Storm damage claim for roof and internal water damage, mould remediation and contents; roof damage declined, internal damage and mould accepted with cash settlement and delay
Text of the determination
Determination
Case number 801667
Financial firm The Hollard Insurance Company Pty Ltd
Determination | Case number: 801667 Page 1 of 19
Case number: 801667 21 July 2022
1 Determination overview
1.1 Complaint
The complainant has been represented by her sons (TA and GA) at various points during this
complaint. Any reference to the complainant in this determination includes her sons.
The complainant lodged a claim for storm damage under her home building and contents
insurance policy with the financial firm (insurer) after she noticed rainwater coming through
the ceiling following a storm on 9 February 2020.
The insurer tried unsuccessfully to make a decision about the claim using information it
requested and obtained from the complainant. The insurer subsequently appointed builder
(CC) to inspect the damage. This was over a year after the claim was initially lodged.
The insurer concluded that the roof damage claimed was not caused by storm . It says CC‟s
report shows the roof damage was due to pre-existing defects/workmanship and maintenance
issues, not storm. However, the insurer agreed to cover internal water damage and mould
damage caused by water ingress from the roof during the storm.
The complainant disagrees with the insurer‟s decision and seeks a review. She says the roof
was damaged during storm events in 2020 and 2021. She also:
suggests any pre-existing issues can be attributed to the insurer not adequately
addressing damage under a 2015 storm claim
suggests the make-safe put in place by the insurer in March 2021, has become loose and
has caused further damage
disagrees with the insurer‟s scope of works and settlement/proposed settlement for
internal damage (to building and contents) and mould remediation.
1.2 Issues and key findings
Is the insurer required to lodge additional claims?
No. The available information shows all loss/damage claimed is appropriately considered
under the claim lodged in February 2020.
Is the insurer liable for any roof damage?
The insurer is not liable for the repair/replacement of the roof. On the available information:
the damage was not caused by storm and
the damage was not „ accidental ‟ within the policy meaning
The insurer has paid the complainant costs she had incurred to repair the roof (prior to its
assessment) in acknowledgment of its delays. The insurer is not required to make any
additional contribution to the roof repairs.
What is the insurer’s liability for internal damage and mould remediation?
There is no dispute about cover for resultant water damage to the home.
Determination | Case number: 801667 Page 2 of 19
The panel accepts that th e complainant‟s mould reports are more persuasive. It considers the
remediation quote (for items other than the roof) is reasonable. The insurer should settle this
aspect of the claim based on MR‟s quote, in the manner set out in section 2.2 of this
determination.
However, the panel accepts the scope of building works is adequate. As the insurer‟s
settlement was based on a quote which dates back to 2021, market cost of repairs is likely to
have increased. Additionally, a cash settlement means some risk is transferred to the
complainant. As such, it is fair that the insurer pays an additional 20% of the total cost for
contingencies.
Is the insurer required to compensate the complainant?
Yes. This is because the insurer‟s handling of the claim as a whole, was less than ideal and
was not in line with the General Insurance Code of Practice (GICOP). The panel notes:
the insurer did not determine the cause of damage or make a decision about indemnity for
over a year,
the insurer did not contact the complainant regularly in that time, and
the insurer‟s delays contributed to the home becomi ng uninhabitable (due to mould).
While the insurer provided or covered some temporary accommodation cost once mould was
identified in the home, the need to move out of the home along with the delays would have
caused the complainant stress and inconvenience
In view of the above, the panel considers it fair that the insurer pays the complainant $4000
non-financial loss compensation.
Is the insurer required to pay any other costs?
On the information provided, the panel considers it fair that the insurer reimburses costs
incurred by the complainant in obtaining the mould reports from specialist (MR).
1.3 Determination
This determination is partially in favour of the complainant.
If the complainant accepts this determination, the insurer is to take the steps outlined in
section 2 of this determination.
Determination | Case number: 801667 Page 3 of 19
2 Reasons for determination
2.1 Is the insurer required to lodge additional claims?
Circumstances of the claim/complaint
The complainant appointed builder (AP) to conduct emergency repairs prior to lodging the
subject claim on 13 February 2020. AP‟s quote/invoice of 11 February 2020 shows i t
replaced/repaired some roof tiles.
The insurer did not take steps to assess the claim and had limited contact with the
complainant, immediately following lodgement of the claim.
After the complainant made several attempts to follow up the claim, she notified the insurer in
June 2020, that she would commence roof repairs on her own due to its inaction and delays.
The complainant then provided the insurer with roof repair quote/invoice from AP and
carpenter (IM) seeking reimbursement of those costs. In response, the insurer requested
additional information from the complainant, particularly a break-down of repair works by AP.
It says it needed this to complete its assessment (by „desk - top‟).
The available information shows:
the complainant was unable to provide any detailed break-down or additional information
it became apparent the relationship between the complainant and AP had broken-down
around December 2020/January 2021 and that police had become involved.
the complainant later advised the insurer that AP was no longer in business.
The insurer appointed CC to inspect the damage in March 2021. This was after it determined
that the documents provided by the complainant were insufficient for it to make a decision
about the claimed roof damage. The insurer also conducted make-safe to the roof, at the
complainant‟s request, on 22 March 2021. The request was made after she says further water
ingress had occurred from the roof.
After reviewing CC‟s report (including input from a roofer appointed b y CC), the insurer
concluded:
that the reports show the roof was not damaged by storm
any damage to the roof relates to maintenance and workmanship issues
based on information from a previous claim in 2015, the maintenance issues were pre-
existing.
In acknowledgement of the delays in assessing and making a decision about the claim, the
insurer offered to reimburse costs which the complainant said she had incurred for AP‟s roof
repairs and carpentry. It says the make-safe in March 2021 was completed for the same
reason.
Further, the insurer says it agreed to complete mould remediation and resultant internal
repairs. However, the complainant did not provide evidence the roof repairs were complete
despite the insurer‟s requests and this meant it was unable to do the work and a cash
settlement was provided.
The complainant maintains the insurer is liable for damage to the roof and all damage which
flows from water ingress from the roof. Among other things, the complainant suggests quotes
and work done by:
Determination | Case number: 801667 Page 4 of 19
“[AP] and also [IM] were for works relating to storm damages caused by the “First
Storm on or around February 2020 (09/02/2021)” for which we have been
reimbursed. However we have not been reimbursed for Storm damages caused
by “Second Storm on or around March 2021 (03/2021)” which remain outstanding.
The complainant also says the insurer‟s delay in finalising this matter has resulted in the
make-safe it put in place causing further damage. This was first raised with the insurer on 28
February 2022 in an email to the insurer which included:
…We are having another problem with the make safe unfortunately.
The ropes that are attached to the tarp at the back of our home have damaged
the roof and is leaking in upstairs lounge room and bedroom. See attached
photos…
The complainant wants the insurer to cover a complete replacement of the roof, building
works and remediation based on quotes from her trades and reimburse costs she says she
incurred:
from installing „Air Scrubbers‟ at the premises from August 2021 to February 2022
for temporary accommodation for periods between 2021 and 2022 when the insurer
ceased providing it.
to obtain mould specialist ‟s reports
Additionally, the complainant wants the insurer to pay the sum insured for contents.
The complainant has also suggested there are three distinct claims which the insurer should
be considering.
Information does not show insurer should lodge more than one claim
The panel has reviewed the available information and notes there is no evidence any claim
other than claim number ending ***629 was lodged by the insurer from 13 February 2020 to
date.
Contrary to the complainant‟s suggestion CC‟s assessment was conducted in relation to a
second claim in March 2021, the following information does not support this. The panel notes:
CC‟s report does not identify its assessment was for a new claim. The assessment was
arranged prior to the complainant reporting further water ingress, the report refers to the
same claim ending 629, and the description of the claim is as lodged in February 2020.
the insurer‟s email to the complainant of 8 June 2021 does not show there is a separate
claim for storm in 2021. The email was sent to the complainant about payment for the roof
repairs; the insurer says a payment of $21,389.40 had been made for the roof under the
original date of loss. It also refers to mould remediation, but there is no mention of a new
claim.
file records only relate to claim ending 629.
Having considered all the exchanged material, the panel does not consider separate claims
are required for it to address the loss/damage claimed as a whole. The panel questions what
(if any) benefit could come of a separate claim/s given having additional claims would mean
additional excess payment for each claim, and a higher number of claims on the
complainant‟s claim‟ s record.
Determination | Case number: 801667 Page 5 of 19
Further, to be covered under a claim, the complainant must first show the loss/damage
occurred in circumstances covered by the policy. The complainant has not provided evidence
she suffered loss or damage to the roof from an incident in March 2021, the information only
shows further water ingress into the home.
2.2 Is the insurer liable for any roof damage?
Onus on complainant to establish a valid claim
The complainant‟s home insurance policy covers loss or damage that occurs during the
relevant period of insurance because of several listed events. The policy also provides
additional accidental damage (AD) cover. All cover under the policy is subject to conditions
and exclusions which are set out in the applicable product disclosure statement (PDS).
When lodging a claim, the complainant is required to first show, on the balance of
probabilities, (that is more likely than not) she suffered a loss caused by an event which the
policy covers. This is known as establishing a valid claim. The onus to establish a valid claim
extends to showing all damage claimed was caused by the event claimed or any other event
covered by the policy.
If the complainant can establish a valid claim, then the onus shifts to the insurer to show, on
the balance of probabilities, it is entitled to rely on a policy exclusion or is otherwise entitled to
deny the claim.
Consideration of evidence on cause of damage to roof
The insurer does not dispute that a severe storm occurred on the reported date of loss, or
that it impacted the complainant‟s property. However, it says available evidence:
does not show the roof damage claimed was caused by storm, and
shows the roof damage is pre-existing, due to defects/workmanship and maintenance
issues.
The complainant provided a quote from builders AP and IM, as well as a statement from
buildi ng consultant „IB‟. The panel notes :
the emergency make-safe invoice from AP dated 11 February 2020, shows some roof tiles
were replaced/repaired. There is no detailed explanation of the damage or cause other
than a tick-box next to „Other‟ and notation “storm damage reasons‟
the quote from IM dated 14 March 2020 for carpentry works, does not address the cause
of damage
the roof re pair quotes from AP dated 28 October 2020 and numbered „30‟ and „3‟
respectively, do not address the cause of damage to the roof and only summarises repairs
required without any breakdown of quoted amount.
The panel is of the view that IB‟s statement does not assist in establishing any damage to the
roof from the storm or an „ event ‟ which the policy covers. It has taken the following into
account:
IB did not physically inspect the roof or make a finding on the cause of damage. IB says it
could not assess the roof as it was not willing to remove and re-instate the tarpaulin (which
was put in place by the insurer as part of make-safe in March 2021).
IB‟s report does not show the roof damage could reasonably have been caused by a one-
off storm/event.
The report mainly points out perceived deficiencies in the insurer‟s reports, particularly, the
roofing report because of how brief it is and the lack of information about its author. It does
Determination | Case number: 801667 Page 6 of 19
not provide any information that assist in showing the comments purportedly made by the
roofer were factually incorrect.
The panel also notes that the involvement of the complainant‟s own builder and the
emergency make-safe as well as repairs reportedly completed by AP, were not mentioned by
IB. This suggests IB‟s comments have been made without taking the impact of AP‟s
involvement into account. This seems evident fro m IB‟s reference to the insurer carrying out
temporary repairs/make-safe to the area of the roof under the subject claim, when it
concluded that there had been actual repairs rather than just make-safe by the insurer. IB
seems to conflate what appears to be repairs by AP with views provided to it by the
complainant, that the roof was not adequately repaired under previous claims (2015 and
2020).
The panel notes that CC found water ingress was occurring due to design issues with the roof
„valley‟. CC says a „box gutter‟ should have been installed rather than a „valley‟. It considered
this is a defect and said this defect resulted in water ingress into the home during heavy
rain/storm as the „valley‟ is unable to handle the volume of water .
There is nothing in CC‟s report to show it considered there was actual damage to roofing
materials from the storm or any other covered event.
In addition to its first report, the insurer provided an email from CC explaining its findings. The
email is dated 23 June 2021, which supports the above.
There is no dispute CC is suitably qualified to report on the cause and extent of damage to
the complainant‟s roof. In the absence o f any contradictory evidence, the panel is persuaded
by the conclusions reached by CC about the roof.
CC‟s reports followed inspections of the roof and premises. While the inspection occurred just
over a year after the claim was lodged, it is the only document available which addresses the
cause of any damage to the roof based on its own inspection. Consequently, the panel
prefers CC‟s findings. The panel is satisfied, on balance, that CC‟s statements/report show:
damage to the roof is likely from a combination of:
> the age of the roof (36 years).
> ongoing maintenance issues (evidenced by reported rotted timber roof battens when
the fascia/barge was removed by the complainant‟s trades and mould found by MR)
water ingress which had occurred due to desi gn issues with the roof „valley‟
Evidence does not establish any ‘ accidental ’ damage to the roof
As mentioned above, the complainant‟s policy also provides accidental damage cover.
Accident is defined in the PDS as “ an event that you did not plan, intend or expect to
happen ”. Event is also defined to mean: “ a single occurrence which you did not intend or
expect to happen that results in loss or damage.” (emphasis added)
This means to be covered for the claimed roof damage, under the accidental damage
provisions of the policy, the complainant must show the damage was „ accidental ‟ as defined
above.
Based on the definition of „accident‟ and „event‟ above, for damage to be covered under the
provision, it needs to be the result of a one-off occurrence which is unexpected.
There is no evidence to show a single event resulted in damage to the roof in the present
circumstances. Rather, as discussed in the preceding paragraph, the available information
Determination | Case number: 801667 Page 7 of 19
suggests there were defects/workmanship or maintenance issues with the roof which were
long-term and present prior to February 2020.
No evidence roof damage relates to defective repairs by the insurer in 2015
The complainant‟s submission s include that any pre-existing issues with the roof are due to
inadequate assessment and repairs by the insurer, under a prior storm claim in 2015.
In response, the insurer says it did not conduct any roof repairs under the 2015 claim and
only conducted internal repairs and limited make-safe which was not in the area of the roof
currently under review.
The insurer provided a report completed by CC in 2015. The panel has reviewed the report
which followed an inspection on 4 May 2015. The report includes that the complainant
reported, and CC found:
1. water damage to areas of the building, specifically the carport ceiling, external light
fittings, „‟A/C sheet filling‟ at the front entry eave which had been dislodged, window
frame and wall lining in the rumpus area
2. water damage to contents, specifically carpet and a free-standing wardrobe in the
rumpus area
3. wear and tear to timber beam supporting a garage door as well as damage to that door
which was unrelated to the claim.
At the time, CC concluded the cause of damage to 1 & 2 above was the storm event claimed.
It says the damage occurred due to wind driven rain being “ blown in through the window and
eave linings above the rumpus room and the extreme wind has caused the light to be blown
around and timber eave trims and infills to be blown off ”.
The pane l has considered the complainant‟s submission seeking to link any maintenance or
workmanship issues with the roof (post-2015), to the 2015 claim. It is not satisfied the
available information shows the loss relates to that claim. It has taken the following into
account when forming this view:
CC‟s report of 2015 does not show repairs were conducted to the area of the roof which is
the subject of the 2020 claim.
CC‟s report of 30 March 2021 also confirms:
> it did not conduct any roof repairs to the area affected in 2020, under the 2015 claim
> suggests AP‟s incomplete repairs relate to maintenance issues which were present and
was noted in their 2015 report
the complainant did not raise any concerns about the repairs under the 2015 claim, and
the complainant has not provided any evidence showing maintenance or repairs to the roof
between 2015 and 2020
while the complainant refers to IB‟s statement as showing the insurer completed repairs,
as explained earlier, the panel is satisfied that IB‟s statement raises questions about the
information it was provided and considered. IB refers to the insurer completing
repairs/make-safe on the area of the roof currently in dispute, when the available evidence
suggests this was done by AP.
The insurer is not required to cover any roof repairs
On the available information, the panel accepts the claimed roof damage was not caused by
storm. The panel is also not satisfied the damage can be considered „accidental‟ as defined in
Determination | Case number: 801667 Page 8 of 19
the policy. This is because the available information shows, on balance, it is not the result of a
„single occurrence‟ and relates to maintenance issues which pre-date the storm or were not
addressed over a period of time.
Further, the complainant says she had repaired the roof in 2020. Available information,
including the insurer‟s file notes show:
she indicated these repairs were to commence in or around July 2020,
the roof repairs were occurring from that time until around December 2020
the complainant has been unable to provide evidence showing the specific roof repairs
completed
CC and IB‟s report both suggest prior repairs to the roof were incorrectly done or
incomplete
It would be unfair to hold the insurer responsible for the roof damage where the evidence:
does not show it was caused by the storm or a one-off event in 2020
information provided by the complainant does not establish that the roof itself was
damaged during this storm or any other storm for which the insurer is required to cover
under a separate claim.
the complainant had not conducted any maintenance to the roof including that
recommended to “wood rotted timber fascia, lead flashing onto the carport and timber
above the garage door” under a previous claim in 2015
the insurer made payment to the complainant on 8 June 2021, for the roof repairs despite
its position that it was not liable for the roof repairs for the reasons explained above. The
complainant did not repair the roof at this time or take to steps mitigate against further
damage from this time.
Further, the available information does not support a conclusion that any damage occurred to
the roof itself from March 2021 to date (including from make-safe tarpaulins) or that any leak
from the roof was caused by issues distinct from the issues which CC concludes likely pre-
date February 2020.
Other matters
The complainant says additional damage has occurred over between March 2021 and
February 2022 (particularly during a storm at the end of February) due to issues with the
make-safe tarpaulins installed by the insurer.
The insurer was provided with information from the complainant including an email of 28
February 2022. The insurer did not respond to the assertion/allegations and on the available
information, has not lodged a separate claim to address this.
In its response of 17 March 2022, the insurer re-iterated that its position remains as outlined
in its „Notice of Response‟ to AFCA of 13 August 2021. It also :
maintained the proximate cause of roof damage was not the storm and that it agreed to
cash settle based on roof repair quotes provided by the complainant in recognition of “the
poor claims experience and delays”.
It agreed to complete internal remediation and repairs once the complainant repaired the
roof, however the complainant has not done so to date.
As to the complainant‟s suggestion a separate claim should exist, the panel does not agree
the complainant has provided information showing a separate event occurred for which a
claim needs to be lodged.
Determination | Case number: 801667 Page 9 of 19
In any case, the panel does not consider the insurer is liable for any damage which may have
occurred after it paid the complainant to repair the roof and communicated to her its decision
not to cover the claimed damage for the roof. In those circumstances it would be unfair to
hold the insurer responsible for any damage after 8 June 2021.
2.3 What is the insurer’s liability for internal building damage
and mould remediation?
No dispute building’s interior suffered rainwater damage
There is no dispute the insured property suffered damage from rainwater ingress. The insurer
agreed to cover resultant damage to areas/content identified in CC‟s report including:
ground and first floor linen/storage cupboard
main bathroom on the first floor (from the exhaust fan)
wall on top of intercom handset in the first-floor lounge room
first floor toy/rumpus room and lounge room
Parties disagree on scope and cost of mould remediation required
The insurer says its restoration company (SR) submitted a scope of works to it in May 2021
which it based its initial settlement of $14,256 to the complainant (for mould remediation). It
provided a copy of SR‟s “Amended restoration report” dated 22 July 2021 , which appears to
include SR‟s initial report wording with „amendments‟ in red letters. This amended report
followed SR‟s revie w of the mould specialist report from the complainant‟s expert - MR.
In SR‟s amended SOW, it increased its estimated costs for mould remediation to $31,802.26.
The panel notes SR specifies this estimate:
does not include allowances for hygienist to remove and remediate contents, install
containment, remove and dispose of upper level carpets, scaffolding as required for works
to the stairwell/atrium.
does not include “ Further works may be required once ceiling is removed due to length of
time since event and exten t of mould growth in roof space”
is subject to variation
excluded post remediation variations (PRV). According to the insurer PRV refers to costs
to obtain a sign-off upon completion of remediation works.
The insurer cash settled the complainant for the difference between its initial payment and
SR‟s updated quote in August 2021 , after the complainant did not take an option it had
previously offered (for the complainant to repair the roof and provide evidence of repairs,
refund amounts it already paid for building repairs and mould remediation totalling
$27,453.51, after which it would complete building and mould remediation works itself).
The complainant was and remains dissatisfied with the settlements in July and August 2021,
both of which she says the insurer went ahead with, even though she clearly expressed:
she did not want a cash settlement
she wanted the insurer to repair the roof first, then complete all other repairs itself because
of her age and limited command of the English language.
The complainant has obtained further comment and estimates from MR on the adjusted SOW
and this information was provided to the insurer.
Determination | Case number: 801667 Page 10 of 19
In an effort to resolve this matter amicably after reviewing the SOW from late 2021, by email
dated 17 March 2022, the insurer offered an additional $16,015.37. It explained the amount
as follows:
Complainants Remediation cost provided $63833.00
Less Prior remediation settlement paid $31802.26
Total $32030.74
50% of variance $16015.37
Total offer $16015.37
The complainant rejected the offer and has recently provided a mould remediation estimate
from MR (dated 6 April 2022) with a total cost for remediation of $121,814 (exc GST). The
insurer has not commented on this SOW.
Mould report from MR is preferred
The panel has carefully reviewed the restoration and mould removal reports provided by SR
and MR respectively.
The panel notes both seem to be on the same page regarding the areas of the home which
have mould damage and require remediation being mainly:
the roof cavity
room 1 (or daughter‟s room)
room 2 (or insured‟s room)
Hallway (including a linen cupboard located there)
stairwell atrium
upstairs bathroom
The panel accepts both SR and MR are suitably qualified to provide the opinion and
estimates contained in their respective reports. However, after carefully considering the
reports, the panel pre fers MR‟s because it follows an inspection of the premises, and contains
detailed analysis based on its own observations and expertise, in reaching its conclusions on
what is required to address mould within the premises.
The insurer is required to increase settlement for mould remediation
As explained earlier in this determination, the insurer is not liable for damage to the roof.
MR ‟s report includes; “ tertiary coloniser stachybotrys which an indicator of long-term water
damage in roof cavity ”.
The panel accepts mould is likely to have been a long-term issue within the roof cavity. As
such, is satisfied the insurer is also not liable for mould remediation in the roof cavity.
MR‟s estimates of 13 September 2021 and 6 April 2022, do not provide for certain
actions/activities which need to be carried out by a builder or hygienist prior to, or after its
remediation.
The building works required for remediation such as removal and disposal of ceiling and
insulation batts are provided for in the insurer‟s building quote and will be addressed in the
following paragraph. However, the panel is satisfied the allowances in the building quote
sufficiently addressed this in the mould affected rooms on the upper level of the home.
The panel accepts it is reasonable for the mould remediation costs to be cash settled based
on MR ‟ s quote of 13 September 2021, for the following reasons:
Determination | Case number: 801667 Page 11 of 19
the roof damage was not caused by an insured event
the complainant advised the roof had been repaired, did not provide sufficient evidence of
the extent of repairs completed and despite being informed that the roof would not be
covered in June 2021, took no steps to repair the roof, or mitigate against further water
ingress into the home to date.
the insurer reimbursed the complainant for the costs she said she had incurred to repair
the roof in June 2021. Arguably, this and other payments subsequently made to the
complainant could have been applied to repair the roof while this complaint remained on
foot. This also did not occur.
MR‟s estimated cost to remediate the home significantly increased between August 2021
and April 2022 as shown in the table below)
In
view
of
the
abo
ve,
it
woul
d be
unfa
ir to
requ
ire
the
insu
rer
to
settl
e the mould portion of this claim using the quotes of 6 April 2022. Had the complainant taken
steps to mitigate further water ingress, arguably, the remediation could have occurred earlier,
and the increased cost of remediation could have been avoided.
The panel therefore considers it reasonable that the insurer bases its settlement on the 13
September 2021 quote, less the cost relating to the „ Roof cavity/labour/consumables ‟ and
previous amount cash settled.
The insurer is to pay an additional $53,313.29, which includes a 20% uplift for contingencies.
The insurer is to pay interest on this amount, in accordance with section 57 of the Insurance
Contracts Act 1984 (the Act), from 13 September 2021 to the date of payment.
The panel has considered the additional $56,470 payment which the complainant is seeking
for installing “air scrubbers” / “ Negative Air Machine from 27 August 2021 to 28 February 2022
= 186 Days @ $100 per day per filter ” for $56,470 .
The panel notes that the air scrubbers were recommended by MR.
It is the panel‟s view that the air scrubbers were required in part due to the combined impact
of the complaina nt‟s failure to properly repair the roof and the insurer‟s early inaction
regarding the claim.
Item MR’s quote – 13 Sep tember
2021 (Total = $8 8,880 inclusive
of GST)
MR’s quote – 6 April 2022
(Total = $121814 inclusive of GST)
C ontainment/set up $ 1,760.00 $1760
Pack - o ut/storage
/consumable
$34.980.00 (includes laundry) $60,390 (excludes
laundry)
Roof cavity / labour /
consumables
$12,650.00 removed as advised
entire roof to be r eplaced.
Remediation/labour/
consumables
$14,300.00 $27,500
Structural drying/AFDs $19,140.00 $26,664
Post remediation variation (PRV) $ 6,050.00 $5500
Determination | Case number: 801667 Page 12 of 19
In the circumstances it is fair that the insurer contributes 50% of the cost of the air scrubbers,
that is, $31,058.50. The insurer is to pay interest on this amount from the date the account
was paid by the complainant until the insurer makes payment.
Further, the complainant wants the insurer to pay the total sum insured for contents under the
policy ($73,400) and $13,200 to replace all carpets. The panel notes that carpets fall under
contents within the policy. As such, the carpet replacement costs are part of the total contents
sum insured.
While both SR and MR say affected contents need to be remediated, there is nothing in their
documents to suggest affected contents cannot be remediated or restored.
There is insufficient information to determine a contents settlement (other than carpet). The
insurer was provided with the complainant‟s carpet quote and has not provided any
information to dispute the quoted amount. As such, the insurer should cash settle the
complainant for the cost of replacing the carpet based on her quote for $13,200.
In relation to the remaining contents, the following is to occur:
the insurer is to provide the complainant with an option of two independent
hygienist/restorer within 14 days of the complainant accepting this determination
once the complainant decides which restorer to proceed with, the insurer is to arrange for
the restorer to attend location of the stored contents and complete a detailed report within
a further 7 days.
within 7 days of receiving the restorer‟s re port, the insurer is to assess the contents claim
in line with the policy terms and propose settlement to the complainant.
the parties should work together to reach a resolution to this aspect of the case.
Insurer’s quote for internal building repair
The insurer cash settled the complainant $14,256 (incl GST) for building repairs based on
CC‟s SOW/quote. It has not provided a copy of the SOW, however, a screenshot is
contained in its email to the complainant, of 5 July 2021, outlining the payment.
The insurer subsequently obtained and provided an updated SOW/quote from CC with a total
cost of $18, 837.10. The quotes provide for the following (where required) and to different
extents in 1-bedroom, upstairs bathroom, upstairs hallway and a linen cupboard in the
hallway, and a stairwell:
electrical work
carpentry
remove, dispose and supply ceiling, wall plasterboard, insulation batts and cornices
prepare and paint ceiling, cornices, plasterboard walls
It also provides for:
remove, dispose, supply and install 2 wardrobe swing doors, built in cupboards and
shelves for the hallway and linen cupboard
painting only 1 wall in the living area and
preliminaries (remove& dispose: 4 M3 waste bins, scaffolding)
Complainant’s quote for building repairs
The complainant recently provided quotes which she considers adequately reflects the
present cost of repairs to the building. This includes roof replacement and the scope is not
limited to the internal areas of the home which were affected by water ingress.
Determination | Case number: 801667 Page 13 of 19
The complai nant also provided a separate painting quote which (similar to the builder‟s quote)
is not limited to the areas of internal water ingress.
The available evidence (including the complainant‟s own reports) do es not suggest the entire
home requires repairs due to claim related water ingress.
Insurer’s building quote is sufficient and meets internal repair obligations
The panel has reviewed both the insurer and complainant‟s building quotes.
The complainant‟s quotes allow for repairs well beyond the scope of internal damage caused
by water ingress under the subject claim.
The panel accepts the insurer‟s quote is reasonable. However, the insurer should add a 20%
uplift and pay the complainant the total amount less any previous payment for building
repairs. The 20% uplift has been added to account for transference of risk from the insurer to
the complainant as well as contingencies.
The insurer is to pay interest on the amount to be paid, in accordance with the Act, from the
date of the quote, until the date of payment.
Temporary accommodation
The exchanged material confirms that the insurer has paid the complainant for various
periods of temporary accommodation.
Noting that the issue of contents has not yet been resolved, the panel is of the view that it
would be fair that the insurer pay the complainant an additional $13,288, being eight weeks at
$1,661.00 per week.
This payment will finalise the obligations of the insurer for temporary accommodation,
regarding the claim and the complaint.
Cash settlement
The panel is satisfied that the policy coverage allows for the insurer to settle on a cash
settlement basis.
Noting that non-covered repairs to the roof have not been completed, the panel is satisfied in
the circumstances of this claim and complaint, that the insurer is entitled to meet its
obligations to the complainant under the policy, on a cash settlement basis.
2.4 Is the insurer required to compensate the complainant?
Insurer caused some delays
On 13 February 2020, the complainant lodged the claim. The insurer requested information
from the complainant, however, it clearly did not take timely action to assess the claim or
make a determination on the cause of damage and extent of its liability.
Considering the nature of the claim (water ingress), it is less than ideal that the insurer did not
take steps to identify and deal with any moisture or mould until the complainant raised
concerns in or around May 2021.
Determination | Case number: 801667 Page 14 of 19
Insurer did not comply with Code
The GICOP to which the insurer subscribes, says an insurer will decide whether to accept or
deny a claim, and tell the insured about its decision, within 10 business days of receiving all
relevant information.
The insurer did not assess the claimed damage for over year and had limited or irregular
contact with the complainant in the months after lodgement of the claim. This was the case
even though the complainant tried following up with the insurer.
Insurer provided assistance to the complainant in recognition of its delays
The insurer contributed to the costs which the complainant says she incurred to repair the
roof. It also provided temporary accommodation to the complainant
from 11 June 2021 until 31 November 2021,
for 28 days from 3 March 2022 (after make-safe issue was reported in February 2022),
then for a further month from 23 March 2022 and 27 April 2022, respectively.
The panel acknowledges that the insurer did try to provide some assistance by paying for roof
repairs outside policy terms, conducting make-safe (also outside policy terms) and extending
temporary accommodation even after the roof claim had been declined and it had cash
settled the complainant. However, the panel considers the insurer‟s delays would have
caused additional stress and inconvenience to the complainant.
Insurer should pay $4,000 compensation
The panel accepts the insurer‟s handling of the claim has been poor. The available
information shows there was extensive delays and poor handling of the claim. This has
resulted in the claim being substantively protracted.
While the panel accepts the complainants ought to have taken steps to mitigate damage by
repairing the roof and ensuring the home was water tight once the insurer made its decision,
this does not change its views about the insurer‟s initial poor handling of the claim.
The complainant has been in and out of temporary accommodation and the uncertainty about
further accommodation being provided and the fact that she constantly had to seek an
extension is likely to have had a significant impact and caused additional stress and
inconvenience. Consequently, the panel considers it fair that the insurer pays the complainant
$4,000 in non-financial loss.
2.5 Is the insurer required to pay any other costs?
Insurer is to pay the complainant the cost of mould reports
Paragraph D.5.1 of our Rules provides that AFCA may determine an insurer contribute to
legal or other professional costs incurred by a complainant in the course of an AFCA
complaint.
Unless exceptional circumstances apply, AFCA will not require an insurer to contribute more
than $5,000 to these costs. When determining whether an insurer should contribute to the
payment of professional fees incurred, AFCA will take into account the complexity of the
dispute, whether the advice was reasonably needed and whether the costs incurred were
because the expert advice was genuinely required.
Determination | Case number: 801667 Page 15 of 19
In the panel‟s view, the complainant needed to incur the cost to obtain a mould reports as it
was important to assist in establishing her case for mould growth and damage during the
claim.
Further the report assisted the panel in its review of this complaint.
In view of the above, the insurer is to reimburse the complainant for the total cost incurred for
obtaining MRs reports.
The panel does not accept that the insurer should be required to contribute to the cost of
other reports.
Determination | Case number: 801667 Page 16 of 19
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel
includes:
an ombudsman
a member with significant experience in consumer and small business advocacy
a member with extensive experience in the insurance industry.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
Determination | Case number: 801667 Page 17 of 19
3.2 Relevant policy terms
Document/page Wording
PDS/17 Insured events – You are covered for
loss or damage to your building or
contents (as applicable) caused by
You are not covered for
Storm, rainwater and flood Loss or damage …
caused by gradual
deterioration due to
rainwater; or
PDS /21 - 26 Additional benefits
Building and contents benefits
If we accept your claim for loss or damage due to an Insured event, we will also
provide the following Additional benefits where applicable. These Additional
benefits are in addition to the sum insured for bot h building and cont ents cover.
…
PDS/ 43 - 52 General exclusions
No insurance covers everything so it is important to understand the exclusions
of your policy. These exclusions apply to your chosen cover.
Determination | Case number: 801667 Page 18 of 19
What is not covered under your policy?
Exclusions
The following General exclusions apply to all covers under your policy.
You are not covered for any loss or damage caused by or resulting from, or the
costs incurred from or of:
…
gradual deterioration, including wear and tear, rust, corrosion, depreciat ion,
fading or det erioration from exposure to light;
…
inherent defects, structural faults, faulty workmanship or faulty design;
failure to maintain the property in good repair;
…
Your re sponsibilities
Keep your building and contents in good condition and well maint ained
You must ensure you maintain your building and contents in a good state of
repair and condition.
This includes but is not limited to the following:
ensuring that the building is watertight, structurally sound and secure;
ensuring t hat gutters, downpipes and roof valleys are not clogged with debris
and are not rusted, loos e, falling down or missing;
ensuring that floors, walls or ceilings are intact and secure and that any
damage to these items and any other parts of the building th at are not the
subject of a claim under this policy are repaired; and
Any loss or damage or liability or costs or expenses arising from your failure to
maintain your building and contents in a good state of repair and condition will
not be covered under the policy. ..
If you do suffer loss or damage to your building or contents, you must also make
reasonable efforts to prev ent any further loss or damage.
Definitions
The following words have been given special meaning for the purpose of the
policy.
accident an event that you did not plan, intend or expect to happen.
…
event a single occurrence which you did not intend or expect to happen that
results in
loss or damage.
…
Insured events the events which are insured under your policy subject to its
ter ms and conditions
…
storm a violent atmospheric disturbance generally producing strong winds. It
can be accompanied by rain, lightning, hail or snow and it includes cyclones and
tornadoes. Storm does not mean persistent bad weather, heavy or persistent
ra in by itself or heavy or persistent wind by itself.
Determination | Case number: 801667 Page 19 of 19
3.3 GICOP wording
7.10 If you make a claim and we require further information or assessment, within
ten business days of receiving your claim we will:
(a) notify you of any information we require to make a decision on your claim;
…
7.13 We will keep you informed about the progress of your claim at least every 20
business days.
7.14 We will respond to routine requests made by you about your claim within ten
business days.
7.15 If we engage an External Expert to provide a report which is necessary to
assess your claim, we will ask them to provide their report to us within 12 weeks
of the date of their engagement. If the External Expert cannot meet or fails to
meet this timeframe, we will inform you of this, and keep you informed of our
progress in obtaining the report.
7.16 Once we have all relevant information and have completed all enquiries, we
will decide whether to accept or deny your claim and notify you of our decision
within ten business days.
7.17 Our decision will be made within four months of receiving your claim, unless
Exceptional Circumstances apply. If we do not make a decision within four
months, we will provide details of our Complaints process.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.