Flood damage claim partly declined as long-term pre-existing earth movement; claim preparation costs
Text of the determination
Determination
Case number 830241
Financial firm Allianz Australia Insurance Limited
Determination | Case number: 730453 Page 1 of 9
Case number: 830241 20 July 2022
1 Determination overview
1.1 Complaint
The complainant holds a business insurance policy (policy) with the financial firm (insurer).
The complainant lodged a claim against the policy for damage to the insured property (a
holiday park) caused in a flood event on or about 9 February 2020.
The insurer has accepted the claim. However, the insurer is seeking to limit its liability to only
that damage which it has assessed to be consistent with the claimed flood event. The insurer
has declined cover for damage which it says is not the result of the flood event but rather is
due to long term pre-existing issues, which is excluded under the policy.
The complainant disputes the insurer’s assessment of its liability and also seeks cover for
claim preparation costs. The complainant is represented by its broker ‘J’ in this complaint.
1.2 Issues and key findings
Is the insurer’s assessment of its liability under the claim reasonable?
Yes. The panel accepts, on balance, the insurer’s assessment of its liability and final claim
settlement offer of $62,586.56 (net of deductibles) for the damage covered under the policy is
fair in the circumstances. The information provided by the insurers appointed consultants
‘SW’ and ‘D’ is more persuasive when compared to the reports from consultants ‘AB’ and ‘TK’
appointed by the complainant.
Is the complainant entitled to claim preparation costs?
Yes. The panel is of the opinion it is fair in the circumstances that the complainant be
compensated for expenses relating to claim preparation given the complexity of the claim and
damage to multiple insured buildings. However, the panel believes a fair contribution to this
expense is $10,000 as opposed to the $18,166.06 claimed.
Why is the outcome fair?
The decision is fair because it is consistent with the policy provisions and is based on the
more persuasive supporting information and opinions provided by engineers SW. The
information from AB and TK lacks compelling supporting information and is light on details.
Given the complexity of the claim it is fair to require the insurer to contribute $10,000 towards
the complainant’s claim preparation costs.
1.3 Determination
This determination is substantially in favour of the insurer.
Within 14 days of the complainant’s acceptance of this determination, the insurer is to settle
the claim in line with section 2 of this determination.
Determination | Case number: 730453 Page 2 of 9
2 Reasons for determination
2.1 Is the insurer’s assessment of its liability under the claim
reasonable?
Yes. The panel is satisfied the available material shows not all the damage claimed is
because of the flood event. Rather, a significant portion of the damage noted to the insured
buildings is more likely than not due to factors excluded under the policy.
Complainant must establish a claimable loss
The complainant is required to show, on the balance of probabilities (that is more likely that
not) that the claim falls within the terms of the policy. This is commonly called a prima facie
claim.
Once the complainant establishes a claimable loss, the onus shifts to the insurer to show an
exclusion applies or it is otherwise entitled to deny the claim.
The policy covers property that is damaged at the premises during the period of insurance.
The policy defines ‘ damage ’ and ‘ damaged ’ as accidental physical damage, destruction or
loss. The relevant section of the policy does not define accidental loss or damage however
this is generally accepted to mean damage which occurs unexpectedly and unintentionally.
The panel accepts the property sustained damage that was unintended and unexpected.
Accordingly, the panel accepts the complainant has established a claimable loss given the
broad cover for accidental damage provided under the policy.
The insured property experienced flooding and associated damage
The insured property (a holiday park) was inundated with water during a flood event on 9
February 2020. The storms created a large amount of water that affected several cabins and
management buildings on the site. There is no dispute this event occurred.
The complainant says its employees consistently noted there were no pre-existing issues at
the property, and it was aware of the condition of the property. The complainant says the
insurer’s appointed engineers were not aware of the pre-loss condition of the insured property
and therefore their opinions are based on assumptions and not factual information.
The insurer has accepted there is some damage to a few of the insured cabins and buildings
consistent with flood damage. This included the rear decks of cabins 6 and 7, flooring in the
camp kitchen, replacement of one pier under cabin 5, lattice work surro unding the manager’s
residence and minor work to pumps. The remaining damage has been assessed to be the
result of long term pre-existing issues and damage, which is excluded under the policy.
The insurer has assessed its liability and offered/paid a total cash settlement of
$62,586.56(net of deductibles). The complainant, based on a scope of works and quote from
consultants TK, says the total cost of repairs for the flood damage is $265,513.96. This
includes claim preparation costs of $18,166.06.
Policy excludes damage due to earth movement subject to exceptions
The policy excludes damage caused by various types of earth movement, unless:
caused by a specific event (in this case storm or flood) and
the damage occurs within 72 hours of the event.
Determination | Case number: 730453 Page 3 of 9
There is a consistent view amongst the various consultants appointed to the claim that a
significant portion of the damage to insured building is because earth movement.
However, there is a dispute between the parties as to whether the damage subject of the
claim occurred within 72 hours of and due to the flood event in question. The insurer says
most of the damage noted to the insured building is consistent with long term ongoing earth
movement, which is excluded under the policy.
Parties’ experts disagree on causation and timing
SW, the first engineer to attend the insured property, says all the cabins have an open
subfloor without provisions for surface drainage or cross-fall. SW says this causes the soil
around the piers to become regularly wet resulting in long-term settlement. SW says this is
indicated by the existing packing of multiple floor bearers and piers. SW did not observe any
damage consistent with sudden movement from short-term settlement.
D observed previous timber joist/bearer strengthening works and cracking/rotting consistent
with long-term degradation in cabins 2-7 as well as the office. D says minor foundation
movement is associated with slightly reactive founding soils.
D observed previous packing between bearers and joists as well as the piers and bearers. D
did not find evidence of soil erosion in the underfloor areas of the cabins, suggesting it would
be unlikely the event caused any significant loss of founding material locally below the pier
locations.
AB having assessed the insured property formed the opinion that the flooding event has
caused significant damage to the cabins, campers kitchen floor and settlement of the
amenities building. AB says as the cabin structures are relatively light-weight and small in
area, therefore, it is unlikely differential settlement led to its current condition.
AB says, given the age of the structures; most of the long-term settlement would have already
taken effect prior to the flood event. Also, that given their age it is reasonable to expect there
would be present evidence of previous repairs and/or maintenance works. AB concludes all
the damage was caused by flood.
Relevant information from these consultants’ rep orts has been provided in section 3.3 below.
The information from SW and D is more persuasive
The panel notes AB ’s report mentions there is ‘ packing ’ of the subfloor in cabins 2-4 and 13,
which is consistent with long-term differential movement.
The expert reports indicate the cabins and buildings were built in the 1930s or 1940s, and
there is evidence of previous repairs and ongoing issues with drainage. This indicates an
ongoing issue rather than damage caused by a one-off flood event.
Significantly, D inspected the property around eight months after the event (October 2020),
and noted the appearance of new cracks in cabins 5, 7 and the office block. SW had attended
the property on 14 April 2020 and did not observe such damage. The panel accepts this
suggests soil related earth movement remains an ongoing issue at the property.
SW says it did not observe short-term settlement and the spring within the flooring is a result
of:
long-term settlement of the timber and brick piers
long-term moisture exposure and creep of timber bearers and joists.
Determination | Case number: 730453 Page 4 of 9
Having considered the multiple reports and photos made available by the various consultants,
the panel finds the reports from the insurer’s appointed consultants (in particular SW) to be
the more persuasive. The findings from SW and D have been well explained, reasoned and
supported by compelling information consistent with the damage noted to the insured
buildings.
The panel does not accept the information establishes, on balance, that the excluded damage
to the insured building has been shown to have occurred 72 hours immediately after the flood
event. Rather, most likely it has been occurring over an extended period and continues to
occur months later.
The panel has considered AB ’s reports, however, it finds there is an absence of persuasive
information and explanation in support of AB’s conclusions. The panel is not satisfied the
information from AB can reasonably be accepted to show any of the disputed damage
occurred in the 72 hours immediately after the flood event.
Given this, the panel is not satisfied the proposed repairs and quote from TK, based on AB ’s
findings, to be fair in the circumstances. The panel is satisfied the policy does not respond to
the damage the insurer had declined under the claim. It is fair in the circumstances to permit
the insurer to limit its liability under the claim in line with the findings of its appointed
consultants and policy provisions.
Tree removal costs not covered
The policy provides cover for tree branch removal if the tree has impacted the insured
property. The complainant seeks cover for the cost to remove two large eucalyptus trees
located at the property.
The insurer had declined cover for the cost to remove these trees. The insurer notes the trees
have not caused any damage to the insured property through impact or any other cause.
The panel is satisfied the trees have not fallen and impacted the insured property. Also,
having reviewed information from consultant ‘M’, the panel is not satisfied it h as been shown
the issues with these trees relate to or are caused by the flood event giving rise to the claim.
Rather, on balance, the trees require removal due to several previous contributing factors
including seasonal factors, previous drought conditions and fire storm.
The panel accepts it is fair that the insurer be entitled to rely on the policy provision to decline
cover for the cost to remove the two trees in question. costs.
2.2 Is the complainant entitled to claim preparation costs?
Yes. It is fair in the circumstances that the insurer be required to contribute to the
complainant’s claim preparation expense given the complexity of the claim.
Policy covers claim preparation costs in certain instances
The policy provides cover for costs necessarily and reasonably incurred for the preparation
and negotiation of a claim. The complainant is seeking $18,166.06 in claim preparation costs
having utilised consultants ‘L’s’ services in this regard.
The insurer does not consider these costs were necessarily or reasonably incurred. The
insurer says it had not agreed to these costs, however, it is willing to consider this further if
the complainant were to provide a detailed breakdown of each of the actions/services
performed by L.
Determination | Case number: 730453 Page 5 of 9
The panel notes there is no requirement under the policy for the complainant to have sought
the insurer’s consent prior to the appointment of L or relating to claim preparation costs. The
policy includes a benefit where there exists cover for the reasonable claim preparation costs.
The panel has reviewed the information from the complainant and is satisfied the invoice and
information provided by L in support of its claim preparation costs have been reasonably
broken down and itemised. However, the panel is of the view that the costs seem excessive
and it would not be fair to require the insurer to cover the full extent of the costs claimed.
In the interest of bring this matter to conclusion and considering what is fair in the
circumstances, the panel determines the insurer is to pay the complainant $10,000 towards
the claim preparation costs under the claim.
In the interest of completeness, the panel notes the complainant is also seeking
reimbursement of costs incurred in sourcing the consultants’ reports. The panel is of the
opinion this is a fair expectation in the circumstances. Subject to the complainant providing
reasonable information of payment or costs of the reports, the insurer is to reimburse the
complainant for these costs up to a maximum of $5,000.
Therefore, within 14 days of the complainant’s acceptance of this determination, the insurer is
to arrange payment to the complainant in line with this determination.
2.3 Why is the outcome fair?
The decision is fair because it is consistent with the policy provisions and is based on the
more persuasive supporting information and opinions provided by engineers SW. The
information from AB and TK lacks compelling supporting information and is light on details.
The available information indicates most of the damage claimed is due to a combination of
factors which have occurred over an extended period. Such damage is excluded from cover.
In the circumstances, the insurer ’ s cash settlement offer for the accepted damage in the
amount of $62,586.56 (net of deductibles) is fair.
The policy only provides cover for tree removal if it has impacted the insured property. There
is no evidence this occurred. Accordingly, the insurer should not be liable for this cost.
Given the complexity of the claim, it is fair that the insurer be required to contribute to the
complainant’s claim preparation costs and reimburse the complainant for costs, if any,
relating to the reports from AB and scope of works from TK.
Determination | Case number: 730453 Page 6 of 9
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel
includes:
an ombudsman
a member with significant experience in consumer and small business advocacy
a member with extensive experience in the insurance industry
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
3.2 Terms of the policy
Section Key points
Our Agreement
Subject to all of the terms and conditions
contained in Your Policy and payment of
1. Approved Claim Preparation Costs
In addition to the amount of cover provided by each
Policy Section, we will pay up to $25,000 for costs
Determination | Case number: 730453 Page 7 of 9
(or agreement to pay) the Premium, We
will provide You with the cov er shown in
the Cover Sections of Your Polic y up to
the amount shown in the Schedule or
other limits shown in Your Policy
necessarily and reasonably incurred for the preparation
and negotiation of a claim under a Policy Section, for
which We agree to indemnify You under the Policy. This
is in addition to the specified amount within the
applicable Cover Section.
Fire – Gold
Defi nitions
The following definitions shall apply to the
words used in this Cover Section .
Damage or Damaged means accidental physical
damage, destructio n or loss
Cover We will pay up to the Limit of Liability in accordance with
the Basis of Settlement for Property that is Damaged at
the Premises during the Period of Insurance.
Exclusions 3. We will not pay for Damage caused by or arising
from: […]
i. erosion, landslide, mudslide, rockslide, subsidence,
settling, seepage, shrinkage or expansion of earth,
vibration or other earth movement, unless caused by
or arising within 72 hours as a direct consequence of
a storm, earthquake, tsunami, subterranean fi re,
vol canic eruption, Flood if Optional Extension of
Cover 1. Flood has been taken, or wat er escaping
from a water main owned by a wat er supply authority
[sic] .
Ext ensions of Cover – A 11. Removal of Trees and Branches
We will pay the reasonable costs incurred by You to
remove and dispose of any branch or tree that has fallen
causing impact Damage to Property insured. We will also
pay the cost of stump removal when required.
3.3 Expert reports
Record Key points
Determination | Case number: 730453 Page 8 of 9
Insurer ’s expert
(DW )
Engineer R eport
13 - 10 - 2020
Cabins 2 – 7 (including the Office):
Access to the subfloor for most cabins was restricted . O bservations of the
subfloor were made through photographs.
T imber floor joists/bearers were in a poor condition in several loc ations , with
evidence of c racking/rotting likely associated with long term degradation.
Several mas onry piers had slight ‘ leans ’ from minor foundation movements.
There is evidence of previous strengthening works and packing between the top
of the existing bearers and the underside of the new/old timber floor joists over,
and between piers and bearers.
N o obvious evidence of soil erosion in the underfloor area (based on limited
visibility) to suggest any locali s ed soil erosion occurred following the event.
There is c racking within th e brick chimney in cabin 2 , with evidence of previous
patch repair.
Did not observe any damage or cracking throughout Cabin 3 and 4 consistent
with abrupt movement caused by short - term settlement from the subject flood
event.
D id not observe any noticeabl e gaps bet ween bearers and piers consistent with
short - term settlement.
The observed cracking within Cabin 3 and 4 is consistent with long - t erm
settlement of piers and general building movement unrelated to the subject
flooding event.
Cabins 10 – 14
Access to the subfloor was restricted at the time of inspection . Ob servations of
the subfloor beneath these cabins has been made through photographs .
There is evidence of packing bet ween the underside of the metal trusses and
the top of the masonry piers.
This suggests movement of the masonry piers has likely occurred in the past
and previous attempts to restore contact between the masonry piers and the
metal trusses over in these cabins has been undertaken.
N o obvious evidence of soil erosion in the underf loor area (based on limited
visibility) to suggest any locali s ed soil erosion had occurred due to the event.
No mortar existed between the masonry blocks used at the concret e block pier
locations. Therefore , these piers may be prone to increased movements
compared to mortar jointed masonry.
Observed minor cracking on the eastern wall of the main bedroom area in
Cabin 13 consistent with minor movement of the eastern metal north - south
spanning floor truss below . I n particular , the masonry pier at the SE corner of
the cabin was not providing support to the metal floor truss over.
The aged nature of the cracking (and the evidence of previous crack repair
works) suggests movement relating to the lack of support from the SE corner
pier has been occ urring for some time and the SE corner pier was likely not
supporting the metal truss prior to the cabin being painted about 2 years ago.
Determination | Case number: 730453 Page 9 of 9
Insurer’s expert
( SW )
Engineer r eport
24 - 04 - 2020
All cabins have an open subfloor without any provisions for surface drainage or
cross - fall.
During general rainfall , water can easily penetr ate into the subfloor areas and
ingress into the soil underlying the piers.
This process will cause the soil around piers to become regularly wet and be
subject to long - t erm settlement which is also indicated by the existing packin g
of multiple floor bearers and piers.
Since the floor bearers and joists are exposed to high moisture conditions
during general rainfall, this will result in the timber bearers and joists warping
and bowing o ver time.
Did not observe any damage or cracking throughout Cabins 2,3,4 that is
consistent with abrupt movement caused by short - term settlement from the
subject flood event.
L imited inspection of the Cabin 2,3,4 subfloor did not show any noticeable gaps
b etween bearers and piers consistent with short - term settlement.
Complainant’s
expert (AT )
Engineer r eport
31 - 08 - 20 20 &
0 8 - 04 - 20 21
Cabins , C2, C3, C4 - The floors are uneven and springy,
W orks for the supporting brick piers below will be required to attain adequate
function.
All piers found unstable to be replac ed with new and all new packing to be solid
dry packing.
AT d isagree s deflection of the timber flooring was caused by long - term
settlement of the piers unrelated to the flood event.
As the structure is relatively light - weight and small in area, it is unlikely
differe ntial settlement has led to its current condition . G iven the structures age,
the majority of long - term settlement has taken effect.
AT disagree s long - term degradation of the tim ber joists and bearers supporting
the flooring is responsible for the deflection observed.
Flooding has affected the supporting piers and caused the floor deflection.
Cabin C13
AT d isagree s lack of packing has occurred from long - term settlement.
The flood damage caused the piers to settle and separate from the packing,
which is a consistent issue related to defects from flooding .
Amenities Building
D ifferential settlement has been caused by the flooding which has affected the
foundations, leading to the c racking that was observed.