Determination 801272

Malicious damage claim settlement amount and repair scope

FirmHollard
Decided2022-01-05
ProductGeneral Insurance · Landlord
OutcomeFor the complainant in part
Amount awarded$63,741
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainant claimed for malicious damage to an insured rental property and disputed the cash settlement amount offered by the insurer. AFCA found the insurer's quote should be the basis for repairs with a 30% uplift, and ordered additional payments for asbestos removal, loss of rent and a rent miscalculation.

Under the accidental damage cover, the repair cost is assessed using the insurer's quote, adjusted by 30% for provisional items, contingencies and transfer of risk, as competing quotes included undamaged or excluded items.

Issues

Subjects and remedies

third party authoritypay claimpay compensationreassess claim

Related

All Hollard determinations · Find similar determinations

Text of the determination

Determination Case number 801272 Financial firm The Hollard Insurance Company Pty Ltd Determination | Case number: 801272 Page 1 of 6 Case number: 801272 23 December 2021 1 Determination overview 1.1 Complaint The complainant holds a home building policy with the financial firm (insurer). A claim was made for malicious damage to the insured property caused by previous tenants or other persons who possibly squatted at the property. The insurer accepted the claim. It offered a cash settlement of the claim based on its assessment of the damage. The insurer said due to safety and other concerns it could not undertake or guarantee the repairs. The complainant disagrees with the amount offered. The complainant wants the insurer to repair the damag es closer to the complainant‟s quote, or cash settle the claim for the value of the complainant‟s quote. The complainant says the property is now secure. 1.2 Issues and key findings Is the assessment of the claim adequate? The assessment of the claim was reasonably adequate. The insurer did not want to complete the repairs when requested and had provisional costs in its quote. A further allowance is to be made to the insurer ‟s quote. Why is the outcome fair? The outcome is fair because it considers all the information provided by the parties. The insurer‟s quote contained estimates. The complainant‟s quotes contained items for works to damage that is excluded under the policy. 1.3 Determination This determination is substantially in favour of the insurer. The insurer is to pay the complainant:  the amount of the quote from its builder (AJ) plus 30% for contingencies and transfer of risk, being the total amount of $38, 891.42  loss of rent of $1,180 for four weeks to make repairs to the property  miscalculation of rent of $1,665.00, if this has not already been paid  the value of the quote to remove asbestos for $18,700 from KZ.  no interest is payable. Determination | Case number: 801272 Page 2 of 6 2 Reasons for determination 2.1 Is the assessment of the claim adequate? The assessment of the claim was reasonable, however, the insurer‟s quote for repairs contains provisional items. As the insurer is not prepared to compete the works, an appropriate allowance should be made for the repairs to be completed. The policy provides cover for accidental damage The complainant has a Landlord Insurance Accidental Damage policy, providing cover for the insured property, subject to exclusions. The cover is for any accidental damage or accidental loss to the property and cover extends to items in addition to the sum insured. Within the coverage section it says what is not covered. This includes rust, corrosion, gradual deterioration, depreciation, wear or tear. The policy describes how it will deal with a claim for loss or damage which includes repairing the damaged portions of the property to the same condition as when they were new. The policy has general exclusions which apply to all the policy. Those exclusions include damage caused by tenant neglect, carelessness, poor housekeeping, or unhygienic living habits. Circumstances of the loss The complainant made a claim after discovering the property had been damaged either by previous tenants or persons unknown. After the claim was lodged the insurer appointed its builders to assess the damage. The claim was accepted. The complainant requested the insurer complete the repair works. The insurer offered a cash settlement to the complainant because it could not guarantee the works and because of safety and/or security concerns. The complainant undertook some works to make the property safe and secure, yet the insurer would not complete the works. The complainant then obtained its own quotes to repair the property. The parties have differing quotes for repairing the property The insurer initially appointed builder AG to assess and report on the damage. In its scope of works (SOW) it included commentary about not quoting for any unforeseen damage and stating that for six different items there was a provisional sum. The SOW was increased with a 20% claim management fee. The complainant obtained quotes from three builders. Each quote, including the SOW, is set out differently. It is difficult to compare the information because of this. The quotes were not accompanied by any report which made it difficult to understand the extent of the works proposed and how closely they corresponded to damage due to the insured event. Additionally, for one of the quotes obtained by the complainant, there is a further quote which includes other work for the property, accepted by the complainant as not being part of the claim. Determination | Case number: 801272 Page 3 of 6 The insurer says the complainant’s quotes include repair for pre-existing damage The insurer says the complainant‟s quotes are excessive, pointing out that they propose to repair pre-existing damage not arising from the claim. The insurer relies on its report from AG. It says: “… There is long-term damage to external doorways, and areas to the rear and side of the residence that present as failing due to water ingress, not due to any insurable event. ‟. The report further describes maintenance issues as “N/A”. There is little in AG‟s report that says there are pre-existing issues other than the above statement. There are photos supplied, some captioning pre-existing damage to the rumpus room and wet ground outside the property. Further, the photos taken show the property needs work including clean-up and removal of what appears to be rubbish. Generally, however, the report does not support the photos and it appears at odds with how the insurer has approached the claim in its notice of response. The insurer also relies of the property inspection done on 19 November 2019 to identify pre- existing damage. After reviewing these photos, the only pre-existing damage is the hole in the ceiling where the agent says maintenance is needed to the „roof‟ and “ …although it does not appear to be getting worse I would still recommend to get it repaired as soon as possible”. Otherwise, the property appeared in a reasonable condition when inspected. Accordingly, it is difficult to accept the insurer ‟ s comments. The insurer’s quote is preferred As said above the quotes have a different structure and are not based on the same SOW. This is understandable given the complaInt is about the cause and extent of the damages, what is covered under the policy provisions and the cost of the required repairs. The report from BD contains, in my view, items which have not been damaged. This includes items such as supply a new shed, rewire the property and a new tank. BD‟s quote must be viewed in this light. The report from BA does not provide an itemised cost for the work quoted. The quote also includes works for asbestos removal and re-wiring of the property. Like the BD quote, much of the quote seems to contain items that are not damaged and likely come within the items excluded from coverage under the policy. There are two quotes from KZ, one for repairs and one for asbestos removal. The quote to repair the damages also appears to include items that were not damaged and are an improvement to the property. For instance, the quote includes costs for replacing the kitchen, repainting the interior and exterior of the property and the complete re-flooring. Given the above information, in my view the quote obtained by the insurer should be used as the basis for the cost of the repairs. Because the information contained within this quote includes items such as „ provisional sum ‟ and unforeseen work described in the insurer‟s quote, an amount of 30% should be added. This would also account for the builder not being prepared to do the work, for contingencies and transfer of risk. Determination | Case number: 801272 Page 4 of 6 There is more asbestos to remove The insurer has already paid $6,150 for the removal of asbestos from the property . The complainant submitted a further invoice for the removal of asbestos from KZ for $18,700. The complainant says “…there was further damage caused by the insurer’s asbestos removalists (the asbestos removalists drilled holes and spray-painted parts of the wall with yellow paint to indicate asbestos was present). ” The insurer has not responded regarding the further asbestos removal. This additional amount should be paid to the complainant. Rubbish removal from the property was said to be paid by the insurer to the complainant prior to the property being assessed for an amount of $20,310.52. Loss of rent miscalculation The insurer is yet to respond to a request from the complainant about an incorrect calculation about the loss of rent payment made. The complainant says due to the miscalculation, an amount of $1,665 is outstanding. The insurer should pay for this corrected amount, if it has not already done so. In addition, the insurer should pay the complainant an additional 4 weeks loss of rent to complete the repairs to the property. This amounts to $1,180 ($295 per week). 2.2 Why is the outcome fair? The outcome is fair because it considers the all the information and provides a cash settlement for the complainant to do works for which there was cover under the policy. Determination | Case number: 801272 Page 5 of 6 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the avai lable information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 Product Disclosure Statement What is insured Your Buildings … as set out in Your Schedule are insured if they are destroyed, lost or damaged. We w ill cover Your Buildings … for any accidental damage or accidental loss including that caused by … W e will not cover Your Buildings… for any accidental damage or accidental loss caused by: … Rust, corrosion, gradual deterioration, depreciation, wear or tear. GENERAL EXCLUSIONS We will not pay Claims arising from Determination | Case number: 801272 Page 6 of 6 Mould or fungi. Tenant neglect, carelessness, poor housekeeping, or unhygienic living habits. 3.3 Expert Reports Record Key points Financial firm’s expert (A G ) Building assessment r eport 26 - 03 - 2021  It is noted that the property has been vacant since the tenants were removed in November 2020, however whilst on - site, our client stated that there is clear evidence of squatters / former tenants returning to the residence, and of on - going occupation and drug use.