Text of the determination
Determination
Case number 813423
Financial firm AAI Limited
Case number: 813423 9 March 2022
Determination | Case number: 813423 Page 2 of 9
1 Determination overview
1.1 Complaint
The complainant held a Home Building and Contents insurance policy with the financial firm
(insurer) and lodged a claim for storm and flood damage on 16 February 2019 following
heavy storms and flooding in the Townsville area.
The insurer accepted liability and settled the claim for contents damage for the sum insured of
$123,000, electrical works $35,310, and accommodation $2,850. In addition, the insurer has
offered $32,697.89 for the building damage.
The complainant disputes the insurers assessment of damage and seeks $319,969 to rectify
the building damage plus 12 months temporary accommodation.
1.2 Issues and key findings
Is the insurer liable to increase its settlement offer for building damage?
No. The insurer is not liable to increase its settlement offer. The available information does
not support the complainant ‟ s claim for mould related damage to the kitchen or additional
electrical works being required due to the storm/flood related damage. Other damage claimed
is most likely maintenance related damage not covered under the terms of the policy.
Is the insurer liable for any temporary accomodation?
Yes. The panel considers the insurer should pay an additional 4 weeks temporary
accommodation at the rate of $200 per night to cover the repair period as per the insurer ‟ s
scope of works (SOW).
Why is the outcome fair?
The panel has made its determination based on all the evidence presented for this complaint.
The panel is satisfied the insurer has acted fairly in determining its liability. In so far as there
may have been additional damage sustained, the insurers ability to assess that damage has
been prejudiced by the complainant stripping the property prior to the insurer having the
opportunity to further assess the damage.
1.3 Determination
This determination is in favour of the insurer.
Within 30 days of the complainant‟s acceptance of this determination the insurer is to pay the
complainant $32,697.89 in settlement of the claim plus $5,600 for four weeks temporary
accommodation. The insurer has otherwise met its liability under the terms of the policy.
Determination | Case number: 813423 Page 3 of 9
2 Reasons for determination
2.1 Is the insurer liable to increase its settlement offer for
building damage?
No. The insurer is not liable to increase its settlement offer for building works. The available
information does not support the complainant ‟ s claim for mould related damage to the kitchen
or additional electrical works being required due to the storm/flood related damage. Most
likely the kitchen was damaged due to exposure to the elements as the complainant
completed extensive private works and maintenance repairs
Complainant has onus to establish that damage claimed falls within the terms
of the policy.
The complainant has the initial onus to prove on the balance of probabilities (that is more
likely than not) that the loss or damage claimed falls within the terms of the policy. This is
commonly called a prima facie claim.
The complainant‟s home and contents policy cover loss or damage arising from a series of
listed events including flood and storm as well the optional benefit chosen of accidental
damage.
There is no dispute that the complainant‟s property was damaged during the storm/floods that
impacted on Townsville in January/February 2019. The insurer accepted liability for the flood
related damage and appointed RPF to complete the relevant make safe works including
sanitation works.
The insurer then arranged an assessment of the damage by ABC. ABC attended the property
on 15 March and identified water damage to 3 bedrooms, loungeroom, sunroom, laundry and
carport that was considered flood/storm related.
A roof report provided by a roofing specialist CV, identifies maintenance related issues with
the roofing including loose screws in the valley gutters, poor sealing of the roof pitch changes,
split sheets and a rotting valley board indicating pre-existing damage.
SRE provided an engineering report on damage to an ensuite and second bathroom. SRE
considered the damage was pre-existing and found no evidence of the damage being caused
by the flood/storm event.
The insurer partially accepted the claim. It agreed to cover the loss of contents for the sum
insured of $123,000, disposal of the contents $13,200, electrical items including AC units and
an invertor $35,310.
The insurer sent the complainant the scope of works for the building repairs in September
2019 and offered to either cash settle the building damage claim for $29,854.21 or complete
the repairs following the complainant completion of the roof maintenance. The insurer has
now offered the complainant $32,697.89 being the assessed SOW of $27,248.24 plus a 20%
contingency.
The insurer says that it was unable to complete, and warrant repair works until the
maintenance issues were rectified. It says it offered a cash settlement for the claim repairs
based on this reason.
Determination | Case number: 813423 Page 4 of 9
Around this time the complainant raised concern as to damage to the pool. The insurer
rejected this aspect of the claim which was subsequently subject of a complaint to AFCA.
AFCA determined (Complaint 762018) that the insurer was not liable for the damage to the
pool.
The complainant did not accept the insurers offer and in October 2020 provided a quote from
his builder for $45,234, based on the scope of works from AB. The complainant now claims
$319,969 in respect of building damage. He advised he was willing to negotiate a decrease of
20%, leaving $256,000 remaining.
The complainant wants the insurer to cover:
Repairs
Demolition and removal
Electrical
Kitchen replacement/repairs
Roof re-screwing and repairs
The onus is therefore on the complainant to prove that most likely this additional damage
claimed is due to the storm/flood event.
Mould damage not caused by delay by the Insurer
The complainant says the insurer did not inspect the ceiling cavity properly after the event,
which caused further damage later in the claim. The complainant believes the insurer‟s
liability has increased due to the delay in assessing the mould in the roof cavity. The
complainant says the delay caused further mould damage to the remainder of the home.
The insurer‟s claim notes indicate that the complainant initially said he would consult a local
remediator about any ongoing mould concerns. There is no evidence that the complainants
consulted a local remediator. The claim notes also record the complainant informed the
insurer on 27 February 2019 that the mould was continuing to grow despite the home having
bee n “fogged”.
The insurer does not agree that initially there was no inspection or mould remediation
conducted. It appointed RPF who conducted a mould remediation treatment.
A builder assessment report obtained by the insurer from ABC acknowledged the mould at
the home:
It is the agreed opinion that all mould to internal ceilings and walls is a direct
result of flood event.
At the time of the inspection, a brief but prolonged sun shower came over the property, so
access to the roof for an inspection was not possible. ABC later obtained a roof report from
CV. CV noted:
1. Water entered through a flat section (extension) of roof over the two rooms on
the far right side of the property (spare rooms). The roof is below the required
pitch and is currently sitting between 1-2 degrees. Water entered through the
flashings and sheet laps.
…
Determination | Case number: 813423 Page 5 of 9
2. Water entered through loose screws (screws not down tight and sitting up).
Water entered the lounge and bedrooms
AB (a different entity to ABC) inspected the property on 4 September 2019 . AB‟s building
assessment report noted the insulation to the ceiling is dry and free of mould on inspection. In
providing a SOW, AB referred to the maintenance issues with the roof and likelihood of
further water entry until the maintenance repairs were completed.
The panel agrees with the complainant that the insurer should have conducted further testing
to the roof cavity. This was not completed at the initial site inspection by ABC.
However, the roof report from CV did not comment on any issues with the roof insulation
being waterlogged. The later report provided by AB advised that the insulation to the ceiling
was dry and free of mould on inspection.
The onus is on the complainant to establish the damage was caused by an insured event,
including the extent of damage claimed. The panel is not satisfied the complainant has
established any additional damage was caused to the building due to any delay in the
handling of the claim by the insurer.
The panel is satisfied the insurer acted reasonably in assessing the damage sustained from
the storm/flood event in a timely manner. There is no evidence that any delay by the insurer
has caused an increase in the mould impacting on the building.
Evidence shows building was exposed to the elements
The insurer advised that between August 2019 and 4 December 2020, extensive works were
conducted at the property. The complainant says he had no choice but to conduct these
works, as he says the insurer refused to complete the claim related repairs. The insurer
clarified the issue with the maintenance works being required to be completed first, as
discussed above.
M advised in its report (following a site visit on 18 February 2021) that the building was not
considered air/watertight at the time of inspection. It noted that the building was open to the
elements, with several external walls/windows having been removed, and that builders were
onsite during the inspection.
The panel accepts there was higher than normal fungal ecology present in some areas of the
property as identified by M. M‟s report is dated 18 February 2021, t wo years after the initial
event. During this time the property had been subject to extensive stripping and exposure to
the elements, through work being conducted by the complainant. The report from M indicates
the building was open to the elements and not in normal environmental fungal ecology.
The panel is satisfied that even if there are mould issues now, it is unknowable whether any
of that resulted from the flood, more likely this would result from the recent exposure.
Insurer not liable for Kitchen replacement
The complainant wants the insurer to accept liability for the cost of replacing the kitchen. The
complainant says that due to the insurer‟s delays in assessing the mould and completing the
remediation the kitchen needs to be replaced due to mould damage.
As determined above, the panel does not accept the evidence establishes any increase in
mould damage was due to the insurers claims handling. The claim for the replacement of the
Determination | Case number: 813423 Page 6 of 9
kitchen was first brought by the complainant over two years after the event. When brought,
the kitchen had been removed by the complainant‟s builder during extensive renovations.
The insurer was not able to assess the damage nor was it provided with evidence of the
damage from the builder. The kitchen had been exposed to the elements during extensive
repair works and it is likely it would have been damaged during this time.
The panel is not satisfied the complainant has established a valid claim, within the terms of
the policy, for the replacement of the kitchen. The insurer is not liable for the claimed cost of
$35,000 for the replacement of the kitchen.
Insurer not liable to increase allowance for Electrical items
The complainant wants the allowance for electrical items increase to $68,450 for claimed
electrical works at the property. The complainant has not explained the grounds upon which
the costs relate to the claim or the storm/flood related damage.
The insurer also previously settled the complainant $35,319 for electrical costs claimed.
There is no evidence of additional electrical items being damaged. In the absence of any
further information the panel accepts the insurer has met its liability for the electrical works in
accordance with the terms of the policy.
Insurer not liable for roof repairs
The complainant ‟ s claim includes the cost of repairing the roof of $24,487.
There is no evidence that the roof was damaged in the storm/flood. The issues with the roof
were identified by CV as maintenance issues. These are the responsibility of the complainant.
The insurer is not liable for the roof repairs.
Insurer not liable for rusting to deck
The complainant has claimed for damage to the rear deck. The complainant says the rear
deck had begun to rust after the storm/flood.
JHA (the insurer‟s engineer) completed a report on 24 December 2020 . JHA considered one
steel pier should be replaced and the pier had been rusting for years, prior to the storm/flood.
JHA considered the surface rust to the other piers was caused by the close proximity of the
pool.
The complainant has not provided any evidence that is contrary to this expert advice. Based
on the expert opinion of JHA, the panel considers that the insurer is not liable for the damage
to the rear deck.
Insurer not liable for damage to ensuite/bathroom
The complainant claimed for damage to the ensuite/bathroom.
ABC identified cracking to both bathroom tiled surfaces which it considered pre-dates the
flood event. The insurer also obtained an engineering report from EC. EC confirmed the
presence of cracked tiles and separated grout and tiles. It stated:
As reported, our inspection of the house returned evidence of only cracking to a
small section of wall located to the ensuite and second bathroom shower. There
was no evidence of any foundation movement throughout the entire house.
Determination | Case number: 813423 Page 7 of 9
For the cracking damage to the shower wall tiles to be related to the Townsville
weather event, there would need to be foundation movement. It is possible that
when a slab or foundation is submerged by flood waters the supporting soils can
either react or subside.
…
The exact cause of the tile cracks is not known however we suspect that the tile
cracks may relate to a waterproof membrane performance issue allowing
movement of the wall frame. We also believe that there is the possibility of termite
attack of the framing.
Based on the expert evidence, it appears likely that the cracked tiles and grout are unrelated
to the flooding event. The insurer is not liable for the damage to the ensuite/bathroom.
Insurer not liable for damage to the fence
The complainant has also noted damage to the side fence causing the fence to lean.
ABC reported damage to the fence was a combination of age and the fact that directly on the
other side of the "lean", (in neighbour's property), garden beds have been built and hardware
has been stored on and against the fence exerting weight and pressure.
EC noted the fence was „aged‟ and „approaching the end of its service life‟. EC said that, „We
are of the belief that the fence was not submerged by flood waters.‟ It noted that on the
neighbour‟s side of the fence, there were garden beds and old building materials against the
fence, which was placing pressure on the fence, causing it to lean.
Based on the expert evidence submitted, the panel finds that the additional damages are
maintenance items, that are the responsibility of the complainant. The insurer is not liable for
maintenance issues.
Conclusion – insurer not liable to increase settlement for building works
The insurer is not liable to increase its settlement for building works.
The complainant has not provided information to show that mould from the ceiling cavity
caused further damage to the home. He has not substantiated his claim for further electrical
works. The kitchen was likely damaged due to exposure to the elements. The roof repairs and
other repairs are maintenance related.
Subject to the complainant‟s acceptance of this determination the insurer is to pay the
complainant $ $32,697.89 being the assessed SOW of $27,248.24 plus a 20% contingency.
2.2 Is the insurer liable for any further temporary
accomodation?
The insurer is liable for an additional four weeks temporary accommodation costs.
Insurer is liable for further temporary accomodation costs
The complainant is seeking cover for 12 months of temporary accommodation (TA). The
insurer advised it would cover an additional 4 weeks temporary accommodation and review
any further information.
Determination | Case number: 813423 Page 8 of 9
The complainant has not established that the scope of works for the storm/flood related
damage should be extended. The panel accepts in the circumstances that the insurer ‟ s offer
of an additional four weeks temporary accommodation is fair and reasonable.
The insurer has already paid the complainant ‟ s $2,850 being 57 days temporary
accommodation calculated at $50/day. The calculation was based on the complainants
staying at a relative‟s place during that time.
Given the likely cost of short term temporary accommodation would be based on a
commercial daily rate the panel considers it fair that the insurer calculates the additional four
weeks at $200/day.
The panel determines the insurer is to pay the complainant $5,600 in final settlement of the
complainants claim for temporary accommodation.
2.3 Why is the outcome fair?
Why is the outcome fair?
The panel has made its determination based on the evidence presented for this complaint.
The panel is satisfied the insurer has acted fairly in determining its liability.
The complainant has not established a valid claim for the additional damage claimed. In so
far as there may have been additional damage sustained, the insurer ‟ s ability to assess that
damage has been prejudiced by the complainant stripping the property prior to the insurer
having the opportunity to further assess the damage.
The panel is satisfied it is fair in the circumstances for the insurer to limit is liability in
accordance with the terms of the policy.
Determination | Case number: 813423 Page 9 of 9
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel
includes an ombudsman, a member with significant experience in consumer and small
business advocacy and a member with extensive industry experience.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence. When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
3.2 Relevant policy documents
Document Key sections
Certificate of
Insurance (COI)
30 July 2018
Period of ins urance:
From 1 August 2018 until 11.59pm 1 August 2019
Sum insured:
Home $591, 300
General Contents $123,000
Legal Liability $20 million
…
Determination | Case number: 813423 Page 10 of 9
Automatic Inclusions with Classi c Extra s cover
As you have chosen Classic Extras cover, the following covers are automatically
included in your policy.
Home options:
Accidental damage at the home
Motor burnout
Safety net protection
Contents options:
Accidental damage at the home
Motor burnout
Product
Di sclosure
Statement (PDS)
19 October 2012
Pages 17 and 18
Flood
We cover
Loss or damage caused by flood.
…
Storm
We cover
Loss or damage by a storm.
Page 62 General exclusions - (Cont’d)
You are not covered under any section of this policy for damage, loss, cost or
legal liability that is caused by, arises from or involves:
…
Wear, tear and gradual deterioration
wear, tear, rust, fading, rising damp, mould, mildew, co rrosion, rot, action of light,
atmospheric or climatic conditions or gradual det erioration such as but not limited
to:
– tiles and their adhesive or grouting breaking down;
– weathering of roof tiles or roof ridge capping;
– gradual weathering and breakdow n of bricks, mortar or concrete.
Pages 63, 64 Claims
…
What you must not do
– do not dispose of any damaged parts or items of your home or contents without
our cons ent;
– do not carry out or authorise repairs without our consent unless you cannot
contact us and need
to make emergency repairs to prot ect your home or cont ents;