Determination 835146

Insurer's offer to settle storm damage claim was insufficient, omitting insulation and roof battens

FirmQBE
Decided2022-05-06
ProductGeneral Insurance · Business / commercial
OutcomeFor the complainant
Amount awarded$94,651
Non-financial loss—
Amount claimed$95,151
SourceAFCA PDF

Summary

A business insured for hail storm damage disputed the insurer's cash settlement offer, which omitted insulation and roof battens. AFCA found the policy covered these items and ordered payment of the complainant's repair quote less excess, plus interest from 27 August 2021.

The policy required repair to the same condition as when new, and the insurer did not refute evidence that these items were covered and needed, so the settlement must include them; interest runs under section 57 of the Insurance Contracts Act 1984.

Issues

Subjects and remedies

business interruptionhome or building damagenatural disastersmall businesspay claimpay interest

Related

All QBE determinations · Find similar determinations

Text of the determination

Determination Case number 835146 Financial firm QBE Insurance (Australia) Limited Determination | Case number: 835146 Page 1 of 6 Case number: 835146 28 April 2022 1 Determination overview 1.1 Complaint The complainant is a company that held a business insurance policy with the financial firm (the insurer). The complainant lodged a claim for storm damage. The insurer accepted the claim and agreed to pay the cost of repairs, which it assessed as $72,795.07 (ex GST). The complainant says this is insufficient to repair the damage. The complainant has provided a repair quote dated 24 June 2021 totalling $95,151 (ex GST). The complainant says the cost of repairs will have increased since then, and a fair settlement should be based on new quotes to account for cost increases. 1.2 Issues and key findings Wa s the insurer’s offer sufficient ? No. The insurer’s offer was not sufficient, because it did not include the costs of replacing insulation and roof battens. How should the claim be settled? The best available estimate of the cost of repairs is the complainant’s quote of 24 June 2021 totalling $95,151. The insurer should settle the claim by paying this amount, less the excess of $500. The insurer should pay interest on the settlement sum from 27 August 2021, the date it rejected the complainant’s request to settle the claim based on the quote. Since 24 June 2021, the insurer has not prevented the complainant from starting repairs. Therefore, the insurer is not required to pay for any additional loss caused by a delay in starting repairs. 1.3 Determination This determination is mostly in favour of the complainant. The insurer must settle the claim by paying the complainant $94,651 (excluding GST) plus interest at the rate determined under section 57 of the Insurance Contracts Act 1984 (Cth) from 27 August 2021. Determination | Case number: 835146 Page 2 of 6 2 Reasons for determination 2.1 Wa s the insurer’s offer sufficient ? Complainant provided quotes for $95,151 The insured property was damaged by a hailstorm on 19 April 2020. The complainant is involved in the building industry, and wants to have repairs done by itself and associated companies. The complainant appointed a plumber (RTH), who inspected the property on 25 May 2020. RTH prepared a report dated 26 May 2020, and a scope of works and quote dated 28 May 2020. The complainant provided copies of these documents when it lodged the claim with the insurer on 1 June 2020. The complainant provided several quotes from RTH. Details of the quotes are set out in the following table: Quot e date Total (ex GST) Itemised? Changes from previous quote s 28 May 2020 $64,395.10 Yes Undated ( circa October 2020) $88,022.15 Work items listed, but not costed  allows for new solar system ($20, 500) ; previous quot e only allowed for removal and reinstatement of existing solar system ($4,000)  project management fee increased from 10% to 15% 14 March 2021 $95,151 Work items listed, but not costed  included ‘QBCC Insurance’ ($1,000) and ‘Certification Form 18’ ($2,600), which were not included in previous quotes  l/m of 40mm Cyclonic Metal roof battens in main building increased from 370 to 410 ($400)  other work items remain, but costs increased by about 8%  complainant said industry costs had increased substantially since previous quote 24 June 202 1 $95,151 Yes  same as previous quote, but work item costs included The complainant has not provided any further quotes. However, it says building costs have continued to increase. It says a fair settlement should be based on new quotes to account for cost increases. Insurer provided quotes for $72,795.07 The complainant lodged a claim with the insurer on 1 June 2020 The insurer appointed a loss adjuster, who inspected the property on 9 June 2020. Determination | Case number: 835146 Page 3 of 6 In or about January 2021, the loss adjuster obtained undated repair quotes from three builders:  AN ($55,860.77)  TB ($55,100.01)  DJ ($51,630.63). The insurer offered to settle the claim by paying $51,630.63 (less excess). The insurer ’s quotes did not include a new solar system. At the time, the insurer said there was no damage to the solar panels. The insurer now says the hail damaged the solar panels in a way that was not immediately obvious. In or about March 2021, after both parties arranged several expert reports on the solar system, the insurer agreed to pay for its replacement. On 21 April 2021, AN provided a quote for $21,164.44 (ex GST) to replace 36 solar panels. In May 2021, the insurer offered to settle the claim for $72,795.07, calculated as follows: Item Amount (ex GST) DJ’s quote for building repairs $51,630.63 AN’s quote for new solar panels $21,164.44 (less excess) ($500) TOTAL $72,295.07 In December 2021, AFCA asked the insurer whether these quotes were actionable. The insurer said:  DJ’s quote was actionable, but did not account for any further damage or deterioration that may have occurred since January 2021  AN’s quote had increased to $ 22,700.25 (about 7%) due to increases in material and labour costs since April 2021. Insurer’s off er does not include insulation RTH’s quotes allow $7,630 for: ‘Supply and install AirCell Insulation’. DJ’s quote does not include insulation. The loss adjuster ’s report of 9 October 2020 said: ‘ no photographs have been provided by any builder to verify that there is actually insulation in either building ’. The complainant said the buildings were insulated, and it could provide photographs confirming this. On 9 February 2022, the complainant provided photographs of what looks like AirCell roof insulation. The insulation shown in the complainant’s photographs is also visible in one of the photographs included in RTH’s report of 26 May 2020. The loss adjuster said RTH’s report showed ‘ what was identified as sarking ’. Sarking is a type of insulation. Other than the alleged lack of photographic evidence, the insurer has not given any reason for declining to pay for the insulation. It has not explained why it does not accept the complainant’s photographs as proof that the buildings were insulated. Determination | Case number: 835146 Page 4 of 6 Having considered the information provided by both parties, I am satisfied that the cost of repairs includes the cost of supplying and installing AirCell Insulation. Insurer’s offer does not include roof battens RTH ’s latest quote allows $5,500 for: ‘ Supply and install new 40mm Cyclonic Metal roof battens ’. DJ’s quote does not allow for new battens, and includes the following note: Roof sheet fixings to be moved along the batten to avoid re-fixing into existing hole within the batten. The complainant says reusing the existing roof battens would compromise their structural integrity. The complainant has provided a document titled Tradie Tour, Metal Roofing Webinar 19 September 2019 Q&A Session Responses , published by the Queensland Building and Construction Commission (QBCC) . The document says that, ‘in general’, roof battens must be replaced during a re-roof. It says only one supplier is prepared to consider reusing roof battens, and that supplier says it should be considered on a case-by-case basis and no roof batten should be reused more than once. The insurer says the QBCC document is ‘ not a directive ’, and it only applies to residential buildings. The loss adjuster says the complainant should provide ‘ the exact requirement under the QBCC guidelines ’. Neither the insurer nor the loss adjuster has said whether reusing roof battens would be allowed under the QBCC guidelines. The loss adjuster says: ‘ We would trust that the panel builder [DJ] would be acting within tolerance of the industry requirement. ’ The policy says the insurer will pay the cost of repairing the building to the same condition as when it was new. The complainant has provided evidence that reusing the battens would leave the roof in a worse condition than when it was new. The insurer has not provided evidence to refute this. Having considered the information provided by both parties, I am satisfied that the policy covers the replacement of the roof battens. Insurer’s offer insufficient to cover cost of repairs I am satisfied that the policy covers replacement of insulation and roof battens. The insurer’s settlement offer did not include these costs. Therefore, the insurer’s offer was insufficient to fulfil its policy obligations. 2.2 How should the claim be settled? Settlement should be based on complainant’s quot e RTH’s quote of 24 June 2021 exceeds the insurer’s offer by $22,355.93. Most of this difference ($13,130) is due to the allowances for insulation and roof battens. I have concluded the insurer should pay for these items. The insurer has not provided information showing RTH’s quotes include unnecessary work items, or that the amounts quoted for the work items are excessive. RTH’s quote of 24 June 2021 is the best available estimate of the cost of repairs. Therefore, the fairest way to settle the claim is for the insurer to pay the amount of this quote: $95,151. Determination | Case number: 835146 Page 5 of 6 The excess payable on the claim is $500. Subtracting this from $95,151 yields $94,651. Insurer not required to pay allowance for transfer of risk When an insurer settles a claim by repairing damage, it guarantees the quality of the repairs. If the repairs are unsuccessful, or cause additional damage, the insurer is responsible for the cost of rectification. When the insurer settles a claim by paying the cost of repairs, it transfers this risk to the customer. Furthermore, the customer may find it more difficult and expensive to arrange repairs, because they do not have the insurer’s industry knowledge and bargaining power. AFCA considers that where an insurer settles a claim by paying the cost of repairs, it should consider paying an allowance for the transfer of risk. Generally, AFCA considers that a reasonable allowance is likely to be between 5% and 25% of the quoted cost of repairs. The complainant is involved in the building industry, and says repairs will be carried out by itself and associated companies. In these circumstances, it is reasonable for the insurer to settle the claim without paying an allowance for the transfer of risk. Insurer not required to pay for delay The complainant says the cost of building work has increased since it obtained RTH’s quote of 24 June 2021, and a fair settlement should be based on new quotes that account for this. The complainant says some repairs have been completed, but other repairs will not start until the claim is settled. It says repairs will take about 12 months, and it expects the cost of the work to increase by 20-35%. It says costs will continue to increase until the claim is settled. Throughout the claim, the parties have agreed that the insurer will not undertake repairs, but will pay the cost of repairs. This means it is the complainant’s responsibility to arrange repairs. The complainant has not been made to wait for the insurer to arrange repairs. Before March 2021, the insurer had not agreed to pay for new solar panels. If the complainant had replaced the solar panels, it may have removed evidence showing the solar panels were damaged by the storm. Since the complainant obtained RTH’s quote of 24 June 2021 , the insurer has not prevented the complainant from repairing the property. Therefore, the insurer is not required to pay for any loss caused by a further delay in starting repairs. Insurer must pay interest Section 57 of the Insurance Contracts Act 1984 (Cth) says an insurer must pay interest on a claim settlement payment from the time it was unreasonable to have withheld payment. In the circumstances, I consider this to be 27 August 2021, the date the insurer rejected the complainant’s request to settle the claim based on RTH’s quote . The insurer offered to pay the complainant $72,295.07, but only if the complainant accepted this in full and final settlement of the claim. It did not give the complainant the option of accepting $72,295.07 in partial settlement of the claim. Therefore, the insurer must pay interest on the entire settlement sum, not just the part exceeding its settlement offer. The insurer must settle the claim by paying the complainant $94,651, plus interest from 27 August 2021. Determination | Case number: 835146 Page 6 of 6 3 Supporting information 3.1 The AFCA process AFCA’s approac h is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. I have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, I have restricted this determination to the issues that are relevant to the outcome. 3.2 Complainant represented by insurance broker The complainant was represented by an insurance broker. In this determination, statements by the complainant’s representative are treated as if they were made by the complainant.