Home / Hollard / Determination 813537

Determination 813537

claim delay causing increased repair costs

FirmHollard
Decided2022-01-04
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$500
Amount claimed—
SourceAFCA PDF

Summary

The complainant's home insurance claim for cracking damage was denied after a delay, and he said the delay increased repair costs. AFCA found the insurer unreasonably delayed the claim but that the cost increase was not caused by the delay, and ordered $500 non-financial loss compensation.

The insurer unreasonably delayed claim determination, but the available information does not show the delay increased repair costs, so only non-financial loss compensation is awarded.

Issues

Subjects and remedies

home or building damagepay non financial loss

Related

All Hollard determinations · Find similar determinations

Text of the determination

Determination Case number 813537 Financial firm The Hollard Insurance Company Pty Ltd Determination | Case number: 813537 Page 1 of 3 Case number: 813537 2 December 2021 1 Determination overview 1.1 Complaint The complainant lodged a claim for cracking damage to his property with his home insurer, the financial firm (insurer). The insurer denied the claim. The complainant does not dispute the claim denial. However, he says that due to the insurer’s delay in de nying the claim, the costs of repairing the damage increased substantively. He is seeking compensation for this. The insurer disputes it is liable for this. 1.2 Issues and key findings Is the insurer liable to pay compensation? The available information does not show that any delay in declining the claim increased the cost of repairs. However, as the insurer did unreasonably delay the claim, it is fair in all the circumstances that it pays $500 in non-financial loss. 1.3 Determination This determination is mostly in favour of the insurer. The insurer should pay $500 in non-financial loss in full and final settlement of this complaint. Determination | Case number: 813537 Page 2 of 3 2 Reasons for determination 2.1 Is the insurer liable to pay compensation? Information does not show claim delay increased the cost of repairs The claim was lodged on 30 November 2020. The insurer did not deny the claim until 7 April 2021. This is despite the fact it appeared to have all the relevant information by early December 2020. Therefore, I accept the insurer has delayed the handling of the claim. However, I am not persuaded this caused the cost of repairs to increase. The complainant provided two quotes from contractor MW. The initial quote was for $13,000. The second was for $27,000. These appeared to be for the exact scope of works, being nine underpins. On the face of these quotes, it is unclear why the quote increased so significantly. When asked to explain the basis for the increase, MW said the following: In the regard of the work on the property address […] and the reason of the variation on the contract price for the work. Is been the delay of the work that caused the cracking in the concrete that was replaced after the underpinning work was done. and also, after the jacking up of the foundation to bring it to the original level caused some stumps that supports the subfloor close to that area to crack and break, and need to be replaced. And also brick work is required after the underpinning work was done. All this extra work is required is the reason of the variation to the cost of the work. This does not show the increase was due to the delay. MW referred to the concrete cracking after underpinning and stumps needing replacement after ‘ jacking up the foundation ’ . MW also said brickwork was needed after underpinning. These increased costs appear to be due to the type of work being done, not the insurer’s delay in denying the claim. That is, these costs would have been incurred regardless. Therefore, the available information does not show the cost of repairs increased because the insurer delayed declining the claim. Given this, I am not persuaded the insurer’s delay in declining the claim resulted in any financial loss. Insurer should pay $500 in non-financial loss Under the AFCA Rules, we may award compensation (capped at $5,400) for non-financial loss where a complainant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with their expectation of enjoyment or peace of mind. We award compensation conservatively. For reasons expressed, I am persuaded the insurer has unreasonably delayed the claim. Given this, and considering our conservative approach, it is fair in all the circumstances for the insurer to pay $500 in non-financial loss. Determination | Case number: 813537 Page 3 of 3 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.