Home / Suncorp Group / Determination 831475
Determination 831475
Loss of rent beyond policy limit and delayed repair and decontamination of insured property
Summary
The landlord insurer accepted a property damage claim and agreed to complete repairs and decontamination, but repairs were protracted. AFCA found the insurer's experts' failings meant the 52-week loss of rent limit should not apply and ordered an additional 52 weeks of loss of rent plus $5,400 non-financial loss compensation.
Where the insurer failed to complete repairs within a reasonable time due to its own representatives' inadequate work, it would be unfair to rely on the policy's 52-week loss of rent limit.
Issues
- Repairs or contractors primary · upheld
“insurer and its representatives did not have a proper understanding of the amount and type of the damage and the extent of decontamination and remediation required”
- Poor claim handling secondary · upheld
“the recommendations of VA have not been followed from the beginning”
- Delay secondary · upheld
“It is clear to me that repairs have not been completed in a reasonable time frame.”
Subjects and remedies
home or building damagepay compensationpay non financial lossrepair or rectify
Text of the determination
Determination
Case number 831475
Financial firm AAI Limited
Determination | Case number: 831475 Page 1 of 5
Case number: 831475 19 May 2022
1 Determination overview
1.1 Complaint
This complaint relates to a claim by the complainant under his landlord insurance policy held
with the financial firm (insurer), for damage to the insured property.
The insurer accepted the claim but a dispute continues.
The claim has been the subject of two previous determinations issued by AFCA, 669081 and
735565.
The insurer has agreed to complete the repair and decontamination at the property, but the
complainant seeks loss of rent beyond the policy limit and non-financial loss compensation.
1.2 Issues and key findings
Is the complainant entitled to loss of rent beyond the policy limit?
Yes. Given the exchanged material the insurer is required to pay loss of rent beyond the
policy limit, in accordance with the provisions of this determination.
Is the complainant entitled to non-financial loss compensation?
Yes. The insurer is required to pay the complainant non-financial loss compensation of
$5,400.
Why is the outcome fair?
The outcome is fair given the circumstances of this claim and the delays that have resulted.
1.3 Determination
This determination is in favour of the complainant.
The insurer is required to pay additional loss of rent in accordance with the provisions of this
determination.
The insurer is required to pay the complainant the further amount of $5,400, for non-financial
loss compensation.
Determination | Case number: 831475 Page 2 of 5
2 Reasons for determination
There has been a full exchange of all material information relied on for the purposes of this
determination and each party has had the opportunity to address any issues raised by the
other.
This complaint has been determined based on what is fair in all the circumstances, having
regard to the relevant law, good industry practice, codes of practice and previous decisions
where applicable.
While the parties have raised numerous issues in their submissions, for the purposes of this
determination commentary has been restricted to those issues considered directly relevant to
the outcome only.
2.1 Is the complainant entitled to loss of rent beyond the policy
limit?
Coverage of the policy
The complainant’s landlord insurance policy provides cover for loss or damage at the insured
address caused by an insured event during the period of insurance.
The coverage provided by the policy is subject to conditions, limitations, and exclusions.
The full details of the policy coverage, conditions, limitations, and exclusions are contained
within the Product Disclosure Statement (PDS) and Certificate of Insurance (COI).
The coverage provided by the policy extends to loss of rent.
The PDS details:
Additional features
….
Loss of rent following an insured event
We Cover
….
The longest period we will provide cover for is 52 weeks and the most we will pay
under the feature is:
10% of the property sum insured for a property claim;
….
As the insurer has accepted the claim, I am satisfied that the onus transfers to the insurer to
establish the application of this limitation to determine its obligations to the complainant
regarding the claim for loss of rent.
Circumstances of the loss and claim
As stated, the insurer has accepted the complainant ’s claim and agreed to complete repairs
and decontamination of the property.
Determination | Case number: 831475 Page 3 of 5
The exchanged material confirms that the insurer has already paid the complainant loss of
rent up to the policy limit of 52 weeks. The loss of rent was paid from 3 May 2019.
The exchanged material confirms that repair and remediation of the damage at the property
continued until 2 March 2022, when hygienist (VA) provided a clearance certificate.
The complainant seeks payment of loss of rent beyond the policy limit of 52 weeks.
The insurer says that 52 weeks loss of rent is the maximum extent of its policy obligation.
I am satisfied that the resolution of this matter has been protracted, partly due to the nature of
the damage and the required repair and decontamination. Part of the decontamination related
to methamphetamine use at the property.
However, I am satisfied that the insurer and its representatives did not have a proper
understanding of the amount and type of the damage and the extent of decontamination and
remediation required.
The complainant’s original scope of works is dated 2 July 2019. This scope of works allowed
for removal of electrical items, fans, vents, plastic fixtures and fittings and to flush plumbing.
These items were also part of VA’s recommendation of 22 Oct ober 2021.
The insurer appointed a cleaning and restoration specialist (ST), on 11 December 2020. The
exhaust fans and electrical items were not removed until 29 April 2021.
On 10 September 2021, the insurer appointed a disaster recovery service (AM), as it was
clear that ST was not completing the work required in either an efficient or adequate way.
AM details the various earlier failings and the work still required.
In its report dated 22 October 2021, AM confirmed that floor coverings in the kitchen, laundry
and bathroom areas required removal. Further, high affinity surfaces such as internal doors,
varnished timber panelling, window architraves, door jambs and plastic toilet seat and cistern
also required removal.
In its report dated 9 February 2022, AM recommended the removal and replacement of the
same items, including doors, panelling architraves and door jambs, as previous cleaning had
been unsuccessful in reducing Methamphetamine levels to an acceptable level.
Conclusion
I am satisfied that the recommendations of VA have not been followed from the beginning.
Indeed, the insurer’s latest scope of works does not contain replacement of all the high affinity
surfaces referred to above or in all recommended areas of the property. According to VA, this
leaves open the possibility that in some isolated cases there can be an increase in
Methamphetamine levels over time.
Whilst I accept that VA confirms that the risk of this is low, I am satisfied that the risk that
does exist, albeit low, is there because of the work, or lack of work, carried out by the
insurer’s remediatio n and decontamination experts.
I am also satisfied that the delays in the remediation and decontamination of the property are
the result of the work, o r no work, carried out by the insurer’s remediation and
decontamination experts.
The policy of ins urance that provides coverage for complainant’s property, limits loss of rent
to a period of 52 weeks. However, I am satisfied that in circumstances where the insurer
Determination | Case number: 831475 Page 4 of 5
and/or its representations have not conducted the repairs in an efficient or adequate way,
leading to an excessive delay, it would not be fair to the complainant to restrict loss of rent to
the policy limit of 52 weeks.
It is accepted insurance law and consistent with the terms of the PDS that the insurer is
required to complete repairs in a reasonable timeframe. Where the insurer has not complied
with this obligation, it would not be fair to allow the insurer to rely upon a separate policy
provision to limit its obligations to the complainant for loss of rent.
It is clear to me that repairs have not been completed in a reasonable time frame.
Based upon the exchanged material, I am satisfied it would be fair that the insurer pays the
complainant an additional 52 weeks loss of rent, beyond the policy limit of 52 weeks.
2.2 Is the complainant entitled to non-financial loss
compensation?
AFCA may award compensation for non-financial loss
Under AFCA’s Rules, we may award compensati on (capped at $5,400) for non-financial loss
where a complainant has suffered an unusual degree or extent of physical inconvenience,
time taken to resolve the situation or interference with their expectation of enjoyment or peace
of mind.
However, we adopt a conservative approach to the award of compensation for non-financial
loss. We expect complainants to be moderately robust and bear the usual stress and
inconvenience associated with an insurance claim.
I have already detailed my concerns regarding the actions of the insurer’s representatives
during this protracted claim.
From the exchanged material, it is also clear to me that those actions have not only delayed
the process, but also led to a great deal of stress and loss of enjoyment and peace of mind
for the complainant.
In the circumstances of this claim and this complaint, I am satisfied that it would be fair that
the insurer pays the complainant $5,400 for non-financial loss compensation.
2.3 Why is the outcome fair?
The outcome is fair given the circumstances of this claim and the delays that have resulted.
Determination | Case number: 831475 Page 5 of 5
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the avai lable
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.