The complainant's home and contents policy excluded flood and rainwater run-off, and he said he had requested contents flood cover. AFCA found the policy documents were sent by email and the loss was more likely caused by flood/rainwater run-off, so the insurer's decline was upheld.

The insurer may rely on the policy terms where it sent the documents correctly and the complainant did not have flood cover for the proximate cause of the loss.

Issues

Subjects and remedies

home or building damagenatural disasterno remedy

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination Case number 813593 Financial firm Insurance Australia Limited Determination | Case number: 813593 Page 1 of 4 Case number: 813593 24 November 2021 Determination overview 1.1 Complaint The complainant holds a home building and contents insurance policy with the financial firm (insurer). He lodged a claim for damage to his contents after water inundated the insured property in March 2021. The insurer declined the claim, saying the policy did not include cover for flood, rainwater run- off or storm surge. The complainant does not accept that. He says he had requested flood cover for his contents when setting up the policy in a phone call with the insurer, but he had never received his policy documents to confirm that was in place. The insurer maintains it sent policy documents to the complainant’s email address as requested, and that he did not have flood cover at the time of the incident. 1.2 Issues and key findings Is the insurer liable for the damaged contents? No, the insurer is not liable for the damaged contents. The available evidence shows, on balance, the complainant had opted to remove cover for flood, rainwater run-off and storm surge from his combined home and contents policy. The proximate cause of the damage was, on balance, flood and rainwater run-off. The policy documents had been sent to the complainant by email (as he had agreed should happen), and they clearly showed cover for flood/rainwater run-off was not included. The complainant should reasonably have been aware of the cover he held before the loss occurred, and he had the opportunity to change that if necessary, but did not do so. Why is the outcome fair? It would not be fair to require the insurer to pay for a loss which is not covered under the complainant’s policy. 1.3 Determination This determination is in favour of the insurer. It is not required to take any further action. Determination | Case number: 813593 Page 2 of 4 Reasons for determination 2.1 Is the insurer liable for the damaged contents? Insurer provided policy documents as it was required to do The complainant says he did not receive the policy documents for his holiday house and contents. He indicated there had been issues with his email provider, and he had not been able to follow that up because of the stress he has been experiencing during the Covid-19 pandemic. However, the available evidence shows the complainant had consented to receiving policy documents by email, and the insurer had sent those documents (at inception and renewal) to the complainant’s correct email address. The insurer cannot be held responsible if it sent the documents correctly, but the complainant (for reasons outside the insurer’s control) did not receive or read them. The complainant has a responsibility to read the documents to ensure the policy meets his needs and reflects his understanding of the cover in place. If he had any queries, then he could have contacted the insurer to clarify those, and adjust the cover if necessary. I am satisfied the insurer is entitled to rely on the terms and conditions of the policy in dealing with the claim. Complainant did not have flood/rainwater run-off cover at the time of loss The complainant’s certificate of insurance (COI) for the building and contents policy renewal year during which the loss occurred, clearly states, in several different places, that he is not covered for ‘ loss or damage caused by flood, rainwater run- off and storm surge’. That was unchanged from the previous policy year. The complainant maintains his intention was to keep flood cover for his contents only. Several telephone call recordings have been provided, including the policy inception call during which this was discussed between the complainant and insurer. The call is lengthy and involves discussi on about both the complainant’s primary residence, and the holiday home the subject of the damage now being claimed. The call was apparently prompted by a premium increase which was clarified as having arisen because the lat ter property was in a flood zone. It is clear the complainant felt comfortable the property was unlikely to suffer flooding, and so was not interested in keeping flood cover for the building itself, although he asked for a quote to cover contents only for flood. The conversation proceeded to a quote for a combined building and contents policy, without flood cover. The complainant indicated he considered there was very little, if any, chance of a flood, and he accepted the combined policy quote without flood cover. He submits he intended to keep flood cover for contents, however I am not persuaded the call clearly establishes that. I appreciate there may have been a misunderstanding on the complainant’s part, given the way the conversation unfolded, and the several different options considered. I have seen nothing to indicate the insurer’s representative deliberately misled or deceived the complainant ‘ to push [him] into a sale ’ , as the complainant has suggested. He did still have the option of taking 2 separate policies, for the building and for the contents, which would Determination | Case number: 813593 Page 3 of 4 have been more expensive. Based on the call, I consider it was reasonable for the insurer’s representative to have proceeded to set up the combined policy without flood cover, as they did. I am also satisfied the complainant had the opportunity to check the policy documents which were sent to him, and to amend his cover if it was not what he intended at that time. Available evidence shows, on balance, damage from flood/rainwater run-off The policy defines ‘flood’ as ‘the covering of normally dry land by water that has escaped or been released from the normal confines of …a river…; another natural watercourse (whether or not it has been altered or modified);…’. Shortly after the event, the insurer’s loss adjuster CL in spected the property which is identified as being located about 500m form a bay and river. CL reported there was no water ingress from roof level or wind-driven rain around windows, but instead all the water ingress had occurred at ground level only. The whole house has been inundated, up to a level of about 500mm. It was concluded the damage was from a combination of runoff, overflow from water course and drainage back up. In the absence of any other evidence to the contrary, I am satisfied the proximate cause of the damage was more likely than not flood/rainwater run-off. Insurer is entitled to decline the claim The available evidence shows the complainant did not have cover for flood/rainwater run-off for either his building or contents. As that was the proximate cause of the loss, the insurer is entitled to decline the claim. 2.2 Why is the outcome fair? It would not be fair to require the insurer to cover a loss which does not fall within the scope of cover under the policy. Determination | Case number: 813593 Page 4 of 4 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.