Insurer denied cover for disputed structural damage, relying on pre-inception cause and earth movement exclusions
Text of the determination
Determination
Case number 829432
Financial firm Allianz Australia Insurance Limited
Determination | Case number: 829432 Page 1 of 19
Case number: 829432 29 June 2023
1 Determination overview
1.1 Complaint
The complainant lodged a claim with the financial firm (insurer) after discovering extensive
structural building damage.
The insurer accepted the claim. However, it did not agree that stormwater escaping from the
downpipes caused all the claimed damage. The complainant disputed this and is seeking
cover for all the disputed damage.
The insurer has now taken the position that it is not required to cover any of the claimed loss,
mainly because the proximate cause of damage it previously accepted pre-dates the policy
inception. However, it says it will maintain its earlier offer of around $300,000. The
complainant is seeking up to the policy limit ($690,000 plus inflation) for building repairs, his
costs of dealing with the complaint and non-financial loss compensation.
1.2 Issues and key findings
Is the insurer required to cover the disputed damage?
Yes. The panel is satisfied the insurer must cover the disputed damage in accordance with
the findings and terms as outlined in section 2.1 of this determination.
Is the complainant entitled to recover his costs of dealing with the complaint?
Partially. For the reasons provided in section 2.2 of this determination, the panel is satisfied
the complainant is entitled to recover his expert report costs. The insurer should also
contribute $5,000 towards the costs of the complainant‟s representatives.
The panel is not satisfied the insurer should contribute to the complainant‟s legal fees.
1.3 Determination
This determination is substantially in favour of the complainant.
The insurer must settle the complainant‟s claim as set out in section 2.1.
The insurer must contribute to the complainant‟s professional costs as set out in section 2.2.
Determination | Case number: 829432 Page 2 of 19
2 Reasons for determination
2.1 Is the insurer required to cover the disputed damage?
Onus on complainant to establish a valid claim
In order to establish a valid claim the complainant must show, on the balance of probabilities
(that is, more likely than not), that the claimed damage was caused by an insured event
covered by the terms of the policy.
Where this is established, the burden of proof (onus) shifts to the insurer to establish a reason
to deny cover, either by way of the policy exclusions or on some other basis.
The complainant is insured for accidental loss or damage. This is not defined by the policy. In
insurance policies, this normally means loss or damage that is unforeseen and unexpected
from the insured‟s perspective.
The insurer has argued the proximate cause of damage pre-dates the policy inception, and
that it has been ongoing since construction. Further, it says it is entitled to rely on the
following policy exclusions to deny cover:
Accidental loss or accidental damage caused by … settling, shrinkage or any
movement of earth, erosion;
We will not pay claims for loss, dam age or liability arising from … Any event that
does not occur within the period of insurance;
Parties dispute cause, duration and extent of ground movement
The complainant relies on his engineers F and DA‟s findings to demonstrate his home
suffered building damage after a main stormwater pipe sitting outside his property failed (after
being crushed by horse traffic). He says this caused stormwater to backflow and surcharge
(escape) from downpipes during heavy rain and saturate the soil surrounding it. He says this
created abnormal soil moisture conditions which resulted in widespread ground movement,
leading to the sustained damage.
He says he first noticed cracks appearing in one of the bedrooms in late 2015, and says the
damage worsened and progressed to other areas in 2016.
He is seeking cover for the movement and cracking damage throughout the house, the
garage and driveway, the verandas and pool area paving. Further, he is seeking to recover
his cost to rectify the damage to the stormwater pipes. This is because he says the
stormwater system was affected by the initial failure.
In response to the complainant‟s position, the insurer says its experts‟ findings demonstrate
the stormwater outlet‟s failure occurred around 2007, long before the complainant purchased
the premises and it subsequently came on risk. Therefore, it can rely on the above exclusion
about events occurring outside the period of insurance to deny the whole claim.
Further, based on its experts‟ findings, the stormwater leak was likely limited to damage along
the front of the property. The insurer does not accept this caused the remaining claimed
damage. Instead, this was more likely to have occurred as a result of gradual, long-term
changes in soil moisture content from groundwater (referred to as „soil consolidation) . The
Determination | Case number: 829432 Page 3 of 19
insurer‟s experts also noted the drainage provisions to the rear of the property were
inadequate.
Accordingly, the insurer says the other damage falls within the exclusion of „settling,
shrinkage or any movement of earth‟ to deny cover. It also maintained historic evidence (real
estate photographs) demonstrate the driveway damage pre-dated the purchase of the
premises by the complainant.
In addition, following later expert reports obtained, the insurer notes the likely cause of all the
damage is soil consolidation which was ongoing since the premises was constructed.
Relevant extracts from the various expert reports are listed in section 3.2 of this
determination.
Satisfied complainant’s rebuttal evidence is compelling
The complainant‟s forensic engineer F assessed the cracking damage to the concrete
driveway after an onsite inspection.
While acknowledging the photo evidence demonstrates minor shrinkage cracking in this area,
likely caused by seasonal ground movement, F also accepted there would have been
significant leaks from the downpipe closest in proximity. F determined this was more likely the
proximate (dominant, efficient or operative) cause of the substantial damage to the concrete
driveway apron and garage floor slab.
F‟s evidence is consistent with the complainant‟s other engineer ‟s ( DA) opinion and findings.
DA also said the photo evidence relied upon by CS (insurer‟s engineer) to allege the driveway
damage pre-dated the period of insurance is different to the significant heave and resultant
damage arising from ground movement.
DA provided numerous reports on the property damage. D A‟s conclusion is that all of the
damage was proximately caused by the initial stormwater failure. Further, in a report dated 21
December 2022, DA provided a number of compelling arguments rebutting CS‟s findings.
These included the following.
DA‟s positio n regarding the extent of downpipe damage and surcharge from the downpipes
are logical and supported by the available evidence. In forming this view, DA conducted
additional testing to demonstrate there would be a considerable surcharge from the downpipe
spigots when the main outlet is blocked. Further, he provided photographs to support this,
along with photographs of the additional damage to downpipes 2 and 7.
Part of CS‟s concerns is that the stormwater drainage to the rear of the property was
inadequate or improperly done. DA identified several errors regarding this. First, DA said CS
incorrectly noted the catchment area to be 8,000m2 when it is more like 4,827m2. Second,
DA noted the ground does not fall towards the paving in the rear of the property. Therefore, a
spoon-drain was not required which was consistent with the plans drawn. This is contrary to
CS‟s view that a spoon drain was required . Third, there are two grated drains at the base of a
retaining wall that was not considered by CS as part of the rear drainage.
Fourth, DA conducted further testing to demonstrate the intercept drain installed could not be
considered shallow as alleged by CS. Instead, it had adequate capacity to handle a higher
degree of stormwater runoff than CS assumed.
DA id entified errors in CS‟s analysis of the soil profile. CS assumed all footings at the rear of
the property would be found on less reactive soil. DA referred to his analysis of the soil data
and notes:
Determination | Case number: 829432 Page 4 of 19
only a minor section of the premises‟ site foundation is likely to be on less (as opposed to
highly reactive) soil
rather, the entire foundation and pool area is vulnerable to widespread ground movement.
Further, DA relies on a soil test report from PG to support his position. He also refers to his
analysis of survey data to establish CS‟s findings are incorrect.
CS, and the insurer‟s other engineers, presumed the main stormwater pipe had been causing
leaks back in 2007, mainly due to healthier grass growth around that area. However, DA
noted the growth aligns with a communication pit at the same location. DA also noted similar
growth in other locations. This was also supported by the complainant in various photos
which showed inconsistent grass growth in other areas in the vicinity. There is also no
evidence of pre-existing damage at that time or shortly afterwards. Based on this, the panel is
not persuaded the insurer has shown the leaks occurred prior to it coming onto risk.
CS said the damage was likely caused by long term settlement since the building was
constructed. DA noted this is most unusual to have occurred so many years after the fact.
This is because such damage typically within the first 12 and 24 months. This is compelling.
DA also raised concerns the level surveys were flawed as they provided an inadequate
reference point. If a different reference point was used, then evident heave would have been
identified. No comment was made on this.
These arguments are compelling and undermine the insurer‟s expert evidence.
Satisfied insurer’s evidence is les s compelling in the given circumstances
The insurer had a reasonable opportunity to review DA‟s rebuttal evidence and provide a
response. However, the insurer did not approach IX for this purpose and instead approached
C instead. In response, C advised it was not able to provide an effective response, given CS
was no longer its employee and it did not have access to all the relevant source material and
supporting information.
Given this, the panel is satisfied the insurer had a fair opportunity to respond to DA‟s rebuttal
evidence. As previously explained, the panel is satisfied DA‟s findings, particularly those
expressed in its rebuttal report, are sufficiently compelling towards establishing the
complainan t‟s position. Considering this, the panel is persuaded by DA‟s findings about the
likely proximate cause of damage to the areas claimed.
Persuaded insurer not entitled to exclude cover for the claimed repairs
In view of the above the panel notes the following.
There is no dispute the damage being claimed was unforeseen and unintended by the
complainant. Given this, the complainant has established a valid claim.
The panel is not satisfied the insurer can demonstrate the claimed damage occurred prior to
the period of insurance. Further, the panel is not persuaded the damage has occurred due to
normal, or long- term, earth movement. Instead, the panel is persuaded by DA‟s expert
evidence that all the damage being claimed was proximately caused by the stormwater
failure.
Given this, the panel is persuaded the insurer must cover all the claimed resultant damage as
set out in DA‟s repair scope of works. This includes:
all the disputed damage covered in the original DA scope of works (13 December 2018)
the underpinning and other works recommended by DA (10 March 2019)
Determination | Case number: 829432 Page 5 of 19
the paving and landscaping work as scoped and quoted by MPL (15 February 2021).
The insurer paid just over $300,000 in purported settlement of its liability. This was done by
cheque around 9 October 2019, although the insurer now says it was provided on an ex-
gratia basis. Regardless, it is clear the insurer has agreed and paid the above amount so that
part of the claim is not in dispute.
The complainant is seeking cover for his cost to repair all the claimed damage, based on
DA‟s s cope of works, and subsequent information. This totalled around $881,949.18 at the
time of his submission dated 15 October 2021.
There is no information to show this estimated cost of DA‟s scope of works at that time was
unreasonable. Therefore, the panel accepts it fair to base a settlement on this.
However, whilst the panel accepts the complainant‟s quotes likely reflect a fair cost, a 10%
contingency should be added to factor in possible variances that such a complicated job may
arise. This would increase the cost to $970,144.10.
During the relevant period of insurance, the building was insured up to $690,000. However,
the policy contains this additional benefit:
If we agree to pay you for loss or damage to your buildings, we will increase your
sum insured for your buildings by the amount the Consumer Price Index (all
groups) has increased since you took out your policy or last renewed it
There is nothing in the policy that indicates CPI is limited by a certain timeframe. Instead,
based on the wording, it appears CPI is applied from when the policy is last renewed to when
the insurer agrees to pay for loss or damage.
Repair costs to be settled in this way
Considering the above, the panel accepts it is fair the insurer settles the building claim in the
following way.
The sum insured must be adjusted applying CPI. In calculating the CPI adjusted sum insured,
the panel considers it is fair to apply it from renewal until 15 December 2021. The panel has
chosen this latter date because it is two months after the complainant‟s submission dated 15
October 2021 that articulated the amount sought with quotes in support.
If the adjusted sum insured is less than the repair cost, which is likely to be the case, then the
insurer can rely on that amount to limit its liability.
The insurer must pay interest on any outstanding amount pursuant to section 57 of the
Insurance Contracts Act 1984 (the Act). Interest applies from 15 December 2021 until
payment is made.
Insurer must cover additional benefits as applicable
The complainant has sought $21,800 in alternative accommodation expenses and
$13,410.40 for furniture removal, storage and reinstatement.
The complainant estimated the temporary accommodation expenses at $800 per week for six
months. The six month time frame is based on DA‟s scope of works. Given the extent of
works, this appears reasonable. Regarding the rate, the insurer has not raised any
Determination | Case number: 829432 Page 6 of 19
submission about it being unreasonable. For the purposes of bringing finality to this long-
standing claim, the panel considers it fair to apply it.
Part of the complainant‟s claim includes $1,000 for pets and additional living expenses. The
insurer has not raised any submission on this as being unreasonable or inconsistent with the
policy. Again, for the purpose of bringing finality, the panel considers it fair to apply this.
No interest is payable on these amounts given they are estimates only.
The amount for furniture removal, storage and reinstatement was based on quotes obtained.
The insurer has not made a submission to say the amount claimed is unreasonable. The
need for this cost is substantiated by DA. The panel considers it fair to allow this. Interest is
also payable on the amount pursuant to section 57 of the Act given the quote is likely
outdated. Interest is applicable from 15 December 2021 until payment is made.
2.2 Is the complainant entitled to recover his costs of dealing
with the complaint?
Fair insurer covers cost of complainants’ expert reports
Under the AFCA Rules, we can require a financial firm to contribute to legal and other
professional costs a complainant incurred in making a complaint.
In considering whether the insurer should contribute to the complainant‟s costs, we take into
account the complexity of the complaint, whether the complainant needed to incur the costs
to understand or establish their claim, and whether the costs are reasonable in the
circumstances.
We will not require an insurer to contribute more than $5,000 to a complainant‟s professional
costs, unless special circumstances apply. The AFCA Operational Guidelines say special
circumstances may apply if the complaint is complex and involves a very large amount of
money.
The insurer denied the claim based on its experts‟ reports . The evidence and findings in these
reports was extremely complex. It would have been very difficult for the complainant to review
or challenge the insurer‟s decision without expert assistance. In the circumstances, it was
reasonable for the complainant to appoint DA to inspect the property, comment on the cause
of damage and challenge the insurer‟s experts‟ findings.
DA‟s reports identified relevant information that helped provide a better understanding of the
damage and its proximate cause. This, along with the supporting expert material DA
commissioned, was adequate to challenge the insurer‟s experts‟ findings , and assist the
complainant with establishing his position.
Accordingly, the panel is satisfied the insurer must cover the comp lainant‟s expert fees. This
includes all of DA‟s fees as well as the experts he engaged to assist. This is not subject to the
$5,000 cap. This is because the panel accepts special circumstances apply given the
complex technical matters raised, the substantive claim in dispute and the long-standing
history of the matter.
Complainant’s representative fees covered up to $5,000
The complainant is also seeking costs for its representatives. This included I, C and lawyers.
The total amount is at least over $60,000, significantly higher than the general cap of $5,000
for professional costs.
Determination | Case number: 829432 Page 7 of 19
In this regard, the panel note the following.
The panel acknowledges the complaint was complex. However, most of this complexity was
regarding the technical issue in dispute, being whether the leak was the proximate cause of
the damage claimed. It was on this basis the experts‟ fees were allowed in full.
The panel does acknowledge the complainant‟s representative did assist by facilitating this
and providing clear submissions. However, the panel does not consider an allowance of
these costs in full is fair and reasonable given the main assistance was the experts‟ evidence.
Further, regarding the legal costs, there were few submissions provided by lawyers or few
legal issues that required their input. The panel does not accept it is fair the insurer is
required to contribute to their costs.
Given all this, the panel does not accept it is fair that special circumstances apply regarding
the representatives‟ fees. Instead, the panel considers it fair the insurer contributes $5,000
towards the representative‟s fees .
2.3 Is the outcome fair?
Satisfied outcome is fair in all the circumstances
For the reasons provided in this determination, the panel is persuaded the outcome is
consistent with the applicable policy terms, the available information and a balanced
interpretation of the available evidence. Therefore, the panel accepts the outcome is fair in all
the circumstances.
Determination | Case number: 829432 Page 8 of 19
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel
includes:
an ombudsman
a member with significant experience in consumer and small business advocacy
a member with extensive experience in the insurance industry.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
Determination | Case number: 829432 Page 9 of 19
3.2 Report Extracts
Record Key points
PP Report 1 The stormwater system serving this property was found to be extensive and in
a poor state of repair. The owner advised his plumber had recently attended
and performed repairs to the drain connecting downpipe (DP) 2 and installation
of a sump adjacent to the septic system in the northern corner of the dwelling.
Other works also noted was the redirection of downpipes of the atta ched
carport above ground and running out to adjacent land on the south western
side.
We identified crushing/breakage of the stormwater drain at the crossover,
under test conditions water was leaking out of the ground and under a bush
adjacent. We would s uggest that this stormwater system most probably backs
up under moderate to heavy rain events. We would suggest the stormwater
system is, and has been, failing comprehensively for some time across the
front western elevation and that little, if not any, of the front roof water is
reaching the stormwater drain. We suggest the majority of the roof water is
running
into the ground surrounding all of the noted affected downpipes.
Downpipe 7
Flow testing through this downpipe showed it also joins the main storm water
network. With CCTV camera inspection and using pipe locating equipment, we
confirmed this pipe runs in a westerly direction approximately 1200mm
adjacent to the garage. At a point 1000mm past the front of the garage it then
travels through a 45° bend towards the main drain heading down to the
roadway. This pipe is laid very flat and predominantly holding water.
PP Report 2 From our previous investigation, we identified a drain serving the upstairs
ensuite that runs across the front of the property and joins the main sewer just
upstream of IOS2 before the septic tank. This drain passes through under the
front veranda and offsets with two 45deg bends. A test bung was placed
downstream of the second bend approximately 4.75 meters from IOS3 located
in t he garage. Under test this section failed at a rate of 4 litres per minute.
Subsequent CCTV camera inspection identified a break on the 45 degree
Bend at this location. This would support our previous testing and findings
where the complete drain failed to approximately the level of this break.
Determination | Case number: 829432 Page 10 of 19
Record Key points
IE Report
( 2017 ) The stormwater water drain serving DP1 , DP2 toward DP3 is in good
condition.
Testing of downpipes along the front of the home confirmed the Insured‟s
plumber‟s assertion of breakages below ground level at DP4 , DP5 and DP6 .
DP7 is connected to a drain along the western side of the home and connects
to the stormwater drain to the fro nt of the home downstream of DP4, DP5 and
DP6. The drain was noted to be poorly graded holding water but, as a result, is
unlikely to be leaking.
the sewer drain along the front of the house was isolated and tested with a
leak of 4 litres per minute detect ed approximately 4.75 metres downstream of
IOS3.
We would expect, with reference to the likely high reactive clay foundation soil
upon which the house is constructed, localised heaving may have occurred at
locations of identified stormwater leakages. This would be reflected as
increased levels in the perimeter level survey at leak locations. However, this
does not appear to be the case. In fact, the survey suggests the reduced levels
around the areas of reported stormwater fractures and likely spillage of t he
downpipe/ground adapter have not been influential. Therefore, in our opinion
the pipe fractures area “symptoms” of the settlement which has occurred along
the front elevation, not the cause.
The identified leaks to the stormwater pipework, while not app earing to have
resulted in an increased perimeter level, may have “propped up” the front and
rear elevation by regularly replenishing the soil moisture content over the
winter period. It should be noted the repair of the pipe will prevent water entry
which will cause the soil to dry, which may result in further settlement of the
front and rear elevation.
Similarly, the identified sewer leak 4.75 metres down stream of IOS3 does not
appear to be reflected in the level survey and therefore unlikely to have
i nfluenced dwelling behaviour. Nevertheless, it is recommended the fracture
repaired.
The large expanse of concrete driveway movement cannot be reasonably
connected to the stormwater or sewer pipe leakages and therefore it is more
likely that movement and cracking to the driveway is the result of seasonal and
or environmental conditions. With that said, the Insured‟s plumber‟s
observation of water coming up through the concrete driveway and pedestrian
path following rain would make it difficult to rule out there has not been any
possible influence While it cannot be ruled out that stormwater pipe leak at
DP6 has caused damage to the driveway paving at this isolated area, the
further wide spread cracking and movement of the concrete driveway away
from this z one is considered too far removed to be have been influenced the
extensive driveway movement.
To confirm our conclusions, we recommend a repeat level survey is completed
in April 2017 to determine influence environmental and seasonal factors may
have had since our initial survey. We also recommend that following repair the
stormwater and sewer drain the dwelling is monitored by undertaking repeat
level surveys at six monthly intervals to determine if there has been any
contributing influence of leaking pip ework.
Determination | Case number: 829432 Page 11 of 19
Record Key points
C Report 1
(2018)
It is clearly apparent, from the investigations undertaken by both the Insured‟s
Plumber and Priority Plumbing , that there is separation of downpipes 4 and 5
from the stormwater pipework along the house frontage, and shearing off at
the ground - line of downpipe 6. The occurrence of these damages remains
unknown and is difficult to establish.
In CRD‟s opinion, it is plausible that part of the recorded settlement (towards
the house frontage) can be attributable to saturation of the clay founding soils,
however, on the premise that the subject building (particularly the house
frontage) was constructed on fill (presumably engineered fill), and based on
the results of CRD‟s floor level survey, settlement of the structure towards the
hou se is considered to be principally attributed to consolidation (compaction)
of the fill material.
it is CRD‟s considered opinion that, over an extended period of time and under
significant rain storm event conditions, that stormwater deposited onto the ro of
area of the structure and which was serviced by downpipes 4, 5 and 6 along
the frontage of the house, has discharged into founding soils at the location of
separation or cracking to the stormwater pipework beneath the ground. This
process has increased the levels of water in the fill - containing foundation soils,
which has led to soil consolidation and settlement of the structure (and
pavement along house frontage).
In addition to soil consolidation, stormwater in the founding soils (at the
location of downpipe 6) has followed the natural ground contours of the site
and eroded and/or consolidated subbase soil material from beneath the
concrete pavement driveway. The loss of soil bearing from beneath the
concrete pavement driveway has essentially suspende d the pavement, and
upon the introduction of vehicular load, has cracked repeatedly. The damage
is considered to be compounded by the formation of further cracks in the
pavement, which allows for further stormwater entry, and further damage.
Furthermore, blockage of the main arterial stormwater pipe at the front
property boundary has, in CRD‟s opinion, caused backing - up of stormwater in
the stormwater management system, under high intensity rainfall events. This
process has introduced further stormwater i nto founding soils as accumulated
stormwater in the pipework is expelled from the pipework at downpipe base
adaptor locations, seeping further stormwater into the foundation soils and
causing further damage to concrete pavement. CRD attribute settlement of the
stencilled pathway leading to the entrance of the house to the sewer leak
directly below the pavement, as identified by Priority Plumbing.
Based on desktop findings with the assistance of historic street view imagery,
it is the opinion of CRD that th e single stormwater pipe outlet to the Pegasus
Court water table was in an inferior condition since as early as December
2007.
Based on stormwater management system design computations undertaken,
in accordance with the “Simplified Rational Method” within AS 3500.3 - 1990 –
National plumbing and drainage code, Part 3: Stormwater drainage, CRD are
of the opinion the stormwater pipe o utlet design at the time of construction was
satisfactory. Therefore, result damages to the dwelling are not considered to
be attributable to insufficient capacity of the installed stormwater management
Determination | Case number: 829432 Page 12 of 19
Record Key points
system.
In CRD‟ s opinion, the results of the floor l evel survey are consistent with those
of long - term consolidation (compaction) of the fill material the subject site was
founded on, exacerbated by leaking stormwater pipes along the frontage,
which has further consolidated foundation soils and led to furth er structure
settlement.
No evidence of heaving to the footing system was observed from the results of
the floor level survey.
DA Report
(2018)
At most downpipes the stormwater pipe was found to be broken below ground
level.
The entire stormwater system was replaced and upgraded subsequent to the
cracking being found in the house in 2015.
Review of Bureau of Meteorology (BoM) data f rom the nearest weather station
(Upper Hermitage – located approximately 2km from Yatala Vale) revealed
that annual r ainfall of 1,037mm was recorded for 2016, which was the highest
recorded at this station. The Upper Hermitage station has a median rainfall on
record of 652mm. Note also that other nearby weather stations had their
highest annual rainfall in 2016;
Soils o n the site contain highly reactive clays. These type of soils undergo
significant expansion when wet and similarly shrink significantly as the soils
dry
It is my opinion that during the initial period that the stormwater system had
been substantially bloc ked, collected rainwater had overflowed at downpipe
connections resulting in localised heave of the soils in proximity to these
downpipes.
This subsequently resulted in the relevant stormwater pipes breaking in these
locations, further exacerbating heave and damage whenever there was rain
I expect movement and cracking of the house to continue until the subsoils
have been allowed to dry to a stable moisture content
It is my opinion that the substantially blocked stormwater outlet at street level
caused by horse traffic is the proximate cause of:
Damage to the remainder of the stormwater network;
Heaving and cracking that has caused the observed damage to the
house and
garage;
Lifting, buckling and twisting of the pool;
Heave beneath the general pool area resulting in the pool area paving
becoming dishevelled etc.;
Lifting of the verandahs;
Damage to the driveway, apron and carport concrete;
The initial effect of the blockage has been that collected stormwater has
penetrated the soils in proximity to downpipes, resulting in localised heave,
Determination | Case number: 829432 Page 13 of 19
Record Key points
and subsequent further breaking of the stormwater pipes by this heave, in
turn causing increased moisture penetration beneath the house, adjacent
paving, concrete aprons and driveway, and extend ing throughout the en tire
pool area.
C Report 2
(2019)
It is noted the original stormwater drainange collection and disposal system
detailed a drainage swale around the bench of the building, to collect and
dispose of stormwater surface run - off away from the building (refer to Image
1).
It is understood that this drainage s wale does not exist.
Additionally it is noted that if the crushed and blocked pipe within the road
rerserve had been the cause of surcharging the system aroudn the building
then this would have been obvious to the insured prior to the event from
leakage a round the stormwater connections itno the ground around the
building prior to the claimed event.
DA Report
2019
(addendum)
The original stormwater system (and the general layout of the sewer drainage)
was designed by DSA .
The design of the ground water drainage around the bottom of the retaining
wall in the backyard included direction for all ground surfaces to fall away from
the house to be collected by an open drain around the base of the cut wall.
This drain was designed to drain to the front of the property (downhill) keeping
surface water away from the foundations.
The surface drainage system was subsequently replaced with an in - ground
grated stormwater system and an intercept drain above the backyard retaining
wall.
Furthermore, the stormwater system around the house has proven to be
suitably effective until such time s the street level outfall was damaged,
evidenced by the fact that there had been no cracking anywhere on the
property during your tenure until first observed in 2015.
The initi al effect of the blockage was that collected stormwater penetrated the
soils in proximity to downpipes, resulting in localised heave of the verandah
paving. The stormwater pipes… subsequently were broken from the initial
heave, and in turn resulted in incr eased moisture penetration beneath the
house, adjacent paving, concrete aprons and driveway, and extending through
the pool area.
F Report
( 2019 )
While I accept the concept that drying shrinkage cracking affects almost all
pavement slabs to some degree……I regard it as being more probable than
not in this case that the original garage floor shrinkage cracks have opened
wider and possibly extended longer as a result of downpipe leakage during the
heavy 2016 rainfall. I regard only three driveway slab panels at the
commencement of the driveway…to be unaffected by the downpipe leakage in
2016.
Determination | Case number: 829432 Page 14 of 19
Record Key points
I am of this opinion because in the very heavy 2016 rainfall the stormwate r
outlet pipe blockage would have been a far more significant influence in
generating a well above average volume of stormwater overflow from the two
proximate roof downpipe spigots located near the garage end of the premises.
The 2016 annual rainfall re corded…of 1037.9mm is 57% greater than the
annual rainfall (660.7mm that is derived from records…
In my opinion, this fact explains the otherwise satisfactory behaviour of the
garage and driveway pavement slabs…up until the time cracking was
observed by t he owners to have worsened significantly in 2016.
C Report
( 2022 )
Due to the time constraints between receiving your instructions on 24
December 2021 and the necessity to produce this Report by 7 January 2022,
a fully detailed investigation and response was not possible. As a
consequence, I have only provided opinions based on a brief desktop review
of supplied documentation. A significant volume of documentation was
provided for review, however, due to time constraints, not all of the supplied
documenta tion was reviewed prior to the production of this Report .
IX Report
(2022)
It is my understanding that the [DA] reporting claims, that due to the breakage,
stormwater filled the stormwater system and eventually discharged from exit
points (such as stormwater spigots at the base of downpipes) adjacent to the
residence. As a result of such discharge, founding clay soi ls had lost their
bearing strength causing the residence to be subjected to widespread
movement.
It is my opinion that damage to the stormwater pipe, noted to be the proximate
cause of all damage to the residence within the DAHI reporting, pre - dates the
Insured‟s purchase of the property.
Heaving of the soils under the concrete d riveway has occurred, with the [DA]
reporting suggesting that the leakages from the spigots caused the heaving
and the subsequent damage.
Floor level surveys indicate only the front portion of the residence (say the
front „third‟) has undergone any significant settlement.
Following the damage to the stormwater pipe, stormwater backflow within the
stormwater system was discharging from the spigots, particularly from
downpipe DP7‟s spigot, for several years prior to the Insured‟s purchase (but
remained un - noticed by both the prior owner and the Insured).
The majority of the leakage from the remaining downpipe spigots along the
front of the r esidence (should it have occurred) would have been expected to
have flowed downhill & away from the residence.
Leakage from the rear downpipe spigots is not expected to cause significant
soil movement, as the rear edge of the footing system is founded ove r a thin
layer of soil with low reactivity.
The drying of the highly reactive soils is most likely to have commenced
Determination | Case number: 829432 Page 15 of 19
Record Key points
following the construction of the residence and is considered to be the cause
of downpipe breakages across the front of the residence.
With shallow rock being encountered within Borehole 1 (towards the rear of
the residence), the footings for the residence are founded on a thin soil
horizon of low reactivity (i.e. the „B2‟ Horizon, a soil layer unlikely to undergo
significant volumetric c hange upon changing soil moisture conditions).
However, towards the front of the residence, the footing system is likely to be
founded on a thicker, more highly reactive soil horizon (the „B1‟ Horizon), in
which the soils can undergo significant volumetric change upon changing soil
moisture conditions.
In my opinion, with 6 significant locations present where stormwater discharge
can occur from the main stormwater system below the level of the spigots, it is
unlikely that stormwater can “gush” out of the spigots as claimed, except in the
most intense of rainfall events.
A shallow open „intercept‟ drain is present to the rear of the building site (i.e. to
the rear of the sit e‟s „cut‟), a drain that the [DA] reporting claims eliminates
surface flow from the wide, open land to the uphill side of the reside nce in
question.
It has been suggested in the [DA] report that this drain captures all surface
stormwater flow from the uphill side of this drain, an area of at least 8,000m2,
and direc ts it away from the residence.
Surface stormwater flow is expected to bypass this „intercept‟ drain in all but
the most minor of rain events and flow towards and down the embankment of
the „cut‟, and then into the rear yard adjacent to the residence.
Without adequate surface drainage provisions, such as the two omitted
surface drains specified by Dennis Sandery and Associates within the rear
yard (refer to Section 3.15 of the CRD Second Supplementary Report),
surface stormwater can accumulate to the rear of the residence.
Floor levels in the two attached surveys (Figur es B5 & B6 in Appendix A)
indicate that in general, the floor levels along the front of the residence are
significantly lower than that of the rear two thirds of the floor area.
Observations indicate the front of the residence has undergone a significant
settlement relative to the rear portion (the rear two thirds) following plumbing
repairs.
It is the considered opinion of the author of this report, that the primary cause
of building movement was not due to such stormwater leakage from the
downpipe spig ots, but due to the long term drying of a thick layer of highly
reactive soils along the front of the residence, soils not present along the rear
side of the residence.
Excessive surface stormwater flow from the large catchment area to the rear
had inund ated the rear yard for many years prior to the Insured‟s purchase.
Determination | Case number: 829432 Page 16 of 19
Record Key points
Following construction of the residence, the front portion of the building has
undergone a gradual long - term settlement due to the drying of the thick layer
of highly reactive soil (not p resent at the rear of the residence).
Breakages to the downpipes is more likely to have occurred as a result of this
long term drying of the soils along the front of the residence. It is not known
when such breakages may have occurred, but leakage from these locations
across the front may have provided a brief respite to the long term settlement
that was occurring.
DA 2022
Report
At the time of the original inspections and reporting DAHI requested not to
have access to previous reports to remain unbias ed and hence provide an
independent assessment of the cause of damages at the property. However,
these previous documents have now been reviewed by DAHI in preparation of
this response.
As shown in the DAHI Reports the stormwater system was undamaged unt il
the first surcharge event occurred following blockage of the system near the
kerb outlet, at which time localised heave commenced and the respective
risers at each downpipe were cracked by the subsequent localised heave.
A temporary bung was placed at the inlet pipe to the upper sump located near
the northeast corner of the house, which is supplied by downpipes DP2, DP3,
DP4 and DP5. During the rain event, surcharge from the connection between
these downpipes and the stormwater connection were observed and
photographed, as were the details of the rain event (refer Appendix A)
The CRD Report is correct in recognising that water would flow from the
breakages before surcharge occurred at the downpipe to stormwater
connections (spigots). However, the CRD Report does not discuss what the
time difference would be between backflow discharge at the breaks and
surcharge at the spigots. It also does not consider that water would already be
discharging from the breaks before backflow had built up to reach the pi pe
breaks. Furthermore, at the time of the claim, and following the blockage of the
system, after any given rain event had ceased water would have continued
discharging from the spigot at DP7 until all water in the system above this point
had been discharg ed.
The water level would remain in the pipe at the level of the spigot to DP7 until
the next rain event occurred. When the next rain event occurred, water
entering the system through DP7 would immediately discharge from the spigot
and also effectively b lock backflow from the system to a considerable extent.
Discharge into the system from the other downpipes (DPs) in the system
would concurrently fill the system , while discharging from any new breakages
and then surcharging from the remaining DP - spigots.
The writer of the CRD report did not have the advantage of having attended
site, where he would have noted that at least some, if not most of the
surcharge water from the front spigots would flow directly into the soils around
the respective spigot, as the fall of the ground i s not steep at this location.
CRD are also incorrect in stating that the surcharge does not have a clear path
to flow away from the proximity of the rear spigots. The ground surface at the
Determination | Case number: 829432 Page 17 of 19
Record Key points
rear of the property slopes away from the building towards the rear retaining
wall, not towards the building as implied by CRD.
To my knowledge, the information regarding the pipework that was just
repaired was presented to the Insurer, the Insurer‟s engineer at the time, and
to Priority Plumbing when their inspection o ccurred. The fact that the rear
stormwater pipes had been broken and had just been repaired appears to
have been omitted. Furthermore, because the rear pipes had just been
repaired at the time, they were obviously not leaking during the Priority
Plumbing i nspection and testing.
The CRD comment regarding the spoon drain across the rear paving of the
house is incorrect, as the comment highlighted in the diagram shown in the
CRD report clearly shows “ provide spoon - drain if ground falls towards paving ”
(Image 6 below). The ground does not fall towards the paving, as shown in the
Pyper Leaker survey (Appendix B) and shown in Images 15, 16 and 17 below,
therefore the spoon drain along the rear of the house is not required.
CRD provide the incorrect opinion tha t discharge from the rear downpipes will
only occur during heavy rainfall events. This opinion is incorrect. The outlet
from the stormwater system was fully blocked, evidenced by the discharge of
water from the pipe when it was cut by the plumber (Mr Hendr y) on 7 th October
2016. Refer also to the photographs in Appendix A from testing conducted by
the Insured (D [C0m} ) which show simultaneous discharge from each of the
spigots in the system during a recent very moderate rain event.
I have reviewed the FMG (Goldfinch) report on the garage floor and apron
area and agree with Mr Goldfinch‟s findings, based on my own inspection of
the upper areas of the concrete driveway and apron in front of the garage.
ALL damaged plumbing, with the exception of the crushed section of
stormwater pipe at the front of the property, has been a direct result of the
effects of the crushed pipe at the front of the property. This includes, but is not
limited to, the damages to all of the stormwater system around the house, and
also to the damages that have occurred and that have been documented by
various parties as having occurred to the sewer system in proximity to the
house.
The CRD assumption that underpinning was proposed by DAHI to the
perimeter only is incorrect. CRD have n ot read the DAHI proposal completely,
as DAHI propose underpinning throughout, including to provide additional
support to internal footing beams. Furthermore, the DAHI proposal, which
recommends that all underpins found into underlying rock, mitigates the effects
of soil movement due to saturation shear failure at the property, and allows for
earlier full repair of the property from the movement that has occurred resultant
of the surcharge from the stormwater system while it was blocked, without
required de lays to accommodate soil moisture stabilisation once all current
outstanding plumbing repairs are complete.
As discussed in the DAHI Reports, the pipe breakages themselves are
resultant damage from the initial surcharge events. The breakages at each of
t he stormwater pipes (see Image 7 below) have occurred to the top of the first
elbow joint, indicative of lifting and stretching of the joint, which will only occur
due to heave and not from subsidence.
Determination | Case number: 829432 Page 18 of 19
Record Key points
Accumulation of stormwater along the rear of the resi dence is only going to be
sourced from spillage out of the spigots. The ground at the back of the house
slopes away from the building towards the rear retaining wall and hence
rainwater falling directly on the lawn and paved area would flow towards the
wal l and the installed stormwater drains at the base of the wall (refer Images 4,
15, 16 and 17 below).
The level surveys that Intrax refer to are flawed. These have been skewed in
interpretation by placement of an arbitrary „zero‟ and have not been provided
by an independent third - party surveyor. The survey levels used by Intrax (and
CRD) to determine that settlement has occurred can readily be shown to
indicate significant heave at the property by using a different point as the
arbitrary zero. In actuality, the building has twisted, with the southeast (rear
corner, pool end of the building) and the northwest (front corner of garage)
having significant differential heave. (as an example, refer Image 12 below
which shows the extent of heave along the western w all of the garage taken
using a Bosch PCL20 self - levelling laser level).
The Intrax proposition that the damage has been caused by long - term drying
of the soils across the front of the property is unsupported. One of the Intrax
propositions is that this long - term drying has caused the damages exhibited to
the stormwater pipes at the fron t of the property (while also ignoring the
damage that had occurred to the stormwater pipes at the rear of the property).
However, the damage to the stormwater pipes at the front of the property
indicates that significant heave resulting in the breaking of the upper section of
the respective first elbow joints.
T he CRD assumption that all of the footings across the rear of the building will
be founded within the less reactive B2 horizon is incorrect. Only a small
section of the rear footings, at the western end of the single storey part of the
house, may actually be in the B2 soil horizon. The natural surface slopes
diagonally from approximately southwest towards northeast, hence it is
reasonable to consider that the subsoil horizons follow a similar alignment.
T he soil profiles beneath the southeast corner of the hous e (pool end – rear of
the house) are more closely aligned with Borehole BH2 than borehole BH1,
whereas the western of the single storey of the house, at the rear is
approximately 1.5 metres from BH1 (refer survey data in Appendix B). Hence
the CRD assumpti on that all of the rear of the building will have minimal or nil
movement is invalid. Note also that minimal movement has occurred to the
house in proximity to BH1, whereas the eastern end of the rear of the house
(pool end) has survey evidence of signific ant movement.
Agree that water would initially flow from DP7 in the blocked system. However,
Intrax have failed to mention or even consider that during a rain event water
enters the blocked system from all downpipes simultaneously. The quantity of
water entering the blocked system during most rain events is substantially
greater than the quantity that can be discharged from the small gap between
downpipe and stormwater pipe on any single connection. Hence during a rain
event water will quickly backfill th e blocked system above the lowest outlet
(DP7) and will simultaneously begin to discharge at the next lowest
Determination | Case number: 829432 Page 19 of 19
Record Key points
connections, as the system is being filled at all of these.
Once the rain event has stopped, water in the system will continue to escape
from the pipe damages until the level in the pipe system falls below the lowest
point of all breaks, and in the blocked system will continue to flow from the
DP7 connection until the level in the system is below the level of the DP7
connection. Obviously, when the system was unblocked by Mr Hendry on 7 th
October 2016, this scenario ceased to occur, and the subsequent testing by
Priority Plumbing could not reveal that the system was backfilling and
surcharging. Had Intrax properly reviewed and considered all the doc uments
they were provided, without any bias, this would have been evident.
The intercept drain could not be considered shallow, having cross - sectional
dimensions of nominally 700mm deep x nominally 450mm wide.
Intrax is incorrect. The hose test performed on the intercept drain was only
performed to show that the drain functioned. Furthermore, because Intrax have
chosen to state that the uphill catchment is almost double what it actually is,
they have provided an inacc urate scenario that discredits the functionality of
the intercept drain.
Intrax have again incorrectly stated that the drains required by Dennis Sandery
and Associates have been omitted. The drain required at the base of the
retaining wall has been insta lled below ground level with grated inlets (refer
Images 4 and 5 below).
The surface drain Intrax continue to state as being required along the edge of
the back verandah is not required as the ground slopes away from the
verandah (refer survey data in Ap pendix B and Images 15, 16 and 17 below).
The Dennis Sandery and Associates requirements clearly state that this drain
is only required if the ground slopes towards the verandahs (refer Image 6
below).
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.