Home / IAG / Determination 802400
Determination 802400
Claim handling delay in repairs after fire damage to rental property
Summary
A landlord complainant's rental property was damaged by fire and repairs took almost two years instead of about five weeks, leaving him unable to let it. AFCA found the insurer mishandled the repairs and ordered payment of additional loss of rent beyond the policy limit plus $3,000 for non-financial loss.
Where the insurer unreasonably delayed repairs, loss of rent flowing from that delay is direct financial loss recoverable even beyond the policy's 12-month loss of rent limit.
Issues
- Repairs or contractors primary · upheld“The repairs were defective and the builder refused to restore roof bedding and pointing; repairs took almost two years rather than about five weeks.”
- Delay secondary · upheld“The insurer took an unreasonably long time to complete repairs; repairs completed 14 July 2020 but complainant not told until 30 September 2020.”
- Poor communication secondary · upheld“Builder did not inform the complainant repairs were complete until 30 September 2020, and gave no detail on reasons for delay.”
Subjects and remedies
pay compensationpay non financial loss
Related
Text of the determination
Determination
Case number 802400
Financial firm Insurance Manufacturers of Australia Pty Ltd
Determination | Case number: 802400 Page 1 of 6
Case number: 802400 31 January 2022
1 Determination overview
1.1 Complaint
The complainant holds a landlord insurance policy with the financial firm (the insurer). He
lodged a claim after the insured property was damaged by fire on 12 February 2019. The
insurer accepted the claim and agreed to repair the property.
Repairs were initially estimated to take five weeks. The complainant says repairs took almost
two years, and he could not let the property until repairs were complete.
The insurer paid loss of rent from 13 March 2019 (when the tenants moved out) to 25 June
2020. The complainant wants the insurer to pay loss of rent from 26 June 2020 to 11 January
2021 (when repairs were complete).
The policy covers loss of rent for up to 12 months. The insurer says it has already paid more
than this, and will not pay any more.
1.2 Issues and key findings
Is the complainant entitled to additional compensation for loss of rent?
The insurer has paid more than the policy limit for loss of rent. However, the complainant
suffered additional loss of rent because the insurer took an unreasonably long time to
complete repairs. The insurer should compensate the complainant for this additional loss of
rent, even though it is not covered under the policy.
The additional loss of rent caused by the insurer’s delay is $16,654. Therefore, the insurer
must pay the complainant an additional $16,654 for loss of rent.
Is the complainant entitled to other compensation?
AFCA can award up to $5,400 for non-financial loss if an insurer causes an unusual degree of
stress, inconvenience, or delay.
The complainant is entitled to $3,000 compensation for non-financial loss.
1.3 Determination
This determination is in favour of the complainant.
The insurer must pay the complainant:
$16,654 for additional loss of rent
$3,000 for non-financial loss.
Determination | Case number: 802400 Page 2 of 6
2 Reasons for determination
2.1 Is the complainant entitled to additional compensation for
loss of rent?
Property damaged by fire
On 12 February 2019, the insured property was damaged by fire. The complainant lodged a
claim the same day.
The insurer accepted the claim and repaired the property. The repairs were defective. The
insurer agreed to carry out further repairs.
On 11 January 2021, the complainant inspected the property and agreed it had been properly
repaired. The insurer returned the property’s keys to the complainant.
Complainant claims additional loss of rent
The policy covers loss of rent if the property is damaged by an insured event (such as a fire),
and the insurer agrees the tenants can’t live in it.
The insurer paid loss of rent from 13 March 2019 (when the tenants moved out) to 25 June
2020. The complainant wants the insurer to pay loss of rent from 26 June 2020 to 11 January
2021 (when repairs were complete).
The policy covers loss of rent for up to 12 months. The insurer has already paid more than
this. The policy does not entitle the complainant to any further payment for loss of rent.
However, if the complainant suffered additional loss of rent because the insurer mishandled
the claim, the insurer should compensate him for this loss, regardless of the policy terms.
Insurer mishandled claim
The insurer’s builder inspected the insured property on 13 February 2019, the day after the
fire. The builder estimated repairs would take about five weeks. Repairs were not completed
for almost two years.
The insurer said repairs were delayed because ‘ unforeseen damages were identified during
the course of repairs ’. It says it cannot say what a reasonable time to complete the repairs
would have been. It says the cost of repairs ended up being about three times the original
estimate. If the time required to complete repairs is proportional to cost, a reasonable time to
complete the repairs would have been about 15 weeks.
The insurer asked its builder to comment on why repairs were delayed. The builder said
repairs were delayed ‘ due to plans permits, engineering weather and client delays ’. The
builder did not provide any more detail than this. The builder did not mention unforeseen
damages being identified during the course of repairs.
The information provided by the parties (including the insurer’s claim n otes) indicate repairs
were delayed because:
the builder refused to restore the roof bedding and pointing to the condition it was in before
the fire. The builder said building regulations did not require the roof to have bedding and
pointing. The insurer agreed to restore the bedding and pointing (using a different builder)
after the complainant complained
Determination | Case number: 802400 Page 3 of 6
the builder completed repairs on 14 July 2020, but did not inform the complainant the
repairs were complete until 30 September 2020
the repairs completed on 14 July 2020 were defective. The complainant told the insurer
about the defects on 7 October 2020, one week after he was told the repairs were
complete. The insurer says the defects were ‘minor’, but the builder did not rectify the
defects until 11 January 2021.
The insurer has not provided information showing the complainant contributed to the delays.
Having considered the information provided by both parties, I am satisfied the repairs took an
unreasonably long time to complete. I am also satisfied the delays were primarily the fault of
the insurer and its builder.
Mishandling of claim caused additional loss of rent
The insurer says the defects remaining after 14 July 2020 were minor, and did not make the
property uninhabitable. The insurer says the complainant could have moved tenants into the
property from 14 July 2020.
The complainant says the property was unsafe until 11 January 2021, because water was
leaking through the roof and through a light fitting. The builder says water was leaking ‘in the
v icinity of the light’, but the property was still habitable. In an email on 25 February 2021, the
builder said the leak ‘ did not form a real danger to life and limb ’. In an email on 26 July 2021,
the builder said: ‘All properties are fitted with RCD which protects all electrical circuits. There
was at no time any risk.’
In my view, it would be unreasonable to expect the complainant to move tenants into the
property while water was leaking through a light fitting, especially since the fire that gave rise
to the claim was caused by an electrical fault.
Having considered the information provided by both parties, I am satisfied repairs were not
complete, and the complainant was not able to let the property, until 11 January 2021.
Complainant entitled to additional compensation for loss of rent
I am satisfied that the insurer mishandled the claim by taking an unreasonably long time to
complete repairs. I am also satisfied that this caused the complainant to suffer a loss,
because he was not able to let the property until repairs were complete.
The insurer has paid more than the policy limit for loss of rent. However, the complainant
suffered additional loss of rent because the insurer mishandled the claim. The insurer should
compensate the complainant for this additional loss of rent, even though it is not covered
under the policy.
Additional loss of rent totals $16,654
The insurer should pay additional loss of rent from 26 June 2020 (when it stopped paying loss
of rent) to 11 January 2021 (when it completed repairs). This is 200 days.
The complainant says the insurer should pay loss of rent at a rate of $83.27 per day. The
insurer does not dispute that this rate is reasonable. 200 days at $83.27 per day is $16,654.
The insurer should pay the complainant an additional $16,654 for loss of rent.
Determination | Case number: 802400 Page 4 of 6
Loss of rent is direct financial loss
Under the AFCA Rules, AFCA can award compensation of up to:
$542,500 for direct financial loss
$5,400 for indirect financial loss
$5,400 for non-financial loss.
The AFCA Rules do not define direct or indirect financial loss.
When reviewing AFCA’s jurisdiction , Australian c ourts have said direct loss is loss that ‘ flows
naturally from the breach without other intervening cause ’ ( Australian Capital Financial
Management Pty Ltd v Australian Financial Complaints Authority Limited [2021] NSWSC
1577).
The insurer took an unreasonably long time to complete repairs, and the complainant could
not let the property until repairs were complete. Loss of rent flowed naturally from the
insurer’s failure to complete repairs. There was no other intervening cause that prevented the
complainant from deriving rental income from the property. Therefore, the additional loss of
rent is direct financial loss. It is subject to AFCA’s jurisdictional limit of $542,500 for direct
financial loss, and is not subject to AFCA’s jurisdictional limit of $5,400 for indirect financial
loss.
The insurer must pay the complainant an additional $16,654 for loss of rent.
2.2 Is the complainant entitled to other compensation?
Complainant entitled to compensation for non-financial loss
Under the AFCA Rules, we can award up to $5,400 compensation for non-financial loss if a
complainant suffered an unusual degree of stress, inconvenience, or delay because an
insurer mishandled a claim.
The insurer failed to complete repairs within a reasonable time. Repairs which should have
taken about 15 weeks took almost two years. The complainant had to engage in extensive
oral and written correspondence with the insurer and the builder, and make several
complaints, to get the insurer to complete the repairs.
The insurer apologised for its level of service not meeting the complainant’s expectations, and
offered to settle the complaint by paying the compensation of $2,000.
I am satisfied that the complainant suffered an unusual degree of stress, inconvenience, and
delay because the insurer mishandled the claim. In my view, this warrants an award of
compensation for non-financial loss in the sum of $3,000.
Determination | Case number: 802400 Page 5 of 6
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. I have reviewed and considered
all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, I have restricted this
determination to the issues that are relevant to the outcome.
3.2 Relevant AFCA Rules
Section D – Remedies
Section D sets out the remedial action that an AFCA Decision Maker has the power to
decide upon.
D.3 Compensation for complaints other than Superannuation Complaints
D.3.1 An AFCA Decision Maker may decide that the Financial Firm is to
compensate the Complainant for direct financial loss. When calculating
the value of such a remedy, monetary compensation and any remedy
where the value can readily be calculated, such as the waiving of a debt,
are included.
D.4 sets out the maximum amount that an AFCA Decision Maker can
award for direct financial loss.
D.3.2 In addition or instead, an AFCA Decision Maker may decide that the
Financial Firm is to compensate the Complainant for indirect financial
loss. This is not the case if the complaint arises as a result of a claim:
a) on a General Insurance Policy that expressly excludes such
liability; or
b) by the Complainant under another person’s Motor Vehicle
Insurance Product.
D.4 sets out the maximum amount that an AFCA Decision Maker can
award for direct financial loss.
Determination | Case number: 802400 Page 6 of 6
D.4 Monetary limits for complaints other than Superannuation Complaints
Limits applying to complaints submitted to AFCA on or after 1 January 2021
Claim for direct
financial loss
Type of claim
Compensation
amount limit
per claim
All other claim s (excluding Superannuation Complaints)
[All non - superannuation complaints not arising from income
stream insurance, general insurance broking, uninsured
motor vehicle s , or credit facilit ies ] $542,500
Claim for indirect financial loss $5,400
Claim for non - financial loss $5,400
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.