Home / Suncorp Group / Determination 823725

Determination 823725

Storm damage claim to garage floor and walls denied

FirmSuncorp Group
Decided2021-12-20
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainant claimed storm damage to a garage floor and walls, which the insurer denied as gradual deterioration after the complainant repaired the damage without consent before an engineer could inspect. AFCA found the insurer entitled to deny the floor and wall damage claim.

The policy excludes gradual deterioration and prohibits repairs without the insurer's consent, and the complainant's repairs prejudiced the insurer's ability to review the cause.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 823725 Financial firm AAI Limited Determination | Case number: 823725 Page 1 of 5 Case number: 823725 20 December 2021 1 Determination overview 1.1 Complaint The complainant holds a home and contents insurance policy with the financial firm (insurer). On or about 24 March 2021, the complainant lodged a claim for storm damage to the home. The insurer agreed to cover some of the claimed damage. It says the damage to the garage floor and walls was caused by gradual deterioration, which is excluded under the policy. It also says its ability to properly review this damage was compromised by the complainant’s decision to repair it without informing the insurer. The complainant disagrees and seeks cover for this loss. 1.2 Issues and key findings Is the insurer liable for the garage floor and wall damage? No. The insurer is entitled to deny the complainant’s claim for floor and wall damage. Why is the outcome fair? The exchanged information shows the insurer obtained expert evidence which cast doubt over whether the loss should be covered. When the complainant challenged this, the insurer agreed to involve an engineer to review the damage. The complainant repaired the damage before the engineer could inspect it. The insurer ’s policy entitles it to exclude claims where repairs are completed without the insurer’s consent. Given the complainant did not permit the engineer to review the floor and wall damage, it is fair that the insurer is allowed to deny this part of the claim. 1.3 Determination This determination is in favour of the insurer. The insurer is entitled to exclude the claim for the floor and wall damage. It is not required to take any further action in relation to the claim. Determination | Case number: 823725 Page 2 of 5 2 Reasons for determination 2.1 Is the insurer liable for the garage floor and wall damage? No. The insurer is entitled to deny the complainant’s claim for floor and wall damage. Complainant says loss should be covered by the insurer The insurer accepted a claim for some damage at the property. It does not accept the claimed damage to the garage floor and walls. The complainant says this damage was caused by a storm. The insurer obtained a report from builder ‘HR’ which says the garage floor and wall damage was due to gradual deterioration and possible termite activity. The insurer says the policy excludes these causes. The complainant says he does not believe HR was ‘qualified in pest control’ and therefore considers his views on possible termite infestation irrelevant. He also says the insurer has not provided this person’s qualifications at all (despite being asked for them). Whilst the insurer later tried to arrange an engineer, the complainant says he was away when this person made contact. Weeks went past before the engineer called him again. The complainant says this person only gave him five minutes notice for the visit and the complainant refused (though he says the work was almost completed by this time anyway). Only one expert gave an opinion on the damage Given the relevant repair work was almost completed by the time the engineer contacted the complainant, the only available expert opinion on the unrepaired damage is HR’s. HR ’s report dated 19 April 2021 and noted:  the complainant said a ‘large amount of ground water entered the garage area of the home during a recent storm’ and this caused damage to the skirting and the epoxy floor covering  after this, the complainant undertook waterproofing to the exterior wall to prevent it reoccurring  HR considered the damage was ‘not consistent with a single insurable event’ and due to gradual deterioration  the skirting had rotted and there was evidence of ‘termite activity’  the coating of th e epoxy flooring is ‘flaking and bubbling’, which is also due to gradual deterioration. The complainant raised concerns over HR’s conclusions and credibility . HR’s website says it employs professionals with industry experience and qualifications to review building claims for insurers. I accept HR is suitably qualified to review and provide an opinion about the damage. As outlined above, the insurer also tried to arrange for an engineer to review the cause of the damage. This was because the complainant did not accept HR’s view . The insurer agreed to appoint the engineer on 14 May 2021. However, no suitable time could be mutually agreed. On 23 June 2021 the complainant informed the insurer he had arranged his own repairs and these were almost complete. As the complainant did not want the engineer to attend, the insurer did not proceed with this inspection. It therefore based its decision about the garage floor and wall damage solely on HR’s report. Determination | Case number: 823725 Page 3 of 5 Policy provides cover for accidental damage subject to terms and conditions The insurer’s policy is made up of the Certificate of Insurance (COI) and the Product Disclosure Statement (PDS). There is no dispute the insurer sent these documents to the complainant. The PDS provides cover for a series of listed events. Included in this is an option for accidental damage, which the complainant selected. ‘Accidental damage’ is defined as ‘ loss or damage that occurs without intent ’. For building damage, cover for ‘accidental damage at the home’ says: we cover your home for accidental loss (e.g. losing something) and accidental damage (e.g. breaking or damaging something) during the period of insurance. The policy excludes losses caused by, arising from or involving: wear, tear, rust, fading, rising damp, mould, mild ew, corrosion, rot… or gradual deterioration such as but not limited to: – [ … ] – gradual weathering and breakdown of bricks, mortar or concrete. When making a claim, the PDS says what an insured person must not do: – do not carry out or authorise repairs without our consent unless you cannot contact us and need to make emergency repairs to protect your home or contents [ … ] – do not negotiate, pay or settle a claim with anyone else unless we agree If a person does not comply with the above, the PDS says the insurer can: reduce or refuse your claim and/or recover costs from you or cancel your policy. Complainant elected not to wait for the engineer to inspect the damage Whilst I am not persuaded there is strong evidence of termite infestation, I accept there was evidence of gradual deterioration. HR noted the wall skirting had rotted and the damage to the floors was consistent with ongoing water inundation. This is not consistent with a single incident of storm or accidental damage. As the insurer excludes losses caused by gradual deterioration, this means the insurer likely had grounds to deny the claim. I accept more would have been learnt it the engineer attended the home. This did not happen as the complainant undertook the repairs without obtaining the insurer ’s consent . The complainant says he arranged the repairs as the review process took too long. Between the insurer’s decision to appoint the engineer ( 14 May 2021) and the complainant informing the insurer of the work nearly being finished (23 June 2021) was 40 days. The work undertaken by the complainant started before 23 June 2021. Determination | Case number: 823725 Page 4 of 5 I do not agree the delay with the engineer was too long, noting:  during this period the insurer had to identify, select and appoint the engineer  the engineer had to arrange a time with the complainant that was mutually agreeable  when contact was initially made, the complainant says he was away  after a second attempt was made, the complainant said repairs were almost complete. The PDS outlines that an insured person cannot authorise repairs without consent (unless they are unable to contact the insurer, or it was necessary for safety reasons). I am not satisfied either reason was present in this instance. Where an insured person authorises repairs without consent, the PDS says the insurer may reduce or refuse to pay the claim. The insurer says the complainant’s decision to repair the damage before the engineer’s inspection meant it is entitled to deny the claim. Insurer is not required to cover the damage to the garage floor or the walls The only expert evidence about the damage is from HR. There is no contrary evidence to challenge HR’s view that the loss should not be covered. By proceeding with repairs prior to the engineer’s attendance, the complainant did not permit the insurer to fairly review the claim. He also impacted his own ability to provide sufficient information to show the damage occurred from a storm event or an occurrence of accidental damage. That is, rather than it being a result of gradual deterioration as suggested by HR. Given the insurer’s policy permits it to deny claims where repairs have been authorised without consent, I accept it is fair for the insurer to deny the claim. The complainant’s decision to proceed with repairs prejudiced the insurer. The engineer was unable to review the damage and this affected the insurer’s ability to better understand what caused it. The complainant did not provide any evidence to show the loss occurred due to a one-off storm event. He also did not allow the engineer to attend. It is fair in these circumstances for the insurer to rely on HR’s report regarding the cause of the loss being deterioration over time. This means the insurer is not liable for the claimed damage to the floors or the walls. Determination | Case number: 823725 Page 5 of 5 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.