs
The insurer accepts there is a valid claim. However, the complainants are not satisfied with
the insurer’s settlement offer. They say the insurer must repair the house and be liable for any
additional damage which occurred during the delays in settling the claim. Alternatively, they
don’t want any cash settlement to be subject to the sum insured of $388,344. This is becau se
they say the damage substantively increased as a result of the insurer’s handling of the claim.
The insurer elected to repair the damage. Whilst the policy provides it with the discretion to do
so, there are concerns with this choice. This is because the property had various pre-existing
issues as highlighted by the experts who had inspected the property. This included issues
with ‘the external left of the kitchen wall’ as well as issues with the foundation. One expert (C)
said the structure should not be repaired given these deficiencies.
Despite this, the insurer elected to repair. During the course of repairs, a wall collapsed. This
appeared to be the same one that had pre-existing issues. This resulted in the cost of repairs
increasing significantly. Following this collapse, repairs ceased and a dispute emerged about
how the claim should be settled.
Insurer’s offer on 19 October 2021 was fair
In its letter to the complainants dated 19 October 2021, the insurer offered to pay
$369,306.44 towards the building claim. This was based on quotes it received from its builder
BB for the remaining works along with a 20% contingency.
The complainants disputed this offer. They wanted the insurer to complete all the remaining
repairs without regard to the sum insured, which was $388,334. Alternatively, they did not
believe they could do the works for the amount quoted. However, the complainants did not
provide any information to show the insurer’s offer would have been insufficient to complete
the repairs at that point in time.
The panel accepts the insurer’s offer at that time was fair and reasonable. It was based on its
builder’s quotations which the insurer was later prepared to authorise. The available
information shows the insurer quoted for all the claim related damage at that point. It then
added a substantive contingency (over $61,000) to address any possible variations. There is
nothing to indicate that, at that point in time, the remaining works could not be done for the
amount quoted.
The panel understands that since the offer was made, further damage may have occurred.
However, the panel does not accept the insurer should be responsible for that. This is
because the panel is satisfied the complainants failed to reasonably mitigate their situation
having rejected the insurer’s reasonable offer. It would not then be fair for the insurer to
remain on risk for any additional damage that occurred since then and whilst the
complainants disputed the insurer’s offer.
Determination | Case number: 836973 Page 4 of 12
Insurer’s later offer is not fair
Whilst the dispute progressed through AFCA, the insurer changed its position. In its
submission dated 16 March 2022, it reduced its offer for the building costs to $334,644.66.
This was based on the following:
Sum Insured - $388,344
CPI benefit under the policy - $11,660.66
Less costs incurred due to works done - $65,450
The panel is not satisfied this is fair. The available information indicates the insurer’s decision
to attempt to repair the claim related damage was likely impractical given the pre-existing
damage and the expert evidence. This means the insurer has expended monies under the
policy that may have either been reduced, or mitigated, by the complainant.
Further, and of significance, its decision to repair the damage likely resulted in a substantive
increase to the claim related costs given the collapse of the wall and the further damage that
since occurred. If, instead, the insurer had initially sought to cash settle the claim related
repairs, it is likely it could have done so without the sum insured being impacted.
Given all this, the panel does not accept it is fair the complainant’s claim should be impacted
by the sum insured.
Building claim should be settled in this way
The insurer’s email dated 19 November 2021, and its subsequent submissions, said the solar
panels were likely damaged. It has included a $5,000 allowance for this which is the
maximum sum payable under the policy terms.
The complainants also sought cover for an air conditioner. The insurer did not accept there
was evidence to show this was damaged. The complainants have not provided information to
show this was damaged. The panel does not accept it is fair to provide an additional
allowance for this given:
there is nothing to indicate it was damaged, and
even if it was later discovered to have been damaged, this should be covered by the 20%
contingency.
Therefore, the panel considers the insurer’s offer on 19 October 2021, along with the
inclusion of $5,000 for the solar panels, is a fair basis to determine the extent o f its liability for
the claim related damage. This is because the panel accepts:
this fairly reflected the cost to repair the claim related damage at that time,
that amount is not impacted by the sum insured, and
the insurer should not be liable for any additional losses that have been sustained to the
property since then for reasons already expressed.
Accordingly, the insurer should pay the following in full and final settlement of the building
damage:
the sum of $374,306.44, and
interest on the above sum pursuant to section 57 of the Insurance Contracts Act 1984 (the
Act). Interest is payable from 19 October 2021 until payment is made.
Regarding interest, the panel acknowledges that part of the reason the complainants did not
receive the settlement money was due to their decision to reject the offer. However, the panel
considers it fair to apply interest because:
the insurer later changed its position and reduced the amount offered in unfair
circumstances, and
Determination | Case number: 836973 Page 5 of 12
the information shows the complainants were entitled to this money under the policy at that
point in time.
2.2 Is insurer’s temporary accommodation offer fair?
Complainants are seeking more for temporary accommodation
The complainants seek the full benefit payable. However, the panel notes the following.
There is no information to show the complainants have incurred this type of cost to date. This
is because they have been staying in accommodation they own.
Further, the insurer’s builders said the remaining works could be done in 10 weeks. The
complainants have not provided evidence to refute this. Therefore, the available information
does not show the full benefit is payable.
The complainants sought to be reimbursed for the costs they incurred to improve alternate
accommodation they were using to make it more habitable.
The temporary accommodation additional benefit is for renting a comparable house while the
insured property is not habitable. The wording of the benefit does not extend to improving an
insured’s permanent structure as a solution to the ne ed for temporary accommodation. These
were the type of costs the complainants incurred.
As a result, the complainants’ preferred outcome does not fall within the policy benefit.
Further, the panel does not accept these costs should be awarded. These works improved
the structure and is to the complainants’ benefit. In addition, the insurer offered to contribute
$5,000 towards these costs in its submission dated 16 March 2022. This is reasonable given
this type of cost is not covered by the policy. Neither can it be considered a loss the
complainants suffered due to the insurer’s claims handling.
Insurer should settle temporary accommodation in this way
The insurer’s offer of 12 weeks accommodation was fair on the available evidence. It was
based on its buil der’s estimate of ten weeks. There is no expert evidence to refute the
estimated time. The panel also notes the insurer’s offer included the same 20% contingency
that was added to the building costs (i.e. 10 weeks + 2 weeks contingency).
The insurer’s offer included an allowance of $120 per night. The complainants provided no
evidence to refute this was reasonable. Whilst they said the cost would be doubled to include
their son, they did not provide any information to substantiate this. On the face of it, the panel
considers the insurer’s daily allowance of $120 per day is reasonable given this totals $840
per week.
Therefore, the insurer should pay $10,080 for temporary accommodation plus interest
pursuant to section 57 of the Insurance Contracts Act 1984 (the Act). Interest applies for
similar reasons as expressed for the building costs. Interest is to apply from 19 October 2021
until payment is made.
Determination | Case number: 836973 Page 6 of 12
2.3 Is compensation for non-financial loss payable?
Insurer to pay $5,000 in non-financial loss
Under our Rules, AFCA can consider making awards of up to $5,400 compensation for non-
financial loss. However, we will only award this type of compensation if a complainant suffers
an unusual degree or extent of physical inconvenience, time taken to resolve the situation or
interference with the complainant’s expectation of enjoyment or peace of mind.
Considering the extent of the delays, and the impact this has had on the complainants, the
panel is satisfied the insurer should compensate the complainants for non-financial loss. This
is because the insurer made errors which the panel considers were not caused or contributed
to by the complainants. This includes the decision to proceed with repairs in circumstances
when this was likely impractical and the flow on effects this caused.
The panel accepts the insurer would have mitigated the direct financial loss the complainants
suffered by its offer on 19 October 2021.
Further, the insurer offered $5,000 compensation due to the complainants’ adverse claims
experience. The panel accepts this is fair in all the circumstances as it would at least match, if
not exceed, the amount awarded at AFCA if no such offer was made.
Therefore, the insurer should pay this amount in recognition of the complainant’s claim
experience.
Determination | Case number: 836973 Page 7 of 12
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel
includes:
an ombudsman
a member with significant experience in consumer and small business advocacy
a member with extensive experience in the insurance industry.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
Determination | Case number: 836973 Page 8 of 12
3.2 Contents
Insurer is to finish assessing the complainants’ contents loss
The panel notes the complainants confirmed their contents have been damaged while the
property was not water tight. However, this has not been settled by the insurer as yet. The
insurer confirms an assessment has taken place, but it is still waiting on a report from its
assessor.
The insurer must complete its assessment of the damaged contents and settle the claim
pursuant to the policy and its other obligations. This must occur promptly given considerable
time that has lapsed since the claim was lodged.
If there is a dispute over settling the contents claim, this would form the basis of a new
complaint between the parties.
3.3 Policy excerpts
What We do if Your Home is Accidentally damaged
If ‘Building’ and ‘Replacement’ are shown on the Certificate of Insurance, We replace,
reinstate, or repair the part of Your Home that is accidentally damaged as far as possible to
its original condition, using materials that are readily available in Australia. Or, at Our option,
We pay You the reasonable cost to do so.
…
We pay only up to the amount shown as the sum insured for ‘Building’ on the Certificate of
Insurance where an amount is shown next to the word ‘Replacement’.
…
Additional benefits
Temporary accommodation or loss of rent
If We have paid or agree to pay a claim for damage to Your Home, We pay:
the reasonable cost for You and Your Family to rent a comparable house in a nearby
location; or
…
until:
We replace, reinstate or repair the damage to Your Home; or
We pay You to do so (in which case it will include provisions for this benefit as if We were
replacing, reinstating or repairing the damage to You Home); or
Your Home becomes habitable.
We pay up to $30,000 towards the cost of 52 weeks rental costs or 52 weeks lost rent.
…
The following additional benefit is included in the sum insured shown on the Certificate of
Insurance for ‘Building’
Costs connected with rebuilding
If We have paid or agreed to pay a claim to replace or reinstate Your Home We pay for:
Determination | Case number: 836973 Page 9 of 12
the extra costs to comply with the requirements of a public authority in relation to rebuilding
Your Home, but not the cost for work required before the damage occurred
architects’, surveyors’ and legal fees
demolition costs and the costs to clear debris from the site of the building being replaced
or reinstated.
We only pay these costs under this additional benefit if:
the are incurred as a consequence of the loss or damage for which We have agreed to pay
a claim; and
they are reasonable; and
We have approved them before You incur them.
3.4 Expert evidence
Record Key points
Insurer ’s engineer ( CC )
Report
17 February 2020
The scope of work must take account of the requirement to rectify
the following issues in order to provide a sound structure:
1. Foundation drainage and the foundation is deficient and not
suitable for reuse of repair
2. Footings are non - compliant and compromised due to past
foundation movements and rot ations
3. Load bearing and non - load bearing walls in the West of the
house have settled excessively.
4. Walls lack effective wall ties.
5. The internal cavity and walls are too slender and don’t comply
with modern standards.
6. The roof frame is defectively constructed and tied down.
CC says repairing the building is not feasible considering the
above. CC recommends replacing the house rather than
attempting repairs.
CC says the structure is unsafe to continue living in based on the
extent of non - compliance and dilapidation and the risk of
catastrophic failure. The house is beyond economic repair and
should be replaced.
Complainants ’ building
consultant ( EX )
Report
22 May 2020
Some damage is storm related, and some is maintenance related.
Scope of work provides which is which.
The repairs as outlined and enclosed in plan number 21 01 87 and
Scope of Works comply with the NCC2016 and related standards,
to replac e the roof battens and sheeting and to hold down the roof
structure.
The home is 60 - 80 years old and appears to have been built in
accordance with building practices common at the time of
construction.
Determination | Case number: 836973 Page 10 of 12
Record Key points
The scope of works does not include upgrading all elements of the
construction to conform to the current Australian stand ards:
however, if repairs are completed in accordance with our details
then the home will have been returned to the condition it was in
before the event. (Roof hold down details have been upgraded to
conform to the current Australian Standards.)
Insurers engineer (WG)
Report
10 September 2021
Inspection to quantify additional work following wall collapse
Further water ingress likely after two additional winters
Repair of the wall was possible before the wall collapsed.
Demolish and rebuild is now required.
Repair scope includes additional water damage to the property
interior.
All remaining items should be completed in accordance with the
original scope of works.
3.5 Timeline of events
Date Event
4 February 2020 The complainants lodged the claim as part of the roof and veranda
were blown off.
5 February 2020 A builder sent by the insurer (WB) attended and confirmed there
was damage to the roof consistent with a storm. WB recommended
an engineer attend and scope the work. Insurer understood the
complainants would organise their own make safe work.
27 February 2020 The insurer and its experts were still working to determine the cause
and extent of the loss. The complainants contacted the insurer’s loss
assessor (CR) as the roof was leaking. Insurer agreed with CR’s
recommendation to have trades attend again and perform a make
safe.
29 May 2020 The insurer, CR, CC, WB and BB completed work to determine the
scope of work and quoted on the cost of repair. The insurer then
made an offer to cash settle the clai m using BB’s quot e due to
concerns about warranting the repair work.
10 June 2020 T he parties continued negotiating the claim outcome to this date .
The complainants were concerned they would be out of pocket and
asked for an authorised repair rather than a cash settlement.
21 July 2020 The insurer sent the complainants a partial decline letter explaining
what damage was not accepted under the claim.
30 July 2020 BB supplied a variation quot e to include and additional $6,332.94 of
repairs.
Determination | Case number: 836973 Page 11 of 12
7 October 2020 The parties remained in dispute until this date when CR advised the
complainants had supplied their JR ’s quote totalling $176, 000. The
scope was based on EX ’s scope of work. CR requested a more
detailed quote from JR to review.
26 October 2020 CR followe d up with JR .
18 November 2020 CR followed up with JR again.
2 February 2020 T he dispute continued as JR’s quote had not b e en accepted. The
insurer began double checked the BB quot e for accuracy, and the
complainants maintain the insurer’s trade should repair. BB re -
attended the property and provided updated repair quote of
$153,593.78 based on EX’s scope of work.
17 February 2021 BB confirmed it could proceed with repairs rat her than the ins urer
settling the claim with cash as EX’s maintenance concerns were
largely superficial in nature.
26 February 2021 T he complainants advis ed CR they were happy for BB to proceed
with the repairs.
3 March 2021 T he complainants contacted the insurer to be cash settled as the
make safe had failed and water had entered the property causing
additional damage.
5 March 2021 BB advised it was still waiting on a signed cont ract to begin the
repair work.
8 March 2021 T he complainants advis ed the cont ract had been signed and sent
back that morning and they were now waiting on repairs to
commence.
27 August 2021 BB began the work after getting approvals necessary to begin
through local council. This continued up until a wall partially
collapsed on this date .
10 September 2021 T he complainants called the insurer chasing an update and
requesting a cash settlement as they were not satisfied with BB’s
work or how the claim had been handled. WS acting for the insurer
completed a new assessment of the collapsed wall and supplied a
view on the additional scope of work needed.
20 September 2021 BB supplied an updated scope of work to include the damage which
occurred when the wall collapsed.
23 September 2021 T he insurer’s technical consultant completed a review of the claim in
which she confirmed CC’s original concerns had proven valid. She
disagreed with the choic e to repair the property in hindsight and
recommended accepting the resultant damage.
Determination | Case number: 836973 Page 12 of 12
Further, a dditional damage due to water entry had also occurred
and would need to be included in the repair. She recommended her
colleagues consider whether the property was a total loss.
13 October 2021 T he complainants approached AFCA.
19 October 2021 The insurer emailed the complainants with an offer to have BB
continue the repairs. The offer was not accepted.
27 October 2021 BB also supplied a variation including an additional $12,032.99 of
work needed to complete the repair.
22 November 2021 The insurer sent its final decision letter to the complainants offering
$384,386.44 including $369,306.44 for building repairs. This offer
was not accepted.
8 December 2021 The insurer increased its offer for building repairs to $377,706.44 in
its notice of response to AFCA. This offer was not accepted.
3 February 2022 The insurer sent a further offer to resolve the matter by having BB
complete the repair work, but without waiving the policy sum
insured. This offer was not accepted.
11 March 2022 T he parties remained in dispute over the settlement. The
complainants suggested BB could proceed with the repair if they
could do it for the amount offered, however, they said they would not
accept any limiting of the repair work based on the policy sum
ins ured. The offer was not accepted.
The insurer alleges the complainants were now refusing to allow
trades to come to site until a decision was made on its offer.
16 March 2022 The insurer supplied its final position letter stating it would settle up
to the policy sum insured, including the CPI increase benefit, less
the costs incurred so far while repairing the property.
24 March 2022 T he complainants contacted AFCA and disputed the allegation they
were preventing trades from attending the property. Further
attendance was allowed.
Current date T he parties remain in a position where the property is not repaired,
repairs are not proceeding, and the issue of the policy sum insured
is not resolved. A further assessment was being completed by the
insurer but has not been rec eived to dat e.