Storm damage claim: pool resurfacing, pool deck retiling and garage air vent repairs
Text of the determination
Determination
Case number 817844
Financial firm Strata Community Insurance Agencies Pty Ltd
Determination | Case number: 817844 Page 1 of 8
Case number: 817844 23 June 2022
1 Determination overview
1.1 Complaint
The complainant holds residential strata insurance with the financial firm (the insurer). On 12
February 2020, the insured property sustained water damage due to a storm event.
The insurer accepted the claim and attended to repairs except:
resurfacing the pool, as it says acid cleaning will restore the pool to its previous state
retiling the entire pool area, on the basis not all of the tiles were storm damaged
replacing a collapsed garage air vent, as it says policy exclusions apply.
The complainant wants the insurer to cover those repairs. It says the repairs are required to
address storm damage and to put the property back in the state it was in prior to the storm.
1.2 Issues and key findings
Is the insurer required to pay for resurfacing the pool?
Yes. The insurer‟s acid cleaning proposal will not return the pool to its pre-damaged state.
Resurfacing the pool will rectify the storm related staining and cracking. The insurer is to cash
settle based on the quote dated 26 October 2021 of MP, pool renovators, plus a 20% uplift.
Is the insurer required to pay for retiling the entire pool area?
Yes. It is not possible to come close to matching the colour of the undamaged tiles, so retiling
the pool deck is required to return it to its pre-damaged state. The insurer is to cash settle
based on the quotes dated 25 October 2021 of PT, tilers, and TF, supplier, plus a 20% uplift.
Is the insurer required to pay for replacing the garage air vent?
Yes. The vent structure was not a retaining wall and the proximate cause of the damage was
the storm. The insurer is to pay the cost of replacing the damaged air vent „like for like‟.
Why is the outcome fair?
The policy requires the insurer to return the property to its pre-loss condition. Therefore, it is
fair that the insurer pays the costs of resurfacing the pool and retiling the pool deck, plus a
cash settlement uplift applies to cover contingencies. The new air vent is an improvement on
the damaged version. It is fair that the insurer only pays the like for like replacement cost.
1.3 Determination
This determination is substantially in favour of the complainant.
Upon receiving written notice the complainant accepts the determination, the insurer must:
within 21 days, pay the complainant $108,816.29 (PT, TF and MP ‟s quotes plus 20%)
within 14 days, request AC to provide an estimate of what it would have cost to replace the
damaged vent like for like
w ithin 14 days of receiving AC‟s estimate, pay the complainant the estimate amount.
Determination | Case number: 817844 Page 2 of 8
2 Reasons for determination
2.1 Is the insurer required to pay for resurfacing the pool?
Yes. The insurer‟s acid cleaning proposal will not return the pool to its pre -damaged state.
Resurfacing the pool will rectify the storm related staining and cracking. The insurer is to cash
settle based on the quote dated 26 October 2021 of MP, pool renovators, plus a 20% uplift.
Parties disagree on extent of storm damage and the repairs required
It is not in dispute that the area where the insured property is located was affected by a storm
event on 12 February 2021, or that the property experienced flooding as a result. Further, the
parties agree that the property‟s inground pool was damaged.
However, the parties disagree on the extent of storm related damage and on the repairs
required to return the pool to its condition immediately prior to the storm.
Insurer says storm caused staining that can be acid cleaned
The insurer says that the storm damage to the pool is limited to staining to parts of its surface.
According to the insurer, the staining may be removed through aggressive acid cleaning.
The insurer relies on a report from its builder, WS, dated 18 March 2021. WS says:
We attended the pool … to assess staining issues with the pool after prolonged
period of exposure to stagnate water and associated algal infestation …
We appli ed a… complex acid powder to some of the more heavily stained areas...
There appears to be some slight improvement to the surface, but we would
expect a better result. We can offer a stain removal treatment for the pool with
the water in place, but there will be NO GUARANTEE offered on the result of this
treatment.
In addition, the insurer relies on a representation by BP, pool service supplier, that more
aggressive cleaning treatment will return the pool to its pre-loss condition.
The insurer also refers to comments made by BC, specialist cleaners. On 22 July 2021, BC
said that while there are very few products able to remove coloured stains from swimming
pools, they were confident their „unique product‟ would be able to do so. H owever, BC added
that „there is no guarantee‟.
The insurer submits that while there are cracks under the pool coping, these were caused by
prior subsidence. It refers to photographs of the pool said to be taken prior to the storm event.
Complainant says storm damage and required repairs are more extensive
The complainant says that the storm caused the staining and the coping cracking. It says the
only way to return the pool to its pre-damaged state is resurfacing.
The complainant relies on the report dated 25 October 2021 of AW, pool builder and
inspector. AW concludes:
Determination | Case number: 817844 Page 3 of 8
It is my opinion that the existing damage as detailed in the report is synonymous
with and directly related to the resultant effects of the flood event...
Such flood water is most likely to have impacted the subterranean sub-soils,
particularly on the western side and southern end of the pool zone and has
subsequently impacted the underside of the surround tiles and the back edge of
the coping tiles, thereby creating the existing damage. There does not appear to
be any visual evidence of prior damage to the pool before the flood event of 12
February 2020 other than the necessity to replace a couple of random areas of
surround tiles.
….
But for the fact of the flood event occurring, I believe such damage as reported
would not be evident.
AW supports resurfacing of the pool, including repair of the cracking.
The complainant also says that the photographs the insurer relies on were in fact taken after
12 February 2020. The complainant specifically notes that the photos show muddy water in
the pool and temporary fencing installed following the storm.
Pool resurfacing is required
The insurer is required to cover damage through „Replacement‟ , which the policy defines as:
the reasonable cost of rebuilding, replacing or repairing Your Insured Property to
a condition which is equivalent to or substantially the same as but not better nor
more extensive than when it was new…
I am satisfied that the complainant has established that the storm caused the staining and the
cracking, meaning resurfacing is required to return the pool to its pre-loss condition.
This is because:
AW‟s report provides a detailed analysis of the storm related damage, including by
reference to „before and after‟ photos
the insurer appears to have misinterpreted when some of the photos it relies on were
taken meaning those photos do not show pre-existing damage
none of the insurer‟s experts can guarantee that acid cleaning will remove the staining
even if the cleaning did so, it would not address the coping cracking.
Insurer is to cash settle the complainant
The policy gives the insurer the option of paying an insured the cost of repairing covered
damage, rather than attending to the required repairs. Given the deterioration of the
relationship between the parties, I am satisfied that it is appropriate that the pool resurfacing
claim is cash settled.
When an insurer cash settles a claim, it transfers to the insured the risk that the cost of
repairs may unexpectedly increase and/or that additional works not quoted are required. The
insured also loses the insurer‟s warranty that would apply to repairs arranged by the insurer.
Determination | Case number: 817844 Page 4 of 8
In the circumstances, there is a reasonable expectation that when cash settling a claim an
insurer will:
base its offer on a quote that is actionable for a retail customer, and
increase (uplift) the quoted figure by applying a fair percentage, to allow for the transfer of
risk, contingencies and loss of access to a warranty from the insurer.
The complainant has provided a quote dated 26 October 2021, from MP totalling $45,100. I
am satisfied that MP‟s quote sets out the works reasonably required to return the pool to its
pre-damaged condition.
Given the passage of time since MP provided its quote and supply chain issues affecting
construction related pricing, I am satisfied that an appropriate uplift of 20% is fair to allow for
these contingencies.
Accordingly, the insurer is to pay the complainant $54,120 ($45,100 plus 20%).
2.2 Is the insurer required to pay for retiling entire pool area?
Yes. It is not possible to come close to matching the colour of the undamaged tiles, so retiling
the pool deck is required to return it to its pre-damaged state. The insurer is to cash settle
based on the quotes dated 25 October 2021 of PT, tilers, and TF, supplier, plus a 20% uplift.
Parties disagree on extent of storm damage and the repairs required
The complainant says that the significant and extended flooding due to the storm event
caused damage to the pool deck tiling. That damage includes cracking as well as weakening,
loosening and loss of grouting and adhesive cement. The complainant suggests that the
water also led to some subsidence, leading to further cracking and movement of tiles.
The complainant says that as a result the entire pool deck should be retiled because:
it would be difficult and expensive to replace damaged tiles individually
the tiles are no longer available and the „equivalent‟ options do not come even close to
matching the colour of the original tiles
using the equivalents to replace the damaged tiles alone will result in an unacceptable
patchwork of colours, meaning the pool deck will not be returned to its pre-loss condition.
The insurer disagrees. It says there is „photographic evidence of prior movement in the
paving around the pool and noting the long term nature of the damage‟.
The insurer acknowledges that while undertaking remedial works, WS was required to
remove a section of tiles. The insurer has offered to replace those tiles only.
In relation to the lack of similarly coloured tile options, the insurer relies on the following policy
provisions:
the definition of „Replacement‟ outlined above
„ where materials used in the original construction are not readily available We will use the
nearest equivalent available to the original materials‟
„ We will not pay for the cost to rebuild or replace Your undamaged Insured Property‟.
The insurer submits that retiling the whole area, including undamaged tiles, would not be in
line with the policy and would constitute betterment.
Determination | Case number: 817844 Page 5 of 8
Insurer is to pay for retiling of the entire pool area
I am satisfied that the pool deck tiling damage is due to the storm event. The information the
complainant has provided is persuasive and includes:
Photos of the tiles before and after the storm
A number of building safety reports from 2012 onwards. Other than a note in the 2016
report of a small hole affecting two tiles and creating a minor trip hazard, there is no
reference to any issues with the pool deck prior to the storm
the 2021 building safety report, which says „ there appears considerable erosion beneath
the pool tiles causing many of the tiles becoming unstable/cracking/lifting ‟ .
The insurer has not provided any independent expert reports or other cogent information to
establish that the pool deck tiles damage was pre-existing and not due to the storm.
I note the policy provisions the insurer refers to and accept its submission that the policy does
not include a matching materials benefit. However, a policy without a matching benefit does
not provide the insurer an ability to inadequately repair the property.
The policy requires the insurer to „repair the property to a condition equivalent to or
substantially the same as before the loss .‟ The policy reference to the insurer not having to
replace undamaged property is subservient to this overarching requirement.
There is no available tiling that comes close to the colour of the original tiles. There are no
reasonably equivalent tiles. Replacing one section of a continuously tiled pool decking area in
a tile colour so different would be manifestly inadequate. It would not put the complainant into
the position it was prior to the loss and would not discharge the insurer‟s policy obligation .
Insurer is to cash settle the complainant
For the reasons set out in section 2.1 above, it is appropriate that the insurer cash settles the
retiling claim.
The complainant has provided the quotes dated 25 October 2021 from:
PT totalling $39,820 for the cost of retiling work
TF totalling $5,760.24 for the cost of tiles.
I am satisfied those quotes set out the cost of the work reasonably required to return the pool
deck to its pre-damaged condition. It is fair that a 20% cash settlement uplift applies.
Accordingly, the insurer is to pay the complainant $54,696.29 ($39,820 plus $5,760.24 plus
20%).
2.3 Is the insurer required to pay for replacing garage air vent?
Yes. The vent structure was not a retaining wall and the proximate cause of the damage was
the st orm. The insurer is to pay the cost of replacing the damaged air vent „like for like‟.
Insurer obtained expert engineering report
On 17 July 2020, KM provided a report for the insurer on the damage to the garage a ir vent.
The report says:
The vent structure was approximately 1m deep x 2m long x 1.5 m high, with a buried
section constructed of a fibre cement sheeting supported by a steel frame and an above
ground aluminium or similar louvred section (that is, the actual vent)
The purpose of the vent was to ensure fresh air circulation into the underground carpark
Determination | Case number: 817844 Page 6 of 8
The vent had performed satisfactorily until the storm event, which led to part of the buried
section collapsing
AS4678-2002 Earth Retaining Structures was the standard in existence at the time of the
building‟s construction
„that standard in many ways is written in regards to retaining walls and similar types of
structures and not necessarily for vents and building/basement wall structures‟
„ the sole purpose of the vent and its coverings would have been to mainly provide a space
for the necessary air flow to occur in and out of the basement, and simply keep the earth
out of this area ‟.
KM concluded that the vent structure was satisfactorily constructed to resist normal soil and
weather loads. However:
the inground water pressure had risen to a level where the inground water table
and associated hydrostatic [pressure] was causing the water to bubble upwards
out of the joints in the basement floor. This indicates that the inground water table
and associated water pressures were considerably higher than… normal
Due to the possibility of storms of similar size as the claim event, KM recommended a more
robust design for a replacement vent to „provide a more impact resistant finish to combat
sudden localised p ressure increases from short term, high volume rainfall events.‟
The complainant has follo wed KM‟s recommendation and incurred over $8,000 in having
the more robust replacement structure built by AC in October 2020.
Both parties rely on KM’s report
The insurer says that KM‟s report indicates that:
for all intents and purposes, this vent wall is a retaining structure as it is
preventing soil from the external gardens from collapsing into the carpark.
The insurer submits that this means the garage air vent claim is excluded because the policy
does not cover loss or damage:
(b) to retaining walls resulting from Storm or Rainwater.
(h) caused by underground (hydrostatic) water.
The complainant reaches a different conclusion from KM‟s report. It says that KM clearly says
the purpose of the vent was air circulation and, secondarily, to keep soil from falling into the
garage. The complainant submits:
The vent was not situated at the foot of a slope to “retain” anything – the land is
absolutely flat. The vent was in a 1 metre deep hole in the ground beside the wall
of the building. The vent had withstood 15 years of all kinds of weather. However
when the vent filled with floodwater weighing hundreds of kilograms, the thin
galvanized steel collapsed, allowing more water and rubble to wash into the
basement. Items 1(b) and 1(h) of the policy are not relevant to the situation.
Determination | Case number: 817844 Page 7 of 8
Garage air vent claim is not excluded
A retaining wall is a structure intended to support/resist soil laterally, so it can be retained at
different levels on two sides.
On balance, I agree with the complainant that the garage air vent structure was not a
retaining wall. Its main purpose was to provide ventilation. KM says it was also to „ simply
keep the earth out of [the underground carpark]‟ but this was clearly a secondary function.
Further, stopping soil from falling in is not the same as resisting lateral soil pressure.
The available photos strongly suggest that the below ground part of the vent structure was
designed to act as a plinth on which the vent stood, rather than having a structural function.
Accordingly, the insurer is not entitled to rely on exclusion (b) set out above.
Hydrostatic pressure means the pressure exerted by a fluid at rest because of the weight of
the fluid. The walls and slabs of underground car parks are often subject to increased
hydrostatic pressure during a heavy or prolonged rainstorm.
I acknowledge that KM has referred to the likelihood of higher than normal levels of
hydrostatic pressure associated with rainfall during the storm event. Similarly, the
complainant says the vent structure collapsed due to the weight of the storm floodwater.
It was the storm that caused the abnormal level of hydrostatic pressure that led to the vent
collapsing. This means that the storm was the proximate cause of the damage. Proximate
cause is the dominant, efficient or operative cause of a loss. It is not required to be last in
time or the sole cause. It is a question of fact that depends on the circumstances of each
case. It requires a common sense evaluation of the evidence.
I am not satisfied that exclusion (h) applies in those circumstances.
Accordingly, the insurer is required to cover the cost of returning the vent structure to its pre-
loss condition.
Steps need to be taken to determine the amount payable by the insurer
The replacement air vent structure installed by AC in October 2020 is much more substantial
than the structure damaged by the storm. The insurer is only required to cover the
complainant to the extent required to reinstate the vent to its pre-damaged condition.
In the circumstances, it is appropriate for the insurer to request AC to provide an estimate of
what it would have cost to replace the damaged vent like for like. Once the estimate is
available, the insurer is to pay the estimate amount to the complainant.
2.4 Why is the outcome fair?
The policy requires the insurer to return the property to its pre-loss condition. Therefore, it is
fair that the insurer pays the costs of resurfacing the pool and retiling the pool deck, plus a
cash settlement uplift applies to cover contingencies. The new air vent is an improvement on
the damaged version. It is fair that the insurer only pays the like for like replacement cost.
Determination | Case number: 817844 Page 8 of 8
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. I have reviewed and considered
all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, I have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.