Home / Westpac / Determination 819194

Determination 819194

Storm damage claim declined for defective roof construction; make safe and claims handling disputed

FirmWestpac
Decided2022-07-25
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$2,000
Amount claimed$242,800
SourceAFCA PDF

Summary

The complainant's home roof was damaged in a March 2021 storm and the insurer declined the claim on the basis of defective roof construction, an excluded cause. AFCA found the claim was rightly declined and the insurer's make safe works did not cause extra loss, but ordered $2,000 compensation for claims management delay in communicating the builder's opinion.

Proximate cause of the damage was the excluded defect in roof construction rather than the storm, so the insurer could decline; compensation awarded for interference with enjoyment and peace of mind.

Issues

Subjects and remedies

home or building damagenatural disasterpay non financial loss

Related

All Westpac determinations · Find similar determinations

Text of the determination

Determination Case number 819194 Financial firm Westpac General Insurance Limited Determination | Case number: 819194 Page 2 of 13 Case number: 819194 20 June 2022 1 Determination overview 1.1 Complaint The complainant lodged a complaint after the financial firm (insurer) declined her claim under her home insurance policy, for damage to her property in a storm event in March 2021. The insurer declined the claim because it says its expert evidence establishes the proximate cause of damage was defective and poor construction of the roof, which is excluded under the policy. The complainant also challenges the insurer’s claims management and its decision to undertake extensive make safe and demolition when it knew the claim would be declined. 1.2 Issues and key findings Is the insurer entitled to deny the claim? Yes. The available information establishes the proximate cause of the damage was not the storm event but the defective construction of the roof. As this cause of damage is excluded from cover, the insurer is entitled to decline the claim. Did the insurer’s conduct contribute to further damage to the property? No. In view of the severity of the storm, the fact that a substantial part of the roof was blown off in the storm, photographs of the initial damage and the initial substantial repair and make safe estimates provided by the insurer, the panel does not accept the property could have been repaired at any stage for as little as $30,000/$40,000. The available evidence does not establish the insurer’s conduct caused or contributed to further damage or repair costs. Is the complainant entitled to compensation? Yes. The available information establishes an award of compensation is warranted. Why is the outcome fair? The insurer is entitled to rely on its policy terms and expert opinion. As the expert opinion does not establish the damage was caused by the insured event of storm, it would not be fair to require the insurer to pay the claim. As the available material does not establish the insurer’s conduct and make safe works contributed to any additional costs to the complainant, it would not be fair to require the insurer to pay the complainant’s repair costs. 1.3 Determination This determination is mostly in favour of the insurer. Should the complainant accept this determination then within seven days of notification of acceptance, the insurer is to pay to the complainant $2,000 compensation. Otherwise, the insurer is not required to take any further action in relation to the claim or the complaint. Determination | Case number: 819194 Page 3 of 13 2 Reasons for determination 2.1 Is the insurer entitled to deny the claim? Complainant must establish storm caused damage The complainant must establish on the balance of probabilities she has suffered a loss caused by an event to which the policy responds. This is known as a prima facie or valid claim. In the context of this claim, the complainant must establish the claimed damage was caused by the storm event. Once so established, the onus shifts to the insurer to prove on the balance of probabilities that an exclusion applies if it seeks to deny or limit its liability for the loss. The insurer says the proximate cause of the claimed damage was not the storm event but defective construction of the roof which directly contributed to the roof lifting off during the storm event. The complainant holds a home insurance policy providing cover for a series of insured events occurring during the period of insurance, including storm subject to limitations and exclusions. Submissions and material considered On 20 March 2021 the complainant reported to the insurer a recent mini tornado pulled the roof off her insured property causing damage and water ingress. When the insurer declined the claim, she argued the material provided by the insurer did not establish the wind speed at the insured property. She says the damage was localised and her street was hit by a strong tornado. She provided reports and photographs of other damaged properties in her neighbourhood. She contends:  while the insurer says the existing roof batten tiedown connections were inadequate to withstand the uplift forces it did not establish the wind force which caused the damage  the wind speed sheet relied on by the insurer was not sufficiently near the insured property  it was a tornado not a normal wind which caused the damage. The insurer says:  the damage is a result of the defective roof which lifted in the storm allowing rain to enter  if the roof was built in accordance with Australian Standards it would been abl e to withstand wind gusts of up to 122.4km/h. In support of its position, the insurer has provided three expert reports. A summary of those reports is set out in supporting section 3.3 of this determination. The builder (MK) inspected and photographed the property on 22 March 2021. He concluded the roof was not built to Australian Standards as it used minimal mechanical fixings which would have contributed to the roof sheets being blown off during the storm. A roofer (K) inspected and photographed the roof on 20 May 2021. He also criticised the way in which the timber roof battens had been fixed to the rafters. A structural engineer (IE) inspected and photographed the roof on 2 June 2021. The engineer undertook a structural analysis of the battens and tiedowns and analysed the wind uplift forces on the roof battens. He concluded the existing roof batten tiedown connections were Determination | Case number: 819194 Page 4 of 13 inadequate to withstand the expected wind uplift forces. He said the connections were not compliant with Australian Standards. He later added that the roof framing must be designed to withstand a gust wind speed equivalent to 122.4km/h. Proximate cause of damage was not the storm but a defect in the roof’s construction The panel notes the Beaufort wind force scale which is an empirical measure that relates wind speed to observed conditions at sea or on land. On that scale, windspeed of up to 122.4 km/h is an extremely strong hurricane wind which causes devastation. While the panel accepts an extreme weather event occurred, having considered the photographs and material provided about the extent of damage, the panel does not accept the weather event included wind speed gusts as high as 122.4km/h. Further, the complainant has not provided any expert evidence to rebut the three opinions provided by the insurer. Having considered the available material, the panel is satisfied the proximate cause of the damage (that is the effective or operative cause) was not the storm event but the defect in the roof’s construction. As this cause of damage is excluded from cover, the panel is satisfied the insurer is entitled to decline the claim. 2.2 Did the insu rer’s conduct contribute to damage to the property? Submissions and material considered The complainant says even if the insurer establishes the claimed damage was not caused by storm, she says the insurer’s conduct contributed to the damage to the proper ty. She contends:  if the insurer’s first contractor had properly made the property safe it could have minimised damage – instead a proper make safe was not made until two days later  SES did not install the plastic tarp – it was installed by the complainants  the property was still liveable regardless of mould  the eventual make safe/remediation made the property uninhabitable  the make safe left the complainant with an estimated rectification cost of $300,000 instead of roof damage repairs of about $30,000/$40,000  if the roof was not built to Australian Standards then this information could have been provided by the insurer earlier  had the insurer’s position been explained earlier she could have decided about the extent of make safe and demolition  she would not have stripped the roof sheets to fix the battens under the sheeting. The insurer says its contractors did not negatively impact the complainant or worsen the damage. It submits:  make safe repairs are a temporary repair to mitigate further damage  its policy provides an additional benefit if the home is unsafe ensuring that even if the claim is declined the property is made safe without delay  further make safe works were required to ensure the property was watertight, to prevent further damage and mould Determination | Case number: 819194 Page 5 of 13  after completing the make safe to preserve the property after the storm some areas could not be preserved  the make safe works did not leave the complainant with further costs  the roof sheeting and battens were compromised and could not be left on the roof. The panel notes the insurer’s contractors attended the property a short time after the claim was made. The insurer’s instructions to the contractors include the observation that “ customer has SES organised so no make safe is required .” The builder MK attended the property early on 22 March 2021. He says most of the roof was blown off with roof sheets and batten timbers landing in the backyard. He noted the emergency repairs had failed. MK reports: On 22 March 21, we met with the (complainant) who advised our Consultant the property has sustained significant damage due to the freak weather event and localised tornado. The Insured advised the State Emergency Services had attended on the date of loss and installed a plastic tarp to the roof. The first report from the insurer’s adjuster also refers to the fact the initial make safe was completed by the SES. The insurer’s contractor provided an invoice which shows at least eight hours work was done on 20 March 2021 to make safe. The invoice does not specifically refer to work to the roof. Later invoices for work done on 25, 26 and 27 March refer to the roof make safe. The complainant is adamant the SES did not make safe the roof but that she and her husband had to unsuccessfully cover the roof because the insurer’s contractors would not go on the roof saying it was unsafe at the time. Having considered the numerous emails from the parties and material provided by the insurer from its contractors the panel accepts the initial make safe (whoever performed it) required further reinforcement which was undertaken on 22 March 2021 to ensure the building was completely watertight. This further work was extensive as evidenced by the builder’s invoice ($6,886). The work included removing compromised roof sheeting and battens, installing ply sheets across the rafters and then securing the tarp. The material shows as most of the sheeting and insulation was blown off the roof further work included removing the remaining roof sheeting and the waterlogged insulation. On 23 March 21 the insurer’s estimating manager (A) attended. His report shows urgent make safe was required to prevent further damage. The insurer’s contractors undertook this work for the next several weeks as evidenced by several reports to the insurer. A also provided further information on this issue which is summarised in supporting section 3.3 of this determination. The insurer obtained the expert reports referred to earlier in this determination. Based on those reports the claim was declined on 17 June 2021. By this time, extensive demolition works were undertaken including mould remediation. A scope of works was prepared. On 20 May 2021 the insurer’s contractor provided a quotation for repairs based on the scope of works for $326,474.10. The insurer’s contractor invoiced the insurer for make safe repairs in July 2021 in the sum of $80,053.03. This latter cost was borne by the insurer. Determination | Case number: 819194 Page 6 of 13 These amounts were not significantly different from the initial estimates provided by A on 23 March 21 which was that the make safe would cost $70- $80,000. A’s initial repair estimate was about $450,000. The complainant obtained an invoice to repair the damage in July 2021 for $242,800. The complainant says she has completed repairs and paid her contractor. Insurer’s conduct did not cause or contribute to further damage or costs The panel has carefully considered the parties’ submissions and their material including photographs. Having considered the available material, the panel accepts the initial make safe required further work. However, as this make safe was an emergency repair, in view of the weather conditions and the further significant work which was required the panel does not consider the initial make safe (whoever performed it) was defective in all the circumstances. Further, in view of the nature of the storm event in which much of the roof had blown off, the panel accepts significant damage including water damage would have already occurred and that water damage should be repaired quickly. Initial reports indicate the contractors needed to get access to external walls to remove insulation and to aid drying out, so some rooms could not be preserved. In the circumstances, the panel also accepts mould damage was likely and required remediation and internal stripping out to prevent further damage. The panel does not accept a property is still liveable regardless of mould. The complainant has the onus to establish the insurer’s conduct has caused the cost of repairs to increase dramatically. She has provided no expert opinion to support her contention. In view of the severity of the storm, the fact that a substantial part of the roof was blown off in the storm, photographs of the initial damage and the initial substantial repair and make safe estimates provided by the insurer, the panel does not accept the property could have been repaired at any stage for as little as $30,000/$40,000. In view of the poor construction of the roof, the panel considers repairs to the roof were unlikely to be simple and inexpensive. This is because the roof was extensively damaged in the storm, and, to make the property waterproof, the roof was significantly altered. The panel considers significant work would have been required to repair or replace the roof at any stage. Because of the water damage and extensive damage to the roof, the panel accepts make safe works were required to prevent mould damage which if not dealt with promptly would have resulted in a costly mould remediation and probable further demolition to access the mould. The panel accepts this is likely even at an early stage because of the extensive damage to the roof and ensuing water damage. Having carefully reviewed the available information, it is the panel’s view the insurer’s conduct did not contribute to further damage. The policy requires the insurer to assess the damage and make safe while investigating the proximate cause of damage to determine whether the policy responds to the claim or not. Although the complainant criticises the time taken for the insurer to make a claims decision, the panel considered it was not unreasonable for it to seek further opinion from a roofer and an engineer in view of the claim potential. In short, based on the available information, the panel does not accept the insurer’s claims handling and make safe works contributed to any additional costs to the complainant. The insurer is not liable for the complainant’s claim for the cost of repairs. Determination | Case number: 819194 Page 7 of 13 2.3 Is the complainant entitled to compensation? Compensation paid in some circumstances AFCA will award compensation (capped at $5,400) if there has been an unusual degree or extent of physical inconvenience, time taken to resolve a complaint or interference with the complainant’s expectation of enjoyment or peace of mind. AFCA takes a conservative approach to awarding compensation. We do not award compensation because the complainant has suffered some inconvenience and anxiety. AFCA expects complainants to be moderately robust and to bear the normal degree of inconvenience experienced when a problem occurs and to take reasonable steps to manage the situation. Fair the insurer pays the complainant $2,000 compensation. The complainant has several issues about how the claim was managed including the failure by the insurer to advise her of the builder’s opinion earlier. She says she should have had the right to make an earlier decision about how to proceed with repairs. The available material shows MK inspected the property on 22 March 2021 but did not provide the report to the insurer until 20 April 2021. The claim was formally declined on 17 June 2021. As set out earlier in this determination, the panel does not criticise the insurer’s engagement of a roofer and an engineer before reaching its final decision particularly in view of the potential of the claim. However, the panel considers the insurer could have been more proactive in obtaining and providing the opinion from MK and keeping the complainant more formally appraised of its builder’s opinion and the possible policy response. While not determinative of the outcome, the panel considers this aspect of claims management has interfered with the complainant’s expectation of enjoyment or peace of mind. The panel considers an award of compensation is warranted in the amount of $2,000. 2.4 Why is the outcome fair? The insurer is entitled to rely on its policy terms and expert opinion. As the expert opinion does not establish the damage was caused by the insured event of storm, it would not be fair to require the insurer to pay the claim. As the available material does not establish the insurer’s conduct and make safe works contributed to any additional costs to the complainant, it would not be fair to require the insurer to pay the complainant’s repair costs. Determination | Case number: 819194 Page 8 of 13 3 Supporting information 3.1 Process AFCA’s approach to this complaint This matter was determined by a panel Due to the nature of this dispute, it has been referred to a panel for determination. The panel comprises the ombudsman, a member with significant experience in consumer and small business advocacy and a member with extensive experience in the insurance industry. The panel has decided this complaint based on what is fair in all the circumstances, having regard to legal principles, applicable industry codes or guidance, good industry practice and previous relevant determinations of AFCA or predecessor schemes (which are not binding) A full exchange of the relevant information has taken place between the respective parties. Each party has had the opportunity of addressing any issues raised. All the provided information has been reviewed and considered. The parties have raised numerous issues in their submissions to AFCA. However, commentary in this determination is restricted to those issues considered relevant to the outcome. It is an accepted principle of general insurance law that the insured bears the onus to establish on the balance of probabilities that they have suffered a loss caused by an event to which the policy responds. This is known as a prima facie or valid claim. Once so established, the onus shifts to the insurer to prove on the balance of probabilities that an exclusion applies if it seeks to deny or limit its liability for the loss. Caselaw and proximate cause Case law establishes:  The proximate cause of the loss is the dominant or effective or operative cause of the loss whether or not that be the last in time or the sole cause.  If there are several causes operating contemporaneously, each must be examined for the qualities of reality, predominance and efficiency as the active, efficient cause that sets a relevant chain of events in action. If one cause would have caused the harm in any case, and the other would not have done so in the absence of the first, the first is the proximate cause.  A common-sense approach is taken to determine proximate cause. How we assess complaints AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider available documents, the recollections of the parties, and all relevant circumstances. We give more weight to documents created at the time the events occurred. If there is no relevant documentation, we will decide what is most likely to have occurred based on the information provided to us. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. Determination | Case number: 819194 Page 9 of 13 3.2 Relevant policy terms The relevant policy extracts are referred to in the correspondence between the parties and in the insurer’s Notice of Response. Both the policy document and the Notice have been exchanged with the complainant. Your policy does not cover any loss or damage that is caused by or arises from: Maintenance and building ▪  defects in design, structure, materials, workmanship or construction, 3.3 Extracts from material relied on by the parties Date Action Email from insurer’ s estimating manager (A) to insurer 23 March 21  A’s estimating manager attended site today and advis es much to be arranged urgently as part of a make safe to prevent further damage to the property:  Building consultant to be engaged to put together a scope of works.  All internal areas (ground floor and first floor), including the kitchen and wet areas, to be stripped of plasterboard, insulation, fixtures/ fittings/ tiling to wet areas and all fixed cabinetry/ joinery.  Dryin g regime to be inc orporated to dry out the property and prevent further mould development.  Roof to be entirely stripped and then properly resealed to prevent further water ingress (ideally with ply and tarp/ plastic making it watertight) .  Please note that the above is looking at costing approximately $70,000 - $80,000.  Please also note repairs estimated to be $450, 000. Report (A) 30 March 21  Inspected property 22 March 21 .  Mini cyclone/recent storm activity caused widespread damage .  Initial make safe completed by SES and then by A  Subsequent to inspection at a break in the weather initiated further mak e safe to ensure house watertight as water dripping through the ceilings to the first and ground floors .  Water damage means house must be stripped out to enable a drying regime and to eliminat e mould  Describes wides pread water damage throughout the first and ground floors .  Most colorbond sheeting and anticon insulation had blown off on the roof area, as part of the second make safe remo ved the remaining roof sheeting which exhibited pedestrian damage from make safe works and needed to be removed to also remove the waterlogged anticon blanket.  D amage observed to the parapet wall cladding to the Determination | Case number: 819194 Page 10 of 13 front elevation parapet (both sides) and to the roof side of the rear parapet wall to Unit 67 .  Due to needing to get access to external walls to remove insulation and to aid the drying out regime, we will not be able to preserve the Ensuite, Bathroom or Laundry.  Damage to the roof sheeting due to an opening in the roof that had been covered up prior to our inspection, pedestrian damage which may have been pre - existing but may also have been caused by SES and maybe other trades carrying out make safe works during the height of the storm.  Damage to t he soffit lining to the front elevation first floor area to Unit 67 as well.  D amage had been caused by what was report ed as a mini cyclone during recent storm activity and subsequent water ingress due to extensive main roof damage over Unit 67. Building inspection report (MK) 20 April 21  Inspected and photographed property 22 March 21 .  Complainant claimed significant damage due to freak weat her event and localised tornado .  SES installed the plastic tarp to the roof .  Most of the roof blown off: roof sheets and batten timbers dislodged landing in the backyard impacting the shed fenc es and roofs .  Original emergency repairs to roof had failed. Plastic and tarps were bulging with water. Water damage and dripping water to all the upstairs bedroom ceilings walls and to the shared areas in the stairwell .  All downstairs rooms have also sustained extensive water damage with water dripping through all floors and all ceilings .  Significant building damage has occurred due to heavy sustained rainfall and damage to the compromised roof.  Arranged for builders to undertake emergency repairs to the roof to stop rain coming in. Builder conducted extensive make safe installing ply sheets across the rafters and secured the tarp .  Noted roof battens had been nailed down wit h a single shot per batten. Proper building practice allows for heavy duty batten screws to prevent uplift.  Reinstated electrical emergency repairs to the adjacent side of the duplex where the complainant relocated (noted meters have not been to install d espite house being there for 12 months).  Builder re - attended to undertake emergency water extraction and an int ernal make safe to prevent ceilings collapsing and further damage.  A already attending to undertake emergency repairs . Determination | Case number: 819194 Page 11 of 13  Concluded roof is not to Australian Standards and what was inspected was of poor building practice using minimal mechanical fixings which would have contribut ed to the roof sheets being blow off .  Recommend complainant contact the builder as damage should be covered by builder’s warranty. Roofer (K) 20 May 21  Inspected and photographed roof 20 May 21 .  Did not inspect the main roof because it was tarped but removed roof sheets from a lower - level roof and found timber roof battens had been mechanically fixed to the rafters with a two machine driven nails per raft er .  To properly support the connection between the battens and the rafters the fixings need to be a combination of both nails and bugle b atten screws in a one - to - one ratio across the roof to ens ure a secure fit between the joining timbers. Structural engineer (IE) 7 June 21  Inspected and photographed roof with adjuster and roofer on 2 June 21 .  Roof tarped, and roof sheets and battens re moved  Describes and photographs raft er spacing and nails  Site has N1 wind classification in accordance with AS4055 .  Building in final stage of construction when roof damage occurred .  Undertook structural analysis of battens and tiedowns based on Australia n Standard and analysed wind uplift forces on roof battens .  Existing roof batten tiedown connections are inadequate to withstand the expected wind uplift forces occur within 1200mm ends of the roof edges.  Roof batten tiedown connections are not comp liant with Australian Standards. Email structural engineer (IE) 17 June 21  In accordance with AS 4055 – 2012, the roof framing of this building would have to be designed to withstand an ultimate design gust wind speed of 34m/s (Class N1), which is equivalent to 122.4km/h.  If the batten fixings are compliant with the Australian Standards, they should not have failed at the gust wind speed of up to 122.4km/h. Email from A to insurer 21 October 2021  A arranged make safe works and tenders for repairs.  Attended site on the 23/03/21 and emailed to advise of the severity of damage and the need for major make safe works to prevent further damage and mould infestation.  Not aware there was an issue pertaining to the roof structure that would result in the claim being denied.  Couple of attempts made prior to my attendance to make the roof watertight by means of tarping the roof Determination | Case number: 819194 Page 12 of 13 area, where about half the roof was missing.  Previous make safes were not successful in keeping the effects of the weather out of the property, the property was leaking water into the upper floor and lower floor level upon my initial attendance and unless the property could be successfully tarped to prevent further water ent ry the dwelling would succumb to wides pread furt her water damage and mould infestation, which would res ult in more costly repairs and/or complete demolition of the property.  Decided the remainder of the roof sheeting and roof insulation to be removed so we could adequately tarp and mak e the dwelling weather tight, then proceeded with internal strip out and mould remediation.  These works were required to prevent the dwelling becoming infested with mould whic h would have resulted in a very costly mould remediation and/or complete demolition of the majority of the dwelling to acces s the mould.  On the 23/04/21 insurer emailed our office querying the installation method of the roof sheeting advising that the roof sheets were not installed correctly and that this was the cause of the failure of the roof .  On the 26/04/21 I emailed insurer photos of the roof .  On the 28/04/21 insurer provided MK report saying the roof batten installation was not compliant.  Looking through our file notes and emails to trades, we had completed the demolition works just prior to 28/04/ 2021 and were engag ing the mould restoration team to commence the mould remediation.  Noting the level of water damage observed in the report from MK and their recommendation of further make safe works being required to remove the remainder of the roof sheeting to the dwellin g to make the dwelling watertight and to prevent further water ingress mirrors our recommendations and actions.  Our action was correct to prevent furthermore destructive and costly repairs if the water damaged and mould was not addressed with haste. Daily weather observations (BOM)  Max wind gusts SE 44kms at 13.10  ESE 9kms 9am  ENE 17kms at 3pm Determination | Case number: 819194 Page 13 of 13 3.4 Other relevant material considered and relied on  Parties’ submissions /emails and all attachments to all submissions/emails.  Expert reports.  Photographs and invoices.  Correspondence between the parties.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.