Home / IAG / Determination 809191

Determination 809191

Repairs and cash settlement amount for storm damage

FirmIAG
Decided2022-07-12
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$164,949
Non-financial loss$3,000
Amount claimed$179,778
SourceAFCA PDF

Summary

The complainants lodged a storm damage claim for their property, which the insurer repaired poorly and then offered a cash settlement of $73,732.25 plus 15% uplift. AFCA found the complainants' quote more reliable, ordered a higher cash settlement with interest, storage and temporary accommodation costs, and $3,000 non-financial loss, but rejected most other financial losses.

The cash settlement must allow the complainants to complete all necessary rectification works, and the complainants' builder quote was more complete, current and actionable than the insurer's quote.

Issues

Subjects and remedies

elderly or capacityhome or building damagemental healthnatural disasterpay claimpay compensationpay interestpay non financial lossrefund fees or charges

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination Case number 809191 Financial firm Insurance Australia Limited Case number: 809191 5 July 2022 Determination | Case number: 809191 Page 2 of 8 1 Determination overview 1.1 Complaint The complainants hold an insurance policy with the financial firm (insurer) and are represented by their son. Reference to the complainant will include both unless stated otherwise. On 23 April 2020, a claim was lodged for storm damage to the complainants’ property. Following claim lodgement, the insurer assessed the damages and completed repairs to the property. A dispute has arisen over the repairs to the property and the work required to restore the home to its pre-event condition. The complainants also say offers made by the insurer to resolve the dispute are not adequate. Accordingly, the two parties have not been able to come to a resolution and have approached AFCA to determine how the dispute should be resolved. 1.2 Issues and key findings Is the insurer required to increase its settlement offer? Yes. The insurer is required to increase its settlement offer as set out in section 2.1. Are the complainants entitled to compensation for non-financial loss? Yes. The insurer must pay the complainants $3,000 for non-financial loss given their claims experience. 1.3 Determination This determination is mostly in favour of the complainants. The insurer should settle the claim in full by paying:  the amounts set out in section 2.1, and  $3,000 in non-financial loss. Determination | Case number: 809191 Page 3 of 8 2 Reasons for determination 2.1 Is the insurer required to increase its settlement offer? Complainants have raised various concerns about the insurer’s scope of works There is no dispute that:  the complainants ’ property was affected by storm  the insurer accepted the claim and elected to repair the damage  the repairs were poorly done and require rectification The outstanding works are limited to the home, particularly the roof. The insurer has offered to cash settle the required repairs by paying $73,732.25 plus a 15% uplift. This amount is based on CCC’s quote. The insurer says CCC’s quote includes a scope of works provided by engineer NE and approved by its loss adjuster. The complainants have raised various concerns about the insurer’s scope of works and quote. In particular, they say the scope of works has various missing items, including:  the removal of original timber battens on the front and rear edges of the house and the top hat battens on the front of the house to allow for installation of new metal battens  gable end overhang rectification  the cost of timber materials for barge rafters  removing ceiling insulation to inspect electrical component damages  roof bracing  rectification of nail plates. The complainants are also concerned the actual costs to fully rectify the house cannot be known until the roof is removed and further engineer input is provided. Given all this, and according to their submission dated 13 May 2022, the complainants are seeking a total of $179,777.70 for the rectification works. This comprises of the following:  rectification of defective works and calculable consequential damages $137,065  cost of rectification risk premium $24,671.70 (18%)  roof make safe repairs $3,490.00  storage costs $3,297.86 (October 2021 – May 2022)  storage costs $2,015.88 (June - December 2022)  refund for cost of council report $1,848.00  cost of temporary accommodation $5,740.00 (4 weeks @ $1,435 per week)  bushfire attack level assessment $1,650.00. The first bullet point is supported by a quote from builder G. Various concerns with the insurer’s scope of works and quote Having carefully considered the two quotes and scope of works, as well as the other exchanged information, I note the following. It is not clear if CCC’s quote is actionable or current. For instance, the complainant s provided two quotes from G that were about eight months apart. The costs had increased by almost $30,000. Whilst high, this increase is consistent with the fact there are well-known shortages of trades and material in the building industry that is driving up demand. Determination | Case number: 809191 Page 4 of 8 I accept the complainants ’ submission that the extent of works is far from certain. This is reflected in CCC’s scope of works as it makes several references to the possibility of variances and other items to be done that are not quoted for. This includes the following:  possible additional costs for ‘stand down time’ during engineering inspections  CCC’s quote says that, for the tie downs, ‘any faults/non conformance iss ues will be rectified by the original builder …’ . No allowance has been provided for this item. This is inconsistent with the principle of the cash settlement, which is to allow the complainants to engage another builder to do the works, not seek warranty repairs from the original contractors  a variation may be required for fuse relocation or other costs for working safely near overhead power line connection  a ‘PC’ has been allowed to inspect and complete any tie -down upgrades – this indicates the cost is uncertain and could be greater  installation of hardwood laminations and fly rafter with the note that ‘if any changes are required variation will be submitted’  engineering advice to be obtained about joining detail – this indicates a further possibility of variances depending on the engineer advice. Whilst the insurer has allowed a 15% contingency, I am not persuaded this adequately mitigates the fact:  the costs have likely substantively increased since CCC prepared its quote  the possibility of variances, and the extent of them, could be significant and beyond this proportion  this quote does not appear actionable given G’s quotes . Further, whilst G’s quote is not as detailed as CCC’s quote, it appears to provide more certainty of the extent of works. This includes the likely possibility of damage to the nail plates and the gable end overhang. The nail plate issue was commented on by other engineers and G specifically referred to the gable end overhang. These points were not addressed in the insurer’s expert reports. Complainants ’ quote is preferred There is no dispute extensive rectification works are required. Whilst the parties have agreed to a cash settlement, it is important that any sum provided should allow the complainants to complete all the necessary rectification works. When comparing the two quotes, I am more persuaded G’s quote provides a fairer foundation for a cash settlement in line with this principle. This is for the reasons outlined above. I do accept a contingency should be included in G’s quote as there is still a possibility of further variances. I am not, however, persuaded that 18% is necessary. G’s quote is actionable, more complete, current and substantively higher than CCC. Instead, given these factors, I consider a 10% contingency would be fairer. The complainants have also sought reimbursement of make safe costs and storage costs incurred. The insurer agreed to these in an email dated 21 February 2022. These should be included. The insurer should also pay for the storage costs incurred up until eight weeks after the insurer receives notification the determination is accepted and has issued payment. Eight weeks is to allow for the following:  four weeks for the repairs themselves, and Determination | Case number: 809191 Page 5 of 8  four weeks to allow the complainants to engage the builder and for the builder to prepare for the works (which would include sourcing the building materials). The complainants have sought reimbursement of an engineer report obtained. The invoice in support noted it was a roof report provided for the complainants. I am not persuaded any such report made a material difference to the outcome of this complaint. Therefore, I am not satisfied this should be reimbursed. The complainants have sought four weeks temporary accommodation at $1,435 per week. This is con sistent with the rate agreed to by the insurer’s email dated 21 February 2022. There is nothing to indicate four weeks is unreasonable for these works. This should be allowed. The complainants provided a quote for a bush fire attack level assessment at $1,650. The insurer has not disputed this. It does not appear to be included in G’s quote. This should be allowed. Therefore, after careful consideration of all the available information, the insurer should pay $164,949.36 plus interest pursuant to section 57 of the Insurance Contracts Act 1984. Interest should apply as most of these costs have either been incurred or are based on an outdated quotation from G. Further, as most of this sum comprise s of G’s quote, it is fair for interest to apply from when G’s quote expired (26 May 2022) until payment is made. This sum does not include the additional storage costs that should be settled as set out above. No interest is payable on that portion as that should be based on current rates. Complainants’ claim for other financial losses is mostly not substantiated The complainants have also sought compensation for what they describe as direct financial loss associated with their inability to sell their home. These mainly included legal costs and real estate fees. I am not persuaded these are covered for the following reasons. It is clear such costs are not covered under the policy. If I am to consider these costs based on the insurer’s failure to propert y repair the property, the following must at least be satisfied:  such losses were reasonably foreseeable to the parties at the time the contract was entered into  the losses were caused by the insurer’s failure . I am not persuaded either of these grounds are satisfied. First, I do not accept such a loss was reasonably foreseeable. This is because such circumstances appear remote given it would likely require these steps:  improper repairs to be done,  a person failed to recognise this and then decided to sell the home,  during the sale process, the improper works are identified, and  the sale fell through as a result. Second, even if I accept the loss was not too remote, it is not clear why the complainants sought to sell the property in circumstances when they appeared aware the property was not properly repaired. In light of this, I am not satisfied these losses can be said to have been caused by the insurer’s conduct or, if it was, the complainants have reasonably mitigated the situation. Determination | Case number: 809191 Page 6 of 8 The complainants have also sought financial losses associated with farm time losses and loss of health wellbeing. I am not persuaded these financial losses are substantiated. There is no evidence showing the complainants lost any income associated with their farm or otherwise. Loss of health wellbeing at a rate of $500 per month is not substantiated in any way as a financial loss that an insurer can be held liable for under an insurance contract. The complainants have included copying costs as part of their dispute to AFCA ($162.21). As this was a cost incurred in circumstances where their position was mostly substantiated, it is fair this be reimbursed. 2.2 Should the insurer pay non-financial loss Compensation is awarded conservatively Under the AFCA Rules, we may award compensation (capped at $5,400) for non-financial loss where a complainant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with their expectation of enjoyment or peace of mind. We take a conservative approach to compensation for non-financial loss. It is not awarded when a person suffers the normal degree of inconvenience when a problem occurs. Insurer should pay $3,000 in non-financial loss It is clear this claim has been poorly handled. Significant rectification works have been required to address the claim related repairs. This has resulted in the complainants having the claim substantively protracted. Further, I am not persuaded the insurer’s offer for the rectification works was substantiated. There is no dispute this has impacted the complainants, particularly given their age. Further, the complainants provided evidence to show it impacted their mental health. I accept the insurer has acknowledged the poor repairs and has genuinely attempt to engage with the complainants to rectify this. This has been demonstrated in its ability to settle the poor rectification to the shed and carport. Also, I do not accept the insurer’s position was completely unreasonable given it was supported by an engineer and loss adjuster. Despite these mitigating factors, I do accept the claims experience still had a substantive impact to the complainants. Whilst the insurer offered an amount of $1,000 for non-financial loss in recognition of this, I consider the complainants’ experience warrant a higher amount. Therefore, it is fair in all the circumstances the insurer pays $3,000 in non-financial loss. Determination | Case number: 809191 Page 7 of 8 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. 3.2 Relevant policy sections Section Paying claims How we pay a claim for your farm buildings and unspecified farm buildings When damage occurs to the Farm Buildings and/or Unspecified Farm Buildings, We will either:  reinstate or repair the Farm Buildings and/ or Unspecified Farm Buildings to the condition they were in just before the damage occurred, or  pay You the cost of reinstating or repairing the Farm Buildings and/or Unspecified Farm Buildings to the condition t hey were in just before the damage occurred, or  pay You the value of the Farm Buildings and/or Unspecified Farm Buildings just before the damage occurred. We will reduce this payment by the value of the Farm Buildings and/ or Unspecified Farm Buildings af ter the damage occurred. Section 2 – Farm property Cover 1 Listed events We will cover Your Domestic Farm Buildings and Domestic Cont ents, shown on Your Schedule, for the events listed below. There must be damage or loss from one of these events to the Domestic Farm Buildings or Domestic Contents for You to make a claim: […] Determination | Case number: 809191 Page 8 of 8 storm, tempest, rainwater or wind. This includes storm, tempest, rainwater or wind damage to gates, fenc es or walls that are part of the structure of Farm Buildings and/ or Unspecif ied Farm Buildings 3.3 Expert reports Report Findings Building consultant (CC ) report 17 - 08 - 2021  Refer to section 2.1 for scope of works Complainants’ builder (GPA ) Quote 08 - 09 - 2021  Refer to section 2.1 for scope of works