Progress payment of $159,950 released to builder on complainants' instruction
Summary
The complainants, who took a construction loan from HSBC, authorised a $159,950 builder's progress payment after disputing the quality of the work. AFCA found the bank acted within its contractual obligations and reasonable care, and made no award.
The bank's relationship with the borrowers is contractual; it made the progress payment on the complainants' authorisation, invoice and a satisfactory valuer's report, and owed no duty to supervise building quality.
Issues
- Inadequate claim investigation primary · not upheld“The bank was not required to inspect the site to ensure it met quality standards; the builder is responsible for the quality of construction.”
- Complaint handling failure secondary · not upheld“The bank responded to the complainants' complaint within 45 days and met its complaint handling obligations.”
- Failure to disclose secondary · not upheld“The bank's inspection report was for its own purposes and benefit, not the complainants; the bank was not required to provide it.”
- Payment error secondary · not upheld“I accept E Group and builder C were associated companies; the bank exercised reasonable care and skill in paying the account on the invoice.”
Subjects and remedies
home or building damagerelated party investmentno remedy
Related
Text of the determination
Determination
Case number 825730
Financial firm HSBC Bank Australia Limited
Determination | Case number: 825730 Page 2 of 11
Case number: 825730 29 August 2022
1 Determination overview
1.1 Complaint
The financial firm (bank) provided the complainants with a home loan to purchase land. In
September 2018, the bank provided the complainants with an additional $330,000 home and
investment property loan (loan) to construct a house on their land (property).
The complainants say:
the quality of the building works described in the builder’s invoice for the sum of $159,950
for brickwork, roofing and windows (works) were unsatisfactory
prior to the inspection of the building works by the bank’s agent , they emailed the bank
with details of their concerns regarding the works
the bank did not provide them with a copy of its inspection report which should have
addressed both their concerns about the unsatisfactory works, and a report of the
completed works
in response to pressure from the builder they authorised the payment of $159,950 as
invoiced
the payment was paid into the wrong builder’s account , and
the bank did not meet its complaint handling obligations.
On 9 February 2022, an Australian Financial Complaints Authority (AFCA) case manager
issued a recommendation on these issues. The recommendation was in favour of the bank
and a copy of it is attached. The complainants have rejected the recommendation.
1.2 Issues and key findings
Were the findings in the recommendation correct?
The findings in the recommendation were correct and are adopted in this determination. I
have considered further submissions provided after the recommendation was issued.
The complainants ’ further submissions do not change the outcome. The complainants have
not established the bank made an error or breached its obligation when it made the progress
payment of $159,950.
Does the bank owe the complainants a duty of care?
The bank does not owe the complainants a duty of care. The bank’s relationship with the
complainants is based in contract. The bank exercised reasonable care and skill when it
made the $159,950 progress payment to the account nominated on the invoice and as
approved by the complainants.
Did the bank meet its obligations regarding the progress payment?
The bank met its contractual obligations when it made the $159,950 progress payment.
Determination | Case number: 825730 Page 3 of 11
Did the bank exercise reasonable care and skill?
The bank exercised reasonable care and skill when it made the $159,950 progress payment
to the account as directed on the invoice and approved by the complainants.
Did the bank have an obligation to approve a new builder?
The bank was not obliged to approve the complainants’ new builder or continue to advance
loan funds to the complainants whilst the dispute between the complainants and the builder
remained unresolved.
Why is the outcome fair?
I acknowledge that the complainants will be disappointed with the outcome. However, after
reviewing all the available information, I am satisfied the bank acted appropriately and did not
breach its obligations to the complainants. It wold not be fair to require the bank to
compensate the complainants because of issues in dispute between the complainants and
their builder.
1.3 Determination
This determination is in favour of the bank. I agree with the recommendation and the
recommended outcome.
The bank is not required to provide compensation to the complainants. The complainants
remain liable to the bank for the loan.
Determination | Case number: 825730 Page 4 of 11
2 Reasons for determination
2.1 Were the findings in the recommendation correct?
The findings in the recommendation are correct
I am satisfied that the case manager’s recommendation contains an accurate summary of the
complaint, the issues to be determined, any applicable paragraphs of the rules and any
relevant law. The findings in the recommendation are correct and are adopted in this
determination.
The complainants’ further submissions do not change the outcome. The complainants have
not established the bank made an error or breached an obligation when it made the $159,950
progress payment.
The complainants rejected the recommendation
The complainants’ reasons for rejecting the recommendation include:
the bank owed them a duty of care which it breached particularly in relation to the
inspection of the building works its agent (the independent valuer) completed in March
2019
the bank ’s standard of service it provided was poor
although the building works were undertaken by the builder (builder C) it was not a party to
the building contract and not entitled to receive the payment made by the bank
the bank did not cross check the builder’s invoice against the stage works in the building
contract before making payment
the bank provided incorrect information (building contract version) when it instructed its
agent
the bank should have undertaken a second inspection of the building works to ensure the
building works were completed to the required stage under the building contract
the bank authorised an overpayment of $22,850
in responding to their complaint, the bank incorrectly referred to the Queensland domestic
building legislation rather than the New South Wales (NSW) equivalent
the bank refused to approve the appointment of the new builder they engaged to complete
constru ction of the house and pay the new builder’s invoices.
I have carefully considered the available material. I agree with the case manager’s reasons
and findings in the recommendation which I adopt as part of this determination. I do have the
following additional comments to make on the subsequent submissions the complainants
have raised which I hope will assist them further in understanding the outcome.
2.2 Does the bank owe the complainants a duty of care?
The relationship between the parties is contractual
The complainants say the bank owed them a duty of care which it breached when it paid the
$159,950 progress payment causing them loss.
The bank does not owe the complainants a duty of care as suggested by the complainants.
The bank’s relationship with the c omplainants is based in contract. The bank exercised
Determination | Case number: 825730 Page 5 of 11
reasonable care and skill when it made the $159,950 progress payment to the account on the
invoice which was approved by the complainants.
The law does not recognise the relationship of banker and customer as one of the accepted
categories of fiduciary relationship giving rise to a duty of care. Absent some special feature,
such as the giving of advice, t he bank’s relationship with the complainants is found ed in
contract.
The bank acted as lender and was not the complainants’ advisor in relation to the building
contract, including the complainants’ decision to authorise the $159,950 progress payment. It
acted in line with the contractual terms and conditions of the loan agreement which it did
exercising reasonable care.
2.3 Did the bank meet its obligations regarding the progress
payment?
By receiving:
a copy of the builder’s invoice for $159,950
the complainants’ email confirming they were satisfied with the works completed by the
builder and authorising payment of the invoice
the inspection report confirming the progress of the works met the stages under the
building contract and the costs at that point in time,
the bank was satisfied that the costs to complete the works did not exceed 75% of the on-
completion valuation of the property. In these circumstances it was reasonable for the bank to
make the $159,950 progress payment to meet its funding obligations under the loan
agreement.
The complainants provided the builder’s invoice to the bank
The complainants maintain the bank made an error when it released funds to make the
$159,950 progress payment.
On 22 February 2019, the builder sent Mr M an invoice for $159,950. The invoice required
payment by 1 March 2019. The description of the works completed was
Completion of Brickwork, Roofing and Window... TOTAL AUD 159,950
The description on the invoice matched the building contract payment schedule for stage 3 of
the works, which was:
(3) LOCKUP- BRICK WORKS, ROOFING & WINDOW - 35% $159,950.
Mr M provided a copy of this invoice to the bank.
The bank’s inspection report was for its own purposes and benefit
Before making the $159,950 progress payment, the bank arranged a progress inspection of
the property by an independent valuer. The valuer provided a progress inspection report
dated 25 March 2019 to the bank.
The complainants say the bank has a duty of care to check the progress inspection report or
conduct a second inspection where:
Determination | Case number: 825730 Page 6 of 11
it provided incorrect information (original contract without the modified progress payment
schedule amended at the bank’s request) to its valuer before the valuer’s site inspection
it instructed inspection of “brickwork, roofing and windows” but approved payment for the
lock-up stage of works which was not a stage payment under the contract
it accepted the inspection report showing 60% of the work was completed with the total
payment due of $274,200 which did not align with the building contract progress payments
the works identified in the valuer’s report did not align with the stage works or progress
payments percentages under the building contract.
Mr M also asked the bank about the purpose of the bank’s site inspection and report . The
bank responded:
you should not authorise the invoice until all work is completed satisfactorily as
this may result in unsatisfactory valuation and additional cost for additional
inspection to be completed.
Mr M responded by saying that he wanted the bank’s inspector to inspect specific issues.
The purposes of the progress inspection report commissioned by the bank is to assess its
credit risk. The bank’s valuer is not a building inspector or building expert. The bank is not
responsible for the building works being undertaken by the complainants, that responsibility
rests with the complainants. The bank also made it clear to the complainants that they should
not authorise payment of the invoice if the work was not satisfactory. The bank’s inspection
report was for its own purposes and benefit, not the complainants.
In short, when approving the payment request, the complainants acknowledged the build had
reached the staged indicated by the builder and they were authorising payment.
There was no independent obligation on the bank to inspect the build or satisfy itself if the
builder should be paid. There was nothing in the loan contract which required it to do so
before it released the payments (other than the final payment, which was not released). In the
ordinary course, a bank does not act as a “project manager” when construction is being
undertaken. The complainants were responsible for ensuring the build was progressing
satisfactorily before the builder was paid and it was at the complainant s’ discretion to instruct
the bank to pay it.
In other words, the bank was not required to inspect the site to ensure it met quality
standards. Ultimately, the builder is responsible for the quality of the construction.
The complainants addressed building issues with the builder
The building contract was between the complainants and the builder. If the complainants
were not satisfied with the building works they had to address this with the builder which they
did.
The email correspondence between the builder and the complainants in March 2019 shows,
that after rendering the $159,950 invoice for completion of brick work, roofing and windows:
the builder agreed to replace eight windows
the complainants wanted a variation outside the original plans.
Despite these changes the complainants had an obligation to make payments to the builder
under the building contract. In March 2019, the builder required payment of the $159,950
invoice, so they could pay contractors for subsequent work. The complainants were obliged to
pay the builder.
Determination | Case number: 825730 Page 7 of 11
The complainants instructed the bank to pay the invoice
On 7 April 2019, the complainants confirmed by email to the bank they were satisfied with the
completion of building works. They included photos of roofing and replacement windows on
site and asked the bank to transfer loan funds to pay the builder ’ s invoice for $159,950. The
bank made the payment on the instruction of the complainants.
The bank met its obligations when it made the progress payment
Under the loan agreement a progress payment can be made from loan funds when
the borrowers give the bank a request for payment completed and signed by the builder
with details of the building works competed
the borrowers confirm that they are satisfied with the quality of the workmanship and the
value of the claim
the bank’s assessor certifies he/she is satisfied:
> with the claim, variation and the progress of the works
> with the costs so far incurred with respect to the work
> that the total of all drawings plus the amount requested and cost to complete the works
does not exceed 75% of the on- completion value of the property and improvements on
it as assessed by the bank’s assessor.
The bank’s inspection report shows the building works as 60% complete at a cost of
$274,200 representing completion of the concrete slab ($45,700), frame ($68,550) and
brickwork ($159,950) in an accordance with the progress schedule in the building contract. I
acknowledge there is a difference between the description in the inspection report and the
building contract which shows progress payment 3 as “lockup – brickwork, roofing and
windows.
The bank’s inspection report correctly records the costs so far incurred to completion of stage
3 as $274,200 which is consistent with the building contract’s construction payment schedule.
The photos attached to the inspection report show all exterior walls erected on a concrete
slab with a roof. While no windows appear to be installed, the March 2019 emails between
Mr M and the builder refer to discussions and an agreement on installation of replacement
windows.
The valuer did not, nor was he required to, provide an assessment of the “on completion”
value of the security property. By March 2019, the on-completion valuation of the security
property was $937,000 (being the land valuation of $480,000 together with the construction
contract price of $457,000).
In March 2019 the total of all loan drawings was $361,800 (the loan to purchase the land) with
nil drawings on the construction loan. The valuer assessed the costs to complete as
$182,800. So, the total of all loan drawings together with the costs to complete the works was
58% which did not exceed the bank’s requirement not to exceed 75% of this valuation. Also,
the total of all loan drawings which included the cost to complete the works was 73.8% which
is consistent with the amount shown in the loan contract and did not exceed 75% of the
valuation.
Determination | Case number: 825730 Page 8 of 11
2.4 Did the bank exercise reasonable care and skill when it
made the payment of $159,950?
The bank exercised reasonable care and skill when it released the $159,950 progress
payment to the account nominated on the builder’s invoice which was approved by the
complainants.
E Group and builder C are associated companies
The complainants say the bank paid the $159,950 progress payment to the wrong company
because:
the building contract named E Group as the builder
all the building works were undertaken by builder C which was not the builder named in the
building contract.
Section 2.1 of the recommendation sets out the history of the $159,950 progress payment.
Section 2.3 of the recommendation sets out information about E Group, the builder named in
the building contract and builder C, the company which received the $159,950 progress
payment.
Additionally:
email correspondence from a director of the builder to Mr M sent between July 2018 and
April 2019 bears the logos of both E Group and builder C and both companies have the
same address
a search of the Australian Securities and Investment Commissions database for both
companies show in April 2019 they had the same registered office address and shared a
common director.
I accept E Group and builder C were associated companies.
The builder does not dispute receiving the progress payment
There were no red flags to indicate to the bank that by releasing the $159,950 progress
payment the rightful builder would not be paid. There is no information to show E Group and
or builder C:
have claimed the progress payment was not made
made a claim against the complainants for breach of the building contract because of non-
payment of the $159,950 progress payment.
The bank made a recall request
The bank says in response to the complainants’ request on 5 June 2020, it initiated a recall
request for the $159,950 progress payment. However, no money was paid back. This is
because after more than a year it would require the consent of the beneficiary of the funds
(builder C) to return the funds and this consent has not been given.
The bank’s action in initiating the recall against builder C at the complainants’ request does
not mean the bank made an error when it released the progress payment to builder C. It
simply shows the bank agreed to the complainants ’ request.
There is no information to show the progress payment was made to the wrong company.
Even if the progress payment was made to the wrong company, this did not result in a loss to
the complainants.
Determination | Case number: 825730 Page 9 of 11
A mistaken reference to Queensland legislation did not result in loss
The complainants say in responding to their complaint, the bank incorrectly referred to the
Queensland domestic building legislation rather than to the NSW equivalent. The
complainants have provided no details regarding this issue or how it may have caused them
loss. I am satisfied even if the bank incorrectly referred to the Queensland rather than NSW
domestic building legislation the complainants did not suffer any loss as a result.
Consequently, there is no need to consider why or how this error may have occurred.
2.5 Did the bank have an obligation to approve a new builder?
The bank was not obliged to approve the complainants ’ new builder or continue to advance
loan funds to the complainants following their breach of the loan contract in September 2019.
The complainants breached the loan agreement
Under the terms of the loan agreement:
the complainants were required to draw the entire balance of the loan funds within 12
months of the settlement date
the specified builder could not be replaced without the bank’s approval
the building works had to be completed to the specifications and within the construction
period.
The loan settled on 12 September 2018. Due to the dispute which emerged between the
complainants and the builder regarding the quality of the build, the complainants did not draw
all the loan funds down by 12 September 2019. Consequently, the complainants did not
complete the building works within the construction period.
The bank did not breach the loan agreement
In May 2020, the complainants terminated their building contract with the original builder and
appointed a new builder to complete the construction or their house.
The complainants say the bank failed to release the balance of the construction loan funds
when they engaged the new builder.
The loan agreement requires the bank ’s approval before the builder specified in the building
contract is replaced. The bank refused to approve the new builder or provide construction
funds to the new builder until a decision was made by the tribunal considering the dispute
between the complainants and the original builder.
By mid-June 2020 however, whilst the dispute with the builder was continuing, the
complainants obtained finance from another financial firm to complete the construction of their
house. Even if the bank was not entitled to refuse to approve a new builder, which it was,
there is no information to show how the bank’s refusal resulted in a loss to the complainants
in any event.
2.6 Why is the outcome fair?
The outcome is fair in all the circumstances because the bank did not make an error or
breach a duty or obligation owed to the complainants.
Determination | Case number: 825730 Page 10 of 11
The outcome is fair
I acknowledge that the complainants are likely to be disappointed with the outcome. However,
after reviewing all the available information, I am satisfied the bank acted appropriately and
did not breach a duty or obligation owed to the complainants. It wold not be fair to require the
bank to compensate the complainants because of issues which arose between the
complainants and the original builder.
Determination | Case number: 825730 Page 11 of 11
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted our
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
Recommendation
Case number 825730
Financial firm HSBC Bank Australia Limited
Recommendation | Case number: 825730 Page 1 of 14
Case number: 825730 9 February 2022
4 Recommendation overview
4.1 Complaint
In July 2018, the financial firm (the bank) provided a $330,000 home loan to the
complainants. The loan was to purchase land with additional loan funds to be provided to
construct a house.
The complainants say:
the building works describes in the builder’s invoice of $159,950 for– brickwork, roofing
and windows were unsatisfactory
prior to the inspection of the building works by the bank’s agent they emailed the bank with
details of their concerns regarding the works
the bank did not provide them with a copy of its inspection report or details of what work
they needed to check and what had been completed
in response to pressure from the builder they authorised the invoice payment
the payment was paid into the wrong builder’s account
the bank did not meet its complaint handling obligations.
4.2 Issues and key findings
Should the bank have made the $159,950 progress payment?
The bank did not make an error or breach an obligation to the complainants when it released
funds to make the $159,950 progress payment.
Is the bank required to provide its report to the complainants?
The bank obtained the independent progress inspection report dated 25 March 2019 (the
report) for its own benefit. The bank is not required to provide its report to the complainants.
Was the $159,950 progress payment made to the correct account?
It was reasonable for the progress payment to be paid to the bank account advised on the
invoice approved by the complainants.
Did the bank breach its complaint handling obligations?
The bank responded to the complainants’ complaint appropriately and met its complaint
handling obligations.
Should the bank pay compensation?
No compensation is payable to the complaints.
Why is the outcome fair?
The outcome is fair because the available information shows the bank met its legal
obligations, acted in line with good industry practice, and complied with applicable industry
codes. It would be unfair to require it to compensate the complainants.
Recommendation | Case number: 825730 Page 2 of 14
4.3 Recommendation
This recommendation is in favour of the bank.
No compensation is payable to the complainants.
Recommendation | Case number: 825730 Page 3 of 14
5 Reasons for recommendation
5.1 Should the bank have made the $159,950 progress
payment?
The bank did not make an error or breach an obligation to the complainants when it released
funds to make the $159,950 progress payment.
The complainants were required to pay the builder’s invoices
The complainants wanted to construct a new home. To do this they entered a fixed price
building contract with a builder. This contract required the complainants to make payments to
the builder when each stage of works was reached except for minor omissions. The
complainants used loan funds to settle the purchase of land. They used their own savings to
pay the first two stage works to the builder for the construction of the concrete slab and
framing.
Relevant sections of the fixed price building contract are set out in section 3.2. The bank
is not a party to the fixed price building contract.
The builder rendered an invoice to the complainants for $159,950
In February 2019, the builder rendered an invoice to the complainants for $159,950 being the
next stage of work. Under the fixed price building contract, within two days of receiving the
builder’s invoice the complainants could identify to the builder works which were omitted,
incomplete or defective. If they were not satisfied with the works, they could withhold payment
of no more than 2.5% unless an alternative amount was agreed between the complainants
and the builder.
There is information to show a few days after the builder rendered the $159,950 invoice the
builder confirmed to the complainants the replacement of eight windows. The builder also
requested payment of the $159,950 invoice the same day. When the complainants withheld
payment, they were contacted by the builder’s lawyers on 13 March 2019.
The complainants were not satisfied with the builder’s work
The complainants required loan funds to p ay the builder’s $159,950 invoice. The
complainants were not satisfied with the builder’s work. Under the fixed price building
contract, they could identify unsatisfactory work to the builder and withhold a portion of the
payment. However, the complainants emailed the bank raising the issue of incomplete works
and asking for advice on any works inspection conducted by the bank, a copy of any
inspection report and the bank’s expectation of the completed works before it released
payment to the builder.
The bank conducted an inspection of stage works
The bank responded to the complainants saying, the complainants should not authorise
payment of the invoice until all work was completed satisfactorily. The bank noted in relation
to the final building works, the bank will only release the final payment once the final
occupancy certificate is provided and the satisfactory construction as confirmed by a final
valuation prepared by the bank’s approved valuer.
Recommendation | Case number: 825730 Page 4 of 14
The complainants responded, requesting the bank’s assessor check a list of specific building
works. The bank passed this list to its valuer prior to the inspection of these interim stage
works.
The bank instructed its valuer to undertake the progress inspection report. Following this first
progress inspection, the valuer provided the report to the bank. Relevant parts of the report
are set out in section 3.4.
The report showed
All building works appear to have been completed in line with the plans and
specifications provided and payment is approved in accordance with the following
schedule
The complainants were not happy with the report
The complainants were not satisfied with the report, again they requested a copy of the report
from the bank and said the valuer failed to identify incomplete works. The complainants
continued to communicate with the builder regarding completion of works before payment of
the $159,950 invoice.
The complainants authorised the progress payment
The complainants provided a copy of the builder’s $159,950 invoice to the bank which was
signed by them and dated 18 March 2019. Despite Mr complainant’s email dated 1 April 2019
setting out his concerns regarding the works inspection conducted by the bank’s valuer, on 7
April 2019 the complainants asked the bank to transfer funds to pay the b uilder’s $159,950
invoice. The complainants email says:
I have gone through pending work on site and being satisfied with the completion
of work.
Along with this I am forwarding you couple pictures of Roofing and replacement
windows which is being replaced.
All good, I would request [the bank] to organise transfer of funds and clear Invoice
Payment of $159,950.00
The account statement shows the withdrawal of $159,950 on 10 April 2019.
The complainants should not rely on the report
The relationship between the bank and the complainants is essentially a contractual one.
Details of and relevant sections of the loan contract are set out in section 3.3.
The bank had a contractual obligation to ensure, the loan account was drawn according to the
progress payment schedule in the complainants’ fixed price building contract after the
complainants authorised payment to the builder.
The loan agreement also included the complainants acknowledgements:
they would not rely on the bank’s inquiries or checks and
the bank would not be responsible if any building works which were not done properly.
Recommendation | Case number: 825730 Page 5 of 14
This included where the bank or its representative say it is satisfied as to any building work
and it lends against the work.
The bank is not obliged to advise a customer that a service or product is not in their interest. It
was up to the complainants to undertake their own inspection or instruct an appropriately
qualified building inspector if they had concerns regarding the stage works before they
authorised the payme nt of the builder’s $159,950 invoice. The complainants should not rely
on the report prepared for the bank.
The bank was required to make the progress payment
The bank was obliged to release loan funds to pay the builder’s $159,950 invoice, where:
the comp lainants provided the bank with a copy of the builder’s $159,950 invoice with the
description “completion of brickwork, roofing and window”
the invoice reflected the stage 3 works shown in the fixed price building contract
the invoice was signed by the complainants and dated 18 March 2019
the bank received a valuer’s report certifying the valuer was satisfied the works were
completed in line with the plans and specification provided
the complainants emailed the bank saying they were satisfied with the completion of work
and requesting the bank transfer the funds and clear the invoice.
The bank did not make an error or breach an obligation to the complainants when it released
funds to make the $159,950 progress payment.
5.2 Is the bank required to provide its reports to the
complainants?
The bank obtained the independent progress inspection report for its own benefit. The bank is
not required to provide its report to the complainants.
T he bank’s inspection report was for its own purposes and benefit
The loan contract includes an acknowledgement by the complainants they would not rely on
the bank’s inquiries or checks and that the bank was not responsible for any building works
not done properly. This included where the bank or its representative says it is satisfied as to
any building work and it lends against the work.
Until construction of the house is finalised the bank faces a security risk. It may be unable to
recover its debt in the event of a default under the loan contract through the sale of the
property where construction is incomplete.
The report was provided by an independent valuer instructed by the bank. The report was for
the bank to understand:
how the proposed construction of the house on the land was progressing against the plans
provided
the value of its security.
The complainants were required to pay the fee for the valuation
The complainants have an obligation under the loan contract to pay the valuer’s fee for the
report. The complainants’ acknowledgement and fees payable are set out in section 3.3
below.
Recommendation | Case number: 825730 Page 6 of 14
The bank was not required to provide the report to the complainants
There is information to show the complainants provided a list of works they wanted the bank’s
valuer to inspect and they requested a copy of the report. The bank provided a copy of the
complainant’s incomplete works list to the valuer for information only. The bank’s valuer is not
a building inspector or building expert.
The valuer was acting as the ban k’s agent only to undertake a first progress inspection and
confirm the construction of the dwelling to brick stage for the bank’s security value
perspective. The bank is not obliged to provide a copy of the report to the complainants.
5.3 Was the $159,950 progress payment made to the correct
account?
It was reasonable for the progress payment to be paid to the bank account advised on the
invoice approved by the complainants.
The progress payment was directed to C* Homes
The complainants say the progress payment was made to the wrong builder account. They
have provided no information to support what they say.
The complainants’ fixed price building contract was with the builder E* Group Pty Ltd. E*
Group Pty Ltd appears to have an association with C* Homes Pty Ltd (C* Homes). The
contract drawings and specifications for the construction of the complainants’ new home were
prepared by C* Homes. The building plans and certificates of insurance are in the name of C*
Homes. The local council’s development application approval for the construction was issued
to C* Homes. The builder’s $159,950 invoice was in the name of C* Homes. This invoice
required payment to a bank account in the name of C* Homes.
In these circumstances, it was reasonable for the progress payment to be paid to the bank
account advised on the invoice approved by the complainants.
5.4 Did the bank breach its complaint handling obligations?
The bank met its complaint handling obligations when it responded to the complainants’
complaint in June 2020.
The complainants complained to the bank
The complainants were not satisfied with the response from the bank to their complaints and
its process/procedure of handling the complaint.
Following a meeting at a bank branch on 14 May 2020, on 15 May 2020 the complainants
emailed the bank with details of their complaint. The bank responded on 22 May 2020, noting
due to the complexity of the issues raised it would take longer than their usual time frame
(within 5 days) to respond to the complaint.
On 26 May 2020, the bank told the complainants it would not consider their proposal for a
new building contract until a decision was reached regarding their legal action against the
original builder. The complainants objected to this response by return email and requested
details of the bank’s policy for termination of a contract and change of builder during
construction works. The bank included these new issues as part of the complainants’
complaint.
Recommendation | Case number: 825730 Page 7 of 14
The bank is not required to provide copies of its internal policies to the
complainants
The complainants say the bank refused to respond to their request to provide its
policy/procedure where there is an insolvency/dispute with the builder. The bank does not
have an obligation under the loan contract or the Banking Code of Practice to provide
copies of its internal policies and procedures to the complainants
The bank met its complaint handling obligations
On 10 and 26 June 2020, the bank responded to th e complainants’ complaint emails dated 15
and 26 May 2020. In both responses, the bank provided details of the contract provisions and
documents it relied on to show it had not made an error or breached an obligation to the
complainants. These written responses were provided within the 45 days of the complaint
being received on 14 May 2020. The response on 26 June 2020 also:
notified the complainants of their right to take the complaint to AFCA
provided AFCA contact details.
By providing these written responses within 45 days of the complaint, the bank met its
complaint handling obligations under the loan agreement, the Banking Code of Practice and
ASCI’s regulatory guide 165.
5.5 Should the bank pay compensation?
No compensation is payable.
No compensation is payable to the complaints
Where the bank has not made an error or breached an obligation to the complainants,
regarding payment of the $159,950 the progress payment, non-provision of its reports and
complaint handling, it is not required to pay any financial loss compensation. The
complainants remain bound by the terms of the loan agreement.
5.6 Why is the outcome fair?
The outcome is fair because the available information shows the bank met its legal
obligations, acted in line with good industry practice, and complied with applicable industry
codes. It would not be fair to require it to compensate the complainants.
The outcome is fair
The events the complainants describe are unfortunate and I understand they have suffered
distress and anxiety due to reasons beyond their control. In undertaking a progress inspection
report and releasing loan funds to pay the builders invoice authorised by the complainants the
bank did not make an error.
Recommendation | Case number: 825730 Page 8 of 14
6 Supporting information
6.1 The AFCA process
AFCA’s approach is based o n fairness
AFCA has assessed this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
recommendation to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information. If there are conflicting recollections and these are evenly weighted, we may find
that a claim cannot be established.
Contractual nature of the banker and customer relationship
The relationship between the financial firm and the customer is essentially a contractual
one. Generally, the financial firm does not have a duty to advise a customer that a
transaction or product is not in their interests, nor is it obliged to put the customer’s
interests ahead of its own. However, the financial firm does have a duty of care to
exercise reasonable care and skill in carrying out transactions for its customer.
Valuations
A financial firm’s valuation is an assessment of the value of the property used as security for
a debt in case it must sell the property to recover the debt. The value identified in the
valuation may be very different from the current market value of the property or the property’s
purchase price.
A financial firm will usually obtain a valuation when assessing a loan application but is not
required to do so. The financial firm uses the valuation to assess the risk involved for it in
lending the money.
Recommendation | Case number: 825730 Page 9 of 14
When a financial firm obtains a valuation, it does so for its own benefit, so it knows the value
of the property which will be mortgaged as security for the loan in case it has to sell the
property at short notice to recover the debt. The valuation is usually provided by an
independent valuer who is appointed to value the property according to specific criteria laid
down by the financial firm. The borrower is required to pay the valuer’s fees as part of the
costs of obtaining the loan.
Good industry practice
Financial firms that subscribe to the Banking Practice Code of Conduct have an
obligation to exercise the care and skill of a diligent and prudent lender. As a financial
services licensee, the financial firm will also have a statutory obligation to provide its
services covered by the licence efficiently, honestly and fairly.
6.2 Fixed price building contract
The contract between the complainants and the original builders [E* Group Pty Ltd] dated 29
March 2018 included a contract price of $457,000, deposit 5% of $22,850 and stage
payments. The stage payments were changed to meet the bank’s requi rements being 5%
(deposit), 10%, 15%, 35%, 20%, 15%.
Clause 2 Owner’s Responsibilities Concerning the Works – pre construction & during
constructions
The Owner must:
…
c) make payment as required by the contract. This includes directing any Lending Authority to
make payment direct to the Builder. Refer to Schedule 2 point 4 and Clauses 18,19, 20 and
23
Schedule 2 on page 8 sets out under the heading payments
Payments are to be made in all cases in accordance with Cluses 18,19, 20 and
23. Payments can be claimed when the following stages of the work are 95%
reached:
1 Completion of concrete slab – 10% $45,7000
2 Completion of framework -15% $68,550
3 Lockup – brickwork, roofing & windows – 35% $159,950
4 Completion of internal linings – 25% $114,250
5 Practical completion – 10% $45,700
….
Recommendation | Case number: 825730 Page 10 of 14
Payment for Work
(c) When to claim
The request for payment is to b make when a stage of works has been reached.
Refer to Clause 20(d).
(d) When to pay claim
Claims are to be paid no later than seven days after a written request for
payment.
…..
Clause 20(d) on page 23
How to determine if a stage has been reached?
d) (i) A stage of the works is to be treated as reached, and therefore
enabling a payment claim to be made, when it is complete except for
minor omissions, incompleteness or defects.
(ii) If the Owner identifies in writing within two (2) days of receipt of the
claim work which is omitted, incomplete or defective and for which no
deduction has been made then an amount equal to no more than 2.5%
of the amount claimed may be withheld unless an alternative amount has
been agreed between the parties. Any amount withheld becomes
payable once the work omitted, incomplete or defective has been
completed
6.3 Loan agreement terms and conditions
The loan agreement between the complaint and the bank is made up of the letter of offer
dated 26 July 2018 which incorporates the bank’s booklet of standard terms and conditions
which applied at the relevant time.
Letter of offer dated 26 July 2018
At page 7 and 8
If your Loan Account is a Construction Loan Account and a drawing has been
made none of you can terminate your liability in respect of the Loan Account until
the Bank issues a certificate saying the construction or renovation has been
finished to its satisfaction.
Standard terms and conditions – April 2017
YOUR ACKNOWLEDGEMENT OF RISK
Recommendation | Case number: 825730 Page 11 of 14
No reliance on Bank’s enquiries or checks
You know that if we or our representative inspect any building work on any Property, we
are doing so for ourselves and not you. You should not rely on that inspection.
We and our representatives are not responsible to you if any building work has not been
properly done, even if we or our representative have said it is satisfied as to the work,
and we lend against the work.
The same applies to any search, enquiry, review, inspection or valuation which is
checked, carried out or obtained by us or our representatives with respect to any other
aspect of any Property or your business or affairs.
In particular, if you are buying any Property, you are responsible for making sure you get
good title. If you have one, your lawyer or conveyancer should do this. You should not
rely on us or our representatives to do this.
…
Schedule 1
How do you draw the Loan Account
• your Loan Account will be drawn according to the progress / event payment
schedule contained in your fixed price building contract and as authorised by you
prior to payment to your builder.
…
Progress Payments
…
A drawing can only be made for a purpose other than purchase of the Property if:
(a) you give us a request for a progress payment completed and signed by the
builder providing full details of all building works completed (and for which
payment is requested);
(b) your request states that you are satisfied with the quality of the workmanship
and the value of the claim;
(c) our assessor certifies to us that he or she is satisfied with:
Recommendation | Case number: 825730 Page 12 of 14
(i) the claim, variation and the progress of the works; and
(ii) the cost so far incurred in respect of the works; and
the total of all drawings plus the amount requested and the cost to complete the
works does not exceed 75% of the on completion value of the Property and
improvements on it as assessed by the Bank’s assessor.
……
Schedule 3
Fees and Charges
The following fees and charges together with others set out in the Letter are or
may become payable by you under this Facility.
…
Specific Loan Account Fees and Charges
Construction Loan Accounts
Fee Valuer’s Certification Fee
Amount or Method of Calculation Unascertainable, at cost
Payable by you At the time of each progress payment request
6.4 The report
The bank’s independent valuer’s progress inspection report at the security property address
dated 25 March 2019 was carried out at the bank’s instruction and included the following:
All building works appear to have been completed in line with the plans and
specifications provided, and payment is approved in accordance with the following
schedule…Progress payment inspections are undertaken in our capacity as
valuers, and not as or bui lding inspections or building experts, and the vauler’s
inspection and report does not constitute a structural survey or building report.
……..
Payment type: Progress payment
Comments: Construction of the dwelling is now at brick stage. We advise the
property has completed the brick stage (60%) as per the progress schedule
Recommendation | Case number: 825730 Page 13 of 14
advised in the original building contract. Total payment due for completing this
stage is $274200 inclusive of 5% deposit.
We confirm an executed Building Contract and a schedule of finishes and
specification have been sighted.
We confirm Council Approved/Privately Certified plans have been sighted.
The Lender should note that the payment percentages differ from our estimate
guideline, however, have been agree between the customer and the builder in the
building contract.
This is the FIRST progress inspection we have carried out on this property.
6.5 Other issues not considered as part of this complaint
Appointment of new builder
The complainants say in May 2020 they terminated their building contract with the original
builder and subsequently appointed a new builder to complete the construction or their house.
The bank refused to provide construction funds to the new builder until the dispute with the
original builder was resolved. The complainants have provided no details of any error by the
bank or how it impacted them. The complainants subsequently obtained finance from another
financial firm to complete the construction of their house.
Reference to Queensland legislation
The complainants say in responding to their complaint, the bank has incorrectly referred to
Queensland rather than NSW domestic building legislation. Where the complainants have
provided no details regarding this issue or how it impacted them, AFCA is unable to
investigate it.
Legal action against the builder
Following payment of the $159,950 invoice the fixed price building contract was terminated
and the complainants commenced legal action against C* Homes. An agreement was
reached that C* Homes pay the complainants $340,000 by instalments however no payments
were made. A subsequent application by the complainants for renewal of proceedings to seek
a money order of $340,000 against C* Homes has been dismissed. While the complainants
may continue legal action against C* Homes there is no information to show they have done
so.
Chargeback request
The bank says a chargeback on the payment of $159,950 to C* Homes was initiated at the
complainants’ request on 5 June 2020 more than 12 months after the payment was made.
The pa yment could not be charged back without the beneficiary’s (C* Homes) consent which
was not provided.
A chargeback is the process of reversing a charge made on a cardholder’s credit card
account. The credit card schemes (Visa and MasterCard) have detailed rules which set out
the situations where a chargeback can be claimed. Where the payment made to the builder
Recommendation | Case number: 825730 Page 14 of 14
was not by credit card the chargeback rules will not apply. Consequently, a payment made to
the builder 12 months earlier could only be returned if the builder agreed to refund the
payment, which the builder did not do.