Determination 810734
Claim denial for retaining wall damage
Summary
The complainants claimed under home insurance for storm-related damage to a retaining wall. AFCA found the wall failed due to defective construction, gradual deterioration and tree roots, which are excluded, and dismissed the complaint.
The proximate cause of the wall's failure was faulty design, gradual deterioration and tree roots, which the policy excludes, so the insurer was entitled to deny the claim.
Issues
- Claim denial primary · not upheld“The insurer is entitled to deny the claim. It is not required to take any further action.”
- Inadequate claim investigation secondary · not upheld“I am not satisfied the opinions of MC and CT are based on inaccurate assessments.”
Subjects and remedies
no remedy
Related
Text of the determination
Determination
Case number 810734
Financial firm Insurance Australia Limited
Determination | Case number: 810734 Page 1 of 6
Case number: 810734 28 March 2022
1 Determination overview
1.1 Complaint
The complainants hold home and contents insurance with the financial firm (the insurer).
On 11 November 2020, the complainants lodged a claim on the policy following damage to a
retaining wall. They said the damage was caused by a storm on 31 October 2020.
The insurer investigated the cause of the retaining wa ll’s failure. It concluded that the wall
failed due to gradual deterioration, poor construction and tree encroachment. The insurer
says damage from these causes is excluded from cover. The insurer has denied the claim.
The complainants disagree with the insurer. They say the wall was in sound condition
immediately prior to the storm. They refer to the statement by one of the insurer’s exper ts that
the wall’s ‘failure may in part be attributable to recent rainfall…’ . They want the claim covered.
The complainants are represented by their insurance broker, JH. For the sake of brevity, the
complainants and JH are referred to in this determination as ‘the complainants’.
1.2 Issues and key findings
Is the insurer entitled to deny the claim?
Yes. The available information shows the proximate cause of th e retaining wall’s failure is
poor construction techniques and gradual deterioration, not the storm. This means the insurer
may rely on policy exclusions to deny the claim. The expert’s statement quoted by the
complainants does not reflect that expert’s opinion.
Why is the outcome fair?
The outcome is fair because the insurer has established that the damage claimed is excluded
from cover. It would not be fair for the insurer to have to pay the claim when the policy does
not require it to do so.
1.3 Determination
This determination is in favour of the insurer.
The insurer is entitled to deny the claim. It is not required to take any further action.
Determination | Case number: 810734 Page 2 of 6
2 Reasons for determination
2.1 Is the insurer entitled to deny the claim?
Yes. The available information shows the proximate cause of t he retaining wall’s failure was
poor construction techniques and gradual deterioration, not the storm. This means the insurer
may rely on policy exclusions to deny the claim. Th e expert’s statement quoted by the
complainants does not reflect that expert’s opinion.
The complainants have established a valid claim under the policy
The complainants are required to show, on the balance of probabilities, that they suffered a
loss caused by a risk covered by the policy. This is known as a valid claim.
The complainants hold a home and contents policy. The product disclosure statement and
policy document (PDS) confirms that the policy provides cover for accidental loss or damage
to the insured property.
Relevant extracts of the PDS are set out in section 3.2 of this determination.
For the purpose of the policy, retaining walls form part of insured buildings.
It is not in dispute that the complainant’s retain ing wall has been damaged. There is no
suggestion that the damage was caused intentionally.
Accordingly, I am satisfied that the complainant has established a valid claim for accidental
damage to the retaining wall.
Once the complainant establishes a valid claim, the insurer is liable for the loss unless it
shows an exclusion or limiting condition applies. The insurer has the onus of proof in
establishing the application of the exclusion. The standard of proof is the balance of
probabilities.
The proximate cause of damage must be determined
The insurer argues that the proximate cause of the damage is excluded from cover.
Proximate cause is the dominant, efficient or operative cause of a loss. It is not required to be
last in time or the sole cause. It is a question of fact that depends on the circumstances of
each case. It requires a common sense evaluation of the evidence.
The insurer relies on expert evidence
After the claim was notified, the insurer appointed a builder (MC) to undertake an assessment
of the damage. In its report dated 22 November 2020, MC concluded:
I am of the opinion that a hollow core block wall to retain approximately 1.8m high
build-up soil that is subject to seasonal movement would not be considered to be
structurally adequate or of a sufficient design to retain the soil. I am of the opinion
that this has occurred over a period of time and is not the result of a singular
incident. It is not the result of storm activity.
Determination | Case number: 810734 Page 3 of 6
As the complainant did not agree with the opinion of MC, the insurer obtained a building
inspection report dated 21 December 2020 from CT, building consultants and engineers. The
report included the following observations:
the retaining wall was constructed of concrete blocks without reinforcement, has no
drainage and improper soil has been used as fill
two trees planted directly behind the retaining wall have pushed against the wall as they
have grown, and contributed to its failure over time
lack of surface drainage and fill subsidence was causing water to pond behind the wall
the fill had been saturated many times over the years, increasing the loads on the wall and
reducing soil strength
t he wall’s failure would continue to progress in the short and long term, likely exacerbated
by future rainfall events and the ongoing effect of the trees.
CT concluded:
We are of the opinion that the retaining wall has failed due to Defective Building
Work and Maintenance Related Issues and whilst failure may in part be
attributable to recent rainfall events and rainfall Events over a period of years we
are of the opinion that the failure of the retaining wall was inevitable and cannot
be attributed to any single rainfall Event.
CT provided supplementary reports dated 6 February 2021 and 12 March 2021, responding
to a correction of the date of the storm, Bureau of Meteorology (BOM) records and the
complainant’s submissions. CT confirmed that:
it maintained the view that defective building work and age deterioration over time
attributable to the tree encroachments had caused the wall to crack and rotate
none of the damage was due to a storm event
it stood by the findings set out in its original report.
Given its expert evidence, the insurer says that the proximate cause of the retaining wall’s
failure is a combination of faulty design/structural defect, gradual deterioration and tree roots.
Accordingly, it says it is entitled to rely on policy exclusions that preclude cover for damage
from those causes.
The complainants say that the storm must have caused the damage
The complainants have not provided any expert evidence on what caused the retaining wall
to fail.
Nevertheless, they say the storm on 31 October 2020 must have been the proximate cause of
the damage. In summary, they submit:
the retaining wall was in place for 40 years and was structurally sound until the storm
the complainants observed the wall the day before the storm and it was in sound condition
the storm was of sufficient intensity to shred an outdoor blind
their landscaper, SS, told them that:
> he had seen similar cases of ‘rapid change in recent times after significant storm
activity’
> the two trees near the wall are camelias. This species has a non-invasive root system
and would not have caused damage to the wall.
t he insurer’s expert (CT) confirmed the wall’s ‘failure may in part be attributable to recent
rainfall…’.
Determination | Case number: 810734 Page 4 of 6
The complainants also say that the insurer and its experts had initially referred to the claim
lodgement date as the date of loss and had quoted for a four metre wall repair when the wall
is 10 metres long. They submit these errors ‘create doubt regarding the integrity, competence
and accuracy in their assessment. ’
The insurer is entitled to deny the claim
Having reviewed all of the information provided by both parties, I am satisfied that the insurer
has on the balance of probabilities shown that the proximate cause of the damage is faulty
design/structural defect, gradual deterioration and tree roots. This means the insurer is
entitled to rely on policy exclusions to deny the claim.
I acknowledge that the wall was in place for 40 years prior to the storm on 31 October 2020
and that a visual observation the day before did not suggest any problems with it.
However, the available expert evidence is unequivocal – the wall was constructed without
drainage or reinforcement; it has gradually deteriorated over time, particularly given the
increasing pressure applied to it due to the growth of trees abutting it.
I am unable to place much weight on the comments attributed to SS as there is nothing from
SS to confirm the statements or setting out the context in which they were made.
The complainants’ reliance on the statement by CT that the wall’s ‘failure may in part be
attributable to recent rainfall…’ is misplaced. It does not accurately reflect C T’s opinion on
causation which is maintained in its three reports.
The shredding of the blind does not show that the consistent views of MC and CT on
causation are wrong.
I accept that there has been some confusion regarding the date of loss. That confusion
appears to have been in part contributed to by the complainants (for example, the claim form
recorded the wrong date). To the extent that CT’s first report commented on BOM data for the
wrong days, that was rectified in its supplementary reports.
While MC did provide an estimate of the cost of repairs that included replacement of 4 metres
of the wall, it nevertheless recorded that the wall was 9.4 metres in length.
Accordingly, I am not satisfied the opinions of MC and CT are based on inaccurate
assessments.
The insurer is entitled to deny the claim. It is not required to take any further action.
2.2 Why is the outcome fair?
The outcome is fair because the insurer has established that the damage claimed is excluded
from cover. It would not be fair for the insurer to have to pay the claim when the policy does
not require it to do so.
Determination | Case number: 810734 Page 5 of 6
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. I have reviewed and considered
all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, I have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
Determination | Case number: 810734 Page 6 of 6
3.2 PDS extracts
Page 13
We will cover your buildings and your cont ents for accidental loss or accidental damage...
Page 14
We will not cover your buildings and your contents for any accidental loss or accidental
damage caus ed by:
…
• settling, shrinkage or any movement of eart h
…
• rust, corrosion, gradual deterioration, depreciation, wear or tear
…
• roots from trees, plants, shrubs or grass.
–– however , this exclusion applies only for loss or damage caused directly by roots
…
• a defect in an item, faulty workmans hip, structural defects or faulty design