Home / Suncorp Group / Determination 834640

Determination 834640

escape of liquid claim: liability assessment, repair quality and out-of-pocket expenses

FirmSuncorp Group
Decided2022-10-21
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$30,869
Non-financial loss$2,500
Amount claimed$19,259
SourceAFCA PDF

Summary

The complainant made a home building and contents claim after a laundry water overflow; the insurer's repairs were defective and its cash settlement was disputed. AFCA ruled in the complainant's favour, ordering a cash settlement or completed repairs, contents payments, out-of-pocket expenses and non-financial loss compensation.

The insurer's repairs were not completed to a reasonable standard and it is fair for the complainant to choose between insurer-completed repairs and a cash settlement at a reasonable cost, plus non-financial loss under AFCA Rule D.3.3(b).

Issues

Subjects and remedies

home or building damagepay claimpay compensationpay non financial lossreassess claimrepair or rectify

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 834640 Financial firm AAI Limited Determination | Case number: 834640 Page 2 of 9 Case number: 834640 13 July 2022 1 Determination overview 1.1 Complaint The complainant holds a home building and contents insurance policy (policy) with the financial firm (insurer). On 31 May 2019, a claim was lodged for damage to the insured building and contents because of an overflow of water from the laundry when a tap was left running by mistake. The insurer accepted the claim and arranged for repairs. The complainant remains dissatisfied with the quality of repairs completed, the insurer’s assessment of its liability relating to several contents ’ items and the insurer’s overall management of the claim. 1.2 Issues and key findings Is the insurer ’s assessment of its liability fair in the circumstances? No. The insurer is to:  at the complainant’s discretion , either arrange for the outstanding building works and mould remediation, or alternatively, in the instance the complainant wishes to be cash settled for these works, the insurer is to arrange a cash settlement as set out in section 2.1 of this determination  the insurer is to cash settle the complainant in the amount of $18,199.00 for the outstanding contents, carpets and special rug component of the claim  subject to being provided with reasonable supporting information, the complainant is to be reimbursed for reasonable temporary accommodation expenses up to six weeks. Is the complainant entitled to reimbursement for out-of-pocket expenses? Yes. Considering the information provided by the complainant, the insurer is to reimburse the complainant $12,670.15 for her out of pocket expenses. On being provided with any further supporting information for any additional out of pocket expenses, the insurer is to consider this information in line with the policy provisions. Is the complainant entitled to non-financial loss compensation? Yes. The insurer is to pay the complainant $2,500 in non-financial loss compensation in line with the AFCA Rules. Why is the outcome fair? This outcome is fair because there is compelling information showing the repairs to the insured building were not completed to a reasonable quality in the first instance, requiring further repairs to be completed. The complainant is entitled to replacement of damaged contents to the same quality as those damaged because of the insured event. Further, the complainant would not have incurred the out of pocket expenses but for the issues experienced under the claim. As such, it is fair that she be reimbursed for the reasonable expenses incurred as well as receive non-financial loss compensation in line with the AFCA Rules for her poor experience under the claim. Determination | Case number: 834640 Page 3 of 9 1.3 Determination This determination is in favour of the complainant. Within 14 days of the complainant accepting the determination:  The complainant is to inform the insurer whether she wishes for the insurer to complete the outstanding building repairs or whether she wishes to be cash settled under the claim  If the complainant chooses to be cash settled, the insurer is to arrange the cash settlement for the building works ($47,566.41) and $18,199.00 towards the outstanding damaged contents, carpets and special rug in line with this determination  The insurer is to pay the complainant $12,670.15 as reimbursement of her reasonable out of pocket expenses  Subject to supporting information, the insurer is to cover the complainant up to six weeks temporary accommodation  the insurer is to pay the complainant $2,500 in non-financial loss compensation. Determination | Case number: 834640 Page 4 of 9 2 Reasons for determination 2.1 Is the insurer’s assessment of its liability under the claim fair? No. The insurer is to settle the claim as outlined in this determination. The policy is an insured events contract of insurance The policy covers the insured property against loss or damage caused by one or more of the listed insured events, including ‘ Escape of liquid ’. Cover under these benefits is subject to the conditions, limitations and exclusions specified in the product disclosure statement (PDS). The insurer provided the complainant with the relevant policy documentation including the PDS and certificate of insurance (COI). Therefore, I accept the insurer is entitled to rely on the policy provisions to assess its liability under the claim. The complainant has established a valid claim There is no dispute a valid claim exists under the policy for loss or damage caused to the insured building and contents due to an escape of liquid event. The parties differ in their position s regarding the insurer’s assessment of its liability under the claim as well as the level of service provided by the insurer over the life of the claim. It is fair to allow the complainant to choose how claim is settled The insurer has sought to fulfil its obligations under the policy by way of cash settling the complainant for what it has assessed as the fair cost of the building repairs and scope of works. The insurer says this is because the complainant has failed to co-operate and prevented the insurer from proceeding with the repairs by refusing access to the insured property. The complainant refutes the insurer’s position and says she did not refuse access to the insured property. She was unable to allow access due to mould treatment works being completed at the relevant time. However, I accept the complainant does hold concerns regarding the insurer’s ability to complete the repairs given the issues with the repairs completed in the first instance. There is no dispute the insurer originally authorised and completed repairs to the insured building under the claim. Further, that these works were not completed to an acceptable standard requiring further repairs and rectification works, for which the insurer now seeks to cash settle the claim. I accept the complainant did cancel two appointments made with the insurer, however, I accept the complainant has provided reasonable cause for doing so. Therefore, I am not satisfied it is an issue of non-co-operation but rather confusion caused through a mix up in communication. I am not satisfied it would be reasonable to require the complainant to accept a cash settlement where the insurer has already authorised and commenced repairs under the claim. Allowing the insurer to do so would unreasonably transfer the risk of arranging and managing the outstanding repairs as well as deprive her of the repair guarantees available under the policy if the repairs are completed by the insurer. Determination | Case number: 834640 Page 5 of 9 Accordingly, considering what is fair in the circumstances, I determine the complainant is entitled to choose whether she prefers the insurer complete the repairs or if she would like to be cash settled under the claim. In the interest of completeness, should the complainant wish for the insurer to complete the repairs, she is to inform the insurer within 14 days of accepting this determination. Further, the complainant is to allow the insurer and its appointed consultants access to the insured property for the entirety of the time required to complete the repairs. In the instance, the complainant elects the option to be cash settled, the insurer is to cash settle the claim in line with this determination within 14 days of the complainant confirming her preference for a cash settlement. Insurer is to increase the final cash settlement offer for building repairs Where a claim is to be settled by a cash settlement, the insurer is required to pay the complainant the reasonable cost of repairing the damage to the property. This means the cash settlement amount should be sufficient to ensure that the complainant is able to engage their own contractors to complete the necessary repairs. The insurer relies on a scope of works and repair quote from its appointed consultants ‘B’ in the amount of $24,419.11 as the basis of its cash settlement for the outstand repairs. I note this quote includes costs associated with replacement of damaged carpets as well. The complainant disputes the insurer’s cash settlement and has recently provided a quote for repairs from her preferred consultant “SB’ in the amount of $31,900. 00. On review of this quote and in the absence of any persuasive information showing this to be excessive, I am satisfied SB’s quote is fair . This is both in terms of the scope of works and costing as well as being a fairer reflection of the higher cost of works and materials currently present in the market. This quote from SB does not includes the cost of replacing the damaged carpets. The issue of the carpets and the insurer’s liability in this regard will be considered in more detail later in this determination. The insurer has also offered to cash settle the complainant for the mould remediation works in the amount of $7,738.68. I have not been provided with any information that shows this amount is not fair or sufficient to complete the required mould remediation works. Therefore, I accept is it fair that the insurer be permitted to rely on this quoted amount to settle this component of the claim. I determine, if the building repairs and mould remediation components of the claim are cash settled, this is to be in the amount of $47,566.432 based on the above noted quotes and including a 20% increase to allow for contingencies and the transfer of risk to the complainant in arranging the repairs. In addition, the policy provides additional benefits following an insured event, including temporary accommodation payments. Subject to proof, the insurer is required to pay the complainant up to six (6) weeks reasonable cost for temporary accommodation. Insurer is to cash settle the complainant for the below items The complainant has raised concerns regarding the insurer’s assessment of its liability with respect to the carpets at the insured property as well as several other contents ’ items. The Determination | Case number: 834640 Page 6 of 9 insurer has since accepted and offered to cover the complainant for the below, which I accept is reasonable:  a Zuma dining suite costed at $3,799.00  a split system air conditioner system for $4,690 In addition to the above, there exists the issues relating to the replacement of carpets in the various rooms affected by the escape of liquid and special rug which had been damaged beyond repair/restoration. The insurer’s offer for the damaged sections of the carpet sits at $4,620.00 which the complainant says is not enough to replace the damage carpets like for like in terms of quality. Further, that the insurer’s preferred supplier was not able to provide the required quality of carpet. The complainant also says it is reasonable to expect the insurer to replace all carpets within the home, including undamaged sections to ensure a uniform appearance. The complainant has provided a tax invoice for the cost to replace the damaged carpets $8,690.00, the undamaged carpets $5,890 and replacement special rug $2,620. I do not accept the insurer is required to cover the complainant for the replacement of the undamaged sections of the carpet. This is not covered under the policy. I note there is no dispute the damaged carpet and underlay at the insured property were of a high quality nor have I been provided with information refuting the complainant’s position regarding the insurer’s supplier not being able to supply comparable carpet. In the interest of bringing this matter to conclusion and in the absence of information to the contrary, I determine it is fair the insurer reimburse the complainant $8,690.00 for the damaged carpets and $2,620.00 (less $1,600 it has already paid) for the special rug. Accordingly, within 14 days of the complainant’s acceptance of this determination the insurer is to pay the complainant $18,199.00 for dining suite, AC, damaged carpets and special rug. 2.2 Is the complainant entitled to reimbursement for out of pocket expenses? Yes. The insurer is liable to reimburse the complainant for reasonable out of pocket expenses. The complainant says she incurred expenses relating to the claim The complainant says due to the delays and inadequate investigations completed by the insurer, mould developed within her home. Unaware of this, she had remained in the home and began feeling unwell. She arranged investigations by various consultants to determine the cause of her illness, which the complainant maintains was the result of the mould infestation. The complainant says she has incurred various out of pocket expenses arising form and relating to her attempts to identify issues with the repairs and investigations under the claim. These expenses include investigations which identified the presence of black mould due to the event and efforts to mitigate this issue within the home. The complainant says she has incurred the below listed out of pocket expenses:  ‘ EH ’ mould testing for $2,838.00  ‘ M P’ to fog and treat the mould for $5,800.00 Determination | Case number: 834640 Page 7 of 9  toilet and installation for $979 ($829 and $150.00)  builder to pull out arcs and skirt board for $1,210.00  completed tile work for $1,050.00  tiles for $113.00  new ceiling in the master bedroom and labour for $2,262.00  painting of ceiling and wall for $800.00  electrical works for $240.00  plaster board and sheet replacement for $617.15  painting works for $2,100.00  mouldy carpet removal for $390.00  tip fees for $360.00  extractor fans and humidifier cost for $500.00 She seeks the insurer to reimburse her the total sum of $19,259.15. Insurer accepts reimbursement of reasonable expenses subject to proof The insurer says it is open to consider reimbursement of the expenses the complainant reasonably incurred and requested proof from the complainant. The complainant has provided information of having incurred the below expenses:  EH mould testing for $2,838  MP to fog and treat the mould for $5,800  Completed tile work for $1,050  New ceiling in the master bedroom and labour for $2,262  Painting of ceiling and wall for $800  Electrical works for $240  Tiles for $113  Plaster board and sheet replacement for $617.15. I note the available information shows the insurer has already settled the complainant $1,050.00 for the completed tiles work and is not obliged to pay this amount again. The insurer says it is not obliged to reimburse the complainant for expenses relating to the mould testing by EHS or for the works completed by MP as its proposed cash settlement includes $7,738.68 for mould restoration works. I am not of the same opinion and accept the works by EH and MP were necessary in identifying the mould issue as well as an attempt to mitigate the spread of the mould. Accordingly, I determine wi thin 14 days of the complainant’s acceptance of this determination, the insurer is to pay the complainant $12,670.15 as reimbursement for reasonably incurred out of pocket expenses. 2.3 Is the complainant entitled to non-financial loss compensation? Insurer is to pay the complainant $2,500 in non-financial loss compensation The AFCA Rules (Rule D 3.3) allow for an award of up to $5,400 for non-financial loss compensation, if the insurer caused the complainant to suffer an unusual degree or extent of inconvenience, delay or interference. AFCA takes a conservative approach when considering any award of compensation. Determination | Case number: 834640 Page 8 of 9 In this instance and considering AFCA’s approach to compensation, I accept the insurer’s overall management of the claim has caused and/or contributed to an undue level of stress, anxiety and physical inconvenience experienced by the complainant as well as delayed the time taken to finalise the claim. This relates to a failure to complete the repairs authorised under the claim to a reasonable and acceptable quality in the first instance which has then resulted in a break down in the relationship between the parties. Also, a failure to identify and/or attend to the development of mould within the home, which further contributed to the complainant’s poo r experience over the life of the claim. I acknowledge it was not the insurer and its appointed representatives conduct alone that has contributed to the delay in bring this matter to conclusion. However, overall, I am satisfied that had the assessing and associated repairs process been managed efficiently from the start, it may well have been that most of issues faced by the parties would not have eventuated. Accordingly, given AFCA’s approach to compensation and the available information, I determine the insurer is to arrange payment of $2,500 in non-financial loss compensation to the complainant within 14 days of her acceptance of this determination. 2.4 Why is the outcome fair? This outcome is fair because there is compelling information showing the repairs to the insured building were not completed to a reasonable quality in the first instance, requiring further repairs to be completed. The complainant is entitled to replacement of damaged contents to the same quality as those damaged because of the insured event. Further, the complainant would not have incurred the out of pocket expenses but for the issues experienced under the claim. As such, it is fair that she be reimbursed for the reasonable expenses incurred as well as receive non-financial loss compensation in line with the AFCA Rules for her experience under the claim. Determination | Case number: 834640 Page 9 of 9 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 AFCA Rules D.3.3 An AFCA Decision Maker may decide that the Financial Firm is to compensate the Complainant for non-financial loss: a) for a complaint relating to an individual’s privacy rights - injury has occurred to the Complainant’s feelings or humiliation has been suffered by the Complainant; or b) for other complaints – an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the Complainant’s expectation of enjoyment or peace of mind has occurred.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.