Cyclone damage claim: scope and cash settlement of repairs, debris removal, temporary accommodation, contents and delay
Text of the determination
Determination
Case number 831121
Financial firm AAI Limited
Determination | Case number: 831121 Page 2 of 12
Case number: 831121 21 July 2022
1 Determination overview
1.1 Complaint
The complainant holds home and contents insurance with the financial firm (the insurer). On
12 April 2021, the complainant lodged a claim on the policy after the insured property and
contents sustained damage following a cyclone.
The insurer accepted the claim and has taken steps to assess and rectify the damage.
However, the complainant says that the insurer has taken too long to do so, has not
adequately scoped the work required to return the property to its pre-damaged state and has
not sufficiently covered him for loss of contents.
The complainant wants the insurer to:
cash settle him for items not included or adequately included in the insurer’s scope of
works (SOW)
pay additional debris removal (DR) and temporary accommodation (TA) costs
pay out the remainder of the contents sum insured
pay non-financial loss compensation for the stress and inconvenience it has caused.
1.2 Issues and key findings
Is the complainant entitled to additional amounts for repairs?
Yes. The insurer is to cash settle additional repairs for the totals specified in section 2.1 of
this determination plus a 25% contingencies uplift. The insurer is also to reimburse $5,099.43
for plumbing hardware. The insurer does not have to pay the rest of the plumbing claim until
further supporting documents are provided. The insurer is not required to pay anything more
for the external blinds or pay for replacing the corroded flashing window. Other previously
agreed but yet to be finalised repairs are to be cash settled.
Is the insurer required to pay additional DR and TA costs?
No. The invoices the complainant relies on in support of his claims for DR and TA costs are
insufficient. Until the complainant provides adequate supporting documents, the insurer is not
required to assess or pay the additional DR and TA costs claims.
Is the insurer currently required to pay more for the contents claim?
No. The complainant has not yet submitted adequate proof of loss to justify payment of
additional amounts for loss of contents. Until such time as he does, the insurer is not required
to assess or pay the additional contents loss claim.
Is the complainant entitled to non-financial loss compensation?
Yes. The insurer’s claims handling and delays have been unreasonable and have caused the
complainant significant stress and inconvenience. It is to pay the complainant $4,000 in non-
financial loss compensation.
Determination | Case number: 831121 Page 3 of 12
Why is the outcome fair?
The insurer has not adequately assessed the repairs required as a result of the cyclone. It is
fair that the insurer cash settles the cost of additional repairs plus a 25% contingencies uplift.
However, it would not be fair to require the insurer to pay additional amounts for DR, TA or
contents until the complainant provides adequate proof of loss. Given the insurer’s poor claim
handling, it is fair that the complainant receives non-financial loss compensation.
1.3 Determination
This determination is substantially in favour of the complainant.
Within 21 days of receiving written notice that the complainant accepts this determination (the
notice), the insurer is to pay him:
$45,851.69 for the additional repairs (the total of the amounts set out in section 2.1 of this
determination, plus 25%)
$5,099.43 by way of reimbursement for plumbing fixtures and fittings
$4,000.00 in non-financial loss compensation.
Upon the complainant submitting sufficient invoices relating to the additional DR and TA costs
claimed and the remainder of the plumbing claim, the insurer is to assess those claims
pursuant to the terms of the policy.
Upon the complainant submitting proof of loss relating to the additional items of contents
claimed, the insurer is to assess those claims pursuant to the terms of the policy.
To the extent that the parties previously agreed in writing to resolve other aspects of the claim
not dealt with in this determination, but the item has not been provided or the work
undertaken, the insurer is to obtain within 21 days of receiving the notice, a current actionable
quote for the cost of each item and the cost of completing the work. Within 14 days of
receiving the quotes, the insurer is to pay the complainant:
the cost of the item(s)
the cost of completing the work, plus a 25% contingencies uplift.
Determination | Case number: 831121 Page 4 of 12
2 Reasons for determination
The relationship between the parties has broken down. In the circumstances, it is in the best
interests of both parties for a determination to be made that as far as possible concludes the
claim and the complaint. Unfortunately, the available information does not enable an
immediate final resolution of all issues, meaning further investigations are required. The
parties are to work collaboratively to bring those aspects to prompt finalisation.
2.1 Is complainant entitled to additional amounts for repairs?
Yes. The insurer is to cash settle additional repairs for the totals specified in section 2.1 of
this determination plus a 25% contingencies uplift. The insurer is also to reimburse $5,099.43
for plumbing hardware. The insurer does not have to pay the rest of the plumbing claim until
further supporting documents are provided. The insurer is not required to pay anything more
for the external blinds or pay for replacing the corroded flashing window. Other previously
agreed but yet to be finalised repairs are to be cash settled.
Cyclone caused extensive damage
In April 2021, the rural area where the insured property is located was affected by a tropical
cyclone. The insured property sustained significant damage, including loss of its roof. This led
to internal water damage.
The insurer attended to a make safe which included tarping the entire roof structure.
However, further water ingress occurred due to strong winds and rain in the period
immediately after the cyclone. The damp conditions eventually resulted in mould growth
inside the house.
Parties disagree on repairs required
The insurer accepted the claim and appointed experts to assist it in assessing and rectifying
the damage. The experts included CR, engineers, and KB, builders. CR and KB have
provided a number of SOWs and quotes as additional damage has been identified over time.
Some of the required repair work has been undertaken by the insurer’s trades. The
complainant, who is a plumber, has attended to some repairs and seeks reimbursement of
the associated costs.
There has been ongoing debate between the parties as to the extent of repairs required and
the adequacy of some of the repairs un dertaken by the insurer’s trades. The situation has
been exacerbated by miscommunications involving the parties and the insurer’s trades,
additional items being added over time and periodic lack of clarity on the status of the work
done and to be done.
Nevertheless, by reference to a table of unresolved items submitted by the complainant on 31
May 2022 and subsequent communications between the parties, the remaining areas of
potential dispute now appear to be relatively limited. The disputed items and my
determination in relation to them is set out below.
Rendering
The complainant says that the property’s external rendering requires full restoration. He has
provided a quote dated 28 April 2022 from HH, plasterers, totalling $13,635.82. The
complainant says that prior to moving into the insured property approximately six weeks
Determination | Case number: 831121 Page 5 of 12
before the cyclone, he obtained a building inspection report which did not identify any issues
with the render.
The insurer accepted liability for some of the cracking damage to the upper part of the
external walls , based on a notation in CR’s SOW . KB confirmed it would not be able to carry
out and warrant repairs as it considered the materials originally used were unsuitable and
poorly applied. KB said patching work could be done but would not result in a good match
and the existing surface is unsuitable for painting.
The insurer has offered to pay the complainant $2,530 as a cash settlement, based on the
estimated cost of patching. It has indicated it is willing to consider paying a higher amount if
the complainant provides a supporting report.
The provided photos of the damage show that the property’s external walls have cracking, no t
just to upper sections. The upper and lower cracking appears to be similar and is clearly
observable. It is not obvious in the real estate advertisement for the property, which the
complainant purchased only a few months before the cyclone. It is also reasonable to accept
that the property inspection would have identified any pre-existing cracking.
The insurer has accepted liability for the some of the damage to the external walls. I am not
satisfied that it has adequately established that its liability should be as limited as it suggests
or that its requirement for the complainant to provide an expert report is reasonable in the
circumstances.
The insurer is required to cash settle the complainant based on HH’s quote.
Garage doors
The complainant wants the insurer to pay $7,249 plus $8,090 for the replacement of two
garage doors. He has provided three quotes dated 17 March 2022 from SO, supplier:
quote 13239 for panel lift door and secure opener replacement ‘as per existing’ - $4,870
plus GST ($5,357 inclusive of GST)
quote 13240, being quote 13239 plus $1,720 to upgrade the door to a version ‘Rated for
Region C cyclonic’ – total of $6,590 plus GST ($7,249 inclusive of GST)
q uote 13241, for panel lift door and secure opener ‘as per existing’ - $6,285 plus GST, plus
$1,720 to upgrade the door to a version ‘Rated for Region C cyclonic’ – total of $7,355 plus
GST ($8,090 inclusive of GST).
The insurer has agreed to cash settle the garage door claim for $5,357, in accordance with
SO’s quote 13239. It is not clear why the insurer has not made an offer relating to the second
garage door the subject of quote 12341.
As set out on page 54 of the product disclosure statement (PDS) applicable to the home
building insurance, the policy includes as an additional benefit cover for the reasonable and
necessary costs:
to make the damaged building components comply with current home building
regulations and laws. We only pay these costs if the building components
complied with home building regulations and laws when they were built or when
construction, repairs, renovations or alterations were undertaken.
There is no information available to confirm that the allowances in quotes 13240 and 13241
for upgrades are necessary to ensure the garage doors comply with home building
Determination | Case number: 831121 Page 6 of 12
regulations and laws. Even if that was the case, there is no information to indicate whether
the damaged garage doors originally complied with home building regulations and laws.
In the circumstances, the insurer is not required to pay for the upgrades. It is to cash settle
the garage door claims based on the combined total of the ‘per existing’ figures set out in
quotes 13240 and 13241, being $12,270.50 inclusive of GST ($5,357 plus $6,913.50).
Blinds, windows and security screens
The complainant seeks:
$1,500 for internal blinds
$9,000 for external blinds
$1,516 for window tinting
$3,797.20 to replace a window due to corroded flashing
$1,600 to replace two door security screens.
The complainant says that the internal and external blinds are part of the building rather than
contents so should be paid for under the building policy. The insurer disagrees, saying that
the blinds are contents and that it paid for them in the total it previously paid for contents.
Having reviewed the definitions of buildings and contents in the relevant PDSs, I agree with
the insurer that the blinds are contents. By reference to the list of contents the complainant
submitted and pursuant to which the insurer calculated the amount it has paid for contents,
the insurer has already paid $9,000 for external blinds but only $500 for the internal blinds.
It is reasonable that the insurer pays a further $1,000 for the internal blinds under the
contents policy. It is not required to pay anything more for the external blinds.
The complainant says the bedroom windows require tinting and relies on a quote from MW ,
supplier, totalling $1,516 (including travel expenses) for the cost to do so. The insurer says it
has installed grey glass, which is the closest match to the pre damaged glass.
The complainants say that the grey glass is ‘standard’ and not a reasonable match. By
reference to the complainant’s continuing dissatisfaction with the installed grey glass, it is
reasonable to conclude there are issues with its adequacy. In the circumstances, I consider it
is reasonable for the insurer to cash settle the window tinting claim based on MW’s quote.
The complainant says he incurred $3,797.20 in replacing a window which had been identified
as having a corroded flashing. The insurer says that it has not be shown the corrosion is a
result of the cyclone and the policy includes a general exclusion relating to corrosion. I accept
the insurer’s position not to cover the cost of the window’s replacement i s reasonable.
The complainant says the security screens for the front and back door require replacement.
He seeks $800 for each screen. The insurer says it is willing to consider the claim upon
provision of proof the screens were damaged in the cyclone.
The insurer has had ample time to assess the claim. Given the extent of damage generally
caused by the cyclone, it is reasonable to assume that it more likely than not it damaged the
screens. The insurer is to pay the $1,600 claimed.
Freestanding bar
The complainant seeks $3,000 for replacement of a damaged freestanding bar that was on
their deck. The complainant has disposed of the bar . The insurer ‘ confirms it accepts liability
for the cost of replacing the bar. The Insurer requests the Customer provide a quote for
consideration for cash settlement’.
Determination | Case number: 831121 Page 7 of 12
The insurer has had sufficient time to assess the cost to replace the bar. It has not submitted
that th e complainant’s estimate is unreasonable. It is fair that the insurer cash settles the bar
replacement claim based on the complainant’s estimate.
Hot water system and water pump
The complainant says he paid $600 for a hot water system. He also says that the water pump
the insurer provided was not the same brand as the pump that was damaged, and was
inferior. He says he paid $765 to replace the pump.
On 2 June 2021, the insurer paid the complainant a cash settlement of $465.30 for the hot
water system. On the available information, I am satisfied that was a sufficient allowance. The
insurer also says the pump supplied was an equivalent replacement and that it is not required
to provide the same brand of pump. As the complainant has not explained why the
replacement pump is inferior, the insurer is not required to pay anything further.
Kitchen appliances
The complainant seeks a total of $7,445 for k itchen appliances (oven, dishwasher, coffee
machine & gas cooktop) . He says that the items were damaged when stored offsite and/or
have not worked properly since installation.
The insurer has accepted the claim for the oven. It says that it does not have any evidence to
substantiate the claims for the other appliances. It says it is willing to consider any report that
the complainant provides in relation to them.
The insurer is to pay the amount claimed for the oven, being $1,299. As the complainant has
provided a photo showing that the gas cooktop no longer sits flat on the benchtop and has
bowed/crooked edges, I am satisfied that it should also pay the claimed cost of replacing it,
being $2,000.
The dishwasher and coffee machine are contents. As discussed further below, the insurer is
not required to pay additional amounts for contents until satisfactory proof of loss is provided.
Clothesline
The complainant seeks $360 to replace the clothesline. I accept it is likely the clothesline was
damaged by the cyclone. The insurer is required to pay this amount under the building policy.
Plumbing
The complainant seeks $1,030 to replace two showerheads. The insurer says that the
showerheads were not damaged so do not require replacement. Given the available
information, I accept the insurer’s submission.
In addition, the complainant seeks reimbursement of $10,449.43 for plumbing fixtures and
fittings he purchased and for his labour costs. He has provided invoices totalling $5,099.43 in
support. He says that he had to purchase the hardware as items that were removed during
repairs went missing.
The insurer invited the complainant to provide invoices for plumbing materials and parts for it
to reconcile against its records ‘to determine if any further payments are warranted’. The
invoices totalling $5,099.43 were provided on 24 May 2022. The insurer has had sufficient
time to raise any objections to them. It is to cash settle based on the amount of the invoices.
The insurer is not required to make any other payments towards the plumbing claim until the
complainant provides additional invoices or other supporting documents.
Determination | Case number: 831121 Page 8 of 12
Insurer is to pay a cash settlement plus a 25% contingency uplift
The PDS gives the insurer the option to pay (cash settle) an insured the cost of covered
repairs rather than attend to the repair work. However, the insurer must act reasonably in
choosing whether to exercise that option.
The relationship between the parties appears to have deteriorated to the point where it is no
longer functional. In the circumstances, I am satisfied that it is in the best interests of both
parties that the claim is as far as is reasonably possible resolved by way of a cash settlement
rather than the insurer attending to some or all of the required repairs.
When an insurer cash settles a claim, it transfers to the insured the risk that the cost of
repairs may unexpectedly increase and/or that additional works not quoted are required. The
insured a lso loses the insurer’s warranty that would apply to repairs arranged by the insurer.
Taking into account those matters, the complainant ’s relatively remote location and the
current challenges in obtaining trades, I am satisfied that an appropriate uplift to be applied is
25%.
In light of the matters set out above, the insurer is to cash settle the complainant based on the
following amounts:
$13,635.85 for rendering
$12,270.50 for the garage doors
$1,000 for the internal blinds (under the contents policy)
$1,516 for window tinting
$1,600 for the security screens
$3,000 for the freestanding bar
$3,299 for the oven and the gas cooktop
$360 for the clothesline.
Those amounts total $36,681.35. Allowing a 25% uplift, the amount payable is $45,851.69.
In addition, the insurer is to reimburse the complainant $5,099.43 for plumbing hardware.
The insurer is not required to pay any additional amount for the external blinds and is not
required to reimburse the complainant the cost of replacing the window with the corroded
flashing. Nor is it required to make any other payments towards the plumbing claim until the
complainant provides additional invoices or other supporting documents.
How previously agreed but uncompleted aspects of the claim are to be resolved
The repairs said to be required as a result of the cyclone has expanded over time and the
insurer has agreed to attend to additional work as a result. Unfortunately, the status of those
repairs cannot be established from the information the parties have provided.
Accordingly, to the extent that the parties previously agreed in writing to resolve other aspects
of the claim not dealt with in this determination, but the item has not been provided or the
work undertaken, the insurer is to obtain a current actionable quote for the cost of each item
and the cost of completing the work. After receiving the quotes, the insurer is to pay the
complainant:
the cost of the item(s)
the cost of completing the work, plus a 25% contingencies uplift.
Determination | Case number: 831121 Page 9 of 12
2.2 Is the insurer required to pay additional DR and TA?
No. The invoices the complainant relies on in support of his claims for DR and TA costs are
insufficient. Until the complainant provides adequate supporting documents, the insurer is not
required to assess or pay the additional DR and TA costs claims.
Complainant seeks payment of additional DR costs
The insurer has paid the complainant $590 for DR costs, based on KB’s estimate.
The complainant claims a further $15,690 in DR costs. In support, he has recently provided
an invoice addressed to the insurer which he prepared. The invoice covers:
labour provided by the complainant, family and friends at $30 per hour
bobcat hire fees for 32 hours at $150 per hour
tip fees for five deliveries at $66 per trailer.
Complainant is yet to establish entitlement to payment of additional DR costs
The building policy states that the cover includes as an additional benefit for ‘the reasonable
and necessary costs of demolishing and removing the damaged parts of the building from the
insured address.’
The insurer says it is willing to review the claim for additional DR costs but requires further
supporting documents to enable assessment.
I am satisfied it is reasonable for the insurer to require the complainant to provide additional
proof of payment (such as invoices, receipts or bank statements) of the claimed labour costs,
bobcat hire costs and tip fees. Upon provision of any such proof, the insurer is to assess the
claimed amounts in line with the policy’s terms.
Complainant seeks payment of additional TA costs
The insurer agreed to pay costs to support the complainant and his partner living on a bus on
the property rather than in TA at a separate location. The insurer attended to various
associated payments, including for a portable toilet, generator fuel and for water supply.
The complainant has recently provided an invoice addressed to the insurer for the cost of
hiring the bus, fuel costs to bring the bus to the insured property and travel expenses totalling
$24,820.75.
Complainant is yet to establish entitlement to payment of additional TA costs
The building policy PDS states that the cover provided includes up to 52 weeks of TA where
the insured property is damaged to the extent it cannot be lived in.
In relation to the invoice the complainant recently provided, the insurer says:
It is not clear to us whether the Customer hired the bus or how they came into it.
A search of the ABN on the invoice (which is the same font and presentation as
the invoice for removal of debris) does not indicate that the Customer has been
invoiced by a company which lets out buses. An ABN search shows [PS and PJS]
as the associated entity trading under a Family Partnership type. We would
appreciate clarity from the Customer as to who the [S’ s] are as [the company
referred on the invoice as the supplier] is also not affording us any insight as to
who has actually invoiced the Customer. We are not averse to considering
Determination | Case number: 831121 Page 10 of 12
temporary accommodation costs but the invoice presented by the Customer (in
addition to the one for removal of debris) is not GST-compliant.
I am satisfied that the insurer’s request for further information concerning the TA invoice is
reasonable. Upon the complainant providing a response as well as a GST compliant invoice,
the insurer is to assess the claime d TA amount in line with the policy’s terms.
2.3 Is insurer currently required to pay more for contents?
No. The complainant has not yet submitted adequate proof of loss to justify payment of
additional amounts for loss of contents. Until such time as he does, the insurer is not required
to assess or pay the additional contents loss claim.
Policy sets out proof of loss requirements
The requirements for proving a loss covered by the contents policy are set out on pages 73
and 74 of the applicable PDS as follows:
You must give us proof of loss, value and ownership of items claimed when we
request it.
Allowing us, a repairer or an expert appointed by us, to look at what is damaged is
usually all that is needed to prove your loss. Sometimes though we might ask you
to produce recent photographs of your contents or other evidence that proves the
extent of the loss you have suffered.
For lost, damaged or stolen items that are no longer available for ins pection… you
must validate your claim by giving us details of when and where they were
purchased and proof of ownership and value. The type of proof we might ask for
includes proof of purchase (e.g. a sales receipt that has the item description or
code, a purchase price, date purchased and where the item was purchased), a
valuation from a qualified professional valuer, original operating manual,
manufacturer’s box, certificate of authenticity, close -up photograph, proof of
inheritance and a full description of the item (e.g. brand, model etc.).
…
If you are unable to substantiate your claim, we might reduce or refuse your claim.
The PDS states on page 21 that the most the insurer ‘ will pay for loss or damage to all
contents arising from any one incident is the contents sum insured shown on [the] certificate
of insurance... ’
The sum insured for contents is $100,000.
Complainant yet to provide adequate proof of loss for further contents payment
In mid-2021, the complainant provided to the insurer a list of damaged contents with
estimated replacement costs totalling $64,770. Upon review, the insurer identified a number
of items included in the list which were not considered contents such as the oven, hot water
Determination | Case number: 831121 Page 11 of 12
system, air-conditioner, and gas cooktop. Upon subtracting these items, the insurer paid the
complainant $55,120 for contents.
The complainant submits he should be paid out the remainder of the contents sum insured
($44,880) because the insurer’s in itial assessment report dated 1 May 2021 includes the
statement ‘ Unfortunately the majority of the damaged content items were disposed of. ’
The insurer says:
while page 21 of the PDS refers to the contents sum insured as the most it will pay for loss
or damage to all contents arising from a single incident, that is a maximum potential payout
not a guaranteed sum
the complainant has not yet provided adequate proof of loss in accordance with the
policy’s requirements to justify a further amount for contents.
I am satisfied that the insurer’s position is correct. The assessor’s comment does not
establish an entitlement to pay out of the contents sum insured. Until such time as the
complainant provides adequate proof of loss, the insurer is not required to assess or pay the
additional contents loss claim.
2.4 Is complainant entitled to non-financial loss compensation?
Yes. The insurer’s claims handling and delays have been unreasonable and have caused the
complainant significant stress and inconvenience. It is to pay the complainant $4,000 in non-
financial loss compensation.
AFCA may award non-financial loss compensation in certain circumstances
Under paragraph D.3 of the AFCA Rules, we may award compensation for non-financial loss
(capped at $5,400) where the insure r’s actions have caused an unusual amount of:
physical inconvenience
time taken to resolve the situation
interference with the complainant’s expectation of enjoyment or peace of mind.
Insurer has caused stress and inconvenience
The complainant says that the insurer’s poor claims handling, delays and miscommunication
have caused he and his partner significant stress and inconvenience. Amongst other things,
he highlights the difficulties experienced in having to live in a bus for more than 12 months as
well as distress caused by not being adequately informed of developments.
I am satisfied that the insurer has not overall handled the claim in a sufficiently proactive and
efficient manner. Even allowing for proof of loss issues, the claim should have been further
progressed if not finalised within the 15 months since the cyclone. There is also evidence of
ongoing miscommunication leading to frustration and confusion.
The insurer is to pay the complainant $4,000 in non-financial loss compensation.
2.5 Why is the outcome fair?
The insurer has not adequately assessed the repairs required as a result of the cyclone. It is
fair that the insurer cash settles for the cost of additional repairs plus a 25% contingencies
uplift. However, it would not be fair to require the insurer to pay additional amounts for DR, TA
or contents until the complainant provides adequate proof of loss. Given the insurer’s poor
claim handling, it is fair that the complainant receives non-financial loss compensation.
Determination | Case number: 831121 Page 12 of 12
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. I have reviewed and considered
all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, I have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.