Home / Suncorp Group / Determination 808374
Determination 808374
cash settlement inadequate for water damage repairs; insurer denied liability for remediation of warped parquetry
Summary
The complainants accepted a cash settlement for water damage repairs to parquetry flooring, and later warping occurred. AFCA found the cash settlement did not provide for managed drying and the insurer must carry out the remediation specified by its flooring expert, with the complainants reimbursing any excess over actual costs.
A cash settlement must reflect what it would cost to repair or rebuild, and the scope of works omitted managed drying needed for a proper repair.
Issues
- Repairs or contractors primary · upheld
“The insurer is to proceed with remediation measures specified in the October 2019 expert report; scope of work fell short of what was required to achieve the necessary repairs.”
- Claim amount dispute secondary · upheld
“Cash settlement did not include provision for managed drying and was therefore inadequate; insurer not in a position to say it paid the full cost to repair or rebuild.”
Subjects and remedies
home or building damagepay compensationprovide documentsrepair or rectify
Text of the determination
Determination
Case number 808374
Financial firm AAI Limited
Determination | Case number: 808374 Page 1 of 4
Case number: 808374 13 April 2022
1 Determination overview
1.1 Complaint
In 2018 the insured property sustained water damage from a leaking pipe. The claim was
accepted by the insurer under a home and contents insurance policy and settled by a cash
payment to the complainants.
Following completion of repairs a section of the parquetry floor developed further warping.
The insurer denied liability saying the policy does not respond to repairs by a contractor of the
policy holder(s).
1.2 Issues and key findings
Has the insurer satisfied its obligations by virtue of the cash settlement?
No, the cash settlement did not include provision for managed drying and was therefore
inadequate.
Is the insurer liable for the remediation?
Yes. The insurer should carry out the remediation specified by its flooring expert and the
complainants should reimburse any excess received in the cash settlement above actual
costs incurred.
Why is the outcome fair?
Cash settlements are a convenient method for an insurer to discharge liability. The discretion
to cash settle must be exercised fairly and with an appropriate level of care and detail.
Unfortunately, in the present case the scope of work fell short of what was required to achieve
the necessary repairs.
1.3 Determination
The determination is in favour of the complainant.
The insurer is to proceed with remediation measures specified in the October 2019 expert
report subject to agreeing a reasonably convenient timeframe with the complainants.
In the event temporary accommodation is reasonably required for the remediation work the
insurer is to pay an allowance at a rate of $400 a night.
Not less than 21 days prior to the date for undertaking of the above work the complainant is to
account to the insurer and reimburse to the insurer any part of the cash settlement it received
in excess of actual costs incurred for the work specified in the September 2018 scope of work
and related accommodation costs.
Determination | Case number: 808374 Page 2 of 4
2 Reasons for determination
2.1 Has the insurer satisfied its obligations by virtue of the
cash settlement?
Claim accepted for escape of liquid
In 2018 the insured property sustained water damage from a leaking pipe under the kitchen.
The claim was accepted under the insured event of escape of liquid. The insurer arranged for
urgent plumbing work to be carried out.
The policy provides that the insurer pay reasonable costs of locating the leak. Rather than
carry out expensive investigation work to find the exact location of the break in the pipe, the
plumber turned off the water to that pipe and re-routed new pipes. This was completed in May
2018.
The insurer appointed its builder, AB to assess damage. AB issued a report as well as a
scope of works and a quote for repairs dated 18 September 2018. The quote contained items
to remove and replace 6 sqm of parquetry flooring as well as to sand, seal and polish 30 sqm
of parquetry flooring.
Insurer proceeds by cash settlement
In addition, there was other work required to replace cabinetry and undamaged parts of the
insured property to achieve a uniform appearance. These works were at the cost of the
complainants.
The complainants requested the additional works be completed by AB when repairing claim
related damage. For reasons unknown AB did not do the repairs and instead the insurer
opted to cash settle the complainants. The policy says the insurer is entitled to pay what it
would cost to repair or rebuild. The complainants said they felt they were forced to cash
settle.
The insurer paid $19,541 comprising the amount of the AB quotation of $16,841 as well as an
amount for temporary accommodation during the repair work. The insurer wrote to the
complainants advising that if they delayed repairs the insurer would not be liable for any
further damage which might occur. The complainant’s son was in his HSC year and the
complainants waited until November 2018 for the work to be carried out.
Further warping of parquetry occurs
During the work the complainants observed that the tradesperson chose not to replace the 6
sqm of parquetry. He explained the result would be less noticeable. There is no statement
provided from that tradesperson but the complainant says he first tested moisture levels in the
parquetry. However, by July 2019 warping had occurred although in a limited area of only 1 to
2sq m. This is only about 3% of the wooden floor area.
The insurer obtained a report from flooring expert AT which stated the warping was a
condition known as crowning being a result of a failure to carry out managed drying of the
concrete subfloor prior to completing the repairs. He stated the problem is aesthetic and not
structural. The complainant considers it unsightly. AT acknowledged it does not conform with
an acceptable standard and can be remediated, but this would require re-sanding, staining
and finishing not just to the 1 to 2 sqm, but to the greater wooden floor area.
Determination | Case number: 808374 Page 3 of 4
Insurer denies liability
The insurer says responsibility lies with the tradesperson who in fact did not perform the
scope of work specified. The insurer says if the warped section of parquetry tiles had been
replaced the contractor would have detected the dampness in the sub floor and the insurer
could have added to the cash settlement for drying.
We don’t have evidence of what the contractor detected but it seems likely he would have
had to uplift at least some tiling from the floor, even if he then placed those tiles back. In my
opinion it is speculative to say that had the tradesman completely removed the warped tiles,
he would have detected moisture in the sub-floor and would have stopped until drying work
was carried out.
In any event the insurer denied liability saying the policy does not respond to repairs arranged
and/or completed by the policy holder(s). Under the policy the insurer is only required to
provide a lifetime guarantee on works it arranges or authorises. The insurer submits it would
be unfair if it was required in effect to guarantee works which were outside of its control.
The complainants say:
they were not given a choice to have the work completed by the insurer’s repairer,
AB failed to identify the leak and/or dry the concrete subfloor and/or indicate that drying
was required.
Expert evidence says warping a result of failure to carry out managed drying
The flooring expert AT in its October 2019 report confirmed that the warping was a result of a
failure to carry out managed drying of the concrete subfloor prior to completing the repairs.
The insurer ’s entitlement to cash settle requires that it make payment for what it would cost to
repair or rebuild. In the present circumstances the scope of work did not contain any provision
for managed drying processes. Arguably in the parquet flooring industry it is well known that
drying is critical although usually this may be by effluction of time.
Possibly due to the fact that the new tradesperson was not involved in the initial investigatory
work, more information could have been provided as to the dampness issue. In any event in
my opinion the insurer is not in a position to say it paid the full cost to repair or rebuild.
Managed drying was not provided for in the scope of works. It does not assist to say that the
insurer would have been willing to retrospectively include an amount for drying.
I am satisfied that on the facts of this case the cash settlement has not discharged the
i nsurer’s obligation.
2.2 Is the insurer liable for the remediation?
Yes. The insurer should carry out the remediation specified by its flooring expert and the
complainants should reimburse any excess received in the cash settlement above actual
costs incurred.
Fair in circumstances for insurer to complete remediation
In the circumstances the insurer should proceed with the remediation described by AB in its
report. As a result, the insurer is to some extent paying twice for the repair work.
Determination | Case number: 808374 Page 4 of 4
It is unknown to me if the actual costs incurred by the complainant on the scope of work
specified by AB and the temporary accommodation were more or less than the cash
settlement they received. The complainant should provide the insurer with details of the
actual costs incurred for the work performed and the temporary accommodation.
In the event that actual costs were less than the cash settlement, the complainants should
reimburse that difference to the insurer within 21 days of accepting this determination.
2.3 Why is the outcome fair?
Cash settlements are a convenient method for an insurer to discharge liability. The discretion
to cash settle must be exercised fairly and with an appropriate level of care and detail.
Unfortunately, in the present case the scope of work fell short of what was required to achieve
the necessary repairs.
2.4 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.