Home / Suncorp Group / Determination 834082

Determination 834082

Mould remediation and repair following 2012 water damage claim

FirmSuncorp Group
Decided2022-08-31
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$10,000
Non-financial loss$5,400
Amount claimed—
SourceAFCA PDF

Summary

The complainants claimed further mould damage and related losses after a 2012 storm claim the insurer had repaired. AFCA found the insurer's 2012 remediation was inadequate and ordered remediation, reimbursement of financial losses and expert fees, and $5,400 non-financial loss compensation.

The insurer's 2012 repairs did not conform to applicable water damage restoration standards and the lifetime guarantee on repairs applies, so it is liable for remediation of the resulting mould damage.

Issues

Subjects and remedies

financial hardshiphealth or medicalhome or building damagenatural disasterpay claimpay compensationpay interestpay non financial lossreassess claimrepair or rectify

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 834082 Financial firm AAI Limited Determination | Case number: 834082 Page 1 of 8 Case number: 834082 11 August 2022 1 Determination overview 1.1 Complaint The complainants hold a home building and contents insurance policy with the financial firm (insurer). They lodged a claim for water damage in November 2012. That claim was accepted and the insurer undertook repairs (including mould remediation), completed in June 2013. In May 2018, the complainants contacted the insurer about ongoing mould and associated health concerns, all of which they believe to be related to the 2012 event. The insurer has denied any further liability. The complainants believe the insurer should cover the cost of full mould remediation. They are also seeking loss of rent and accommodation costs, as well as medical costs and lost wages arising from mould-related illness. 1.2 Issues and key findings What is the extent of the insurer’s liability for the claimed damage? The insurer is liable for the mould remediation (and associated repairs) as identified by the complainants’ experts. That is because the available evidence shows, on balance, the work undertaken in response to the 2012 claim was inadequate to properly deal with the nature and extent of the water damage, specifically in relation to mould; and more damage resulted. Is the insurer required to pay compensation for other losses? Yes. While the policy itself does not cover consequential loss, AFCA can require the insurer to cover certain direct and indirect financial losses incurred as a result of its handling of the claim, as well as the cost of professional report fees. That is appropriate in this case. The complainants have experienced significant ongoing upset, inconvenience and concern over a number of years as a result of the insurer’s handling of the matter. Compensation of $5,400 for non-financial loss is also warranted in the circumstances. Why is the outcome fair? The policy provides a lifetime guarantee on work conducted by the insurer in response to a claim. It would not be fair for the insurer to avoid liability when the evidence shows the work, in this case, was not adequate to properly address the damage and was not consistent with relevant standards. It is also fair and appropriate, in the particular circumstances, that the insurer pay compensation for other losses which arose from its handling of the claim. 1.3 Determination This determination is substantially in favour of the complainant. The insurer is required to cover the cost of remediation and repair of the property, as set out in section 2.2 below. It is also required to pay the complainants $5,400 compensation for non-financial loss, $5,000 compensation for financial losses, and the costs (up to $5,000, plus statutory interest) of the complainants’ expert reports . Determination | Case number: 834082 Page 2 of 8 2 Reasons for determination 2.1 What is the extent of insurer’s liability for claimed damage? Complainants have the onus of establishing a valid claim There is no dispute the complainants were provided with a certificate of insurance (COI) and product disclosure statement (PDS) which set out the terms and conditions of cover. The onus is on the complainants to establish, on the balance of probabilities, they have a valid claim under the policy in order for it to respond. If the complainants do establish a valid claim, the onus then shifts to the insurer to show it is entitled to refuse or limit liability. The policy covers specified insured events, including flood and storm. That cover is subject to terms, conditions and exclusions. The policy also provides that if the insurer undertakes repairs in response to a claim, it guarantees the quality of materials and workmanship during the lifetime of the building. The current claim and complaint is essentially that all the appropriate repairs to the damage from the 2012 claim have not been carried out, or that they were carried out in a substandard or incomplete manner. Insurer undertook work following the lodgement of 2012 claim There is no dispute the complainants had a valid claim for the November 2012 water damage, which in turn caused mould in the property. When lodging that claim, the complainants are reported as having said: The storm occurred this morning. Water has gone into the wall and flooded the bedroom downstairs and the carpet is wet. Storeroom under the stairs and storeroom in the garage carpet is damaged and some items in the store-room are damaged. It appears the insurer promptly arranged for repairs/mould remediation work. When the restoration technician, J attended on 17 November 2012 (the day the claim was lodged), the recorded moisture levels were 100% in the bedroom, hallway and spare room. The evidence indicates the work undertaken by J was:  four blow dryers (air movers) and one de-humidifier installed to dry the carpet and underlay, and storeroom  cleaning out the storeroom  replacing the underlay  removing and drying the carpet, which was then reinstalled  relocating furniture and removing contents  extracting water from the bedroom and hallway  applying anti-microbial to the affected surface areas. The complainants have pointed out no walls were removed, no electrical points were tested or removed, and the mould treatment was applied to the external surfaces only. After initial remediation work was completed, in March/April 2013 the complainants reported an ongoing musty small. No further testing, investigation or reporting was conducted, but the insurer arranged for restorer J to treat some spots (possibly mould) on the bedroom ceiling. Determination | Case number: 834082 Page 3 of 8 Insurer investigated further mould concerns but declined liability When the complainants made the current claim for further mould contamination in May 2018, the insurer assessed the property, but denied the claim. That was on the basis, it said, new testing by J found no visible mould inside the house, and the mould that was present was related to old mould growth on the ceiling and was most likely due to environmental issues (including contamination of the affected air-conditioner from the outside air, and moss/mould growth outside the bedroom). In other words, the insurer submits there was mould cross-contamination from external parts of property, and that was not related to the 2012 event. The insurer has provided reports from several experts who inspected the property, as well as internal reports, on the nature, cause and extent of the damage to the property. Mould specialist MCL identified mould at the property, but did not comment on the cause. Mould specialist VD, in March 2019, identified the downstairs bedroom as the greatest area of concern and contamination, and the likely source of mould concentrations found in adjacent areas. VD noted that could be due initially to the November 2012 event compromising the carpet and walls. While observing external geological drainage issues which ‘may’ be causing/contributing to the growth and spread of mould to date, VD said the overland flow aligns with the reports of how water entered the property in the November 2012 event. VD stated there were no clear signs of water damage inside the downstairs area when they inspected, noting that is consistent with either no water ingress since the 2012 event or the walls having been removed and no further water ingress due to a similar event/occurrence. They went on to state that if the external drainage was completely inadequate, it would be reasonable to expect to see signs of water damage caused since the 2012 event, as there ha d been several significant downpours between then and their 2019 assessment. VD concluded it was likely the water ingress in 2012 had been Category 3, or black water. On that basis, VD said they would have expected more remedial action to have been undertaken than what was reported: for example, VD noted evidence was not available that ‘complete drying’ or remediation in accordance with applicable building standards had been carried o ut by the original restoration company (J); they recommended (amongst other things) stripping and replacing carpet and walls with new materials. The insurer’s builder AB also inspected and suggested the drainage at the rear of the property was inadequate, and would be unable to disperse large volumes of water during periods of heavy or prolonged rain. The insurer submits there was ongoing water ingress from seepage, and so there were maintenance, as well as environmental, issues which caused the mould. The insurer points out the policy excludes cover for wear and tear and gradual deterioration, including mould; as well as for water seepage. I note, however, VD’s observations about the drainage (above) do not clearly support AB’s or the insurer’s conclusion on that issue. Determination | Case number: 834082 Page 4 of 8 Complainants have provided persuasive expert reports In December 2018 , the complainants’ builder BR found mould in the wall cavity and under the carpet. A brief statement from the complainants’ mould restorer , NL, supports VD’s observations about the need to fully remove Category 3 water-affected carpet and walls, which had not been done in this case. The complainants have also provided detailed and comprehensive independent expert reports from mould specialist/microbiologist IBS and building consultant BIC. In December 2019, IBS conducted an intrusive visual assessment to detect hidden mould growth and water damage, and also included air and surface mould sampling, material moisture testing, relative humidity and temperature monitoring. IBS reported ‘t he airborne results indicated chronic indoor mould amplification in the downstairs bedroom area. Surface mould concentrations were rated as either elevated, contaminated or extremely contaminated. The presence of visible mould, fungal genera identified and the condition of building materials indicated long-term water dam age’. Their scope of work/recommendations for remediation of the affected downstairs area, in accordance with the relevant mould remediation standards, involved safe removal of affected building materials (including walls) under containment and using HEPA filtrations, followed by HEPA cleaning and then post-remediation testing. IBS did not identify areas of concern in the upstairs of the property. I note the insurer has not provided expert responses to the IBS report. In January 2020, BIC inspected the site. They reviewed and provided their opinion on the available information, including the various experts’ reports and on the remedial work performed to date (by reference to relevant standards). They also made recommendations for additional testing and provided a scope of remediation work necessary to address the mould arising from what they effectively concluded was the original storm event. At the time of inspection, BIC did not observe any evidence of current abnormal moisture conditions, or damage consistent with ongoing flooding and/or rising damp. BIC was also of the opinion that the surface drainage around the building was adequate for catchment of stormwater under normal conditions , and specifically refuted AB’s view of the drainage . Based on the reports and testing results, B IC ‘confidently [concluded]’ that the mould presence identified was the result of ‘black water flooding through the bedroom during the 2012 weather event’ , together with the scope of remedial work carried out by the insurer, which did not conform to the relevant water damage restoration standards applicable at the time the insurer carried out the work. Those standards required, amongst other steps, the removal and replacement of wall linings and framing, skirtings and all soft furnishings and carpets, followed by proper sanitising of the entire affected area. BIC stated the building was not currently safe for occupation until the mould was correctly remediated, and in the meantime it posed health hazards for occupants. They agreed with the scope of work proposed by IBS. Available evidence shows, on balance, insurer’s 2012 work was inadequate The complainants’ expert reports are consistent, comprehensive and detailed. They persuasively address the relevant issues around the likely cause, nature and duration of the Determination | Case number: 834082 Page 5 of 8 damage, and the suitability of the initial repair/remediation work. I am satisfied the experts are appropriately experienced and qualified to report as they have done. I am satisfied, given that compelling expert evidence, it is more likely than not that the current mould-affected condition of the property is the result of the 2012 insured storm event, exacerbated by inadequate remediation work by the insurer in response to that initial water damage. That means the insurer is liable for full remediation and repair of the water- and mould-related damage arising from the 2012 event and the inadequate repairs conducted in response to that event. The required scope of works should be based on the recommendations of IBS, as supported by BIC. I note the scope and recommendations only identify work in the downstairs area. That includes treatment/replacement of affected contents. Cash settlement is appropriate in the circumstances The complainants have provided two quotes for repairs from restorer NLR, dated September 2020. These are stated as being based on NLR’s own onsite visit, and the reports of IBS and BIC. One is for work in the lower level of the property only, and the second has been amended to include (at the complainants ’ request) remediation of the upper level to ‘remove any secondary contamination’. I note, however, none of the available expert reports identified contamination of concern in the upper level. It therefore appears the complainants requested that as a precautionary measure, which is not unreasonable in the circumstances, but which is not sufficient in itself to impose liability on the insurer for that additional work. I understand that the complainants may have subsequently attended to remediation work at their own cost. It is not clear when that was done, the scope of that work or the precise cost. If the claim-related work has been completed, the complainants are required to provide the insurer with reasonable evidence and details of the costs incurred (such as itemised paid invoices) and the scope of the work undertaken. The insurer is then required to reimburse the complainants for those costs, together with statutory interest on the amount(s), calculated from the date they were paid by the complainants to the date of settlement. To be clear, the insurer is only liable for remediation/repair of the damage arising from the 2012 event and the subsequent inadequate repairs, as identified by IBS/BIC. That means, based on the available evidence, the insurer is not liable for remediation work to the upper level. If any aspects of the work have not yet been completed, the insurer is required to cover that by making a cash settlement. The cash settlement is to be based on a current itemised quote from an appropriate service provider to be obtained by the complainants. 2.2 Is insurer required to pay compensation for other losses? Complainants seek compensation for other losses The complainants have expressed significant concerns about their health which they attribute to the mould at the property. They say the health issues (first reported in 2016/2017) have meant they have had to move out of the home and incur extra accommodation costs as a result. They say they have also been prevented from renting it out because of the presence of mould. They submit that the deteriorated health of the female complainant has also meant she has been limited in her ability to engage in paid employment. Determination | Case number: 834082 Page 6 of 8 Compensation for non-financial loss is warranted Under the AFCA Rules, complainants may be compensated for non-financial loss (up to a maximum of $5,400) in circumstances where they have experienced an unusual degree or extent of physical inconvenience, time taken to resolve the situation, or interference with their expectation of enjoyment or peace of mind. There were serious shortcomings in the insurer’s initial treatment of the claim -related damage in 2012/2013. Over subsequent years, that has continued to have a significant impact on the complainants, including in terms of health concerns, and uncertainty around their living arrangements and income. In the circumstances, I consider an award of $5,400 is fair and appropriate. Compensation for certain financial losses is warranted in the circumstances The policy excludes cover for consequential loss. However, under our Rules, AFCA may award compensation for certain financial losses (up to prescribed limits) where that is the result of the insurer’s handling of a claim. I consider that to be appropriate here. The complainants are claiming both loss of rent and their own accommodation costs, for various periods since the 2012 claim arose. They are not entitled to both, and specifics of those costs have not been provided. I do accept, however, they had a tenant in occupation for a time after the 2012 event, and were themselves living there intermittently. I am satisfied, on balance, that they have suffered financial loss because of the now confirmed health risks of living in the unremediated property. I consider it fair in the circumstances that the insurer pays $5,400 compensation for those financial losses. To be clear, I am not satisfied, on the available evidence, that the complainants have established an entitlement for lost wages being claimed from 2013. Insurer liable for complainants’ expert report fees The complainants have also obtained expert reports from BIC and IBS which assisted in the resolution of the complaint in their favour. Applying our Rules, I am satisfied they are entitled to reimbursement of those professional costs up to a limit of $5,000. The complainants are required to provide the insurer with evidence of the costs incurred and their payment for those reports. Upon receipt of reasonable evidence of those costs, the insurer is required to reimburse the amount(s) paid, up to a maximum of $5,000, together with statutory interest calculated from the date the complainants paid to the date of settlement. 2.3 Why is the outcome fair? It would not be fair for the insurer to avoid liability for the quality and adequacy of repairs it conducted in response to the 2012 claim. It is liable for the remediation and repair required because of that, and it is also fair that it compensate the complainants for other losses that have arisen as a result. Determination | Case number: 834082 Page 7 of 8 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 Relevant policy extracts Lifetime guarantee on building repairs When we repair or rebuild the building, we guarantee the quality of materials and workmanship of that work for the lifetime of the building if we: • authorise; • arrange; and • pay the builder or repairer directly for this work. What we guarantee We guarantee the material used and standard of the workmanship to be free of defects. If a defect arises in the lifetime of the building as a result of poor quality workmanship or use of incorrect materials, then we will rectify the problem. Determination | Case number: 834082 Page 8 of 8 This guarantee does not apply: • to repairs you authorise or make yourself; • to loss, damage or failure of any electrical or mechanica l appliances or machines; • to wear and tear consistent with normal gradual deterioration of the building (e.g. paint peeling off after its expected life cycle, wood rotting from moisture in the air or ground, roofs weathering or a hot water tank leaking after its guaranteed life); … What we do not cover – general exclusions You are not covered under any section of your policy for damage, loss, cost or legal liability that is caused by, arises from or involves: Consequential losses (financial and non-financial loss) or extra costs following an incident covered by your policy, including: • loss of income or wages;… Wear, tear and gradual deterioration wear, tear, rust, fading, rising damp, mould, mildew, corrosion, rot, action of light or gradual deterioration such as, but not limited to: • tiles and their adhesive or grouting breaking down; • weathering of roof tiles or roof ridge capping; • gradual weathering and breakdown of bricks, mortar or concrete…

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.