The insurer initially declined a water escape building claim, later accepted liability, and offered a cash settlement of about $113,184 that the complainant rejected. AFCA found the offer did not adequately discharge the insurer's obligations and ordered a repair-quote mechanism plus $3,500 non-financial loss compensation.

The insurer is bound by the policy's cash settlement option, but the offer was not actionable and did not account for repairs accepted under the claim, and claim handling caused unreasonable delay and stress.

Issues

Subjects and remedies

home or building damagenatural disasterpay non financial lossreassess claim

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination Case number 825239 Financial firm Insurance Australia Limited Determination | Case number: 730453 Page 2 of 8 Case number: 825239 8 June 2022 1 Determination overview 1.1 Complaint The complainant holds a home building and contents insurance policy (policy) with the financial firm (insurer). On 20 August 2020, a claim was lodged for damage to the insured building said to be due to escape of liquid from an underground water storage tank. The insurer initially declined the claim. However, on further review by the insurer, the decision was reversed, and liability for the claim was accepted on 24 March 2021. The insurer has offered to cash settle the claim for approximately $113,184.03 based on a quote from building consultants ‘J’. The complainant has rejected this offer and is seeking a significantly higher settlement based on a repair quote from his preferred building consultant ‘B’ in the amount of $518,690. The complainant is seeking compensation for his claims experience. 1.2 Issues and key findings Is the insurer’s claim settlement offer fair in the circumstances ? No. The insurer has not adequately assessed the full extent of it ’ s liability under the claim. This is because the proposed cash settlement is not actionable and, on balance, does not account for all the repairs to be accepted under the claim. Is the complainant entitled to compensation for service issues and delays? Yes. The insurer is to pay the complainant $3,500 in non-financial loss compensation in line with the AFCA Rules (Rules). Why is the outcome fair? The outcome is fair because although the available information shows not all the damage to the insured property relates to the claimed event, the insurer’s quote is not actionable or a fair representation of all the possible event related damage. Similarly, the quote from B seems excessive and, on balance, includes works not covered under the policy. Given the complainant ’s poor experience under the claim, it is fair that the insurer be required to pay the complainant non-financial loss compensation. 1.3 Determination This determination is substantially in favour of the complainant. The insurer is to comply with the items outlined in this determination under the heading Mechanism to settle the claim provided in section 2.1 of this determination. The insurer is to pay the complainant $3,500 for non-financial compensation. Determination | Case number: 730453 Page 3 of 8 2 Reasons for determination 2.1 Is the insurer’s claim settlement offer fair ? The policy is an insured events contract of insurance The policy covers the insured property against loss or damage caused by one or more of the listed insured events, including ‘Water and oil leaks’. Cover under these benefits is subject to the conditions, limitations and exclusions specified in the product disclosure statement (PDS). The insurer provided the complainant with the relevant policy documentation including the PDS and certificate of insurance (COI). Therefore, the panel accepts the insurer is entitled to rely on the policy provisions to assess its liability under the claim. No dispute the complainant has established a valid claim under the policy In the first instance, the complainant bears the onus to establish a valid claim. That is, damage was caused by an event covered under the terms of the policy. It is not in dispute a leak from the water tank caused damage to the property. As such, the complainant has established a valid claim. The onus therefore shifts to the insurer to show it may deny or reduce it ’ s liability by way of a policy exclusion or condition. Insurer accepted the claim but limited its liability The insurer initially denied the claim based on a report from its appointed engineering consultant ‘M’. However, on being provided with persuasive information from the complainant challenging M’s findings, the insurer acknowledged the report from M was not accurate. The insurer reversed its decision to decline the claim and is seeking to cash settle the complainant for the cost to repair damage it has assessed to be covered under the policy. The insurer relies on a scope of works prepared by its appointed engineer ‘ C ’ and a repair quote from consultants J. The insurer acknowledges the repair quote from J is not actionable as its trades are not prepared to complete the work. Further, that the quote from J is an estimation of the probable cost of repairs based on a desktop assessment, given the complainant denied J access to the insured property to complete a more accurate cost of repairs. Experts disagree on the scope/cause of damage The parties each engaged experts to assess the cause and extent of the damage. These reports conflict on some points. In chronological order the reports are summarised as follows: Insurer’s E ngineer M’s Report 28-10-2020 M inspected the property which it estimated was constructed circa 1890. It noted cracking throughout the property and says the complainant informed it some of the cracking was evident at the time of purchase, but it had become much worse in a short period of time since then. The possibility of water escaping the water tank was raised during the attendance. M concluded the tank had not leaked sufficiently to affect the property in any significant way, and all damage throughout the property was most likely to have been caused by long term ongoing seasonal movement brought about by a combination of the northern exposure, no Determination | Case number: 730453 Page 4 of 8 provision for pathways at several locations along the northern elevation and significant water uptake of nearby trees. The insurer accepts this report is not an accurate assessment of the cause and extent of damage and no longer relies on this report in support of its position under the claim. Complainant’s b uilding inspector CM Report 12-11-2020 The complainant engaged a building inspector to assess the property inside and out. The author engaged an expert to conduct soil sample testing and provided a point by point analysis of M’s report disagreeing with much of its content. CM concluded the damage was caused by a large volume of water escaping the water tank and not due to general seasonal movement. With respect to providing a scope or repairs and associated costs, CM noted the difficulty with this particular circumstance is the unknown. Clearly the dwelling has heaved and settled because of the free water under the building. CM says there will have to be ongoing soil tests to ensure satisfactory soil moisture content before an evaluation for scope of repairs can be completed. On review of this report, the insurer accepted the claim and engaged its expert C to further investigate the damage. Insurer’s e ngineer C’s reports 24-4-2021 and 18-8-2021 C provided a report and scope of work. The report noted several items believed to be maintenance issues or otherwise unrelated to the claimed event, but agreed water escaping the tank had caused significant claimable damage. C noted the property was 120 years old and misalignment was to be expected and identified certain points for underpinning based on the flooring level survey. Given this, underpinning would also not likely realign the northern wall where the water tank was located, and where most of claimable damage was considered to be. It also recommended a suitably experienced and qualified underpinning contractor attend the site to provide a technical assessment and detailed quote but cautioned misalignment of floor levels remote from the northern side were considered pre-existing and not as a result of the claimed event. Following several questions being raised about underpinning, the complainant agreed to the resulting scope of work. However, a dispute arose around the cost of repairs due to materials, labour and repair methods differing significantly. Insurer’s b uilder J 3-9-2021 The insurer’s builder J estim ated the cost of repair at $82,539.02. The following disclaimer is written on the quote: THE FOLLOWING SCOPE IS BASED UPON ENGINEERING SCOPE PROVIDED BY CFT BUILDING CONSULTANTS & ENGINEERS. THE FOLLOW ING SCOPE WOULD BE SUBJECT TO VARIATIONS BASED UPON SITE CHECK MEASURE. PLEASE NOTE DUE TO THE PRE-EXISTING DETERIORATING CONDITION OF THE PREMISES FROM AGE WEAR AND TEAR, WE ARE UNABLE TO WARRANT REPAIRS AND RECOMMEND CASH SETTLEMENT. Determination | Case number: 730453 Page 5 of 8 J did not attend the property to confirm costings and repair methodology. The insurer subsequently agreed the quote was not actionable and significant variations would likely be required. As such, the panel accepts this quote is not an accurate representation of costs required to reinstate the property to its pre-incident condition. J also provided a separate underpinning quote for $31,416.00. Complainant’s b uilder B 23-6-2021 The complainant provided an independent and actionable quote from builder B in the amount of $518,690.00. The insurer rejected the quote saying it was unnecessarily high. It referred the matter to an internal technical assessor who recommended a cash settlement more in line with J’s quote. The panel notes the sum insured for the property is $476,000.00. Complainant’s u nderpinning specialist ‘ U ’ 11-12-2021 C recommended an underpinning specialist attend the property for a cost accurate quote. The insur er’s builder J provided a quote which was not based on an actual attendance. As such, the complainant engaged independent specialist U to provide a full scope and actionable quote in the amount of $85,305.00 including GST. The panel notes U’s scope mentions using its own unique and patented method. It also appears to be intended to realign all areas of the property, not just those affected by the claimed event and which would exceed cover available under the policy. U has not provided a detailed scope of repairs identifying what works and in what areas such works will be completed. On review of the above quotes, the panel accepts three things:  the quotes essentially follow the same scope of work except for the underpinning  t he insurer’s quote is not actionable and therefore not an accurate reflection of the cost of repair  t he complainant’s quote appears excessive in terms of its costings. Insurer entitled to cash settle the claim and limit its liability The panel accepts the policy allows the insurer to decide how a claim is settled, including settling the claim by way of a cash settlement. The insurer offered the following as full and final settlement:  J ’s repair quote (excluding underpinning $15,000.00) $48,055.02  plus, quote for underpinning - $24,000.00  plus, Builders Margin 19% - $13,690.45  plus 10% GST - $8,574.55  total amount: - $94,320.02  plus 20% uplift - $18,864.01  full and final offer = $113,184.0 The complainant says the insurer does not take in to consideration the following:  J’s quote is not actionable and will require variations as the work progresses  the remote location of the property means builders will need to travel to the site, have all materials delivered and possibly obtain accommodation during repairs  a large increase cost of repair due to Covid and other factors. The panel as noted above, accepts the insurer is entitled to cash settle the complainant and limit its liability under the claim. This settlement method is preferred where there exists pre- existing damage that may impact on the insurer’s ability to complete repairs. Determination | Case number: 730453 Page 6 of 8 The complainant does not dispute there exists damage to the building which pre-existed the insured event and/or that is consistent with ongoing seasonal movement over the years. However, the complainant says, and the panel accepts, the insurer’s quote is not a t rue and accurate reflection what it will cost to repair the damage accepted under the claim. The panel accepts the opinions from the various consultants, that given the age of and nature of the damage the necessary underpinning works may result in additional damage and increase building repair costs. Mechanism to settle the claim Having reviewed the available material, the panel is not satisfied the insurers offer sufficiently discharges its obligations under the claim. However, it is also not satisfied the complainant’s quotes are reasonable and appear excessive in the circumstances. The complainant had declined access to the insurer’s consultants to undertake further assessments so to complete a more accurate scope of works and costing. The complainant has also faced difficulty in locating and appointing a consultant to assess and provide a quote for repairs to the damage accepted under the claim. As such, the panel determines, within 14 days of the complainant accepting this determination, the insurer is to provide the complainant with details of three independent and adequately qualified consultants from its panel of repairers. The complainant is to choose two of these repairers who will attend the insured property to provide repair quotes based on C’ s scope of works, which has been agreed between the parties (including necessary underpinning works). The quotes are to include an estimate for the time for the repairs to be completed: The insurer, within 21 days of receiving the two quotes, is to then arrange a cash settlement to the complainant based on and including:  the higher of the two quotes  the travel/accommodation costs, if any, for the trades as well as any required building permits or other sundry costs  the selected quote is to be increased to include the insurer’s proposed model of 19% builder’s margin if not already accoun ted for in the quotes, as well as the proposed 20% uplift to a maximum of the policy sum insured  any additional benefits under the policy such as temporary accommodation for the expected duration of the repairs based on the estimate from the repairer, if required  the insurer is to reimburse the complainant for expenses he has incurred, if any, in arranging the consultants’ reports, up to a maximum of $5,000 upon provision of paid invoices. 2.2 Is the complainant entitled to compensation? Complainant entitled to compensation for service issues and delays The AFCA Rules allow for an award of up to $5,400 for non-financial loss compensation where an insurer’s actions caused the complainant to suffer an unusual degree or extent of inconvenience, delay or interference. AFCA takes a conservative approach when considering any award of compensation. Determination | Case number: 730453 Page 7 of 8 In this instance and considering AFCA’s approach to compensation, the panel accepts the insurer’s overall management of the claim was not to a level which would reasonably be expected from a professional organisation for the following reasons:  the insurer initially incorrectly denied the claim requiring the complainant to engage an independent expert to appeal this decision  t he insurer’s quote was not actionable, nor did it take into consideration the complainant’s concerns around increased costs for materials and labour, or account for variations.  the matter has been unresolved since lodgement in August 2020, more than 18 months prior  claim file notes indicate the initial denial took approximately 4 months and the decision was not overturned for another 4 months, which are considered unreasonable delays in the circumstances. Overall, the panel is satisfied the above items would reasonably have caused the complainant to suffer an undue degree of stress, inconvenience and physical inconvenience. The panel determines the insurer is to pay the complainant $3,500 in non-financial loss compensation. Why is the outcome fair? The outcome is fair because although the available information shows not all the damage to the insured property relates to the claimed event, the insurer’s quote is not actionable or a fair representation of all the possible event related damage. Similarly, the quote from B seems excessive and, on balance, includes works not covered under the claim. G iven the complainants’ poor experience under the claim, it is fair that the insurer be required to pay the complainants non-financial loss compensation. Determination | Case number: 730453 Page 8 of 8 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. A panel determined this matter Due to the nature of this complaint, we referred it to a panel for determination. The panel includes:  an ombudsman  a member with significant experience in consumer and small business advocacy  a member with extensive experience in the insurance industry. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.